Docket 08-01-03
Application of Burlington Electric Department for Qualification of McNeil Generating Station as a Class I Renewable Energy Source
Decisions and notices11
What the Authority has issued in this docket, newest first.
Filings137
Showing 51–84 of 84 filings of the selected types
- Burlington Electric
- NcNeil Generating Station
Compliance Filing, Order No. 3rd
- Burlington Electric Department
Report for 2nd Qtr.
- Burlington Electric Department
1st Qtr 2015
- Burlington Electric
4th Qtr 2013
- Burlington Electric Department
Compliance, 3rd quarter report
- Burlington Electric Dept.
2nd Qtr 2013 Report
- Burlington Electric
Order No. 4
- Burlington Electric Department
hourly emission data
- Burlington Electric Department
Compliance
- Burlington Electric Dept.
McNeil Station Qtrly Report for CT Class 1
- Burlington Electric Dept.
4th Qtr 2010 Report
- Burlington Electric Dept.
3rd Qtr 2010 report
- Burlington Electric Department
CT Class 1 Compliance
- Burlington Electric
Compliance Filing
- Burlington Electric Department
Compliance Filing, Order No. 4
- Burlington Electric Department
Compliance Filing, Order No. 4
About this docket
- Docket number
- 08-01-03
- Status
- Closed December 17, 2025
- First filing
- January 16, 2008
- Latest filing
- October 21, 2026
- Public filings
- 137
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised October 3, 2017
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.