Decisions and notices
What the Authority has issued in this docket, newest first.
- April 24, 2020Notice of Request for Written Comments Comments due May 8, 2020…
- October 30, 2017Notice Notice of Proceeding…
Filings
Showing 151–200 of 830 filings.
December 2024
Motion No. 285December 17, 2024 · Connecticut Green Bank- Ruling on Motion No. 284December 9, 2024 · PURA
Ruling: Denied
- Ruling on Motion No. 283December 9, 2024 · PURA
Ruling: Denied
- Ruling on Motion No. 282December 9, 2024 · PURA
Ruling: Denied
- Ruling on Motion No. 281December 9, 2024 · PURA
Ruling: Denied
- Ruling on Motion No. 280December 9, 2024 · PURA
Ruling: Denied
- Ruling on Motion No. 279December 9, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 278December 9, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 277December 9, 2024 · PURA
Ruling: Denied
- Ruling on Motion No. 275December 4, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 274December 4, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 273December 4, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 272December 4, 2024 · PURA
Ruling: Granted
November 2024
Motion No. 284November 27, 2024 · 380 Mather St Bldg 7 Hamden, CT 06514extension request
- Motion No. 283November 27, 2024 · 380 Mather St Bldg 5 Hamden, CT 06514
extension request
- Motion No. 282November 27, 2024 · 380 Mather St Bldg 4 Hamden, CT 06514
extension request
- Motion No. 281November 27, 2024 · 380 Mather St Bldg 3 Hamden, CT 06514
extension request
- Motion No. 280November 27, 2024 · 380 Mather St Bldg 2 Hamden, CT 06514
extension request
- Motion No. 279November 27, 2024 · 1298 Hartford Turnpike Bldg 11 North Haven, CT 06573
extension request
- Motion No. 278November 27, 2024 · 1298 Hartford Turnpike Bldg 8 North Haven, CT 06573
extension request
- Motion No. 277November 27, 2024 · 1199 Whitney Avenue Hamden, CT 06514
extension request
- Motion No. 276November 27, 2024 · 2405 Whitney Avenue Hamden, CT 06514
extension request
- Motion No. 275November 27, 2024 · 955 Mix Avenue Hamden, CT 06514
extension request
- Motion No. 274November 27, 2024 · 925 Mix Avenue Hamden, CT 06514
extension request
- Motion No. 273November 27, 2024 · 865 Mix Avenue Hamden, CT 06514
extension request
- Motion No. 272November 27, 2024 · 835 Mix Avenue Hamden, CT 06514
extension request
October 2024
Ruling on Motion No. 267October 17, 2024 · PURARuling: Granted with modification
- Ruling on Motion No. 271October 11, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 270October 11, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 269October 11, 2024 · PURA
Ruling: Granted
- Ruling on Motion No. 268October 4, 2024 · PURA
Ruling: Granted
- Motion No. 271October 1, 2024 · Louth Callan Renewables LLC
Motion for Extension
- Motion No. 270October 1, 2024 · West Haven Solar One, LLC
Motion of West Haven Solar One for extension of the automatic termination date for ZREC LL09-24387
September 2024
CorrespondenceSeptember 30, 2024 · Connecticut Green BankCGB 17-10-19_PURA Motion 248_Compliance & Compliance_SAP1 9-30-24
- CorrespondenceSeptember 30, 2024 · Connecticut Green Bank
CGB 17-10-19_PURA Motion 220_Correspondence & Compliance_SAP2 9-30-24
- Motion No. 269September 27, 2024 · Connecticut Green Bank
CGB PURA Docket 17-10-19 Motion to Extend LREC9-6898
- Motion No. 268September 25, 2024 · VCP Litchfield WPCA, LLC
Motion for Extension of Automatic Termination Date for ZREC Contract #L9-6817
- Motion No. 267September 24, 2024 · C-TEC Solar, LLC
Motion for Additional Extension of Time of VNM Automatic Termination Date
- Ruling on Motion No. 266September 24, 2024 · PURA
Ruling: Granted with modification
- Ruling on Motion No. 265September 18, 2024 · PURA
Ruling: Granted with modification
- Motion No. 266September 17, 2024 · CT Solar PDF LLC
Nokomis Energy LLC respectfully requests that the Public Utilities Regulatory Authority permit the reinstatement of the awarded LREC contract due to unforeseen delays in the interconnection process and grant an extension of the Automatic Contract Termination Date for good cause.
- Motion No. 265September 10, 2024 · Greenskies Clean Energy LLC
Motion for Extension of Automatic Contract Termination Date
July 2024
Ruling on Motion No. 263July 30, 2024 · PURARuling: Granted with modification
- Ruling on Motion No. 264July 24, 2024 · PURA
Ruling: Granted with modification
- Ruling on Motion No. 262July 24, 2024 · PURA
Ruling: Granted with modification
- Ruling on Motion No. 261July 24, 2024 · PURA
Ruling: Granted with modification
- Ruling on Motion No. 260July 24, 2024 · PURA
Ruling: Granted with modification
- Ruling on Motion No. 259July 24, 2024 · PURA
Ruling: Granted with modification
- Motion No. 264July 10, 2024 · 1199 Whitney Ave Hamden, CT 06514
Refile extension request
- Motion No. 263July 10, 2024 · 2405 Whitney Ave Hamden, CT 06514
Refile for extension request