Docket 18-06-13
Application of New Cingular Wireless PCS, LLC for Approval of a Construction Plan to Install Wireless Facilities Within the Public Rights-of-Way
Decisions and notices12
What the Authority has issued in this docket, newest first.
Filings648
Showing 301–325 of 325 filings of the selected types
- New Cingular Wireless PCS, LLC
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE New Haven 19
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE Bridgeport 55
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE New Haven 21 - West Haven
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE Bridgeport 91
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE 41 BRIDGEPORT
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE BRIDGEPORT 34
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE BRIDGEPORT 44
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE Bridgeport 42
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE 39 BRIDGEPORT
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE BRIDGEPORT 25
- New Cingular Wireless PCS, LLC
PUBLIC RIGHTS-OF-WAY AT&T SITE HARTFORD 55
- New Cingular Wireless PCS, LLC
New Haven 25 Motion for Approval of Small Cell Construction
- New Cingular Wireless PCS, LLC
Hartford 17 Motion for Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Hartford 16 Motion for Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Bridgeport 97 Motion for Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Bridgeport 77 Motion for Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Bridgeport 76 Motion for Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Bridgeport 59 Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Bridgeport 53 Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Bridgeport 29 Small Cell Construction Approval
- New Cingular Wireless PCS, LLC
Bridgeport 28 Small Cell Construction
- New Cingular Wireless PCS, LLC
(REVISED) Bridgeport 105 Small Cell Construction
- New Cingular Wireless PCS, LLC
(REVISED) Motion for construction -Hartford 4
- New Cingular Wireless PCS, LLC
Motion for Approval of Construction Plan Bridgeport 106
About this docket
- Docket number
- 18-06-13
- Status
- Closed December 21, 2022
- First filing
- June 18, 2018
- Latest filing
- September 23, 2026
- Public filings
- 648
- Documents
- On the current system
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.