  1. Page 10 of 90

    operating and financial condition of the company will be in the immediate future’5 . . . . [T]he test year may be adjusted ‘forward for a reasonable period of time’ to permit the utility to recover ‘definite, ascertainable expenses maturing or certain to materialize during that period of time.’”6 (emphasis added). e. Prudence As noted above, when reviewing the management decisions of a public utility company, General Statutes § 16-19e(a)(5) directs PURA to determine if “the level and structure of rates charged customers … reflect prudent and efficient management of the franchise operation . . .” This standard requires an assessment of the information available to management at the time the decision was made. CL&P v. DPUC, 216 Conn. 627, 645 (1990) (“The prudence of a management decision depends on good faith and reasonableness, judged at the time the decision is made.”); Violet v. FERC, 800 F.2d 280, 282 (1st Cir., 1986) (“The prudence of the investment must be judged by what a utility’s management knew, or could have known, at the time the costs were incurred.”) f. Administrative Agency Discretion In regard to the Authority’s ratemaking powers, the “legislature . . . has not imposed upon [PURA] any specific formula or policy to use in setting rates.” Town of Greenwich v. DPUC, 219 Conn. 121, 126 (1991). PURA’s “broad grant of regulatory authority carries with it the necessarily equally broad discretion, to be exercised within legal limits . . . to take into account such varying factors as economics, public policies, accounting principles, fairness to the parties, and the context and intent of any prior agreements entered into by the utility, and to 5 6 Quoting Southern New England Telephone Co. v. Public Utilities Commission, 29 Conn. Supp. 253, 258 (1970). Quoting Connecticut Natural Gas Corp. v. Public Utilities Commission, 29 Conn. Supp. 379, 390-91 (1971). 10
  2. Page 11 of 90

    balance those factors by a process of reasoned decision-making”. Office of Consumer Counsel v. Dept. of Public Utility Control, 279 Conn. 584, 593-94 (2006). Given its statutory duty to ensure that the level and structure of rates is sufficient, but no more than sufficient, to allow public service companies to cover their operating costs, “PURA must be able to protect the interests of ratepayers, and, when it determines that a company is overrecovering, it must be allowed to adjust the rates.” GenConn, 348 Conn. at 549. As the Supreme Court of the United States has recognized, “[t]he Constitution does not bind rate-making bodies to the service of any single formula or combination of formulas. Agencies to whom this legislative power has been delegated are free, within the ambit of their statutory authority, to make the pragmatic adjustments which may be called for by particular circumstances.” Federal Power Commission v. Natural Gas Pipeline Co. of America, 315 U.S. at 586. g. Burden of Proof Ultimately, the public service company has the burden of proof to show that a proposed rate is just and reasonable. General Statutes § 16-22 (placing burden of showing that proposed rate under consideration is “just and reasonable” on public service company). As a general rule of administrative law, the moving party bears both the burden of production and the burden of persuasion in an administrative proceeding. Bridgeport Dental, LLC v. Commissioner of Social Services, 2014 WL 6476971 (Conn. Super. Ct. October 20, 2014) (citing 2 Am.Jur.2d, Administrative Law § 342 (2014). In the context of a rate case, the petitioning company bears the burden of proving not only the amounts of its operating costs and other expenses, but also the “basis for charging to its expense accounts and the propriety of including such charges for ratemaking purposes.” Connecticut Natural Gas Corporation v. Public Utilities Commission, 29 Conn. Supp. 379, 394 (1971). To establish the facts to justify a rate amendment, the company 11
  3. Page 12 of 90

    must present facts that exceed the preponderance of the evidence standard. See Goldstar Medical Services Inc. v. Department of Social Services, 288 Conn. 790, 821 (2008). “In the absence of state legislation prescribing an applicable standard of proof, . . . the preponderance of evidence standard is the appropriate standard of proof in administrative proceedings . . ..” Id. The preponderance of the evidence standard requires evidence showing that facts are “more probable than not.” Id. (citing Tianti v. William Raveis Real Estate, Inc., 231 Conn. 690, 702 (1995)). The exclusion of plant additions from rate base is not arbitrary or capricious where supporting evidence is “lacking the particularity and detail necessary to ascertain exactly why the costs were prudently incurred.” Aquarion, 352 Conn. at 402. h. Pragmatic Adjustments As noted above, the United States Supreme Court has held that agencies are “free, within the ambit of their statutory authority, to make the pragmatic adjustments which may be called for by particular circumstances.” Federal Power Commission v. Natural Gas Pipeline Co. of America, 315 U.S. at 586. The Connecticut General Assembly has directed the Authority to make such adjustments. If the Authority finds any proposed amendment of rates to not conform to the principles and guidelines set forth in Section 16-19e, or to be unreasonably discriminatory or more than just, reasonable and adequate to enable the Company to provide properly for the public convenience, necessity and welfare, or the service to be inadequate or excessive, it “shall determine and prescribe, as appropriate, an adequate service to be furnished or just and reasonable maximum rates and charges to be made” General Statutes § 16-19(a) (emphasis added). 12
  4. Page 13 of 90

    IV. Rate Base CWC’s initial application requested setting its average Rate Year rate base at $907,337,093. See Schedule B-1.0A. In LFE-01, Schedule B-1.0A, the Company made several adjustments updating its proposed Rate Year rate base. The OCC’s net result is a decrease of $44,798,459 to $862,538,635. In its expert witness testimony, OCC presented numerous recommended adjustments to the Company’s requested Rate Year level of rate base. Below is a discussion of those recommendations and other areas that have risen out of the development of the record and evidentiary hearings in this proceeding. a. Cash Working Capital The Company derived its cash working capital request for the Rate Year using the 1/8th rule (also known as the 45 Day Rule). Under this methodology, the Company calculates its cash working capital allowance by multiplying its total O&M expenses by 12.5 percent, representing approximately 45 days of operating expenses. Schedule B-4.0. OCC does not dispute the Company’s methodology for calculating cash working capital. However, since O&M expenses serve as the basis for this calculation, the cash working capital allowance must be adjusted to reflect OCC’s recommended adjustments to O&M expenses. Based on the adjustments contained in the Direct Testimony of Grace N. Koenig, OCC originally recommended reducing the Company’s cash working capital allowance to reflect the adjustments contained in her initial testimony. This resulted in a $775,530 reduction to the cash working capital component of rate base. OCC Koenig Direct Testimony, p. 6. Based on final O&M expense adjustments 6, 472,627 discussed later in this brief, OCC recommends a further reduction to cash working capital of $809,078 to rate base. 13
  5. Page 14 of 90

    b. CIAC, Customer Advances, Security Deposits, Accumulated Excess Deferred Taxes OCC had previously offered testimony recommending adjustments to the values used in contributions in aid of construction and customer advances, as well as removal of security deposits and accumulated excess deferred taxes. Direct Koenig, pp. 6-7. However, in its updated LFE-1 filing, the Company resolved these issues in its updated position. See LFE-1, Schedule B9.0. c. Plant in Service i. Overview of CWC’s Proposed Capital Additions Connecticut Water proposes to set rates on a rate base that combines utility plant in service (“UPIS”) as of the close of the historic test year on December 31, 2025, with three successive periods of pro forma plant additions extending two years beyond the test year: (1) additions from the close of the test year through the time of evidentiary hearings, which the Company defined as January 1 through September 30, 2026; (2) additions from October 1 through December 31, 2026; and (3) additions for calendar year 2027. Exh. A.3, Peeling Direct Testimony, p. 19. The pro forma additions exclude investments eligible for recovery through the Water Infrastructure and Conservation Adjustment (“WICA”) and the Water Quality and Treatment Adjustment (“WQTA”), which the Company will recover through those mechanisms. OCC-146; Exh. A.3, p. 20. CWC’s proposed investment levels reflect substantial growth in its UPIS. Between December 31, 2022 and December 31, 2025, the Company’s UPIS increased from approximately $1.091 billion to $1.361 billion, representing an annual compound growth rate of approximately 7.65 percent. This rate of growth exceeded that experienced by Aquarion Water Company over the same period. Although this difference does not establish that CWC’s investments were 14
  6. Page 15 of 90

    imprudent, it illustrates the magnitude of the capital expenditures under consideration and the importance of ensuring that the investments included in rate base are both used and useful and prudently incurred. OCC Larkin-Connolly Direct Testimony, pp. 9–10. During the course of this proceeding, CWC has revised the capital additions included in its proposed pro forma rate base. In LFE-01, the Company submitted updated schedules reflecting revisions and corrections made throughout the proceeding. These schedules include updated additions for the January 1 through September 30, 2026 period and revised forecasted additions for the remainder of 2026 and calendar year 2027. The revised amounts are presented in Table 1 below. Table 1: CWC Updated Pro Forma Plant Additions and OCC’s Recommended Treatment PERIOD UPDATED ADDITIONS (LFE-01) OCC POSITION Allow, subject to documentation and project-specific adjustments Jan. 1 – Sept. 30, 2026 $32,252,063 Oct. 1 – Dec. 31, 2026 $9,036,905 Exclude as forecasted additions Calendar year 2027 $37,031,182 Exclude as forecasted additions Source: LFE-01, Attachment 2. OCC witness Brendan Larkin-Connolly reviewed the capital additions proposed by CWC, the Company’s documented capital authorization and project management procedures, and the supporting project-level information produced through discovery. His review identified significant deficiencies in the documentation provided to support the Company’s capital investments, particularly regarding evidence of initial project authorization and supplemental approval for expenditures exceeding authorized budgets. Direct Larkin-Connolly, pp. 10–21. OCC does not recommend disallowances to the historic plant additions completed through December 31, 2025. However, after reviewing the updated 2026 additions presented in LFE-01 against the documentation provided in discovery, OCC identified $17,718,966.84 in 15
  7. Page 16 of 90

    completed 2026 additions for which CWC has not provided sufficient evidence of compliance with its own capital authorization requirements. OCC recommends that these additions be excluded from rate base. OCC further recommends excluding all forecasted additions for the October 1, 2026 through December 31, 2027 period, totaling $46,068,087, consistent with the Authority’s recent decisions regarding incomplete and forecasted plant. In addition, OCC recommends removing the Company’s proposed Oracle Customer Information System (“CIS”) software-as-a-service (“SaaS”) prepayment balance and associated amortization expense because the system will not be complete and in service as of the cutoff date for supporting plant additions in this proceeding. Direct Larkin-Connolly, pp. 31–38; Surrebuttal Larkin-Connolly, pp. 4–14. ii. Capital Authorization and Project Management Procedures 1. CWC’s documented capital authorization and project management procedures are generally sound. A utility’s capital authorization and project management procedures play an important role in determining whether its capital investments were prudently incurred. Regulatory authorities and other stakeholders necessarily face significant information asymmetry when reviewing utility investments. The utility has greater access to information regarding its operational needs, available alternatives, engineering considerations, procurement decisions, and the circumstances that affect project execution. Further, the relatively limited time available to conduct a base rate proceeding makes it impractical to evaluate every management decision associated with hundreds of capital projects. Direct Larkin-Connolly, pp. 11–13. For these reasons, formal capital authorization and project management procedures provide an important framework for evaluating the prudence of utility investments. When those procedures are reasonable, a prudence review can focus, in part, on determining whether 16
  8. Page 17 of 90

    management followed the established procedures when planning, approving, and implementing individual projects. Id. In his direct testimony, Mr. Larkin-Connolly reviewed the procedures described by CWC witness David C. Peeling, as supplemented by the Company’s responses to discovery. Based on this review, Mr. Larkin-Connolly concluded that CWC maintains generally sound procedures for capital planning, project authorization, and project management. Direct Larkin-Connolly, pp. 14– 17. CWC’s Capital Planning Council provides oversight of the annual capital budget and reviews project funding requests. In response to OCC-133, the Company provided additional materials describing its project prioritization and authorization procedures, including the Capital Planning Council Governance Document, Project Proposal forms, and Change Request forms. These materials establish a process for reviewing projects before funding is authorized and for seeking additional approval when project costs or scopes materially change. OCC-133, Attachments 1–4; Direct Larkin-Connolly, pp. 15–17. The Project Proposal form documents the justification for a proposed investment, its anticipated costs, alternatives considered, and the Company’s initial approval decision. Similarly, the Change Request form documents circumstances in which the Company must obtain supplemental authorization for changes to an approved project. CWC’s procedures require a Change Request when estimated project costs exceed the initially approved budget by the lesser of 15 percent or $100,000, or when bid construction costs exceed the original estimate by the lesser of 35 percent or $250,000. OCC-133, Att. 2–4; Direct Larkin-Connolly, pp. 16–17. OCC recognizes the value of these procedures. They establish an orderly process for evaluating the necessity of proposed investments, approving expenditures, monitoring project 17
  9. Page 18 of 90

    budgets, and reviewing material changes as projects proceed. However, as discussed below, the existence of appropriate procedures does not establish that those procedures were followed for the capital additions the Company seeks to recover from ratepayers. 2. The existence of sound procedures does not establish that they were followed. Sound procedures help address the problem of information asymmetry because, if the procedures themselves are reasonable, part of the prudence review becomes verifying that they were followed. Direct Larkin-Connolly, p. 12. That verification, however, depends entirely on the Company producing the records its procedures generate. A written policy describes what should happen; only contemporaneous records show what did happen. When asked on crossexamination whether he found that CWC maintains procedures for authorizing projects before funding, Mr. Larkin-Connolly drew exactly this distinction: “I would say that I found that they have them. I wouldn’t say that they have provided complete documentation to show that . . . that process was completed for all the projects submitted so far.” Transcript 9/25 pp. 93-94. This distinction also matters because a prudence review concerns more than the initial decision to pursue a project. During his cross-examination of Mr. Larkin-Connolly, Chairman Wiehl described the prudence standard as an evaluation of “whether the decision was reasonable given that information at the time” the company made it. Tr. 9/25 p. 106. Mr. Larkin-Connolly agreed and added that while a company may present its approval procedures as evidence that the decision to pursue a project was prudent, “there are an infinite number of decisions made along the way for projects. So I always think of prudency as sort of all those decisions along the way related to a project.” Tr. 9/25 p. 107. The Chairman maintained that the decision to build is “just the first decision out of 50 million decisions with respect to a regular project.” Id. Commissioner Beecher made the same point, observing that a project can be well justified, “but how you get 18
  10. Page 19 of 90

    there matters.” Tr. 9/25 pp. 130-131. For this reason, contemporaneous authorization records and documented changes to project budgets are essential to a prudence review. Records created at the time a project is planned, approved, and implemented provide the most reliable evidence of what the Company knew, considered, and decided, in the same way that historians treat records created at the time of an event as primary sources. Direct Larkin-Connolly, p. 19. Contemporaneous records also show that management review actually occurred: that management approved the scope and budget before expenditures were incurred, monitored performance, and reviewed material changes as they arose. Id. Without them, “it is difficult to determine whether these decisions were made through the Company’s established processes or whether the later narrative merely provides an after-the-fact explanation of the outcome.” Id. It follows that approval of an annual capital budget does not by itself demonstrate that subsequent expenditures were prudently managed. Board approval of a budget, or the inclusion of a project on an annual project list, establishes at most that the Company decided to pursue the project at an expected cost. CWC’s own procedures recognize that this initial decision is not the end of management’s responsibility: they require a new review and approval when costs exceed the approved budget by more than a defined threshold. Where that review is required and the record contains no evidence that it occurred, the Authority has no basis to conclude that management made a reasoned decision to continue spending at the higher cost. As Mr. LarkinConnolly testified, when a meaningful share of projects run over budget, “it requires some form of investigation into […] what’s driving these cost overruns.” Tr. 9/25 p. 133. iii. CWC’s Documentation Does Not Adequately Support Its Capital Additions 1. CWC’s initial filing did not provide the contemporaneous 19