Page 15 of 44
merits, while recognizing group support, rather than automatically substitute the parent’s consolidated ratio or equate the cost of the parent’s borrowing with the required return on CWC equity. Capital structure and ROE must also be evaluated consistently. Mr. D’Ascendis acknowledged that more equity reduces financial risk, all else equal, and OCC presents a leverageadjusted CAPM indication of 8.0% at the Company’s proposed structure. Sept. 23 Tr. 9:1–9; OCC Brief at 47. The Company does not dispute the direction of that relationship. It disputes deriving an appropriate financing mix merely by replacing higher-cost equity with debt while assuming all other costs and risks remain unchanged. A lower equity ratio increases leverage; its apparent firstorder revenue reduction is not, by itself, proof of a lower sustainable financing cost. The Authority should consider the return and equity layer together in light of the Company’s investment program and cash-flow evidence, rather than treat each proposed reduction as independent of the other. As the Company’s initial brief explains, the requested 10.00% ROE and 54% equity ratio work together to produce the funds from operations needed to support the Company’s credit metrics. Company Initial Brief at 24–27. FFO/debt measures recurring cash generation relative to debt obligations. A lower ROE reduces the cash return on the equity invested in rate base. A lower equity ratio reduces that return further and, to the extent the Company’s financing follows the ratemaking structure, increases the debt that funds from operations must support. OCC and EOE propose both reductions at the same time, which compounds the pressure on the same metric. Dixon Direct at 10–11, 28; Sept. 23 Tr. 7:7–17. That pressure would come when the Company’s actual 2025 FFO/debt ratio was 10.48%, S&P had revised its assessment of Connecticut’s regulatory construct, citing regulatory lag and below-average authorized returns, and the Company’s standalone credit profile was bbb, two notches below its parent. Dixon Direct at 6, 150330368.4 -12-Page 16 of 44
11. The 10.48% ratio is a starting point, not a projected post-case result, and the Company does not claim that any particular rating action is inevitable. But the Authority should not evaluate OCC’s 49% and EOE’s 51% equity proposals separately from their 8.30% and 8.33% ROE recommendations. Together, they reduce the cash flow available for a continuing capital program that will require both debt and equity financing. Schedule F-7.0. Customers benefit from the Company’s request through stronger liquidity, less reliance on higher-cost short-term borrowing, and access to long-term financing on reasonable terms, all of which lower the long-term cost of service. Dixon Direct at 10–11. C. Flotation Costs Are a Financing Issue, Not an Automatic Windfall OCC contends that the Company has not established the jurisdictional basis for a permanent parent-level flotation-cost adder, while EOE and the AG argue that stock issuance above book value eliminates the need for an allowance. OCC Brief at 54–55; AG Brief at 8–9. The economic point in Mr. D’Ascendis’s testimony is narrower: issuing equity involves costs that reduce net proceeds, and financing through a parent does not make those costs disappear. He explained that equity infusions reach the subsidiary through the corporate structure and compared recognition of equity issuance costs with the inclusion of issuance costs in the effective cost of debt. Sept. 23 Tr. 16–18. He also acknowledged that existing shareholders bear those costs outside the regulatory construct. Id. at 17. That acknowledgement describes who initially bears the cost; it does not resolve whether the cost of financing regulated investment should be recognized in rates. An issuance above book value and an issuance cost are different measures. The former compares the issue price with accounting equity per share; the latter compares gross proceeds with the funds available after transaction costs. A premium to book therefore does not by itself show that no financing cost exists. The record identifies H2O America equity issuances and associated 150330368.4 -13-Page 17 of 44
information in OCC-246 and distinguishes physically issued shares from unsettled forward arrangements in RRU-189. That evidence should be evaluated with the Company’s financing presentation, not dismissed because CWC is not publicly traded. Nevertheless, recognition of a financing cost does not excuse proof of attribution or permit duplicate recovery. OCC’s concerns about the amount attributable to CWC and the appropriate recovery mechanism require an express determination; they do not support the categorical conclusion that subsidiary equity can never carry flotation costs. D’Ascendis Rebuttal, Sections V.D and VI.D; Sept. 23 Tr. 138–139. In sum, the Company’s request should be evaluated as a supported 10.00% ROE and 54% common-equity structure, not as the sum of every high model result or supplemental adjustment. The Company’s evidence supports a finding that both are necessary to establish just and reasonable rates. The Company’s updated analysis, financing evidence, and actual capitalization provide the basis for its request, while the separate model limitations and attribution questions should be assessed explicitly and on the record. III. RATE BASE AND PROJECT ELEVATE OCC’s rate base arguments focus more on whether every required document was provided or whether an unnecessary cut-off was met than on whether the projects were prudent or their costs were unreasonable. The Company agrees that proper approvals, timely records, and meaningful review are important. But prudence should not turn solely on whether every form for every project was submitted before the record closed, and a missing document does not automatically justify excluding an entire investment. As explained in the Company’s initial brief, the Authority should consider all available evidence, distinguish completed projects from forecasted additions, and recognize supported investment serving customers during the Rate Year, subject to verification and appropriate customer protections. Company Initial Brief at 18–21; Dixon Rebuttal, Section III. 150330368.4 -14-Page 18 of 44
The Company’s capital documentation is not deficient by historical standards; it reflects a practice the Authority and OCC have already recognized. In Docket No. 23-08-32, PURA Staff audited the Company’s capital additions at its headquarters, including “an in-depth review of invoices and supporting documentation provided by CWC,” and the Authority found, based on that audit and the record, “that the Company demonstrated that its Test Year plant-in-service portfolio is prudent and used and useful,” subject to adjustments of $2,353,206 against $114,440,016 in requested test-year additions. Docket No. 23-08-32, Decision (June 28, 2024) at 9–11 & Table 3. OCC itself acknowledged in that case that the Company’s capital project summaries, which addressed each project’s purpose, service to customers, system deficiencies, risk assessment, alternatives, scope and execution, cost breakdown, and schedule milestones, “provide[] the kind of evidence that has been conspicuously absent in recent rate cases.” Docket No. 23-08-32, OCC Brief at 15. The Company carried that practice forward in this proceeding through Exhibit A.3, Appendix 1, and supplemented it in discovery with project-level plant additions, in-service dates, Project Request forms, and Change Request forms. OCC-136. OCC’s current position reflects a change in what OCC expects, not a decline in what the Company provides. OCC also inaccurately implies substantial portions of the plant additions are missing project narrative explanation, suggesting only 166 of 502 projects listed in OCC-136 Attachment 2 had narratives provided. Larkin-Connolly Direct at 21. In fact, the vast majority of the projects OCC was “unable to match” to a narrative fall into the categories of developer contributed plant (119), WICA/WQTA (159), and in-service amounts below $10,000 (30). OCC-136 Attachment 2, Columns J-H[JB2.1]. The Company noted project narratives for WICA/WQTA and projects below $10,000 were not provided due to their presence on other dockets (in the case of WICA and 150330368.4 -15-Page 19 of 44
WQTA) or their small scale (in the case of projects below $10,000). Peeling Direct, pp. 23-24. The 28 remaining projects were placed in service during the 2023 Proforma period, where corresponding narratives would have been provided as part of Docket 23-08-32. The Company’s capital documentation is comprehensive and consistent with Docket 23-08-32 submissions. A. Prudence Requires More Than Paperwork OCC acknowledges that CWC’s capital planning, authorization, and project-management procedures are generally sound. It also acknowledges that discovery supplied annual budget reports, project-level plant additions and in-service dates, 36 Project Request forms, and 53 Change Request forms; that its witness reconciled historic additions to Schedule B and annual reports; and that the sampled records indicated the described process had been carried out. OCC Brief at 16–25; OCC-133; OCC-136; Sept. 25 Tr. 95. Those concessions are significant. They provide evidence of both the control framework and its operation. The Company does not argue that written procedures prove compliance in every instance, but OCC likewise cannot acknowledge evidence that the process operated and then treat documentation short of a complete population as having no probative value. Sampling Is Valid Evidence. A sample cannot establish with certainty that every management decision on every project was prudent. Nor does a complete collection of forms establish that certainty: OCC itself cautions against a check-the-box standard. OCC Brief at 42– 44. The appropriate question is whether the sample, reconciled accounting records, project explanations, testimony, and other evidence taken together support the requested recovery, and whether specific exceptions warrant further examination. No statistical representativeness or universal inference should be assumed merely from the number of records produced. But OCC accepted a sample for review, found evidence that the process was followed within it, and recommends no historic plant disallowance. Its more demanding position for post-test-year 150330368.4 -16-Page 20 of 44
additions therefore requires a reasoned explanation of the evidentiary difference—not a categorical premise that only review of every authorization document can support prudence. OCC Brief at 21–26; Larkin-Connolly Direct at 24–30. The Company accepts that it has the burden of proof, and material gaps can justify exclusion where the record as a whole is insufficient. Used-and-useful status alone does not establish prudence, just as it is not established by an approval form alone. Nevertheless, missing documentation and an unreasonable investment decision are different propositions. Prudence concerns the reasonableness of decisions given the information available when they were made, including execution and oversight, not merely whether a preferred document appears in the filing. Company Initial Brief at 12–15. Significantly, OCC’s own proposed future standard recognizes that other contemporaneous evidence may demonstrate prudence when a particular record is unavailable. OCC Brief at 44. The Authority should apply that same substantive distinction here rather than convert a documentary deficiency into an automatic full-project penalty. Pro Forma Support Need Not Consist Exclusively of Final Invoices. Updating projects during a rate case presents a practical timing problem: construction, authorization updates, accounting closeout, and placement in service continue while discovery and hearings are underway. That does not excuse inadequate support, and the Company does not dispute the importance of producing available contemporaneous records promptly. It does mean, however, that final invoices cannot invariably be the only acceptable evidence of a supported pro forma amount. Executed contracts, awarded bids, authorized budgets, engineering estimates, commitments, progress reports, cost-to-date reconciliations, project schedules, and supported inservice forecasts can establish different aspects of a proposal before final billing is complete. Their weight depends on their specificity and reliability. A bare budget is not conclusive, but neither is 150330368.4 -17-Page 21 of 44
final invoice-level support necessary to every prospective finding. The Company’s initial brief asks for that practical assessment, with later verification where needed, and not exemption from scrutiny. Company Initial Brief at 18–21; Dixon Rebuttal, Sections III.C–III.D. OCC’s plant objection primarily concerns Project Request and Change Request records, not simply unpaid or unavailable invoices. The Company does not conflate those issues. Its point is that both cost support and procedural compliance should be evaluated through the available evidence, proportionate to the issue being tested. For prospective projects, the Authority can distinguish approval of a supported estimate from final verification of prudent actual costs and service dates. The initial brief specifically proposes compliance filings, reconciliation of the associated revenue requirement, and customer credits for unsupported costs or delayed additions. Company Initial Brief at 20–21. Such a process must preserve a meaningful opportunity for review; it should not be treated as already established or as automatic approval of later spending. It is the Company’s proposed safeguard for resolving uncertainty without excluding supported Rate-Year investment categorically. B. Calling Regulatory Lag a “Feature” Does Not Establish Economic Symmetry OCC describes regulatory lag as a deliberate feature of traditional regulation: the utility retains savings between cases while bearing costs it fails to control. OCC Brief at 36, citing Larkin-Connolly Surrebuttal at 5. The Company disagrees that regulatory lag is a feature as opposed to a defect. It is fair to ask whether the authors of Bluefield and Hope would agree. Bluefield held that rates insufficient to yield a reasonable return on the value of property “at the time it is being used to render the service” are unjust and unreasonable, and that the return should be adequate, under efficient and economical management, to maintain and support the utility’s credit. Bluefield, 262 U.S. at 690, 692–93. Hope likewise required a return sufficient to assure confidence in the financial integrity of the enterprise, so as to maintain its credit and attract capital. 150330368.4 -18-Page 22 of 44
Hope, 320 U.S. at 603. Neither decision treats a persistent gap between the investment serving customers and its recovery in rates as a design objective. The Company does not contend that every lag makes rates confiscatory; under Hope, the end result controls. Id. at 602. But lag cannot be embraced as a virtue without asking whether that end result meets these standards. OCC’s characterization does not establish economic symmetry. Necessary infrastructure investment and unavoidable input-price increases are not equivalent to costs management has failed to control, and the opportunity to achieve savings is not evidence that savings equal those obligations. The relevant question is whether the resulting rates afford an efficiently managed utility a realistic opportunity to recover supported service costs and earn a fair return—not whether lag can be described as part of the regulatory model. Here, investment continues as facilities age and water-quality, reliability, and security obligations evolve, while materials, labor, contracted services, and financing costs do not remain fixed with base rates. Successive additions and cost increases can therefore create a continuing mismatch rather than a temporary fluctuation that reverses before the next case. Efficiencies remain essential, but the shared-service, procurement, governance, and insurance savings already reflected in the Company’s presentation cannot also be assumed to provide an additional, unmeasured cushion for future obligations. OCC identifies an incentive to control costs; it does not quantify an offset sufficient to demonstrate the claimed symmetry. Company Initial Brief at 3–4, 16–20, 39–43, 47–48; Dixon Direct at 4–11. Later inclusion of an asset in rate base does not, by itself, reimburse the Company for revenue not recovered while the asset was already serving customers, absent an authorized mechanism providing that recovery. The Company does not seek a retroactive catch-up; it seeks prospective recognition of supported service-period costs so that the mismatch is not perpetuated. 150330368.4 -19-Page 23 of 44
WICA, WQTA, and other mechanisms materially mitigate specified risks and must be recognized, but they do not provide contemporaneous recovery of every investment or operating cost. The approximately 214-basis-point average earned-return shortfall over eleven years and 10.48% 2025 FFO/debt ratio warrant examination of the combined financial effect of the rate order, although neither proves the cause of every shortfall or the precise relief required. Company Initial Brief at 19–20, 24–26; Dixon Direct at 8, 11. “Advanced Recovery” Is Not Necessarily Recovery Before Service. OCC characterizes forecasted-plant recognition as advanced recovery because it occurs sooner than under its preferred historical cutoff. OCC Brief at 36–38. But recovery earlier than that cutoff methodology would permit is not necessarily recovery before customers receive service. Completed plant already serving customers presents one question; a forecast of later service presents another. The Company does not contend that a forecast makes an asset yet to be completed used and useful. Its initial brief proposes supported service dates, appropriate averaging or proration, verification of prudent actual costs, and reconciliation for delay or unsupported amounts. A defined process preserving meaningful review can align cost recognition with service rather than exclude all postcutoff additions regardless of when customers will use them. Company Initial Brief at 18–21; Dixon Rebuttal, Sections III.C–III.D. Timely Recovery Does Not Eliminate Cost Discipline. OCC’s concern that faster recognition may encourage excessive spending warrants substantive scrutiny, not a presumption that supported pro formas weaken controls. OCC acknowledges generally sound capital procedures and evidence that the sampled process operated; EOE reports competitive bidding covering 79% of spending reviewed while identifying specific change-order documentation concerns. OCC Brief at 16–25, 36–38; EOE Brief at 15–17. Those findings support targeted 150330368.4 -20-Page 24 of 44
improvements in authorization, procurement, and reporting. Under the Company’s proposed verification process, need, alternatives, scope, execution, approvals, actual costs, and service dates remain reviewable, with exposure to disallowance and customer credits where warranted. Timely recognition neither guarantees recovery of all spending nor removes those controls; delaying supported recovery is not a substitute for enforcing them. Company Initial Brief at 18–21. Affordability Must Be Sustainable. Deferring recognition of prudent investment already serving customers may reduce immediate bills, but it does not reduce the investment’s construction, financing, or operating costs. Persistent under-recovery can weaken cash flow and credit metrics and increase subsequent financing costs; it is not an operating efficiency. That does not mean every disallowance causes a downgrade, that future savings necessarily offset the requested increase, or that the Company is entitled to a guaranteed return. It means the Authority should assess immediate bill impacts together with the long-term cost of reliable service. Furthermore, a pattern of deferred recognition of prudent investment encourages under-investment in infrastructure, lowering quality while kicking the can to higher costs during infrastructure failures. Section 16-19e(a)(4) calls for sufficient, but no more than sufficient, rates; targeted assistance, gradualism, genuine efficiencies, and customer-protective reconciliation address affordability without assuming that necessary service can indefinitely be financed through unrecovered prudent costs. Company Initial Brief at 4–7, 12–13, 19–21, 24–30, 47–49; Dixon Direct at 6–11. C. OCC’s Proposed Exclusions Do Not Comport with Prudence, Used-andUseful, and Matching Principles OCC’s rate-base exclusions fall into three categories, each resting on a different premise. The first excludes completed 2026 plant because OCC finds the authorization records incomplete. The second excludes forecasted plant because it was not in service by OCC’s September 30, 2026 150330368.4 -21-
As listed on the current system