  1. Page 21 of 44

    final invoice-level support necessary to every prospective finding. The Company’s initial brief asks for that practical assessment, with later verification where needed, and not exemption from scrutiny. Company Initial Brief at 18–21; Dixon Rebuttal, Sections III.C–III.D. OCC’s plant objection primarily concerns Project Request and Change Request records, not simply unpaid or unavailable invoices. The Company does not conflate those issues. Its point is that both cost support and procedural compliance should be evaluated through the available evidence, proportionate to the issue being tested. For prospective projects, the Authority can distinguish approval of a supported estimate from final verification of prudent actual costs and service dates. The initial brief specifically proposes compliance filings, reconciliation of the associated revenue requirement, and customer credits for unsupported costs or delayed additions. Company Initial Brief at 20–21. Such a process must preserve a meaningful opportunity for review; it should not be treated as already established or as automatic approval of later spending. It is the Company’s proposed safeguard for resolving uncertainty without excluding supported Rate-Year investment categorically. B. Calling Regulatory Lag a “Feature” Does Not Establish Economic Symmetry OCC describes regulatory lag as a deliberate feature of traditional regulation: the utility retains savings between cases while bearing costs it fails to control. OCC Brief at 36, citing Larkin-Connolly Surrebuttal at 5. The Company disagrees that regulatory lag is a feature as opposed to a defect. It is fair to ask whether the authors of Bluefield and Hope would agree. Bluefield held that rates insufficient to yield a reasonable return on the value of property “at the time it is being used to render the service” are unjust and unreasonable, and that the return should be adequate, under efficient and economical management, to maintain and support the utility’s credit. Bluefield, 262 U.S. at 690, 692–93. Hope likewise required a return sufficient to assure confidence in the financial integrity of the enterprise, so as to maintain its credit and attract capital. 150330368.4 -18-
  2. Page 22 of 44

    Hope, 320 U.S. at 603. Neither decision treats a persistent gap between the investment serving customers and its recovery in rates as a design objective. The Company does not contend that every lag makes rates confiscatory; under Hope, the end result controls. Id. at 602. But lag cannot be embraced as a virtue without asking whether that end result meets these standards. OCC’s characterization does not establish economic symmetry. Necessary infrastructure investment and unavoidable input-price increases are not equivalent to costs management has failed to control, and the opportunity to achieve savings is not evidence that savings equal those obligations. The relevant question is whether the resulting rates afford an efficiently managed utility a realistic opportunity to recover supported service costs and earn a fair return—not whether lag can be described as part of the regulatory model. Here, investment continues as facilities age and water-quality, reliability, and security obligations evolve, while materials, labor, contracted services, and financing costs do not remain fixed with base rates. Successive additions and cost increases can therefore create a continuing mismatch rather than a temporary fluctuation that reverses before the next case. Efficiencies remain essential, but the shared-service, procurement, governance, and insurance savings already reflected in the Company’s presentation cannot also be assumed to provide an additional, unmeasured cushion for future obligations. OCC identifies an incentive to control costs; it does not quantify an offset sufficient to demonstrate the claimed symmetry. Company Initial Brief at 3–4, 16–20, 39–43, 47–48; Dixon Direct at 4–11. Later inclusion of an asset in rate base does not, by itself, reimburse the Company for revenue not recovered while the asset was already serving customers, absent an authorized mechanism providing that recovery. The Company does not seek a retroactive catch-up; it seeks prospective recognition of supported service-period costs so that the mismatch is not perpetuated. 150330368.4 -19-
  3. Page 23 of 44

    WICA, WQTA, and other mechanisms materially mitigate specified risks and must be recognized, but they do not provide contemporaneous recovery of every investment or operating cost. The approximately 214-basis-point average earned-return shortfall over eleven years and 10.48% 2025 FFO/debt ratio warrant examination of the combined financial effect of the rate order, although neither proves the cause of every shortfall or the precise relief required. Company Initial Brief at 19–20, 24–26; Dixon Direct at 8, 11. “Advanced Recovery” Is Not Necessarily Recovery Before Service. OCC characterizes forecasted-plant recognition as advanced recovery because it occurs sooner than under its preferred historical cutoff. OCC Brief at 36–38. But recovery earlier than that cutoff methodology would permit is not necessarily recovery before customers receive service. Completed plant already serving customers presents one question; a forecast of later service presents another. The Company does not contend that a forecast makes an asset yet to be completed used and useful. Its initial brief proposes supported service dates, appropriate averaging or proration, verification of prudent actual costs, and reconciliation for delay or unsupported amounts. A defined process preserving meaningful review can align cost recognition with service rather than exclude all postcutoff additions regardless of when customers will use them. Company Initial Brief at 18–21; Dixon Rebuttal, Sections III.C–III.D. Timely Recovery Does Not Eliminate Cost Discipline. OCC’s concern that faster recognition may encourage excessive spending warrants substantive scrutiny, not a presumption that supported pro formas weaken controls. OCC acknowledges generally sound capital procedures and evidence that the sampled process operated; EOE reports competitive bidding covering 79% of spending reviewed while identifying specific change-order documentation concerns. OCC Brief at 16–25, 36–38; EOE Brief at 15–17. Those findings support targeted 150330368.4 -20-
  4. Page 24 of 44

    improvements in authorization, procurement, and reporting. Under the Company’s proposed verification process, need, alternatives, scope, execution, approvals, actual costs, and service dates remain reviewable, with exposure to disallowance and customer credits where warranted. Timely recognition neither guarantees recovery of all spending nor removes those controls; delaying supported recovery is not a substitute for enforcing them. Company Initial Brief at 18–21. Affordability Must Be Sustainable. Deferring recognition of prudent investment already serving customers may reduce immediate bills, but it does not reduce the investment’s construction, financing, or operating costs. Persistent under-recovery can weaken cash flow and credit metrics and increase subsequent financing costs; it is not an operating efficiency. That does not mean every disallowance causes a downgrade, that future savings necessarily offset the requested increase, or that the Company is entitled to a guaranteed return. It means the Authority should assess immediate bill impacts together with the long-term cost of reliable service. Furthermore, a pattern of deferred recognition of prudent investment encourages under-investment in infrastructure, lowering quality while kicking the can to higher costs during infrastructure failures. Section 16-19e(a)(4) calls for sufficient, but no more than sufficient, rates; targeted assistance, gradualism, genuine efficiencies, and customer-protective reconciliation address affordability without assuming that necessary service can indefinitely be financed through unrecovered prudent costs. Company Initial Brief at 4–7, 12–13, 19–21, 24–30, 47–49; Dixon Direct at 6–11. C. OCC’s Proposed Exclusions Do Not Comport with Prudence, Used-andUseful, and Matching Principles OCC’s rate-base exclusions fall into three categories, each resting on a different premise. The first excludes completed 2026 plant because OCC finds the authorization records incomplete. The second excludes forecasted plant because it was not in service by OCC’s September 30, 2026 150330368.4 -21-
  5. Page 25 of 44

    cutoff. The third excludes Project Elevate for the same timing reason, although the CIS is a prepaid service contract rather than a plant addition. The table below groups the exclusions by category. The discussion that follows addresses the common flaw in each category rather than repeating the same response for every component. OCC’s Stated Basis Authorization records not produced or incomplete Category 1. Completed 2026 plant 2. Forecasted plant Not in service by September 30, 2026 Components Not on approved lists: $3,808.58 Zero approved budgets: $2,127,409.60 Substitutions: $253,955.43 Missing Change Requests: $15,333,793.23 October–December 2026: $9,036,905 Calendar year 2027: $37,031,182 Rate-Year average SaaS prepayment balance Gross Exclusion $17,718,966.84 $46,068,087 Net Rate-Base Reduction $16,863,424 $9,161,833 Related Annual Expense Reduction Depreciation: $434,150 Property tax: $82,807 Depreciation: $323,848 3. Project Not live by Not a plant $11,281,442 Amortization: Elevate (Oracle September 30, addition $1,237,300 CIS) 2026 Total $63,787,053.84 $37,306,699 $2,078,105 Source: OCC Brief at 27–45, Tables 3–9; OCC Brief Schedules 10–12. Gross amounts are project expenditures; net amounts reflect Rate-Year averaging, accumulated depreciation, and deferred taxes. The four projects in the “not on approved lists” component also appear among the zero-budget projects. 1. Completed Plant Excluded for Documentation Reasons— $17,718,966.84. All four components rest on the same premise: a budget list, a zero-budget entry, a substitutions report, or a missing Change Request form did not show the authorization OCC expected. None rests on a finding that the work was unnecessary, that the assets are not in service, or that a particular cost was unreasonable. These additions are complete and serving customers, so the used-and-useful test is not in dispute. The question is prudence. On that question, OCC identifies a gap in documentation, not an imprudent decision, and its remedy bears no relationship to the size of the gap: it excludes every dollar of each project’s 2026 additions. OCC Brief at 27– 150330368.4 -22-
  6. Page 26 of 44

    33. OCC’s Change Request analysis illustrates the point. It identifies spending above approved budgets, then excludes the full project rather than the increment it questions, explaining that a lesser adjustment would leave the Company “with no consequence” for bypassing the control. Id. at 33. A consequence is not a measure of imprudent cost. Excluding completed, customer-serving plant on that basis would also mismatch rates and service: customers would use these assets throughout the Rate Year while rates exclude their cost. The Company bears the burden of proof, and the Authority may exclude an amount the record does not support. But the finding should identify the unsupported amount and the reason for it. For the zero-budget projects, many of which are developer and billable service work, that means examining funding and contribution records as well as approval. For the two substitutions, it means assessing the projects’ own records rather than relying on the general caveat that the substitutions column may include unapproved entries. For the Change Request projects, it means evaluating the reasons for the changes and the portion of spending that remains unsupported, treating the original budget as neither a guarantee nor a ceiling. Two reconciliation items also bear on any adjustment. The four projects absent from approved lists also appear among OCC’s zerobudget projects. And OCC’s Gallup Centralized WTP entry reports 2026 additions of $4,024,749.78, more than its displayed cumulative 2023–2026 additions of $3,770,495.54. OCC Brief at 28–33, Tables 4–7. 2. Forecasted Plant Excluded by the Evidentiary Cutoff—$46,068,087. OCC excludes all additions forecast for October 2026 through December 2027 because they were not complete by September 30, 2026. OCC Brief at 34–39. OCC did not find these projects imprudent; its witness testified that he had made no prudence judgment about them. Sept. 25 Tr. 96. The exclusion rests entirely on timing. The Company recognizes the Authority’s recent decisions excluding forecasted plant and does not contend that a forecast makes incomplete plant 150330368.4 -23-
  7. Page 27 of 44

    used and useful. But a uniform cutoff treats plant expected in service before the February 1, 2027 start of the Rate Year the same as plant expected late in 2027. It also denies any recognition for the part of the Rate Year in which customers will actually use the plant. Matching calls for servicecontingent recognition instead: supported in-service dates, averaging or proration so that no return or depreciation is recovered before service, verification of prudent actual costs, and credits for delays or unsupported amounts. Company Initial Brief at 18–21; Dixon Rebuttal, Section III.C. Initial carbon media for the Hopkins and Egypt Road facilities should follow the same approach without duplicating O&M or WQTA recovery, and depreciation reserves and deferred taxes must follow the same service-period methodology. Dixon Rebuttal at 19; LFE-26. CWC recognizes that the Authority has excluded forecasted plant in recent water cases, including the Company’s last rate case. Docket No. 23-08-32, Decision (June 28, 2024) at 18; OCC Brief at 33–34. Those rulings, however, are not wholly consistent with the Authority’s treatment of future investment across the utility sectors it regulates. In Docket No. 17-10-46, the Authority approved a settlement, to which OCC was a party, that set CL&P’s base rates for three rate years beginning May 1, 2018, with step increases in the second and third years. The settlement also created an electric system improvement tracker allowing recovery of core capital spending above a specified annual level without waiting for the next rate case. Docket No. 17-10-46, Decision (Apr. 18, 2018). The Authority likewise approved a multi-year rate plan for UI in Docket No. 16-06-04 and has approved other multi-year arrangements with forward-looking step increases over the last two decades. Each of these plans set rates for future periods based on projected investment and costs, rather than limiting recovery to plant in service when the evidentiary record closed. The Company does not contend that these decisions bind the Authority here, or that settled outcomes are precedent for litigated issues. But they do show that recognizing forecasted 150330368.4 -24-
  8. Page 28 of 44

    investment is not inherently inconsistent with Connecticut ratemaking or with protecting customers. The real question is whether adequate safeguards exist. The service-contingent recognition, verification, and reconciliation the Company proposes would protect customers at least as well as step increases fixed in advance. 3. Project Elevate Excluded by the Same Cutoff—$11,281,442 Rate Base and $1,237,300 Annual Amortization. OCC does not challenge the decision to replace the CIS. On the contrary, the record documents both the deficiencies of the existing system and what the new system will provide. The current CIS was last substantially upgraded in 2009 and has inherent limitations. Williams Direct at 31. For example, it cannot automatically stop the WRAP discount when a customer exceeds the usage cap, so usage is reviewed only at biennial re-verification. EOE-37; EOE-71; EOE Brief at 1. It also cannot track cancelled or rescheduled service appointments. EOE-163. The new system will apply the WRAP usage cap automatically on the billing cycle, support annual recertification, and track service appointments. Oct. 1 Tr. 94:10–16, 96:21–97:1; EOE-210; Williams Direct at 30–31. It will also support accurate billing, account and data management, work-order scheduling, and rate and regulatory programs, improve cybersecurity, and prepare the Company for AMI metering. OCC-205; Dixon Rebuttal, Section III.D. Indeed, OCC and EOE both ask the Authority to order WRAP changes that depend on the new system. OCC Brief at 76–78; EOE Brief at 1–5. Instead, OCC’s objection is that the system was not live by the cutoff and that its final cost is not yet known. OCC Brief at 39–41. Unlike most forecasted plant, however, the record documents the system’s progress: an executed managed-services agreement, a reconciliation of the $12,373,000 implementation estimate, completed cutover rehearsals, and a launch date advanced to January 18, 2027, before the Rate Year begins. RRU-227(a)–(d); Company Initial Brief at 20–21. Excluding the system for the entire Rate Year would leave customers served by a 150330368.4 -25-
  9. Page 29 of 44

    billing, customer-service, and field-service platform whose cost is absent from rates. Recovery should instead be conditioned on confirmed go-live, prudent actual cost, appropriate amortization, and retirement of the legacy system. Sept. 22 Tr. 38–39; Dixon Rebuttal, Section III.D. In short, the project has been reviewed in this proceeding, its benefits are documented and unrefuted, and it remains on schedule to be in service when new rates take effect on February 1, 2027. RRU227(d). OCC could have recommended approval subject to confirmation of go-live and final cost. Instead, it recommends disallowing the entire project based solely on when the evidentiary record closed. That recommendation rests on no finding about the project’s need, benefits, or cost. Its only effect is to lower rates by removing the cost of a system customers will use throughout the Rate Year. The approach mirrors OCC’s treatment of other issues in this case, where it applies a cutoff date, a missing form, or a historical average whenever doing so reduces the revenue requirement, while setting aside record evidence that supports the Company’s costs. See Sections III.C.1–2 and IV.B, above and below. In each category, the Authority should match the remedy to the evidence. It should identify any unsupported amount, distinguish insufficient proof from an affirmative finding of imprudence, and recognize supported investment for the period it serves customers, subject to the verification and reconciliation safeguards in the Company’s initial brief. Related depreciation, property-tax, deferred-tax, and working-capital effects should follow the final determinations. Company Initial Brief at 18–23; OCC Brief at 44–45; OCC Brief Schedules 5 and 10–12. IV. OPERATING EXPENSES AND SHARED-BENEFIT COSTS A. OCC’s Expense Adjustments Grouped by Methodology OCC proposes 21 separate reductions to Rate-Year O&M expense, totaling $5,235,328 excluding the CIS amortization addressed in Section III. OCC Brief at 56–74; Brief Schedules 13–36. Although OCC presents them item by item, the adjustments rest on a handful of recurring 150330368.4 -26-
  10. Page 30 of 44

    rationales: historical averages substituted for Rate-Year costs, shareholder-benefit allocations, categorical exclusions for lack of a quantified benefit, and calculations that flow mechanically from other adjustments. The table below groups the adjustments by rationale. The discussion that follows responds to each group once rather than repeating the same response for every item. Group 1. Total target compensation 2. Shared-benefit allocations 3. Inflation 4. Purchased power 5. Flow-through calculations 6. Rate case expense OCC’s Rationale Historical averages and point-in-time counts replace Rate-Year staffing; 20% of incentive pay excluded for financial metrics Costs labeled as primarily benefiting shareholders; full or 75% disallowance No escalation of residual costs Substituted supply and delivery rates Derived from Group 1; methodology not disputed 7. Statutory categories Conn. Gen. Stat. § 16243p(b); 65-month amortization Conn. Gen. Stat. § 16-243gg 8. Benefit not quantified Exclude for lack of a measured ratepayer benefit Resolved Resolved during the proceeding Adjustments Vacancy allowance: $899,882 Overtime: $467,386 Open positions: $308,930 Short-term incentive: $243,790 Long-term incentive: $226,157 Corporate (“shareholder”) expenses: $874,106 Board of Directors fees: $396,486 Executive liability (D&O) insurance: $106,628 Residual O&M inflation: $509,435 Purchased power: $286,401 Total $2,146,145 Medical and dental: $269,558 Payroll taxes: $119,559 401(k): $109,416 Variable pay increase: $11,974 Rate case expense: $240,819 $510,507 Investor relations: $50,616 Entertainment: $33,778 Corporate gifts: $29,167 Employee wellness: $31,007 Non-industry dues: $18,524 Economic development: $1,709 Industry dues; bad debt; recurring carbon-filter O&M $113,561 $1,377,220 $509,435 $286,401 $240,819 $51,240 — Total $5,235,328 Source: OCC Brief at 56–74; OCC Brief Schedules 13–36. Excludes the $1,237,300 CIS amortization addressed in Section III. Interest synchronization affects income taxes rather than O&M and is addressed with Group 5. B. Responses by Group 1. Total Target Compensation—$2,146,145. OCC’s largest group of adjustments reduces the Company’s total target compensation through five separate adjustments. It raises the vacancy allowance from 10 to 21 positions ($899,882), removes 4.25 open positions ($308,930), replaces Rate-Year overtime with a 2023– 150330368.4 -27-