Page 85 of 151
Docket No. 060038-E1 Date: May 8, 2006 Issue 58: Is FPL’s process for determining whether the upfront bond issuance costs satisfy the statutory standard of Section 366.8260(2)(b)5., Florida Statutes, reasonable and should it be approved? Recommendation: No. The Commission should not predetermine that upfront bond issuance costs resulting from a competitive solicitation, or within a certain range of estimates, meets the statutory standard of Section 366.8260(2)(b)5., Florida Statutes. Accordingly, FPL’s proposed process should not be approved. (Maurey) Position of the Parties OPC: FPL: Yes, for the reasons explained with respect to Issue 56 above. No. The process outlined by FPL in its petition, proposed order, and testimony, does not allow the active participation of the Commission. FPL’s process does not afford independent protection for the ratepayers to ensure that the up-front costs, on-going costs, and interest rates achieve the lowest overall cost based on real time market conditions. Therefore, FPL’s proposed process is not reasonable and should not be approved. FIPUG: Adopts the position of OPC. FRF: - No. Because the process proposed by FPL in its filings does not provide for the active participation of the Commission, FPL’s process does not afford adequate, independent protection for its customers with regard to up-front costs, issuance costs, ongoing costs, and interest rates. Accordingly, FPL’s proposed process should not be approved. AARP: The same as the Office of Public Counsel. AG: Agree with OPC. FEA: Adopts and agrees with the position set forth by OPC. Staff Analysis: The proposed process for determining whether the estimated upfront bond issuance costs satisfy the statutory standard articulated in FPL’s position in Issue 56 is not reasonable and should not be approved. Contrary to FPL’s position, a standard of documented expenditures falling within a range of estimates is not the standard articulated in Section 366.8260(2)(b)5., Florida Statutes. Moreover, a predetermination of reasonableness by the Commission would not provide the appropriate incentive to FPL to attain the lowest upfront bond issuance costs. (Fichera TR 1199-1202,1205-1207,1213-1215) The Commission should not predetermine that upfront bond issuance costs resulting from a competitive solicitation, or within a certain range of estimates, meet the “lowest cost” standard of Section 366.8260(2)(b)5., Florida Statutes. Whether a competitive solicitation results in the lowest cost depends on how the solicitation is conducted and how negotiations that result from the solicitation are conducted. (Fichera TR 1175-1 180) That determination can best be made through active oversight of the proposed transaction as discussed in Issue 74B. (Klein TR 1233- - 175 -Page 86 of 151
Docket No. 060038-E1 Date: May 8,2006 1236; Noel TR 1120-1123; Fichera TR 1185-1190; Olson TR 1480-1482) In addition, as discussed in more detail in Issue 65, FPL should be required to demonstrate in the issuance advice letter that its competitive solicitation and negotiation process resulted in a package of fees and services that will result in the lowest cost consistent with prevailing market conditions and the terms of the financing order. In conclusion, there is no statutory standard or requirement the Commission predetermine that FPL’s upfiont issuance costs resulting from a competitive solicitation, or within a certain range of estimates, are reasonable. Accordingly, FPL’s proposed process for seeking Commission approval of its estimated upfront bond issuance costs is unnecessary and should not be approved. - 176 -Page 87 of 151
Docket No. 060038-E1 Date: May 8, 2006 Issue 59: Is FPL’s process for determining whether the on-going costs satisfy the statutory standard of Section 366.8260(2)(b)5. reasonable and should it be approved? Recommendation: No. FPL’s proposed process for determining whether the estimated ongoing costs associated with the issuance of the storm recovery bonds satisfy the statutory standard is inconsistent with the express language of Section 366.8260(2)(b)5., Florida Statutes, and should not be approved. (Maurey) Position of the Parties FPL: While the standard set in Section 366.8260(2)(b)5 does not apply to ongoing costs, FPL’s testimony and exhibits provide support for the conclusion that FPL’s estimated ongoing financing costs will be reasonable, and that they are consistent with similar rate reduction bond transactions. OPC: No. The process outlined by FPL in its petition, proposed order, and testimony, does not allow the active participation of the Commission. FPL’s process does not afford independent protection for the ratepayers to ensure the up-front costs, on-going costs, and interest rates achieve the lowest overall cost based on real time market conditions. Therefore, FPL’s proposed process is not reasonable and should not be approved. FIPUG: Adopts the position of OPC. FRF: No. Because the process proposed by FPL in its filings does not provide for the active participation of the Commission, FPL‘s process does not afford adequate, independent protection for its customers with regard to up-front costs, issuance costs, ongoing costs, and interest rates. Accordingly, FPL’s proposed process should not be approved. AARP: The same as the Office of Public Counsel. FEA: AG: Agree with OPC. Adopts and agrees with the position set forth by OPC. Staff Analysis: As discussed in Issues 56, 57, and 58, Section 366.8260(2)(b)5., Florida Statutes, explains the statutory requirement regarding Commission review of “the actual costs of the storm recovery bond issuance.” This Section of the statute draws no distinction between upfront costs and on-going costs associated with the issuance of the storm recovery bonds. Moreover, there is no statutory standard requiring the Commission to pre-approve the estimated on-going costs associated with the issuance of the storm recovery bonds as requested by FPL. Approximately 75% of the estimated on-going fees are comprised of the servicing fee (discussed in Issue 50) and the administration fee (discussed in Issue 52). (EXH 8; EXH 171, pp. 40-43) A determination by the Commission whether on-going costs associated with the issuance of the storm recovery bonds are reasonable can best be made through active oversight of the proposed transaction as discussed in Issue 74B. (Klein TR 1233-1236; Noel TR 1120-1123; - 177 -Page 88 of 151
Docket No. 060038-E1 Date: May 8, 2006 Fichera TR 1185-1 190; Olson TR 1480-1482) The statutory requirement is for Commission review of actual costs, not for Commission approval of estimated costs. Since there is no statutory standard or requirement that the Commission predetennine that FPL’s estimated ongoing costs associated with the storm recovery bonds are reasonable, FPL’s proposed process for seeking Commission approval of these costs is unnecessary and should not be approved. - 178 -Page 89 of 151
Docket No. 060038-E1 Date: May 8,2006 Issue 60: If the issuance of storm recovery bonds is approved, should the bonds be sold through a negotiated or competitive sale? Recommendation: It is premature for the Commission to make this decision at this time. Both methods for the sale of storm recovery bonds should be considered to determine the most cost effective means of issuing the bonds based on prevailing market conditions near the time of issuance. However, based on the particular characteristics of these types of bonds and the method that has been used in previous transactions, both FPL and the Commission’s financial advisor believe a negotiated sale will likely be preferable. (Springer) Position of the Parties FPL: Normally an assessment of whether bonds should be sold through a competitive bidding process or a negotiated sale would be made near the time of issuance based on factors such as issue size, complexity of issue, and current market conditions. Given the size of this offering, the risk premium that underwriters would require in a competitive bidding process would likely be greater than the underwriting fee in a negotiated sale. Therefore, a negotiated sale likely is preferable under the circumstances. OPC: The methodology that is employed should be that which produces the lowest overall cost based on real time market conditions. FIPUG: Adopts the position of OPC. FRF: - The sale method that produces the lowest overall cost based on real-time market conditions should be the method that is used to determine allowable costs. If the Commission allows FPL the discretion, after the Commission issues its order in this case, to decide which sale mechanism to use, then any such decisions by FPL must be subject to further prudency review, in subsequent proceedings in which all substantially affected parties have a point of entry. AARP: No position at this time. FEA: - Agree with FIPUG. E: Adopts and agrees with the position set forth by OPC. Staff Analysis: PARTIES’ ARGUMENTS FPL proposes that a negotiated sale is preferable based on the fee for a higher risk premium that underwriters would require for a competitive sale compared to a lower underwriting fee for a negotiated sale. However, FPL proposes that this decision be made near the time of issuance based on factors such as issue size, complexity of issue, and current market The intervenors posit that the methodology employed should be that which conditions. produces the lowest overall cost based on real time market conditions. FRF proposes that if the - 179-Page 90 of 151
Docket No. 060038-E1 Date: May 8, 2006 Commission grants FPL the flexibility to choose the methodology, that FPL should be subject to a prudency review in which all affected parties have a point of entry. ANALYSIS FPL Witness Dewhurst testified that “the decision as to which method may be preferable is dependent on factors such as issue size, complexity of issue, and current market conditions, some of which are not known with certainty.” (TR 76) FPL asserts that, given the size of this offering, underwriters would likely require a higher risk premium for a competitive sale as compared to the fee for a negotiated sale, thus a negotiated sale would be preferable. (FPL BR at 138) OPC states that the parties should be given some flexibility to choose the methodology that will result in the lowest overall costs to ratepayers based on market conditions, but that this flexibility is predicated on the Commission adopting the “best practices’’ standard and being active in the transaction. (OPC BR at 99) In his testimony, witness Noel states that all options should be evaluated, but that this issue should probably be sold through a negotiated offering. (TR 1117-1118) This is based on witness Noel’s evaluation that investor education is needed to inform investors of the unique characteristics of Florida’s first securitization issuance, the first issuance of storm recovery bonds, the effectiveness of the state’s pledge of safety, and the applicability of the true-up mechanism. (TR 1118) CONCLUSION Staff believes it is premature for the Commission to decide the manner in which the storm recovery bonds should be sold. Staff recommends both methods, competitive or negotiated sale, should be considered to determine the most cost effective means of issuing the bonds based on prevailing market conditions. - 180 -Page 91 of 151
Docket No. 060038-E1 Date: May 8, 2006 Issue 61 : What additional terms, conditions or representations should be made in the financing order to enhance the marketability of the bonds and achieve the lowest possible cost? Recommendation: The financing order should include ordering paragraphs, findings of fact, and conclusions of law that will give appropriate comfort to investors about the high quality of storm recovery bonds as a potential investment. Examples include: 1. A finding that the Commission anticipates stress case analyses will show that the broad nature of the State pledge under Section 366.8260( 1l), Florida Statutes, and the automatic true-up mechanism under Section 366.8260(2)(b)2.e. and 4., Florida Statutes, will serve to effectively eliminate for all practical purposes and circumstances all credit risk associated with the storm recovery bonds; 2. A finding and an ordering paragraph directing that the automatic true-up mechanism is to be applied at least semi-annually, as discussed in Issue 83; 3. A finding and an ordering paragraph that the automatic true-up mechanism will be implemented within 60-days after a filing by the servicer, as discussed in Issue 82; 4. A finding and conclusion of law that the broad nature of the State pledge under Section 366.8260( 1l), Florida Statutes, and the automatic true-up mechanism under Section 366.8260(2)(b)2.e. and 4., Florida Statutes, constitute a guarantee of regulatory action for the benefit of investors in storm recovery bonds; 5. A conclusion of law that any interest rate swap counterparty is to be treated as a “financing party” for purposes of Section 366.8260( l)(g), Florida Statutes; 6. A conclusion of law that storm recovery property is not a receivable under Section 366.8260(5)(a)l., Florida Statutes; 7. An ordering paragraph directing that partial payments shall be allocated first to storm recovery charges, including past due storm recovery payments; 8. A conclusion of law that the Commission’s obligation under the financing order relating to storm recovery bonds, including the specific actions the Commission guarantees to take, are direct, explicit, irrevocable, and unconditional upon the issuance of storm recovery bonds, and are legally enforceable against the Commission, a United States public sector entity; and 9. A conclusion of law and an ordering paragraph that the financing order is irrevocable under Section 366.8260(2)(b)4. and (1 l), Florida Statutes. In addition, the financing order should require fully accountable certifications from the lead undenvriter(s), FPL, and the Commission’s financial advisor that the actual structure, marketing, and pricing of the storm recovery bonds in fact resulted in the lowest storm recovery charges consistent with then-prevailing market conditions and the terms of the financing order and other applicable law. (Maurey) - 181 -Page 92 of 151
Docket No. 060038-E1 Date: May 8,2006 Position of the Parties FPL: No additional terms, conditions or representations are necessary. The utility asset-backed bond market is mature and highly liquid, and trading spreads are extremely tight. Issuing a financing order in substantially the form submitted by FPL will enable an efficient, low cost transaction. If the Commission wishes particular statements regarding the quality of the securities to be included in the offering documents, such statements should be included in the financing order as findings of fact or conclusions of law. OPC: To enhance marketability of the bonds and to achieve the lowest overall cost to ratepayers, the “best practices” outlined in witness Fichera’s testimony should be adopted. In addition, the bonds should be marketed broadly with active education regarding the nature of the bond issuance. FIPUG: Staff witnesses have recommended criteria that will result in greater marketability and lower costs, these recommendations should be adopted, except the bonds cannot pledge the full faith and credit of the state or any local government. FRF: - The financing order should prescribe the ratepayer protections described in Staff witness Fichera’s testimony, especially the provisions by which the Commission would be actively involved at all times and in all stages of the structuring, marketing, and pricing of the storm-recovery bonds. AARP : No position at this time. FEA: Agree with FIPUG. E: Adopts and agrees with the position set forth by OPC. Staff Analysis: The Commission is being asked to use its regulatory authority in a way that has never been previously done in Florida. (Fichera TR 1198) To achieve the maximum benefits of the storm recovery financing under Section 366.8260, Florida Statutes, and to minimize the financial burden on ratepayers, FPL should include an accurate and complete description of the credit risk of this investment in the marketing materials and offering documents. (Noel TR 11261127) The storm recovery bonds that will be issued for the recovery of reasonable and prudently incurred storm damage restoration costs and the replenishment of the storm damage reserve that are the subject of this proceeding are very different from the typical bonds issued by FPL. (TR 1120) The Commission is being asked to forego future regulatory oversight in order to create a financing instrument of superior quality and a completely separate credit from the sponsoring utility. (TR 1198) Section 366.8260, Florida Statutes, requires the Commission to issue an irrevocable financing order in which the sponsoring utility is insulated from any and all costs associated with the financing. (Klein TR 1229) The Commission is also required to approve a true-up mechanism that commits the Commission to periodically adjust the storm recovery charge that supports the storm recovery bonds to whatever level is necessary to pay the bonds’ - 182-Page 93 of 151
Docket No. 060038-E1 Date: May 8,2006 principal and interest on time. (TR 1230) In addition, the State and the Commission are required to pledge to the bondholders never to take or permit any action to be taken that would interfere with their right to payment. The irrevocable nature of the financing order, the direct broad-based storm charge applied to all FPL ratepayers, the unconditional Commission guarantee to adjust the storm charge as necessary, and the explicit pledge of the State not to interfere with the bondholders’ rights to repayment result in an incredibly strong credit independent of FPL. (TR 1159) Another difference between typical FPL bonds and storm recovery bonds is the degree of Commission oversight after the issuance. In typical utility debt financings the Commission retains the right to disallow any costs for ratemaking purposes, including adjustments for the interest rate. For the proposed issuance of storm recovery bonds, while the issuance costs are subject to review under Section 366.8260(2)(b)5., Florida Statutes, FPL argues that the interest rate on the bonds is not an issuance cost and is not subject to Commission review. (EXH 4, p. 445) Without conceding to FPL’s interpretation of Section 366.8260(2)(b)5 ., Florida Statutes, regarding whether Commission review extends to the interest rate, the statute does state “the Commission may not make adjustments to the storm recovery charges for any such excess issuance costs.” The final difference between typical utility bonds and storm recovery bonds is how these bonds impact the Company’s financial position. In more typical debt offerings, FPL has a strong incentive to negotiate hard with underwriters for the lowest possible interest rates as well as the lowest possible underwriting fees. FPL also has a strong incentive to minimize other issuance costs. Between rate cases, the benefit from a low net cost of fimds is enjoyed at least in part by FPL’s shareholders and the detriment from a high net cost of funds is borne at least in part by these same shareholders. These same checks and balances do not exist for the issuance of storm recovery bonds. (TR 1120) While typical utility bonds directly impact FPL’s financial ratios, storm recovery bonds are not direct obligations of FPL and are non-recourse to FPL. (TR 11471149) Storm recovery bonds will not be recognized in the determination of FPL’s debt coverage or other financial ratios. For these reasons, the same incentives and consequences for pursuing a lowest cost of funds with regard to FPL’s typical utility bonds are not present with respect to the proposed storm recovery bonds. (TR 1120) Unless the superior credit quality of these bonds is accurately reflected in the marketing materials, the storm recovery bonds will not achieve the lowest cost of funds. (TR 1126-1 127) While FPL concedes that attaining low total cost, including both upfront and on-going issuance costs, is the single most important objective in judging the success of a securitization issuance, the Company does not agree that a lowest cost standard under prevailing market conditions and consistent with the terms of the financing order is a necessary or permissible standard to apply to the proposed issuance of storm recovery bonds. (Dewhurst TR 1684-1686) FPL argues that the Commission should not impose a lowest cost of funds standard in this docket because the Legislature considered and rejected such a standard. FPL states that an early House version of the securitization law included language that explicitly provided a lowest cost of funds standard,14 but that this language was removed in a subsequent House ver~ion,’~ l 4 Committee Substitute 1 for House Bill 303, p. 11 of 32. (EXH 133) Committee Substitute 2 for House Bill 303, p. 10 of 31. (EXH 134) - 183 -Page 94 of 151
Docket No. 060038-E1 Date: May 8,2006 was not present in the Senate’s companion bill (SB 1366), and did not survive the legislative process. (FPL BR at 142-143) Citing Section 366.8260(2)(b)2.b., Florida Statutes, FPL asserts that the Legislature instead chose to impose a standard requiring the Commission to “[dletermine that the proposed structuring, expected pricing, and financing costs of the storm-recovery bonds are reasonably expected to result in lower overall costs or would avoid or significantly mitigate rate impacts to customers . . ..” FPL claims that a lowest cost of funds standard is inconsistent with this standard, thus it cannot be adopted by the Commission. Section 366.8260(2)(b)2.a.-j., Florida Statutes, sets forth the matters that the Commission is required to address in a financing order issued to an electric utility. Subparagraph g. of this section provides that the Commission, in its financing order, shall “[slpecify the degree of flexibility to be afforded to the electric utility in establishing the terms and conditions of the storm-recovery bonds, including, but not limited to, repayment schedules, interest rates, and other financing costs.” (Emphasis added.) Further, subparagraph j. of this section provides that the Commission shall include in its financing order “any other conditions that the commission considers appropriate and that are not otherwise inconsistent with this section.” These provisions clearly provide the Commission with the authority to establish and apply a lowest cost of funds standard with respect to the issuance of storm-recovery bonds. Contrary to FPL’s arguments, adopting a lowest cost of funds standard as a condition to the financing order is entirely consistent with the law. First, FPL has mistakenly identified the standard for reviewing the costs of this type of transaction. FPL suggests that the standard is whether the proposed structuring, expected pricing, and financing costs of the storm-recovery bonds are reasonably expected to result in lower overall costs or would avoid or significantly mitigate rate impacts to customers. This is not the standard for reviewing the costs of the transaction; rather, it is the standard by which the Commission must determine whether to issue a financing order at a11.16 Notably, in the early House Bill cited by FPL, the standard asserted by FPL appears just prior to the “lowest cost” language FPL claims was rejected by the Legislature. (EXH 133) Accepting FPL’s assertion, the early House Bill would have been at odds with itself because it would have included two different standards, side-by-side, for reviewing the same thing - cost of funds.17 Clearly, as demonstrated by the early House Bill, there can be a standard for judging cost of funds that is different fi-om, but not inconsistent with, the standard for determining whether to issue a financing order at all. 16 See Section 366.8260(2)(b)l .b., Florida Statutes, which provides that “[tlhe commission shall issue a financing order authorizing financing of reasonable and prudent storm-recovery costs, the storm-recovery reserve amount determined appropriate by the commission , and financing costs if the commission finds that the issuance of stormrecovery bonds and the imposition of storm-recovery charges authorized by the order are reasonably expected to result in lower overall costs or would avoid or significantly mitigate rate impacts to customers as compared with alternative methods of financing or recovering storm-recovery costs and storm-recovery reserve.” (Emphasis added.) ” Further, staff believes that the standard cited by FPL cannot be applied to cost of finds. FPL would have the Commission judge the cost of funds on the basis of whether the cost achieved is reasonably expected to result in lower overall costs, whch leaves the obvious question: Lower than what? Or under FPL’s analysis, the Commission could judge the cost of funds on the basis of whether the cost achieved is reasonably expected to mitigate rate impacts to customers, which again leaves the question: Mitigated as compared to what? These criteria are clearly at issue in determining whether to approve a financing order versus a more traditional surcharge, but cannot be applied with any meaning in judging cost of fimds. - 184 -