    Docket No. 060038-E1 Date: May 8,2006 To enhance the marketability of the storm-recovery bonds, the Commission should find that the investor protections established through the above provisions - the irrevocable nature of the financing order, the broad nature of the state pledge, the required ongoing application of the true-up mechanism, and the required imposition of non-bypassable charges - constitute a guarantee of regulatory action for the benefit of investors in storm recovery bonds. (Fichera TR 1153-1 154) It is clear under the securitization law that such a guarantee does not make the state or the Commission liable in any way for repayment of the bonds. As noted in Section 366.8260(9), Florida Statutes, all storm-recovery bonds must provide a statement on their face to the effect that “Neither the full faith and credit nor the taxing power of the State of Florida is pledged to the payment of principal of, or interest on, this bond.”27 In addition, based on the statutory provisions discussed above, the Commission should find that its obligations under the financing order relating to the storm recovery bonds, including the specific actions the Commission guarantees to take (Le., implementation of the true-up mechanism and adherence to the state pledge), are direct, explicit, irrevocable, and unconditional upon the issuance of storm recovery bonds, and are legally enforceable against the Commission, a United States public sector entity. This finding will enhance the marketability of the bonds and help achieve the lowest possible cost by qualifying the bonds for a 20% risk weighting. A 20% risk weighting can help expand the market for these bonds to an international level, in turn increasing competition and lowering cost. (Fichera TR 1172; EXH 94) In making this finding, the Commission would not be guaranteeing repayment; as noted above, the securitization law makes clear that neither the state nor the Commission shall be liable in any way, directly or indirectly, for repayment of the bonds other than in the state’s capacity as a purchaser of electricity delivered by FPL. Rather, the Commission would find that its obligations under the Securitization law are legally enforceable against it, but to no greater extent than those obligations would be legally enforceable absent a separate finding. Finally, the financing order should require fully accountable certifications from the lead undenvriter(s), FPL, and the Commission’s financial advisor that the actual structure, marketing, and pricing of the storm recovery bonds in fact resulted in the lowest storm recovery charges consistent with then-prevailing market conditions and the terms of the financing order and other applicable law. If the Commission determines that all required certifications have been delivered and that the transaction complies with the financing order and other applicable law, the transaction would proceed without any further Commission action, as discussed in Issue 74B. Staff believes that if the transaction proceeds on these terms, any costs, including interest, addressed in the lowest cost certifications likely would not need further review in the postissuance review under Section 366.8260(2)(b)5., Florida Statutes. 27 Section 366.8260(9), Florida Statutes. - 188 -
  2. Page 99 of 151

    Docket No. 060038-E1 Date: May 8,2006 Issue 62: Should all legal opinions and other transaction documents and subsequent amendments be filed and approved by the Commission before becoming operative? Recommendation: All transaction documents and subsequent amendments should be reviewed and approved by the Bond Team as discussed in Issue 74B before becoming operative. All legal opinions associated with the proposed storm recovery bond transaction should be submitted to the Commission automatically without requiring the Commission to specifically request the documents. (Keating, Maurey) Position of the Parties FPL: - Documents submitted with the Petition include a Storm-Recovery Property Sale Agreement, Administration Agreement, and Storm-Recovery Property Servicing Agreement, Indentures, and Limited Liability Company Agreement. The substance of the agreements should be approved in connection the financing order, subject to changes as part of the Commission Pre-Issuance Review Process. The agreements themselves require Commission approval of amendments. Forms of legal opinions should be delivered for review as requested by the Commission, but should not be subject to Commission approval. OPC: Yes. FIPUG: Adopts the position of OPC. FRF: - Yes. AARP: The same as the Office of Public Counsel. FEA: Agree with OPC. AG: Adopts and agrees with the position set forth by OPC. Staff Analysis: While it is reasonable to approve the general concept that certain legal opinions and other transaction documents will be necessary elements of the proposed transaction, the specific terms, conditions, covenants, warranties, representations, and specific language contained in the documents will be impacted by the Commission’s decisions on other issues and must be reviewed in consideration of the financing order approved by the Commission. The transaction documents that are the subject of this issue will have a meaningful impact on the structure, marketing, and pricing of the storm recovery bonds. (Fichera TR 1189-1 190) The majority of the documents submitted to date for consideration in this proceeding are simply shells or templates of the actual documents. (EXH 33-39) In some cases, there is no substantive information for the Commission to actually consider and approve. (Appendices A and B to Exhibit B of FPL’s petition) In other cases, the draft financing order as an example, staff will recommend the Commission make certain additions, deletions, and modifications before the documents become operative. (See discussion in Issues 61 and 74B) For these reasons, staff recommends that all transaction documents and any subsequent amendments be reviewed by the Bond Team and be approved before any of the documents become operative. (TR 1187-1 190) - 189-
  3. Page 100 of 151

    Docket No. 060038-E1 Date: May 8,2006 With respect to legal opinions regarding the storm recovery bond transaction, staff recommends the Commission require FPL to submit these opinions automatically to staff without the need for the Commission or its staff to specifically request the documents. (FPL BR at 146) In addition, as part of the review process discussed in Issue 74B, it is recommended that FPL and the Commission (the Bond Team) employ a competitive process in selecting, among equally qualified firms, the various law firms that will ultimately be required for the documentation, marketing, and execution of the proposed financing. (EXH 132, p. 2 ) Finally, FPL attempts to distinguish legal opinions from other transaction documents and says such opinions do not require Commission approval. (FPL BR at 147) Staff does not agree with FPL on this point. Staff recommends that any transaction documents or legal opinions that will have an impact on the structure, marketing, and pricing of the storm recovery bonds be reviewed and approved by the Bond Team before becoming operative as discussed in Issue 74B. - 190-
  4. Page 101 of 151

    Docket No. 060038-E1 Date: May 8,2006 Issue 65: Should the Issuance Advice Letter be approved in substantially the form proposed by FPL? Recommendation: No. The draft issuance advice letter in the form proposed by FPL does not provide sufficient detail for the Commission to make an informed decision regarding the proposed storm recovery bond issuance. (Maurey) Position of the Parties FPL: - Yes. The draft issuance advice letter will provide the most current and up-to-date information concerning the final terms and conditions that only becomes available as the launch date for a bond series becomes very near. OPC: - No position. FIPUG: FIPUG supports the testimony of Staff witness Fichera. FRF: No position. AARP: No position. Agree with FIPUG. E: Adopts and agrees with the position set forth by OPC. Staff Analysis: FPL has proposed filing a draft issuance advice letter at least five days prior to the expected launch date for the sale of the storm recovery bonds. (Olson TR 683) The draft issuance advice letter proposed by FPL will reflect the preliminary bond structuring information for the proposed issuance, the expected and final maturities, over-collateralization levels, any other credit enhancements, and revised estimates of the upfront bond issuance costs proposed to be financed from proceeds of the bonds and estimates of debt service and other on-going costs for the first collection period. (TR 683) The Commission should require FPL to file the issuance advice letter (IAL) and initial true-up letter (combined into one document) in draft form at least two weeks prior to pricing based upon the best information available at that time, and in final form on the day of pricing or within one business day of pricing. (Fichera TR 1191-1 194; 1216) In addition, the final IAL should contain detailed analyses and representations regarding the actual structuring, marketing, and pricing of the bonds, as well as the initial storm recovery charges. (Klein TR 1233) In addition to the information suggested by FPL for inclusion in the IAL, other factors that should be addressed include the actions taken by the Company in the marketing of the bonds; a comparison of the pricing relative to an independent benchmark versus other similar securities historically and at the time of pricing; the amount of orders received and from whom; and other factors the Commission, its staff, and its financial advisor consider in their expert judgment to be necessary. (TR 1234) Finally, the IAL should include certifications from FPL, from the underwriters, and from the Commission’s financial advisor that the structuring, marketing, and pricing of the storm recovery bonds resulted in the lowest cost of funds consistent with - 195 -
  5. Page 102 of 151

    Docket No. 060038-E1 Date: May 8,2006 prevailing market conditions and the terms of the financing order. (TR 1233-1234) The portion of this filing relating to the initial true-up letter is discussed in Issue 66. The IALs filed in numerous successful Texas securitization transactions provide the Texas Commission with this level of detail. (TR 1240-1241; EXH 101) In contrast, the draft IAL as proposed by FPL is a simple summary of the key terms of the transaction. (Appendix A to Exhibit B of FPL’s petition) To afford the Commission an opportunity to render an informed decision regarding the outcome of the proposed storm recovery bond issuance, staff recommends the Commission require FPL to file an IAL with sufficient representations and detailed analyses to demonstrate that the parties took all reasonable steps to produce the lowest cost transaction consistent with prevailing market conditions and the terms of the financing order. The proposed draft issuance advise letter filed by FPL is not sufficient. - 196 -
  6. Page 103 of 151

    Docket No. 060038-E1 Date: May 8, 2006 Issue 67: How should the Commission ensure that the structure, marketing, and pricing of the storm recovery bonds result in the lowest possible burden on FPL’s ratepayers? Recommendation: The ratepayers should be effectively represented throughout the life cycle of the proposed transaction. The Commission can ensure the structure, marketing, and pricing of the storm recovery bonds resulted in the lowest possible burden on FPL’s ratepayers consistent with prevailing market conditions and the terms of the financing order by participating in the transaction as discussed in Issue 74B. (Maurey) Position of the Parties FPL: A financing order in the form submitted with the Petition, including the proposed findings of fact and conclusions of law, contains provisions consistent with the statute and necessary to facilitate triple-A credit ratings, providing the requisite investor confidence in the storm-recovery bond issuance, and resulting in an efficient and cost-effective financing. If the Commission wishes to take an active role in directing and overseeing the issuance process, it should employ the approach recommended by FPL in response to sub-issue 74(b). OPC: The Commission should adopt the “best practices” standard which includes active participation by the Commission, its staff, and financial advisors in the bond issuance process. FIPUG: Adopts the position of OPC. FRF: - If the Commission determines to approve securitization, then the Commission should adopt the “best practices” standard. AARP: The same as the Office of Public Counsel. FEA: - Agree with OPC. AG: Adopts and agrees with the position set forth by OPC. Staff Analysis: The ratepayers should be effectively represented throughout the life cycle of the proposed transaction when information and options are being evaluated and decisions are being made that impact the ultimate cost to ratepayers. It is difficult, if not impossible, to evaluate such decisions after the fact. (Fichera TR 1198-1202; Klein TR 1232-1234) The Commission can ensure the structure, marketing, and pricing of the storm recovery bonds resulted in the lowest possible burden on FPL’s ratepayers consistent with prevailing market conditions and the terms of the financing order by including findings of fact, conclusions of law, and ordering paragraphs in the financing order as discussed in Issues 61 and 74B; by participating in the transaction review process as discussed in Issue 74B; and by insisting on accountability of the principal transaction parties by requiring lowest cost certifications as discussed in Issue 65. - 198 -
  7. Page 104 of 151

    Docket No. 060038-E1 Date: May 8, 2006 Issue 74B: If the Commission votes to issue a financing order, what post-financing order regulatory oversight is appropriate and how should that oversight be implemented? Recommendation: The ratepayers should be effectively represented throughout the proposed transaction. The Commission, its staff, its outside counsel, and its financial advisor, along with FPL, FPL’s financial advisor, and its counsel should work in a collaborative process to ensure the structuring, marketing, and pricing of the storm recovery bonds result in the lowest cost consistent with prevailing market conditions and the terms of the financing order. The Commission should be represented primarily by its staff, who should be advised by the Commission’s financial advisor and outside counsel. Staff should periodically brief the Commissioners and the parties on the progress of the transaction. Issues that arise during the process that cannot be resolved collaboratively should be submitted in writing to a designated Commissioner for guidance. If any party objects to the designated Commissioner’s proposed resolution, the matter should be submitted to the Commission for de novo consideration. The final structure of the transaction, including pricing, should be subject to review by the full Commission for the limited purpose of ensuring that all requirements of law and the financing order have been met. The Commission should specifically determine that the fees and expenses of its financial advisor and outside counsel in this post-financing order collaborative process are entitled to payment from the bond proceeds. (Maurey, Keating) Position of the Parties NOTE: Only OPC stated a separate position on this sub-issue. The positions stated for FPL and FEA represent staffs synopsis of their discussion of the sub-issue. FPL: - FPL and the Commission should designate the members of a “bond team.” The Commission should be represented on the bond team by the Prehearing Officer, who may be advised by the Commission’s staff and financial advisor. The bond team should expect to meet by conference call no less than weekly. Any disputes relative to the transaction documents or the issuance, structuring, marketing, and pricing process that the Commission has reserved the authority to resolve shall be heard by the Prehearing Officer. Any party represented on the bond team should have the opportunity to have the Prehearing Officer’s decision reviewed de novo by the full Commission. OPC: - Commission should take an active role in the issuance process. Parties should receive periodic updates on the status of the transaction through designated Commission staff. The Commission should retain final decision making authority. Any disputes should be addressed by the Commission either at an Agenda Conference with shortened recommendation filing as necessary or through the use of a designated Commissioner as a hearing officer. Parties should be provided a point of entry if there are future disputes. FIPUG: No position. FRF: No position. 7 - 207 -
  8. Page 105 of 151

    Docket No. 060038-E1 Date: May 8,2006 No position. FEA: Agree with OPC. E: No position. Staff Analysis: Procedural Options for Active Commission Participation There are a number of potential options for Commission participation in the review and approval of the final transaction documents and in the collaborative process for structuring, marketing and pricing of the storm recovery bonds. Staff believes that the option selected should balance the need for an efficient process that does not unduly delay the issuance of the bonds with the need to ensure that ratepayer interests are adequately protected. If the Commission decides to use the “Bond Team” approach, there are three basic decisions to be made: Decision 1: Who should participate on behalf of the Commission in day-to-day activities of the Bond Team? Options include: 0 0 0 the Commission staff, financial advisor and counsel a designated Commissioner, staff, financial advisor and counsel a panel of Commissioners, staff, financial advisor and counsel the full Commission, staff, financial advisor and counsel Staff recommends that day-to-day participation should be through the Commission staff, advised by the Commission’s financial advisor and counsel. Due to the anticipated frequency of meetings and/or conference calls, staff believes it is impractical for one or more Commissioners to participate in light of other demands on Commissioners’ time. In addition, notice requirements under the Sunshine Law could delay the process if a panel of Commissioners (or the full Commission) is designated to participate. If staffs recommendation is adopted, staff can brief Commissioners on the progress of the transaction at whatever frequency individual Commissioners desire. Decision 2: What process should be used to resolve any issues on which the Bond Team members are unable to reach agreement? Options include: 0 0 0 decision by the Commission staff and/or financial advisor acting pursuant to authority delegated in the financing order, subject to de novo review by the full Commission decision by a designated Commissioner, subject to de novo review by the full Commission decision by a panel of Commissioners, subject to de novo review by the full Commission decision by the full Commission - 208 -
  9. Page 106 of 151

    Docket No. 060038-E1 Date: May 8,2006 Staff recommends that any issue that the Bond Team participants are unable to resolve should initially be presented in writing for resolution by a designated Commissioner, subject to de novo review by the full Commission. This approach: (i) avoids any potential concern about the scope of authority that can properly be delegated to the Commission staff and/or financial advisor; (ii) recognizes that if the Commission staff and/or advisor cannot informally resolve the issue with FPL, the issue appropriately should be resolved at a higher level; and (iii) avoids the delay that would be introduced by Sunshine Law requirements and Commissioner scheduling concerns if disputes initially had to be submitted to a panel of Commissioners or the full Commission. All parties who took a position on this issue indicated that it would be acceptable for a single Commissioner to initially resolve such issues, provided that parties had the right to seek de novo review by the full Commission or some other point of entry. (FPL BR at 162; OPC BR at 113) Staff agrees that de novo review would be appropriate in this unique situation. The designated Commissioner’s decisions could affect the substantive rights of the parties in a way that is fundamentally different from routine Prehearing Officer decisions that are reviewed under the highly deferential reconsideration standard. Staff recommends that all parties to this docket should be provided notice of any dispute taken to the designated Commissioner and provided the opportunity for comment before the designated Commissioner. All parties should also be provided notice of any decision reached by the designated Commissioner. The parties do not appear to agree on who should have the right to seek full Commission review of a determination made by the designated Commissioner. FPL would limit the right to parties represented on the Bond Team (Le., FPL and the Commission) whereas the Intervenors would extend the right to all parties. Because the specific features of the securitization transaction can affect the rates to be paid by consumers, and hence the substantial interests of the parties, staff recommends that any party be allowed to seek full Commission review. Decision 3: How should the pricing of the storm recovery bonds be approved? Options include: 0 0 0 advance approval by the full Commission contingent upon the final price being supported by fully accountable certifications of lowest cost fkom FPL, the lead undenvriter(s), and the Commission’s financial advisor advance approval by the full Commission contingent upon the final price being fixed within a specified range (e.g. 1-2 basis points) identified no more than 48 hours prior to final pricing pricing subject to limited review by the full Commission after the bonds are priced, but before they are issued Staff recommends the pricing of the storm recovery bonds be subject to limited review by the full Commission after the bonds have been priced but before the bonds have been issued. FPL will file a proposed form of issuance advice letter with the Commission at least two weeks before the expected pricing date. Within one week of receiving the proposed form of issuance advice letter, the Commission’s staff with input from its financial advisor will provide comments and recommendations to FPL regarding the adequacy of information proposed to be provided. Within one business day of pricing, a meeting will be noticed for three business days after - 209 -
  10. Page 107 of 151

    Docket No. 060038-E1 Date: May 8,2006 pricing to afford the Commission an opportunity to review the proposed transaction. The first day after pricing is for receipt of the actual details of the transaction including the lowest cost certifications from FPL, the underwriter(s), and the Commission’s financial advisor. The second day is for the staffs and the Commission’s financial advisor’s review of this information. The third day would be for a staff presentation of the results of its review and the Commission’s deliberations on the transaction. If the Commission determines that all required certifications have been delivered and the transaction complies with applicable law and the financing order, the transaction proceeds without any further action of the Commission. However, if the Commission were to determine that the transaction fails to comply with applicable law or the financing order, or if FPL, the bookrunning undenvriter(s), or the Commission’s financial advisor is unable or unwilling to deliver the required certifications in a form acceptable to the Commission, the Commission would have discretion to issue an order to stop the transaction. The Commission would have no authority to issue an order to stop the transaction for any other reason, for example, a change in market conditions after the moment of pricing. Other Matters FPL’s brief suggests a number of specific limitations on the role of the Commission and its financial advisors. FPL states that, as a result of securities law concems, FPL must retain ultimate editorial control over the statements made in its registration statement and in the materials for an internet-enabled road show. (FPL BR at 160) FPL also states that participation in marketing and sales calls will be limited to FPL and its underwriters for the same reason. (FPL BR at 161). Staff believes that it is premature to address these or other specific limitations. The question of editorial control, for example, will arise only if the Bond Team and FPL disagree about specific disclosure language. Rather than addressing such issues in the abstract, the mechanism recommended above for resolving any future disputes can be used to focus on the specific language in question if a disagreement about such language cannot be resolved informally. FPL also questions for the first time in its brief whether Section 366.8260, Florida Statutes, contemplates that activities by the Commission’s financial advisor and counsel after entry of the financing order and before the post-financing cost review qualify for payment from bond proceeds. (FPL BR at 145; 159 at fn. 50) Staff recommends that the Commission find and direct that such costs are properly payable from bond proceeds. Section 366.8260(2)(b)2., Florida Statutes, provides: In performing the responsibilities of this subparagraph [2.] and subparagraph 5., the commission may engage outside consultants or counsel. Any expenses associated with such services shall be included as part of financing costs and included in storm-recovery charges. Subparagraph 2 identifies the contents of a financing order, and authorizes the Commission to “specify the degree of flexibility to be afforded to the electric utility in establishing the terms and conditions of the storm-recovery bonds” and “include any other conditions that the commission considers appropriate and that are not otherwise inconsistent with this section.” Section 366.8260(2)(b)2.g. and j ., Florida Statutes. Subparagraph 5 relates to the - 210 -