Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Compilations of discovery responses

Files31

Text of ALLCO Set 3_COMBINED.pdf

Extracted from the file · 23 pages · 55,777 characters

Text of ALLCO Set 2_COMBINED.pdf

Extracted from the file · 38 pages · 81,182 characters

Text of ALLCO Set 1_COMBINED.pdf

Extracted from the file · 27 pages · 46,644 characters

Text of ALLCO Set 6_COMBINED.pdf

Extracted from the file · 9 pages · 18,340 characters

Text of AMTRAK Set 2_COMBINED.pdf

Extracted from the file · 2 pages · 3,025 characters

Text of AMTRAK Set 1_COMBINED.pdf

Extracted from the file · 5 pages · 4,881 characters

Text of AMTRAK Set 3_COMBINED.pdf

Extracted from the file · 34 pages · 101,991 characters

Text of CIEC Set 2_COMBINED.pdf

Extracted from the file · 1 page · 1,005 characters

Text of CIEC Set 1_COMBINED.pdf

Extracted from the file · 19 pages · 26,023 characters

Text of CIEC Set 3_COMBINED.pdf

Extracted from the file · 4 pages · 5,355 characters

Text of CLF-SC Set 1_COMBINED.pdf

Extracted from the file · 56 pages · 132,578 characters

Text of CLF Set 1_ COMBINED.pdf

Extracted from the file · 20 pages · 38,243 characters

Text of CLF-SC Set 2_COMBINED.pdf

Extracted from the file · 7 pages · 17,131 characters

Text of EOE Set 3_COMBINED.pdf

Extracted from the file · 11 pages · 23,418 characters

  1. Page 3 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-119 Page 3 of 4 Docket No. 25-12-13 Directives Directive Page Compliance No later than November 30, 2026, the Company shall submit in Docket No. 26-05-10 an analysis of whether the storm fleet has provided a maximum positive The Company plans to file the benefit to ratepayers, including an evaluation of 145 analysis as directed by whether the storm fleet has provided net benefit to November 20, 2026. ratepayers for the catastrophic storms under review in that proceeding, as discussed in Section III.F.6.a, Storm Fleet. No later than December 31, 2026, Eversource shall update its Expense Policy to identify meal stipend criteria and to include the following two requirements: The Company is currently (1) supporting documentation for the calculated 145 assessing the steps necessary to number of meal stipends; and (2) an affirmation from comply with this directive. each employee to confirm that they did not receive a Company-provided meal, as discussed in Section III.F.7.a, Meal Stipends. No later than April 1, 2027, Eversource shall comply with mileage reimbursement requirements as outlined in Section III.F.7.b, Employee Mileage. In the Company’s next application to amend its base distribution rates, the Company shall separately account for prestaging and non-prestaging costs, if the Company is requesting recovery of prestaging costs, as discussed in Section III.E.2, Remediation and Materials Costs. 145 The Company is currently assessing the steps necessary to comply with this directive. 145 The Company is not seeking recovery for any pre-staging costs in Docket No. 26-05-10. The Company keeps separate FERC Accounts for both the catastrophic storm costs and pre-staging event costs. In addition to the Directives listed above, in the 2026 Storm Decision, PURA directed the Company to propose in Docket No. 26-05-10, a modification to the regulatory framework for deferred storm expenses (2026 Storm Decision, at 37). Consistent with that directive, the Company proposed a modified storm cost-recovery framework in this proceeding. The details of that proposal are set forth in Exhibit CLP-ELP-1 at pages 122-156. In addition, in this proceeding, as discussed in Exhibit CLP-STORM-1 at page 87, the Company adjusted by 25 percent the cost of small tools included in its requested recovery in this proceeding. This adjustment is reflected in the cost exhibits for each storm event, specifically Exhibits CLP-STORM-ACCT-2 (CLP-1 through CLP-14), “Materials” tab. The Company made
  2. Page 4 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-119 Page 4 of 4 this adjustment based on PURA’s precedent in Docket No. 18-11-12 (the “2019 Storm Decision”). In the 2019 Storm Decision, PURA determined that a portion of the costs of tools, supplies, and personal protective equipment (“PPE”) should be considered normal operating expenses and, accordingly, found it reasonable to disallow 25 percent of those costs. 2019 Storm Decision, at 13-14. The Company has maintained this approach in this filing. Please refer to EOE119, Attachment 2, for a copy of the 2019 Storm Decision. After the Company filed its testimony in this proceeding, PURA issued the 2026 Storm Decision. In that decision, PURA found that 25 percent of materials expenses were nonincremental and therefore not eligible for deferral. 2026 Storm Decision, at 54, 107-109. The 2026 Storm Decision, however, differs from the 2019 Storm Decision in an important respect, which is that, rather than limiting the adjustment to categories such as tools, supplies and PPE, PURA applied the 25 percent adjustment to materials expenses generally. The Company’s proposal in this case is consistent with the fact that the more targeted approach reflected in the 2019 Storm Decision is appropriate. The relevant inquiry is whether the costs were incremental to the storm event, and the various categories of materials do not necessarily have the same characteristics for purposes of that determination, which is the implication of PURA’s decision in the 2026 Storm Decision. In particular, tools and durable goods may be reusable after the completion of storm restoration activities and therefore may provide benefits beyond the particular storm event for which recovery is sought. Those costs are fundamentally different from materials that are consumed in the restoration process and have no continuing utility following the storm. Accordingly, in this proceeding, the Company is requesting that PURA apply the targeted approach from the 2019 Storm Decision and limit the 25 percent adjustment to those categories of materials that may reasonably be considered reusable or otherwise part of the Company’s normal operating expenses, including tools and durable goods. Applying the 25 percent adjustment indiscriminately to all materials would overstate the portion of the Company’s storm-related costs that is properly characterized as non-incremental and would fail to account for the differing nature and use of the materials included in the Company’s request.
  3. Page 5 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-120 Page 1 of 2 Date Filed: August 21, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Education, Outreach, and Enforcement Question: (STORM CUSTOMER CONTRIBUTIONS) Refer to Exhibit-ACCT-1. Provide a reconciliation of the customer contributions reported within Exhibit-ACCT-1 (i.e., WACC Cust Cont tab) to the customer contribution cutoff authorized within Docket No. 25-12-13. To the extent that the contribution dates do not align, explain if there is an update required to the revenue request and provide documentation or calculations supporting the amount. Response: Please refer to the Company’s response to interrogatory EOE-018 i for a reconciliation of the customer contributions reported in Exhibit-ACCT-1, tab “WACC Cust Cont”, Column E to the customer contribution cutoff authorized within Docket No. 25-12-13. As noted in the Company’s response to interrogatory EOE-018, subsequent to filing this rate amendment application on July 14, 2026, the Company has received the final decision in Docket No. 25-12-13. The Company will be updating its cost of service to reflect the final decision in Docket No. 25-12-13 during the course of this proceeding and will reflect any changes related to Exhibit ACCT-1 including customer contributions. Prior Referenced Response: EOE-018 Question: (STORM CUSTOMER CONTRIBUTIONS) Refer to Exhibit-ACCT-1, WACC Cust Cont, Column E. Explain how each of the customer contribution amounts were derived. i EOE-018 Response: Please refer to EOE-018, Attachment 1, for the calculation of the monthly customer contributions included in ExhibitACCT-1, tab “WACC Cust Cont”, Column E. EOE-018, Attachment 1, is further explained below: (1) Rows 15 through 22 identify the storm amortizations included in CL&P’s base distribution rates established as a result of storm reviews in Docket Nos. 17-10-46 and 18-11-12. This reflects the annual revenue the Company receives from customers associated with prior storm amortizations. As these amortizations fully
  4. Page 6 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-120 Page 2 of 2 collect their respective storm costs the amortizations transition from funding prior storm costs to funding the storm reserve. (2) Rows 25 through 28 identify the total revenues recovered in rates for the storm amortizations and removes the amortizations that are still being applied against prior storm costs. For example, Row 26 shows that the $2.940 million amortization was being applied against prior Docket No. 17-10-46 storm costs through April 30, 2024, and then was utilized to fund the storm reserve effective May 1, 2024 (i.e. increases the storm reserve funding). Row 27 shows that the $23.504 million amortization was being applied against prior Docket No. 18-11-12 storm costs through April 30, 2025, and therefore was not utilized to fund the storm reserve during this time period. (3) Rows 30 and 31 show the base distribution funding of the catastrophic storm and pre-staging reserves authorized in Docket No. 17-10-46, which were each established at $3 million annually. (4) Rows 32 and 34 show the total customer contributions to the storm reserve annually and monthly respectively. As shown on Row 34, customers contributed to the storm reserve $2.839 million monthly for the period May 1, 2023 through April 30, 2024 and $3.084 million for the period May 1, 2024 through April 30, 2025. The customer contributions shown on Row 34 of Attachment 1 are reflected in Exhibit ACCT-1, tab “WACC Cust Cont” on a 2-month lag to reflect the billing and customer payment lag experienced by the Company. For example, the $3.084 million customer contributions beginning in rates on May 1, 2024 are reflected in Exhibit ACCT-1, tab “WACC Cust Cont” beginning in July 2024. Consistent with PURA’s treatment of customer contributions in their final decision in Docket No. 25-12-13 the Company has applied only the contributions during the period for which the storms were incurred (i.e. January 2024 through March 2025). Please note that the February 2024 customer contribution is a net amount resulting from PURA’s final decision in Docket No. 25-12-13. In that Docket the Company presented total customer contributions for the period May 2018 through December 2023 of $101,882,534. PURA’s final decision ultimately utilized $101,469,791 to offset 2018 – 2023 catastrophic storm and pre-staging events resulting in a remaining customer contribution amount of $412,743 as of December 31, 2023. Consistent with the 2-month lag above, the $412,743 remaining amount as of December 31, 2023 is reflected in February 2024. Subsequent to filing this rate amendment application on July 14, 2026, the Company has received the final decision in Docket No. 25-12-13. The Company plans to update the cost of service in this case to reflect the final decision in Docket No. 25-12-13 during the course of this proceeding and will reflect any changes related to Exhibit ACCT-1 including customer contributions.
  5. Page 7 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-121 Page 1 of 1 Date Filed: August 21, 2026 Witness: Leanne M. Landry and John G. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (STORM SNACKS) Provide an unlocked Excel spreadsheet detailing incremental recovery amounts for any costs related to snacks that are included within the storm recovery amounts for each event. To be clear, snacks are defined to include food and beverages that are not specifically required in support of a meal and would include, but not be limited to, candy, chips, beef jerky, and energy drinks. As part of the response, please cite the specific expenses within the respective Exhibit-ACCT-2 filings. Response: Please refer to EOE-121, Attachment 1, and EOE-121, Attachment 2, for the amounts for costs that could be related to snacks that are included in the storm recovery amounts. Please note that in these amounts there are essential, non-snack items, such as cases of water and coffee and it is not possible to distinguish those amounts from the pure snack items. Eversource personnel work under difficult conditions during emergency events, often for long hours and frequently outside and beyond normal working hours. Items such as snacks, candy, drinks, and other basic provisions are regularly stocked and on-hand in our storerooms to support all Eversource employees during storm events. These supplies play a vital role in helping to boost employee morale at a time when all efforts and energy are focused on responding to, and restoring power for, customers effectively throughout extended storm restoration efforts, often under extremely challenging conditions for our employees while working their emergency response roles.
  6. Page 8 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-122 Page 1 of 1 Date Filed: August 21, 2026 Witness: Leanne M. Landry and John G. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (STORM EMERGENCY RESPONSE PAY/STIPEND) Provide copies of any applicable emergency response pay policies or procedures applicable to incremental amounts included within the Company’s storm balance. Response: Please refer to EOE-036, Attachment 1, for the compensation policy in effect for the 2024 and 2025 storms.
  7. Page 9 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-123 Page 1 of 1 Date Filed: August 28, 2026 Witness: Leanne M. Landry and John G. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (INTERNAL STAFFING LEVELS) Provide an unlocked Excel spreadsheet detailing the Company’s average staffing levels by position (e.g., job title, not individual employees) for each year starting from 2018 through present, along with the overall costs (gross). Additionally, identify the average annual counts and actual amounts that were applicable to Operations and Maintenance (O&M), Capital, Storm, and any other allocated use (including allocations to RAM). Response: Please refer to OCC-202, Attachment 1 and Attachment 2, for the staffing level and overall costs (gross). Please refer to EOE-123, Attachment 1, for O&M, Capital, Storms and RAM Labor costs applicable by year.
  8. Page 10 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-124 Page 1 of 1 Date Filed: August 28, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray and Sasha P. Lazor Request from: Office of Education, Outreach, and Enforcement Question: (INTERNAL RESOURCE COSTS) Provide an unlocked Excel spreadsheet listing each employee position (e.g., job title, not individual employees) and separately identify the fully loaded employee cost per year from 2018 through present, along with the calculated hourly equivalent costs. As part of the response, please discuss any assumptions used. Response: Please refer to OCC-202, Attachment 1 and Attachment 2, for the requested information.
  9. Page 11 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-125 Page 1 of 2 Date Filed: September 01, 2026 Witness: Leanne M. Landry and John G. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (EXTERNAL STAFFING) Provide an unlocked Excel spreadsheet detailing the Company’s ‘external’ average staffing levels for each year starting from 2018 through present, along with the overall gross costs. To the clear, this request is looking to identify the roles, counts, applicable external vendors, costs, and any other relevant details that could assist in minimizing follow-up interrogatories. This request is applicable to all types of external staffing including, but not limited to, vendors supporting line crew activities, customer service activities, IT development activities, etc. Response: The Company began tracking external staffing counts on a systematic, reportable basis starting in 2023. As a result, the system has data as of December 2023, and December 2024 and then by month starting in 2025 and 2026. Please refer to EOE-125, Attachment 1, for a headcount by Business Area using the respective December counts. Please note that external staffing counts are not associated with a specific operating company. Therefore in EOE-125, Attachment 1, the Company provides the requested data in relation to any business area that could potentially support CL&P. This includes Shared Services Organizations such as CFO and Customer Group, as well as operational organizations such as Engineering and Safety, Training, and Fleet. “External Staffing” referenced above is generally held to mean short-term temporary staffing that can include administrative/clerical, accounting/financial, technological, and project support. External staffing is hired through staffing agencies (i.e., temp agencies) or can been contracted directly with firms. During the period requested, the Company had two outside vendor companies that acted as staffing agencies, Randstad and Allegis Global Solutions. During the requested period, the Company directly contracted with 30 outside vendor companies. These vendors are Burns & McDonnell, TRC Engineers, Progressive Global Energy, United Utility Power Services, CHA Consulting, Capital Staffing Solutions, Leidos, RLC Engineering, Plant Forward Energy Services, Qualus, Ironhouse, Qualus Consulting, AI Engineers, ESPii, EN Specialty Services, PMA Consultants, Watkins Strategies, Airswift, Wunderlich-Malec, Power Engineers, Cascade, RCM Technologies, Global Technical Talent, Shermco Industries, EPST-A Voltyx Company, Parsons, Asplundh Engineering Services, BHI Energy, Saybrook Associates Inc., and Control Point Technologies.
  10. Page 12 of 22

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-02 Date Issued August 07, 2026 EOE-125 Page 2 of 2 The Overhead Line Department has kept internal reporting on counts for CL&P Distribution Overhead Line crews, as shown in EOE-125, Attachment 2. This includes headcounts by vendor with the averages from 2018 to June 2026. The Company does not track staffing counts for any other types of Contractors. “Contractors” are vendors used to supplement the Company’s internal work force for specific functions and projects to respond to the increase of work during peak need times including the seasonal demand of the work plan, repairs, and project management. The gross costs on all Outside Services are included in EOE-125, Attachment 3, including all Outside Services provided to the Company by vendor. This includes the External Staffing, CL&P Overhead Line Crews and all other Contractors, as described above.

Text of EOE Set 1_COMBINED.pdf

Extracted from the file · 200 pages · 332,382 characters

Text of EOE Set 4_COMBINED.pdf

Extracted from the file · 70 pages · 139,575 characters

Text of ICC Set 1_COMBINED.pdf

Extracted from the file · 30 pages · 51,093 characters

Text of OCC Set 13_COMBINED.pdf

Extracted from the file · 30 pages · 61,971 characters

Text of OCC Set 12_COMBINED.pdf

Extracted from the file · 73 pages · 193,636 characters

Text of OCC Set 11_COMBINED.pdf

Extracted from the file · 48 pages · 62,469 characters

Text of OCC Set 10_COMBINED.pdf

Extracted from the file · 51 pages · 90,368 characters

Text of OCC Set 5_COMBINED.pdf

Extracted from the file · 46 pages · 88,105 characters

Text of OCC Set 4_COMBINED.pdf

Extracted from the file · 159 pages · 268,038 characters

Text of OCC Set 3_COMBINED.pdf

Extracted from the file · 93 pages · 113,517 characters

Text of OCC Set 2_COMBINED.pdf

Extracted from the file · 68 pages · 113,929 characters

Text of OCC Set 1_COMBINED.pdf

Extracted from the file · 139 pages · 225,320 characters

Text of OCC Set 14_COMBINED.pdf

Extracted from the file · 66 pages · 143,197 characters

As listed on the current system

Corres. 09/29/2026 [26-05-10] (Keegan Werlin LLP) - Compilations of discovery responses

This filing on the current system (opens in a new tab)