Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Compilations of discovery responses

Files31

Search terms highlighted
Eversource rate increase is on 144 pages across 21 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
15 pages match
Words on different pages

Text of ALLCO Set 3_COMBINED.pdf

Extracted from the file · 23 pages · 55,777 characters

Text of ALLCO Set 2_COMBINED.pdf

Extracted from the file · 38 pages · 81,182 characters

Text of ALLCO Set 1_COMBINED.pdf

Extracted from the file · 27 pages · 46,644 characters

Text of ALLCO Set 6_COMBINED.pdf

Extracted from the file · 9 pages · 18,340 characters

Text of AMTRAK Set 2_COMBINED.pdf

Extracted from the file · 2 pages · 3,025 characters

Text of AMTRAK Set 1_COMBINED.pdf

Extracted from the file · 5 pages · 4,881 characters

Text of AMTRAK Set 3_COMBINED.pdf

Extracted from the file · 34 pages · 101,991 characters

Text of CIEC Set 2_COMBINED.pdf

Extracted from the file · 1 page · 1,005 characters

Text of CIEC Set 1_COMBINED.pdf

Extracted from the file · 19 pages · 26,023 characters

Text of CIEC Set 3_COMBINED.pdf

Extracted from the file · 4 pages · 5,355 characters

Text of CLF-SC Set 1_COMBINED.pdf

Extracted from the file · 56 pages · 132,578 characters

Text of CLF Set 1_ COMBINED.pdf

Extracted from the file · 20 pages · 38,243 characters

Text of CLF-SC Set 2_COMBINED.pdf

Extracted from the file · 7 pages · 17,131 characters

Text of EOE Set 3_COMBINED.pdf

Extracted from the file · 11 pages · 23,418 characters

Text of EOE Set 2_COMBINED.pdf

Extracted from the file · 22 pages · 42,455 characters

Text of EOE Set 1_COMBINED.pdf

Extracted from the file · 200 pages · 332,382 characters

Text of EOE Set 4_COMBINED.pdf

Extracted from the file · 70 pages · 139,575 characters

Text of ICC Set 1_COMBINED.pdf

Extracted from the file · 30 pages · 51,093 characters

Text of OCC Set 13_COMBINED.pdf

Extracted from the file · 30 pages · 61,971 characters

15 pages match
  1. Page 23 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-528 Page 2 of 2 Prior Referenced Response: i OCC-527 Question: (Level 1 DER Interconnection Processing) The RE02 Performance Evaluation System identifies Level 1 DER Interconnection as a standalone potential PIM. The Company instead proposes to include Level 1 DER Interconnection Processing as one of five components of its Customer PIM Suite. Please explain why the Company selected a composite structure rather than the standalone PIM identified in RE02, including how incorporating Level 1 DER, Interconnection performance into the Customer PIM Suite is expected to improve interconnection performance. OCC-527 Response: The Company selected a composite PIM structure for its customer metrics, including Level 1 DER Interconnection Processing, because customer experience is multidimensional and more appropriately evaluated through a balanced set of performance measures rather than singularly measuring customer metrics in isolation. The five components of the customer PIM suite collectively reflect different aspects of the Company’s service to customers and provide a more comprehensive measure of customer performance. Including Level 1 DER Interconnection Processing as one component of the composite PIM suite recognizes the importance of timely and effective interconnections processing, while avoiding placing disproportional emphasis on a single customer facing operational measure. A standalone PIM for Level 1 DER Interconnection Processing could inadvertently prioritize focus on performance for this metric at the possible expense of other important customer outcomes. The composite structure instead encourages the Company to maintain balanced performance across a full range of customer-focused objectives. The use of the composite PIM does not diminish the significance of Level 1 DER, Interconnection Processing performance but rather recognizes that it is one of several important dimensions of customer service. The composite approach provides a more comprehensive performance framework that is less susceptible to unintended consequences for measuring, penalizing and/or rewarding customer performance versus a stand-alone PIM approach.
  2. Page 24 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-529 Page 1 of 2 Date Filed: September 15, 2026 Witness: Jared A. Lawrence and Timothy W. McGrath Request from: Office of Consumer Counsel Question: Exhibit CLP-CUSTOMER-1: Customer PIM Suite (Controllable Average Call Handle Time) RE02 includes Average Handle Time among the Existing Customer Service Metrics and does not identify it as a potential PIM. Please explain why reducing hold and post-call work time warrants contributing to a positive financial incentive, including why performance above the proposed target represents performance beyond ordinary operational efficiency and identifying any incremental customer benefits expected to result. Response: At Eversource, Average Handle Time consists of three components – Average Talk Time, Average Hold Time and Average Post-Call Work time. Within these components, customer communication with agents – quality time spent interacting and discussing concerns or questions, has high value. Customer Service Representatives must engage and communicate effectively, taking time to get to know the issue being discussed and ensuring customer understanding of very complex items. This valuable time is measured as Average Talk Time – a component of Average Handle Time which the Company does not want to limit or pressure agents to rush. What remains is Average Hold time and Average Post-Call Work time. These categories are an area of focus for efficiency gains, without imposing any negative impact to customers. Each reduced second of Average Handle time results in savings and improved answer times for customers. The faster one call is finished, the sooner the next can be answered. The faster each call is answered, the less resources needed to handle the volume received. By incentivizing reductions in these two areas, costs in the contact center are managed and customer satisfaction improved. The ability to resolve customer concerns in an efficient manner also correlates positively to a customer's overall satisfaction with their phone experience within the Company's Post Transaction Survey. Correlation measures the degree to which variables are related and tend to change together. A strong correlation is generally indicated by a correlation coefficient close to +1.00 or -1.00. When examining the correlation between a customer's overall phone experience satisfaction and their rating of the attribute "Timeliness of resolving your problem, question, or request," we see a correlation score of +0.83 among CL&P customers in 2025, demonstrating a strong nexus.
  3. Page 25 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-529 Page 2 of 2 Including the Controllable Average Call Handle Time measure within the PIM suite, and allowing for a positive financial incentive, as well as financial penalty, is appropriate because it provides the Company with an additional mechanism to encourage continuous improvement to the quality of customer interactions and reinforce behaviors that contribute to a positive customer experience. The five components of the customer PIM suite collectively reflect different aspects of the Company’s service to customers and provide a more comprehensive measure of customer performance as discussed in response to OCC 527 i. Prior Referenced Response: i OCC-527 Question: Exhibit CLP-CUSTOMER-1: Customer PIM Suite (Level 1 DER Interconnection Processing) The RE02 Performance Evaluation System identifies Level 1 DER Interconnection as a standalone potential PIM. The Company instead proposes to include Level 1 DER Interconnection Processing as one of five components of its Customer PIM Suite. Please explain why the Company selected a composite structure rather than the standalone PIM identified in RE02, including how incorporating Level 1 DER Interconnection performance into the Customer PIM Suite is expected to improve interconnection performance. OCC-527 Response: The Company selected a composite PIM structure for its customer metrics, including Level 1 DER interconnection processing, because customer experience is multidimensional and more appropriately evaluated through a balanced set of performance measures rather than singularly measuring customer metrics in isolation. The five components of the customer PIM suite collectively reflect different aspects of the Company’s service to customers and provide a more comprehensive measure of customer performance. Including Level 1 DER interconnection processing as one component of the composite PIM suite recognizes the importance of timely and effective interconnections processing, while avoiding placing disproportional emphasis on a single customer facing operational measure. A standalone PIM for Level 1 DER interconnection processing could inadvertently prioritize focus on performance for this metric at the possible expense of other important customer outcomes. The composite structure instead encourages the Company to maintain balanced performance across a full range of customer-focused objectives. The use of the composite PIM does not diminish the significance of Level 1 DER interconnection processing performance but rather recognizes that it is one of several important dimensions of customer service. The composite approach provides a more comprehensive performance framework that is less susceptible to unintended consequences for measuring, penalizing and/or rewarding customer performance versus a stand-alone PIM approach.
  4. Page 26 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-530 Page 1 of 3 Date Filed: September 15, 2026 Witness: Jared A. Lawrence and Shamus O’Brien Request from: Office of Consumer Counsel Question: Exhibit CLP-CUSTOMER-1: Customer PIM Suite (Post Transaction Survey – CSR Attributes) The Company’s proposed Post Transaction Survey component measures customer ratings of CSR courtesy, friendliness, knowledge, and concern for customer needs following telephone interactions. The RE02 Customer Satisfaction Scorecard measures customer satisfaction across customer service support, DER interconnection, and service interruptions, including satisfaction with issue resolution and overall interaction quality. Please explain why the Company proposes to attach a positive financial incentive to its Post Transaction Survey measure rather than the customer satisfaction measures developed in RE02. In your response, please explain why performance above the proposed 8.43 target represents exemplary performance warranting a shareholder incentive and identify any analysis demonstrating that improvement in the proposed CSR attributes is associated with improved customer outcomes. Response: Including the Post Transaction Survey – CSR Attributes measure within the PIM suite, and allowing for a positive financial incentive, as well as financial penalty, is appropriate because it provides the Company with an additional mechanism to encourage continuous improvement to the quality of customer interactions and reinforce behaviors that contribute to a positive customer experience. The five components of the customer PIM suite collectively reflect different aspects of the Company’s service to customers and provide a more comprehensive measure of customer performance as discussed in response to OCC 527 i. Aside from Level 1 DER interconnection processing metric, the RE02 Proposed Final Decision received on July 27, 2026 did not propose any other PIMS related to customer satisfaction. Combining Post Transaction Survey – CSR Attribute metric with the other four components of the customer PIM suite incorporates the differing aspects of the Company’s service to customers. Further, the proposed Customer PIM Suite, which evaluates customer satisfaction with customer service support and measures DER interconnection performance, complements the System and Customer Reliability PIMs, which measure the frequency and duration of service interruptions and their impact on customer. Collectively, these PIMs provide a balanced and comprehensive framework for assessing the Company’s performance of its delivery of reliable, responsive service to customers.
  5. Page 27 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-530 Page 2 of 3 The target of 8.43 for the Post Transaction Survey – CSR Attributes does not represent the threshold at which the company would earn an incentive. The target represents the level of performance the Company seeks to maintain (equal to 2025 actual). On-target performance in this metric itself doesn’t guarantee an incentive, as it would require exemplary above-target performance in the other metrics included in the Composite Index of the Customer PIM Suite. Customer perception of a customer service representative’s courtesy, friendliness, knowledge, and concern for customer needs are strongly correlated with their overall satisfaction with their phone interaction. Correlation measures the degree to which variables are related and tend to change together. A strong correlation is generally indicated by a correlation coefficient close to +1.00 or -1.00. All four customer service representative attributes in question have a correlation coefficient of +0.77 to +0.84, demonstrating a strong correlation. The benefit of utilizing these attributes is that they are all an indication of the Company’s success in training customer service representatives to successfully assist customers with their questions or concerns. Prior Referenced Response: i OCC-527 Question: Exhibit CLP-CUSTOMER-1: Customer PIM Suite (Level 1 DER Interconnection Processing) The RE02 Performance Evaluation System identifies Level 1 DER Interconnection as a standalone potential PIM. The Company instead proposes to include Level 1 DER Interconnection Processing as one of five components of its Customer PIM Suite. Please explain why the Company selected a composite structure rather than the standalone PIM identified in RE02, including how incorporating Level 1 DER Interconnection performance into the Customer PIM Suite is expected to improve interconnection performance. OCC-527 Response: The Company selected a composite PIM structure for its customer metrics, including Level 1 DER interconnection processing, because customer experience is multidimensional and more appropriately evaluated through a balanced set of performance measures rather than singularly measuring customer metrics in isolation. The five components of the customer PIM suite collectively reflect different aspects of the Company’s service to customers and provide a more comprehensive measure of customer performance. Including Level 1 DER interconnection processing as one component of the composite PIM suite recognizes the importance of timely and effective interconnections processing, while avoiding placing disproportional emphasis on a single customer facing operational measure. A standalone PIM for Level 1 DER interconnection processing could inadvertently prioritize focus on performance for this metric at the possible expense of other important customer outcomes. The composite structure instead encourages the Company to maintain balanced performance across a full range of customer-focused objectives. The use of the composite PIM does not diminish the significance of Level 1 DER interconnection processing performance but rather recognizes that it is one of several important dimensions of customer service. The composite
  6. Page 28 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-530 Page 3 of 3 approach provides a more comprehensive performance framework that is less susceptible to unintended consequences for measuring, penalizing and/or rewarding customer performance versus a stand-alone PIM approach.
  7. Page 29 of 73Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-531 Page 1 of 2 Date Filed: September 15, 2026 Witness: Jessica B. Cain and Daniel M. Traynor Request from: Office of Consumer Counsel Question: Exhibit CLP-CUSTOMER-1: Customer PIM Suite (Average Discount Rate Enrollment Time) Please explain why a financial incentive for faster manual LIDR enrollment is necessary to advance customer affordability given the substantial enrollment already achieved through DSS data sharing and automatic enrollment. Please identify any analysis showing that faster manual processing would materially increase LIDR participation beyond levels achieved through those enrollment pathways. Response: Timely processing of proof of eligibility for, and enrollment in, the low-income discount rate (“LIDR”) is important for eligible customers. The Company’s proposed “Average Discount Rate Enrollment Time” metric 1 intends to measure and incentivize prompt LIDR enrollment for customers who provide proof of eligibility directly to the Company for manual review and processing. Achieving the proposed two-day turnaround takes a significant amount of resources and forecasting to plan for surge staff resources during annual peak times of year. The Company clarifies this proposed metric: • is not intended (or expected) to have any impact on LIDR participation and; • would not include LIDR enrollment performed through DSS data-matching or Community Action Agencies (via Social Agency portal or receipt of LIHEAP) because those are automated and do not require a team of Company resources for manual review and processing. Including the “Average Discount Rate Enrollment Time” measure within the PIM suite, and allowing for a positive financial incentive, as well as financial penalty, is appropriate because it provides the Company with an additional mechanism to encourage continuous improvement in the quality of customer interactions and reinforce behaviors that contribute to a positive customer experience. The five components of the customer PIM suite collectively reflect different aspects of the Company’s service to customers and provide a more comprehensive measure of customer performance as discussed in response to OCC 527 i. 1 The Company notes that it has this as a PBR metric in one if its Massachusetts Companies as well.
  8. Page 30 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-531 Page 2 of 2 Prior Referenced Response: i OCC-527 Question: Exhibit CLP-CUSTOMER-1: Customer PIM Suite (Level 1 DER Interconnection Processing) The RE02 Performance Evaluation System identifies Level 1 DER Interconnection as a standalone potential PIM. The Company instead proposes to include Level 1 DER Interconnection Processing as one of five components of its Customer PIM Suite. Please explain why the Company selected a composite structure rather than the standalone PIM identified in RE02, including how incorporating Level 1 DER Interconnection performance into the Customer PIM Suite is expected to improve interconnection performance. OCC-527 Response: The Company selected a composite PIM structure for its customer metrics, including Level 1 DER interconnection processing, because customer experience is multidimensional and more appropriately evaluated through a balanced set of performance measures rather than singularly measuring customer metrics in isolation. The five components of the customer PIM suite collectively reflect different aspects of the Company’s service to customers and provide a more comprehensive measure of customer performance. Including Level 1 DER interconnection processing as one component of the composite PIM suite recognizes the importance of timely and effective interconnections processing, while avoiding placing disproportional emphasis on a single customer facing operational measure. A standalone PIM for Level 1 DER interconnection processing could inadvertently prioritize focus on performance for this metric at the possible expense of other important customer outcomes. The composite structure instead encourages the Company to maintain balanced performance across a full range of customer-focused objectives. The use of the composite PIM does not diminish the significance of Level 1 DER interconnection processing performance but rather recognizes that it is one of several important dimensions of customer service. The composite approach provides a more comprehensive performance framework that is less susceptible to unintended consequences for measuring, penalizing and/or rewarding customer performance versus a stand-alone PIM approach.
  9. Page 31 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-532 Page 1 of 2 Date Filed: September 15, 2026 Witness: Jared A. Lawrence, Jessica B. Cain and Andrew C. Belden Request from: Office of Consumer Counsel Question: Exhibit CLP-CUSTOMER-1: Customer PIM Suite (Customer PIM Suite Composite Index) The Company proposes to determine incentives and penalties based on the average of the five component index. Please identify whether performance above target on one or more Customer PIM Suite components could offset performance below target on another component, including Level 1 DER Interconnection Processing or Average Discount Rate Enrollment Time, such that the Company would avoid a penalty or earn an incentive. If so, please provide illustrative examples and explain why the Company considers such outcomes appropriate given the objectives of the affected components. Response: As the Customer PIM Suite evaluates financial penalty or incentive based on a Composite Index reflecting the average performance for the entire Customer PIM Suite, it is possible that above average or below average performance in one component could offset the below or above average performance of other components within the Customer PIM Suite. An illustrative example was included in Exhibit CLP-CUSTOMER-1, page 43, in which above target performance in Level 1 DER Interconnection Processing was offset by below target performance in Controllable Average Call Handle Time and Average Discount Rate Enrollment (Days). The Customer PIM Suite is intended to provide a holistic assessment of the Company’s performance across a variety of customer engagement points to ensure focus on continuing to provide a high-level of customer service across its breadth of customers. If using the same illustrative example provided in the Exhibit noted and only changing the actual performance for Level 1 DER Interconnection Processing, performance for that one component would have to improve to an index of 188 before the Company could offset the on target and below target performance of the other four (4) components enough to trigger an incentive. The index of 188 for this measure represents actual performance of 4.3 average days against the target of 35.0 average days.
  10. Page 32 of 73

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-12 Date Issued September 01, 2026 OCC-532 Page 2 of 2 Level 1 DER Interconnection Processing Digital Customer Engagement Controllable Average Call Handle Time Post Transaction Survey - CSR Attributes Average Discount Rate Enrollment Time (Days) Total Score Performance Actual Target Direction Index 35.0 Down is Good 188 4.3 100 92.18% 92.18% Up is Good 86.2 76 Down is Good 87 8.43 8.43 Up is Good 100 2.5 2.0 Down is Good 75 550 Composite Index 110 With regard to the offset, it is worth noting that Digital Customer Engagement cannot achieve an index greater than 108, as this measure cannot exceed 100% in actual performance. This limits the above target offset potential for this component.

Text of OCC Set 11_COMBINED.pdf

Extracted from the file · 48 pages · 62,469 characters

Text of OCC Set 10_COMBINED.pdf

Extracted from the file · 51 pages · 90,368 characters

Text of OCC Set 5_COMBINED.pdf

Extracted from the file · 46 pages · 88,105 characters

Text of OCC Set 4_COMBINED.pdf

Extracted from the file · 159 pages · 268,038 characters

Text of OCC Set 3_COMBINED.pdf

Extracted from the file · 93 pages · 113,517 characters

Text of OCC Set 2_COMBINED.pdf

Extracted from the file · 68 pages · 113,929 characters

Text of OCC Set 1_COMBINED.pdf

Extracted from the file · 139 pages · 225,320 characters

Text of OCC Set 14_COMBINED.pdf

Extracted from the file · 66 pages · 143,197 characters

As listed on the current system

Corres. 09/29/2026 [26-05-10] (Keegan Werlin LLP) - Compilations of discovery responses

This filing on the current system (opens in a new tab)