  1. Page 81 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-054 Page 2 of 4 Response: a. Confirmed. The amount of $16,580,868 shown on line 7552 includes only non-billable third party make ready costs. As noted in Exhibit CLP-REVREQ-4, Eversource began maintaining detailed records of both billable and non-billable make ready costs consistent with the Docket 10-01-52RE01 Decision. The amount reflected in this exhibit represents costs that were classified as non-billable and therefore were not invoiced to attaching entities. b. (i) The non-compliance conditions reflected in Exhibit CLP-REVREQ-4 were identified during the engineering phase associated with attachment requests. (ii) Eversource maintains records related to pole inspections and attachment activity. The availability of records identifying the most recent attachment date and inspection date varies based on the specific pole and historical record availability. c. Yes, columns F through Y are the FERC accounts to which the third party pole make ready costs were assigned. d. Below is a description of the subaccounts for FERC 593 and 594. 593000 – Distribution Maintenance of Overhead Lines 593010 – Poles and Fixtures 593020 – Overhead Construction Transfer 593040 – Overhead Corrective Maintenance Repairs 593050 – Overhead Service Maintenance Repairs 593100 – Tree Trimming Vegetation Control 594000 – Distribution Maintenance of Underground Lines 594010 – Underground Conduit Maintenance 594020 – Manhole Regulating 594030 – Underground Corrective and Emergent Maintenance 594260 – Maintenance of Manholes e. In Docket No. 19-01-52RE01, PURA directed the Company to defer incremental nonbillable make-ready costs (see Docket No. 19-01-52RE01 Final Decision dated May 11, 2022 at page 45). Consistent with this directive, the Company deferred incremental nonbillable O&M make-ready costs to a regulatory asset which is being sought for recovery in this rate amendment application as supported by Exhibit CLP-REVREQ-4. The capital costs for non-billable third party market ready pole work is included for recovery in the Company’s rate amendment application consistent with all other in-service capital and is supported in Exhibit CLP-ADDITIONS-9.
  2. Page 82 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-054 Page 3 of 4 f. For entries indicating “Pole replacement – Pole defective”, if the pole was found during survey to already be defective, it would be the Company’s or the joint pole owner’s responsibility to replace the pole. g. With reference to Exhibit CLP REVREQ-4 (Third Party Make Ready Costs), line 7030, “D&D Conv” is part of the Field Work Order description. The entire Field Work Order description for this line is “*D&D*Conv. 1635692 - Make Ready Non” which is used internally to communicate the contractor assigned to the work order, the Alden One conversation number, the type of work and billing classification. Therefore, “D&D” refers to D&D Contractors, “Conv. 1635692” is the Alden One conversation number, “Make Ready Non” indicates this is for make ready work and is ‘non’ billable. The capital costs associated with the additions and retirements related to the pole replacement were included on lines 64, 65 and 67 of pages 204-207 in the Company’s 2025 Ferc Form 1 filing. h. The table below shows the $16,580,868 by year. The amounts are included in the FERC Form 1 under Electric Operation and Maintenance Expenses under their respective FERC account number (583, 584, 587, 590, 593, 594, 595, 596, and 598) by year.
  3. Page 83 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-054 Page 4 of 4 i. Refer to the Company’s response to NECTA-048 i for the 2023-2025 amounts in distribution rates. Prior Referenced Response: i NECTA-048 Question: (Make Ready Work & Related Costs) Reference Exhibit CLP-REVREQ-1, pp. 44-46. Reconcile the statement that “the Company has not included any pole make-ready costs within base distribution rates in this proceeding…” (p. 46) with PURA’s statement in Docket No. 19-01-52RE01 that “EDCs received some level of recovery in base distribution rates to perform non-billable make-ready work…” A complete response will explain the steps taken by the Company to ensure that there is no double-recovery of non-billable make-ready costs in base rates versus in the deferred regulatory asset for non-billable make-ready costs. NECTA-048 Response: As noted in Exhibit CLP-REVREQ-1 at 44, lines 12 through 15, the Company states “The costs recorded to this deferred asset are associated with the costs of performing non-billable make-ready pole work not recovered in base distribution rates [emphasis added] to meet established standards, as approved in Docket No. 19-01-52RE01…” Further, in Late File Exhibit-01 in Docket No. 19-01-52RE01, the Company notes there is $803 thousand recovered in base distribution rates, annually, that are netted against cumulative non-billable make-ready costs. Therefore, providing assurance that the Company is not double-recovering non-billable make-ready costs in base distribution rates. Refer to Exhibit CLP-REVREQ-4 (Make Ready Pole Work), line 7548 in tab “Non-Billable Reason” for the Removal of 2023-2025 Amounts in Distribution Rates totaling $2.4 million.
  4. Page 84 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-055 Page 1 of 2 Date Filed: September 23, 2026 Witness: David L. Gladey and Jeffrey Richard Request from: New England Connectivity and Telecommunications Association Question: (Make Ready Work & Related Costs) Refer to Exhibit CLP-ADDITIONS-9. Define the following acronyms: (a) ASP, (b) AWC, (c) BC, (d) Conv, (e) D&D, (f) DSL, (g) DR, (h) HAWK, (i) JS, (j) KA, (l) OA, (m) SH, (n) TPA, (o) TW, (p) ZA, (q) 3PA. Response: Please refer to the listing below for the requested definitions of the acronyms noted in the request; (a) ASP = Asplundh (b) AWC = Area Work Center (c) BC = Internal Employee Initials (d) Conv = Conversation (e) D&D = D&D Power (f) DSL = Internal Employee Initials (g) DR = Internal Employee Initials (h) HAWK = Hawkeye (Elecnor Hawkeye) (i) JS = Internal Employee Initials (j) KA = Internal Employee Initials (k) Missing (l) OA = Internal Employee Initials (m) SH = Internal Employee Initials
  5. Page 85 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-055 Page 2 of 2 (n) TPA = Third Party Attacher/Third Party Attachment (o) TW = Internal Employee Initials (p) ZA = Internal Employee Initials (q) 3PA = Third Party Attacher/Third Party Attachment
  6. Page 86 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-056 Page 1 of 1 Date Filed: September 23, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray, Leanne M. Landry and Jeffrey D. Turano Request from: New England Connectivity and Telecommunications Association Question: (Make Ready Work & Related Costs) Refer to Exhibit CLP-ADDITIONS-9. The phrase “Pole replacement -Pole defective” appears 106 times in this file. Provide the following: a. Explain why in each of these cases the expenses related to pole replacement become a deferred regulatory expense, b. Identify the account(s) to which the expenses are booked c. Identify the proposed method of recovery for such costs. d. Compare and contrast recovery of those costs with the recovery of costs associated with new pole placements needed to address expanded service coverage due to industrial, commercial and residential developments. Response: a. Capital expenditures related to pole replacements can be billable to the attachers or nonbillable. When costs are not billable, and the costs are capitalizable (as is the case for a pole replacement and other make-ready work where the replaced property is a depreciable unit of property), those are treated as Company property and would become a capital asset/rate base. Non billable replacements are not deferred regulatory expenses but instead capital assets residing in FERC Account 106 (Completed Construction Not Classified) or FERC Account 101 (Electric Plant in Service (Major Only)). b. Pole replacements are capital expenditures. Therefore, these are capital expenditures initially recorded as construction in FERC Account 107 (Construction work in progress— Electric) and moved to FERC Account 106 (Completed construction not classified— Electric (Major only)) once placed in service and FERC Account 101 once unitized. c. Capital expenditures for assets placed in service, not reimbursed through make-ready billing submitted to attachers, are part of this rate case. d. The recovery is the same as there are capital expenditures incurred for make-ready work that is not billable and would, in the ordinary course of business, be part of the company’s pole replacement process.
  7. Page 87 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-057 Page 1 of 1 Date Filed: September 23, 2026 Witness: David L. Gladey, Jeffrey Richard, Leanne M. Landry and Jeffrey D. Turano Request from: New England Connectivity and Telecommunications Association Question: (Make Ready Work & Related Costs) Does the Company have access to data that can be arranged in the format of Exhibit CLP-Additions-9.xlsx but for billable make-ready work? If so, please provide a workbook with all such data for years 2022, 2023, 2024, 2025 and January 2026 through June 2026. In doing so, add a column of data to identify the applicable application fees and a second column to identify actual charges/fees billed to attachers. Response: Yes. The Company has access to available data regarding billable make ready work and has provided a workbook containing such data for the period May 11, 2022 through June 30, 2026, which encompasses data for years 2022, 2023, 2024, 2025 and January 2026-June 2026, reference NECTA-057 Attachment 1. The workbook includes, among other fields: • • • • • • Frontier application fees Eversource (CL&P) application fees Eversource (CL&P) survey fees Make ready estimate amounts Actual charges billed to attachers, including true up costs Engineering comments associated with the underlying applications The Company notes that the report is maintained on a pole level basis rather than an applicationlevel basis. As a result, applications involving multiple poles may appear on multiple rows, and application-level fees and charges may be repeated across those rows. Accordingly, the data should not be aggregated by summing individual line items without accounting for duplicate application-level charges associated with multi-pole applications.
  8. Page 88 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-058 Page 1 of 2 Date Filed: September 23, 2026 Witness: Marisa B. Paruta and Jeffrey D. Richard Request from: New England Connectivity and Telecommunications Association Question: (FERC Accounts) Explain how Eversource accounts for make-ready payments for pole replacements from third-party attachers, including whether the investment for such poles is booked to FERC Account 364, and how salvage value is accounted for. Response: When a pole replacement work order is written, the responsible party creates the work order in the Company’s work management system by selecting a specific work order type and enters ‘estimates’ into the work order by selecting Compatible Units, which are the assets that are expected to be installed and removed, which creates the FERC Split and the allocation of charges between the FERC Accounts. The combination of the work order type and Compatible Units determines the specific FERC Utility Accounts (typically 364 - Poles, Towers, and Fixtures, and 365 - Overhead Conductors and Devices, for pole replacement work) that the capital expenditures will be applied to when the work order is placed in-service. When the work is about to begin, the work order is approved, set to ‘open’ status, and can start receiving charges. These costs are allocated based on the FERC Split established, and records the capital expenditures to FERC Account 107010 (Construction Work in Progress) and estimated costs to remove retirement units to FERC Account 108030 (Cost of Removal). Any proceeds received from removed infrastructure that is sold for scrap, for example, is recorded to FERC Account 108040 (Salvage). When make ready work is billed to the third-party attacher, the Company records a Receivable from the third party attacher, and an equal and offsetting credit to the specific work order written for that pole replacement, which is reflected as a credit in the work order. The credit is applied based on the FERC Split between FERC Accounts 107010 and 108030 based on the estimate established when the work order was written. Charges or credits are not disseminated at the FERC Utility Account levels in the Company’s plant asset records while the work order is in ‘open’ status and in FERC Account 107010. When the installed assets are deemed ‘used and useful,’ the work order is placed into ‘in-service’ status and the capital expenditures in FERC Account 107010 are moved to FERC Account 106 (Completed Construction not Classified), while charges in FERC Account 108030 remain unchanged. At this time, the assets placed in service begin to depreciate in their assigned Utility Account (364 or 365) while the Company continues to work on finalizing all costs to the work order.
  9. Page 89 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-058 Page 2 of 2 After all invoices are received, all make ready billable amounts have been paid by third party attachers, drawings are finalized and the pre-requisites/tasks in the work management system are completed, and the final costs and credits appropriately flow through the FERC Split, the work order is closed/posted to the Continuing Property Records (CPR). Once the work order is closed, the final costs of the asset in FERC Account 106 are moved to FERC Account 101010 (Utility Plant in Service) and unitized/posted to the CPR with their specific retirement units in Utility Accounts 364 and 365 based on final costs. The final Cost of Removal in FERC Account 108030 is moved to FERC Account 108010 (Accumulated Provision for Depreciation – Cost of Removal). Any salvage proceeds in FERC Account 108040 are moved to FERC Account 108010 (Accumulated Provision for Depreciation – Salvage) upon final close.
  10. Page 90 of 126

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-059 Page 1 of 1 Date Filed: September 23, 2026 Witness: Leanne M. Landry, Jeffrey D. Turano and Marisa B. Paruta Request from: New England Connectivity and Telecommunications Association Question: (FERC Accounts) Provide a description of any Subaccounts for FERC Account 364 maintained by the Company, and identify and produce all plant and accounting records pertaining to FERC account 364 pole plant investment that break out the specific classes of pole investment by the items listed in the FERC Account 364 instructions, including but not limited to any documents that identify the amount of investment in poles, crossarms, or other appurtenances affixed to the bare wood pole, or by subaccount maintained by the Company. Response: Please refer to NECTA-059, Attachment 1, for the plant records pertaining to FERC account 364 pole investment as of December 31, 2025. The specific classes of pole investment are recorded by retirement unit. The adjusting journal entry on line 28 entered as of December 31, 2025, totaling $1,065,950, provides for the estimated increase to the FERC Account 364 pole investments associated with the Frontier jointly owned poles. Under circumstances where Frontier performs the work to install / replace a jointly owned pole, the Company will reimburse Frontier for a portion of those incurred investment costs, in accordance with the joint owned pole agreement, and record its portion of the value of those jointly owned poles in FERC Account 364.
8 pages match

Text of OCC Set 17_COMBINED.pdf

Extracted from the file · 45 pages · 69,741 characters

Text of OCC Set 18_COMBINED.pdf

Extracted from the file · 24 pages · 49,328 characters

As listed on the current system

Corres. 09/30/2026 [26-05-10] (Keegan Werlin LLP) - Discovery compilation for CIEC Set 4, NECTA Set 1, OCC Set 15, OCC Set 17, and OCC Set 18.

This filing on the current system (opens in a new tab)