Discovery compilation for CIEC Set 4, NECTA Set 1, OCC Set 15, OCC Set 17, and OCC Set 18.
Files6
Docket No. 26-05-10 Discovery Compilations September 30 2026.pdf
PDF · 156 KB · 1 pageText searchable
Download Docket No. 26-05-10 Discovery Compilations September 30 2026.pdfRead the text of Docket No. 26-05-10 Discovery Compilations September 30 2026.pdf
CIEC Set 4_COMBINED.pdf
PDF · 146 KB · 2 pagesText searchable
Download CIEC Set 4_COMBINED.pdfRead the text of CIEC Set 4_COMBINED.pdf
NECTA Set 1_COMBINED.pdf
PDF · 1.2 MB · 126 pagesText searchable
Download NECTA Set 1_COMBINED.pdfRead the text of NECTA Set 1_COMBINED.pdf
OCC Set 15_COMBINED.pdf
PDF · 362 KB · 31 pagesText searchable
Download OCC Set 15_COMBINED.pdfRead the text of OCC Set 15_COMBINED.pdf
OCC Set 17_COMBINED.pdf
PDF · 711 KB · 45 pagesText searchable
Download OCC Set 17_COMBINED.pdfRead the text of OCC Set 17_COMBINED.pdf
OCC Set 18_COMBINED.pdf
PDF · 376 KB · 24 pagesText searchable
Download OCC Set 18_COMBINED.pdfRead the text of OCC Set 18_COMBINED.pdf
Page 18 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-596 Page 3 of 3 Based on industry experience, while transformers can operate beyond their typical design life of 40 years, the risk of failure exponentially increases after 70 years of service life, due to paper insulation degradation. OCC-596, Attachment 1 CONFIDENTIAL, a CIGRE study from 2024, shows the failure rate of transformers has a noticeable increase starting at 40 years and exponentially increases as the asset exceeds 65 years old. This study reviewed analysis of thousands of transformers including many voltage classes from around the world to build depth into the data available. OCC-596, Attachment 2 CONFIDENTIAL is an EPRI paper discussing “Large Transformer End-of-Expected Life” which notes “the useful life of a large, oil-filled transformer is between 30 and 40 years with insulation or bus supports being the most likely to fail due to age. For the insulation, thermal aging of the paper insulation is the likely cause of failure.” OCC-596, Attachment 3, is a Department of Energy report from 2024, citing that large power transformers “are typically considered to have a design lifetime on the order of 40 years. In 2014, a DOE report estimated that the average age of LPTs in the North American grid was 38–40 years, indicating that a substantial fraction of those LPTs are at or over that design lifetime. These LPTs will ultimately need to be replaced or refurbished.” These industry research groups and others have provided basis within their published studies to support the concerns of failure with any transformer over 40 years in-service. As a result, Eversource’s Asset Health philosophy for transformers is to operate transformers to their maximum useful life, but plan to maintain a transformer fleet that does not exceed 70 years of age and an average age of approximately 35 years. The objective is to find the balance between affordability and preventing an aged transformer fleet that approaches the “knee of the curve” which results in failure rates that increase significantly. With a large portion of the transformer fleet being between 50 and 80 years old, as these transformers continue to approach and exceed 70 years, the rate of failure will increase rapidly. Due to the complexity and time duration of procuring and replacing transformers, a significant increase in failures would result in the inability to maintain reliability by reactively replacing an increased volume of transformer failures. The six most recent failures of transformers in CT were all attributed to internal failures of the transformer. The ages of the failed transformers were 32, 50, 52, 52, 56, and 83 years old at the time of the failure.Page 19 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-597 Page 1 of 3 Date Filed: September 23, 2026 Witness: John P. DiPaola-Tromba Request from: Office of Consumer Counsel Question: Refer to Exhibit CLP-TSP-1 at 55. For each proposed proactive replacement, identify whether the Company evaluated continued operation through enhanced inspection, testing, monitoring, maintenance, refurbishment, loading limits, load transfer, or use of a spare transformer. Provide each existing analysis and state whether it found that replacement could be deferred by one, three, or five years. If no deferral or life-extension or alternate analysis was performed, please confirm the reason. Response: Eversource employs several methods to both actively and passively monitor the health of all power transformers within its service area. Active and continuous monitoring methods include out-ofspecification alarming. Remote alarming (if applicable) is conducted through the Eversource SCADA system with alarms existing for bushing monitoring, LTC trouble, dissolved gas, oil level alarms, and oil temperature alarms, among others. Per industry best practices, local alarming is performed through panel indication lamps with corresponding nameplate alarm descriptions and annunciation technologies such as bulb annunciators and Human Machine Interfaces (HMI’s). The preventive maintenance procedures for power transformers are documented within the Eversource Maintenance Program (EMP) 5.58 Station Transformers and Oil-Filled Shunt Reactors. The inspection and maintenance tasks are catalogued into three (3) categories which include a list of asset conditions for real-time condition monitoring, time-based regular inspections, and condition-based maintenance activities. These are described in more detail below: Condition Monitoring: Various parameters related to power transformer health are actively monitored as applicable. The monitoring is performed both locally and remotely with local monitoring performed by individual equipment alarms and station annunciators. Remote monitoring is performed via Supervisory Control and Data Acquisition (SCADA) to enable realtime asset parameter output and SCADA equipment alarms. Such parameters include temperature, oil level, pressure, and load tap changer (LTC) status. Time-Directed Maintenance and Inspections: Eversource has established multiple routine maintenance activities required to be performed for all power transformers within specific time intervals. These activities include monthly visual inspections, annual oil sampling including dissolved gas analysis (DGA), thermographic readings, LTC maintenance, and major maintenancePage 20 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-597 Page 2 of 3 activities. Major maintenance activities include power factor testing, bushing testing, excitation testing, confirmation of proper operation and integrity of pressure relief devices and ensuring all alarms operate properly. Condition-Based Maintenance: These activities are on an as-needed basis when identified upon visual inspection, when performing time-directed maintenance activities, and when output from condition monitoring devices indicate outside normal operating values. Such activities include, but are not limited to, acoustic measurements, core grounding tests, leak repairs, and chassis repair. Substation Technical Engineering leverages data collected by the CASCADE, PTX Analysis, and substation equipment databases to perform asset condition assessments of power transformers. The reports are based on the following six (6) parameters with recommendations for replacement by the Substation Technical Engineering team being based upon whether two (2) of the following (6) parameters are considered high risk: • Oil Analysis Results o DGA o Fluid Quality Analysis o Furan Analysis on Main Tanks • Age • Loading • Maintenance History • Historical Test Data • Physical Inspection Findings The above practices are applicable to all power transformers. Asset age and condition will prompt enhanced inspection, testing, monitoring, and maintenance as noted in the EMP toward the goal of maximizing the usable life of a transformer. Historically the Company has effectively maximized the life of Transformers by extensive maintenance and monitoring practices, evidenced by the age demographics of the fleet which far exceed the typical design life of 40 years. While this practice continues, the risk profile of an aging fleet compounded by longer lead times and more challenging outage constraints has resulted in a need to initiate planned replacements, beyond the historical average of 1-2 transformer replacements per year, to minimize overall impact of a failed transformer and maximize efficiency. A typical transformer replacement can take from 2 to 5 years to plan and execute. From the time of identification of deteriorating health, the transformer will continue to degrade over the course of the project execution time period. While spares are an effective mitigation plan for emergent failures, it is not a “one-size fits all” long-term mitigation plan to address the fleet risk because depending on when the failure or urgent replacements occur, it may happen at a high-risk period of the year which cannot be controlled exposing the system and customers to a much higher risk. Allowing transformers to run to failure also poses a serious safety risk to both the public and utilityPage 21 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-597 Page 3 of 3 workers. Additionally a failed transformer could cause damage to adjacent healthy equipment compounding the negative impact. Prior to initiation of a transformer replacement project, the various subject matter experts (SMEs) will confer and review the nameplate data, maintenance records, and PTX scores of the unit. If a transformer is reviewed and a capital project is not to be initiated, the transformer is typically recommended to have further evaluation for maintenance mitigation of the found issue. This may include repairs or minor refurbishment actions that enable the power transformer to be reenergized and placed back in-service. If the transformer is identified as requiring a capital project an initial funding is established and a project team assembled. The project team includes various SMEs and they are required to review the technical and financial feasibility of transformer replacement, transformer refurbishment, load transfer options, and usage of existing spare transformer inventory for a replacement. After the feasible options are developed, the project team will proceed with a formal review of the multiple feasible options within the procedures of the Eversource Solution Design Committee. Using the nameplate data with age and ratings combined with the PTX scores, the power transformers noted in Exhibit CLP-TSP-1 at 55 have been identified to proceed with the initial capital project evaluation within the Targeted System Plan. As these evaluations are completed, the power transformers will be prioritized and projects initiated as confirmed. The project sequencing and deferral options will be evaluated within this review. The two active and ongoing projects for transformer replacements included within the Targeted System Plan followed the processes noted above, were prioritized within the project portfolio, and are planned to be placed in-service in 2028.Page 22 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-598 Page 1 of 1 Date Filed: September 23, 2026 Witness: John P. DiPaola-Tromba Request from: Office of Consumer Counsel Question: Refer to Exhibit CLP-TSP-3 at 67. Confirm whether Shepaug 13A is approximately 85 years old, has Short-Term and Long-Term Health Index values below 0.5, and is not scheduled for replacement during 2027–2031. Identify each younger transformer scheduled for replacement before Shepaug 13A and provide the specific condition, capacity, safety, or compliance reason supporting that ordering. Response: Exhibit CLP-TSP-3, at 67, is correct in the statement that the Shepaug 13A-21X transformer is currently 85 years old. The most recent data from July 2026 indicates Short-Term Health Index of 0.194 and Long-Term Health Index of 0.289. The statement of “No projects for Shepaug 13A are currently in the 5-year plan” included in Exhibit CLP-TSP-3, at 67, was an error. The Shepaug 13A-21X transformer is one of the transformer asset condition transformer replacement projects within the Targeted System Plan. There are two active asset condition projects with transformer replacements scheduled prior to the replacement of the Shepaug 13A-21X transformer. CS00286 is a project that includes replacement of the Franklin Drive 1B substation transformers 1B-4X and 1B-5X. This project was established to replace the transformers that were installed in 1953 (73 years old), increase station capacity, and remove an area phase shift. CS00396 is a project that includes the replacement of the Stevenson 14A substation transformer 14A-1X after its failure. This transformer was 83 years old at the time of failure.Page 23 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-599 Page 1 of 3 Date Filed: September 23, 2026 Witness: David L. Gladey and Lavelle A. Freeman Request from: Office of Consumer Counsel Question: Refer to Exhibit CLP-TSP-3 at 22–24. a. Provide the data underlying the headroom and constrained-area presentations on pages 22– 24. For each substation identified as constrained, provide its normal and emergency rating, five-year historical load and peak load data, available headroom, forecast first year of violation, and proposed project cost. b. For each constrained substation identified, provide the existing analysis of temporary and permanent load transfers. Identify the receiving substation or feeder, available transfer capacity, MW that could be transferred, required enabling work, estimated cost, and reason any transfer was rejected. Please confirm if no transfer analysis was performed. c. Provide a summary of each actual substation capacity violation and stranded-load event experienced from 2016 through the present. Identify the substation, date, maximum loading, applicable rating, duration, contingency, customers at risk, customers interrupted, and whether load transfer prevented or reduced an outage. Response: a. The graphic depicted in CLP-TSP-3, at 22, is derived from headroom data for substations with actual values, time series data, and ratings shown on our public maps using the, Eversource CT Grid Connection Navigator. Loads are based on our most recent summer peak year, 2025. Please refer to OCC-599, Attachment 1 CONFIDENTIAL, for project forecast violation year and the 5-year historical peak load data for each respective project. The table contains the LCC rating of each substation which is the planning criteria identified within the DSPG, please refer CLF-SC-023, Attachment 1. The following substations have projects initiated and have obtained at a minimum a conceptual level estimate: Substation West Brookfield 14H Beacon Falls 11N Franklin Drive 1B Southington 4C Berlin 6A_13.8kV Westside 7A Hopewell 22R Estimated Project Cost $16,900,000 $12,632,000 $17,986,000 $9,772,600 $23,199,000 $18,399,000 $17,518,000Page 24 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-599 Page 2 of 3 All other substations within the attachment have not had a comprehensive evaluation to identify possible solutions and the costs associated with those solutions. The table below depicts a high-level tabletop analysis for possible projected cost of a substation solution. These costs will be refined as these projects progress through the funding process and receive full engineering analysis for solutions and conceptual level estimates. Substations Waterside 22M Flax Hill 24A Rocky Hill 12Y Triangle 11A Middle River 28M Rockville 14W Campville 14R Baldwin 13F Tracy 14M Frybrook 13B Brooklyn 30Y High Level Estimate $600,000 $500,000 Less than $250,000 $4,800,000 $500,000 $10,000,000 $52,300,000 $20,250,000 $9,900,000 $20,000,000 Less than $250,000 Project Status Investigating Project Need Investigating Project Need Investigating Project Need – Anticipating Permanent Load Transfer from West Brookfield 14H with settings changes only Initial Funding Approved Investigating Project Need Initial Funding Approved Partial Funding Initial Funding Submitted Initial Funding Approved Initial Funding Approved Investigating Project Need – Anticipating Permanent Load Transfer from Tracy 14M or Frybrook 13B with settings changes only b. Prior to initiating a funding project, permanent load transfers are, in many cases, a preferred solution if the conditions at the constrained substation and the adjacent area support this as these are typically substantially lower cost than substation investments and have a much more rapid deployment timeline. Historically these load transfers were not explicitly tracked, and the Company does not possess historical data as it pertains to deferrals by means of permanent load transfer. As of 2024 the Company identified this opportunity to begin having a detailed record of load transfers, partly in response to increasingly constrained regional capacity. The Company is now prepared to track these transfers in the Step Load Tracker as a load transfer on the receiving substation and a negative load transfer to the originally constrained station. This tracker will not only allow the forecasted load transfer to be visible but will also allow for historical reporting of deferred major capital upgrades through completed load transfers.Page 25 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-599 Page 3 of 3 The newly identified projects are in early stages of development and have not yet completed the solution selection process yet. Therefore, these projects would not yet have any tracked load transfers or analyses completed to date. Following initial funding of these projects, all available solutions including permanent load transfers, non-wires solutions, and traditional solutions are identified and evaluated for suitability and for viability. No potential solutions have been rejected at this time from these newly identified projects. Temporary transfers are reserved for substations anticipating overload during a current planned peak event, planned or unplanned outages, or other transient system events. Temporary solutions place the system in an abnormal condition which can impact operations, protections and controls, and automations within the system and are not used as a long-term solution except where necessary to address real-time operational needs that do not have a permanent solution placed into service. c. All substation forecasted violations are mitigated by using pre-contingent load transfers to adjacent substations with remaining capacity. In accordance with planning criteria in the Distribution System Planning Guide (CLF-SC-023, Attachment 1), the Company plans and designs its system to avoid overload of major substation assets such as transformers during an N-1 event. During real-time operation, these overload scenarios are avoided through the use of monitoring technology and planned mitigation measures. However, the Company’s substation planning group recreates a normalized substation load to aid in the process of forecasting for future years.Page 26 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-600 Page 1 of 1 Date Filed: September 23, 2026 Witness: Lavelle A. Freeman and Juan F. Martinez Request from: Office of Consumer Counsel Question: Refer to Exhibit CLP-TSP-3, at 24. Define “stranded load” as used on page 24, including its unit of measurement and the conditions under which load is classified as stranded. Response: Stranded load is defined as mega-watts (MW) of load that is at risk of not being restored following a single failure or emergency event until extensive repairs are completed. Customer load will be classified as stranded when a substation’s forecasted load exceeds its emergency rating, also referred to as Load Carrying Capacity “LCC”. Exhibit CLP-TSP-3, page 24, and this definition, are limited in scope to substation planning.Page 27 of 31
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-15 Date Issued September 09, 2026 OCC-601 Page 1 of 1 Date Filed: September 23, 2026 Witness: Lavelle A. Freeman and Juan F. Martinez Request from: Office of Consumer Counsel Question: Refer to Exhibit CLP-TSP-3, at 24. For each year from 2022 through 2026, provide the actual stranded load experienced on the system. For each event, identify the substation, date, stranded MW or MVA, duration, cause, and number of customers whose service could not be restored. If no actual stranded load occurred in a year, please report zero. Response: The chart on Exhibit CLP-TSP-3, at 24, refers to a modeled evaluation of the system based on substation load that would not be restored during an N-1 event even after pre-contingent load transfers. In the years identified, there has not been a substation N-1 event that has resulted in stranded load because the substations are designed to handle the event with customers experiencing either no outage or at worst limited to momentary outages during switching or restoration activities. This exhibit highlights, that for the substation in which this risk has been identified it is highly likely that customers will experience an outage related to a transformer failure. The Company’s response to information request OCC-603, with an anticipated filing date of September 30, 2026, will provide more detailed information regarding the substation of concern.
Text of OCC Set 17_COMBINED.pdf
Extracted from the file · 45 pages · 69,741 characters
Text of OCC Set 18_COMBINED.pdf
Extracted from the file · 24 pages · 49,328 characters
As listed on the current system
Corres. 09/30/2026 [26-05-10] (Keegan Werlin LLP) - Discovery compilation for CIEC Set 4, NECTA Set 1, OCC Set 15, OCC Set 17, and OCC Set 18.