Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Discovery Compilation (0CC Set 16).

Files2

Search terms highlighted
Eversource rate increase is on 13 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
13 pages match
  1. Page 137 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-703 Page 2 of 3 or may have served as standalone agreements. In those instances, documentation consists of either agreements that are managed outside of the system or individual purchase orders that served as the agreement with the associated terms. All of the relevant charges are supported by purchase orders, which represent a form of contract, containing the Company’s terms and conditions, pricing and a description of the goods or services supported. Although purchase orders are generally not dually executed, a supplier’s acceptance of those terms and delivery of materials or services constitutes consent. For transactions involving low risk materials or services, or those not typically subject to negotiation, the purchase order and its associated terms are the typical mode to support the transactions. The Company is compiling a brief description of the work performed for the approximate 559 contracts provided in EOE-005, Attachment 1, and will supplement this response as soon as practicable. ii OCC-044 Question: (Contracts) For all external line crews and vegetation contractors whose costs are reflected in the storms in this docket and for all current external line crews, please provide all contracts and addendums thereto in effect from January 1, 2024, to the present. OCC-044 Response: Please refer to OCC-044, Attachment 1, for a listing of external line crew and vegetation contractors whose services were utilized in the storms under review in this docket and all current external line crews. Attachment 1 includes page number references to the associated contracts, which are provided as OCC-044, Attachment 2 CONFIDENTIAL. iii EOE-014 Question: (STORM 3rd PARTY INVENTORY/CONTRACTS) Respond to the following: a. Provide a complete listing of all outside contractors and vendors used in support of storm remediation, including a brief explanation of the work performed by each contractor and vendor. b. Provide complete copies of all executed contracts for each vendor listed in (a) above, inclusive of pricing schedules. c. Cite the specific documents and applicable pages that support the pricing for each contractor/vendor for each storm event for which the Company is seeking recovery in this docket. EOE-014 Response: a. Please refer to OCC-044, Attachment 1, for a listing of external line crew and vegetation contractors whose services were utilized in the storms under review in this docket, as well as associated contract documents. For external vendors utilized in the storms under review in this docket (and not related to line crews or vegetation management), please refer to EOE-014, Attachment 1, which lists all other contractors and vendors with a brief explanation of work performed. EOE-014, Attachment 1, includes page number references to the associated contracts provided in EOE-014, Attachment 2 CONFIDENTIAL. Contracts identified as “Legacy Agreement” within EOE-014, Attachment 1, represent purchase orders that were migrated from a legacy system. Those legacy agreements may have been supported by a governing contract maintained in a separate system with terms and conditions more specific to the material or service purchased by the Company – or may have served as standalone agreements. In those instances,
  2. Page 138 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-703 Page 3 of 3 documentation consists of either agreements that are managed outside of the system or individual purchase orders that served as the agreement with the associated terms. b. The contracts provided in OCC-044, Attachment 1, and EOE-014, Attachment 2 CONFIDENTIAL, all pertain to vendors providing services to the Company on storm events in 2024 and 2025, as filed in this docket. Each contract may be applicable to each storm event. Exhibit CLP-ACCT-2 (CLP-1) through Exhibit CLP-ACCT-2 (CLP-14) include a detailed listing of the vendor-invoice charges applicable to each particular storm event.
  3. Page 139 of 148Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-704 Page 1 of 1 Date Filed: September 29, 2026 Witness: Brendan J. O’Brien, John G. Griffin, Garrett J. Murray, Leanne M. Landry and Jeffrey D. Turano Request from: Office of Consumer Counsel Question: Payroll. Refer to the response to OCC-319 Attachment 1. a. Update Attachment 1 to include information for 2018, 2019 and 2020. b. Explain why the Company’s O&M expense payroll has not reached $129.285 million authorized in Docket No. 17-10-46 each of the years 2021-2025. Response: a. Please refer to OCC-704, Attachment 1, which has been updated from OCC-319, Attachment 1, to include budgeted payroll for operating expense and capitalized work for 2018, 2019, 2020. b. OCC-704, Attachment 1, presents an estimated budget perspective. The actual operations and maintenance (“O&M”) expense for base payroll is updated in OCC-704, Attachment 2, at Line 1. OCC-704, Attachment 2, is revised from EOE-123, Attachment 1, to disaggregate deferred storm payroll and non-deferred storm payroll and to provide total O&M base payroll expense on Line 1. As shown in the attachments, the Company’s total O&M payroll expense exceeded the amount allowed in rates in Docket No. 17-10-46 for each of the years 2021 through 2025, with the exception of 2021 and 2022. In these years, the total payroll was less than the actual allowed in rates primarily due to an increased level of capital work performed and fluctuations in the overhead costs due to COVID-19 impacts. In total over the 5-year period, labor costs were in excess of the amount in rates by over $30 million.
  4. Page 140 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-705 Page 1 of 1 Date Filed: September 25, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Consumer Counsel Question: Payroll. Refer to the responses to OCC-322 and OCC-325. Explain why the 6/2026 CLP and EESCO FTEs have declined from 12/31/2025 amounts. Response: The Company is unclear of the conclusion drawn by this question that CL&P and ESC FTEs have declined from 12/31/2025 to 6/30/2026. To clarify, the Company is providing the table below which shows that the Service Company (“EESCO”) FTEs increased 75 FTEs and CL&P FTEs decreased from December 31, 2025 to June 2026. The change in CL&Ps FTEs during the first half of 2026 is primarily driven by 30 retirements, 16 terminations and 20 new hires. Please refer to the table below for FTE comparison. Source December 31, 2025 OCC-322 June 30, 2026 OCC-325 Change in FTEs CL&P FTEs 1,417 1,401 (16) EESCO FTEs 4,493 4,568 75 Total FTEs 5,910 5,969 59
  5. Page 141 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-706 Page 1 of 1 Date Filed: September 28, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray and Erin M. Travassos Request from: Office of Consumer Counsel Question: Signing Bonus. Refer to the response to OCC 328. Provide the Rate Year signing bonus as originally requested. Response: Please refer to OCC-328, Attachment 1 CONFIDENTIAL, which provides a list of signing bonuses paid by employee title with amounts paid in 2021, 2022, 2023, 2024, 2025 and YTD 2026. The amount of signing bonuses included in the Rate Year is $59,604.
  6. Page 142 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-707 Page 1 of 2 Date Filed: September 24, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Consumer Counsel Question: Shared Service Expense. Refer to the response to OCC-355. Provide the Rate Year amount as originally requested. Response: OCC-355, Attachment 1, details the Company’s budget process, applying to the shared service organizations rather than the Eversource Energy Service Company (“ESC”). This response explains the Company’s budgeting process, which is not conducted by the service-company organization, but rather from the shared services organizations that provide services through the ESC structure, including both direct and allocated (shared) costs. In addition, OCC-707, Attachment 1, provides a separate response originally provided by the Company during the 2022 CT Management Audit that comprehensively explains the Eversource annual budget process. As explained therein, the first year of the Strategic Plan is used as the basis for the upcoming year’s Corporate Operating Plan, including the capital and O&M area budget targets. The Corporate Operating Plan development takes place throughout the summer and early fall. In the August timeframe, the Vice President of Financial Planning & Analysis (FP&A) presents and discusses the proposed targets with each member of the Eversource Senior Team. The Budget & Financial Analysis Group (within FP&A) issues budget instructions to all the FP&A Budget analysts who support the business areas. This process to develop the annual Corporate Operating Plan incorporates a more in-depth review and analysis of both O&M expenses and capital projects. FP&A analysts then work with each organization, down to every cost center, to develop the organizational budgets from the ground up. Workforce requirements are reviewed by each organization as part of the overall budget development process. When all proposed budgets are accepted, the budgets are compiled into the budgeting system and incorporated into the Corporate Operating Plan. Operating company presidents are responsible for their respective distribution operations budgets. They work closely with their area directors and managers to ensure the details of their budget align with the company goals and requirements. Operating company presidents work with their area directors and managers to review and present their budgets to the Chief Operating Officer, who then has the ultimate responsibility to present the overall Operations budget to the CFO for review and approval.
  7. Page 143 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-707 Page 2 of 2 In the September/October time frame, the budget process begins for the upcoming calendar year and is finalized once reflected in the annual Corporate Operating Plan. The Corporate Operating Plan is presented by the CFO to the Eversource Energy BOT Finance Committee for review on a preliminary basis in December of each year and as a finalized plan in February of each year. On this timeline, the Company is in the process of preparing its budget for calendar year 2027. Amounts presented for the Rate Year in this proceeding, which spans July 1, 2027, through June 30, 2028, were developed based on Test Year data adjusted forward to Rate Year as documented in the Company’s filing in this proceeding.
  8. Page 144 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-708 Page 1 of 2 Date Filed: September 24, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray and Marianne Eichler Request from: Office of Consumer Counsel Question: Severance Expense. Refer to the response to OCC-357. Explain what positions the large severance amount in 2025 relates to. Response: Please refer to OCC-357, Attachment 1 CONFIDENTIAL, for the positions related to the 2025 severance amount. As indicated in the Company’s response to interrogatory OCC-357i the amount of severance expense incurred in 2025 is higher than previous years due to activities related to organizational effectiveness. Therefore, the Company calculated an updated Rate Year amount for severance pay based on an average of 2021 through 2024. The Company will incorporate this Rate Year update as part of an overall update to its cost of service. Prior Referenced Response: i i OCC-357 Question: Severance Pay. a. Please provide the amount of severance expense (direct and allocated) for each of the years 2021, 2022, 2023, 2024, 2025 and the amount included in the rate year. b. State whether the Company has or has plans to terminate any employees in the remainder of 2026, 2027 and the rate year. OCC-357 Response: a. Please refer to OCC-357, Attachment 1, for the amount of severance expense incurred in years 2021 through 2025 and included in the Rate Year. In preparing this response the Company identified that the amount of severance expense incurred in the 2025 Test Year and ultimately escalated for the Rate Year is higher than previous years, due to activities related to organizational effectiveness. Therefore, the Company calculated an updated Rate Year amount for severance pay based on an average of 2021 through 2024. This updated Rate Year amount is also included in OCC-357, Attachment 1. The Company will incorporate this Rate Year update as part of an overall update to its cost of service.
  9. Page 145 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-708 Page 2 of 2 b. CL&P has no current plans to terminate CL&P employees under or subject to the Severance Pay Plan during the remainder of 2026 and 2027; however, the Company regularly evaluates business circumstances to ensure it is providing safe, reliable and cost-effective service to its customers, which could lead the Company to make organizational changes subject to the Severance Pay Plan in the future.
  10. Page 146 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-709 Page 1 of 1 Date Filed: September 24, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Consumer Counsel Question: ESC Capital Cost. Refer to the response to OCC- 373. a. Was the ESC capital funding approved in the prior rate case based on the CL&P or the weighted average ROE? b. Provide the annual amount approved in the prior rate case for each year 2021, 2022, 2023, 2024 and 2025. Response: a. The ESC capital costs approved in the prior rate case (Docket No. 17-10-46) were based on the CL&P ROE of 9.25%, as calculated on Late Filed Exhibit No. 41, Attachment 1 and referenced on page 8 of the Interim Decision dated March 28, 2018. b. The approved ESC Capital Costs amounts for 2021-2025 are based on the Rate Year 3 calculation found in Late Filed Exhibit No. 41, Attachment 1, as filed in Docket No. 1710-46. Year 2021 2022 2023 2024 2025 Amount (000’s) $10,802 $10,802 $10,802 $10,802 $10,802

As listed on the current system

Corres. 10/01/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (0CC Set 16).

This filing on the current system (opens in a new tab)