  1. Page 29 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-627 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-01)(MS24E) p. 52. Please explain why standby work performed at the Torrington WC on March 28, 2024, was charged to the MS24E event. Response: MS24E brought widespread heavy rain that saturated the soil and was immediately followed by strong northwest wind gusts, causing trees to uproot and damage to occur across the Company’s service territory. The specific work performed by this vendor was a post-storm patrol tasked with identifying and repairing any remaining storm-related damage. The tasks performed by this contractor in furtherance of this objective included replacing multiple severed crossarms, removing large limbs off of the power lines, replacing lightning arrestors and re-hanging primary that was floated to temporarily restore power. The contractor was engaged and dispatched by the Company to perform these specific tasks and should have billed the Company at the applicable working rate. Instead, the contractor inadvertently billed the Company at the standby rate.
  2. Page 30 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-628 Page 1 of 1 Date Filed: September 24, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-01)(MS24E) p. 53-63. The work associated with this invoice was performed on March 18-20, 2024. Please explain how the Company verified the work resulted from event MS24E. Response: Please refer to Exhibit ACCT-2 (CLP-5)(MS24E), Outside Line Contractors, at Line 37, Asplundh Construction Corp, in amount of $5,521. The charges on this invoice are related to post storm repairs after post storm patrols were completed. Repairs included replacing cross arms and vice tops. Please refer to OCC-628, Attachment 1, for the results of the patrol findings in the western region of the state that include the job locations associated with the Asplundh Construction Corp invoice.
  3. Page 31 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-629 Page 1 of 1 Date Filed: September 24, 2026 Witness: John P. DiPaola-Tromba, Sean D. Redding and Jenna Turner Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2 (CLP-5A-01) (MS24E) p. 65-66. Please confirm that this crew was on standby throughout March 11 and March 12, 2024, performed no work, and was paid overtime. Response: The tree crew worked a 16-hour overnight shift which was billed as work time at the overtime rate as it was outside the standard work schedule hours. There is no standby designation or rate for tree crews. The crew did not record any ticket locations.
  4. Page 32 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-630 Page 1 of 1 Date Filed: September 24, 2026 Witness: John P. DiPaola-Tromba, Sean D. Redding and Jenna Turner Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2 (CLP-5A-01) (MS24E) p. 67-72. The timesheets were corrected to reflect time billed to MS24E rather than MN24F. Please explain: a. Who corrected the timesheets? b. On what basis (what evidence) were the timesheets corrected to bill these crews who incurred nothing but standby expenses on March 12 to MS24E? Response: a. The Eversource Arborist corrected the timesheet. b. The Arborist corrected the timesheet based on their knowledge of what day the tree crew worked and the associated storm event FWO. The tree crew was placed on storm shift at the direction of Eversource Operations.
  5. Page 33 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-631 Page 1 of 1 Date Filed: September 24, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to Exhibit ACCT-2(CLP-5A-01)(MS24E) p. 218-254. a. Did the vendor Central Connecticut Cable Company perform any work or did they bill for standby for the two days? b. If they billed for work, please indicate where the work was noted on their timesheets. Response: a. During restoration events, the Company relies on underground contractors to assist with direct buried issues as well as major underground cable outages. Their expertise can help significantly reduce outage times when underground issues occur. For this storm specifically, the Company (fortunately) did not experience any major cable faults or underground issues that required Connecticut Cable to be deployed. Accordingly, Connecticut Cable charged standby for the duration of the storm. b. N/A.
  6. Page 34 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-632 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to Exhibit ACCT-2(CLP-5A-02)(MS24E) p. 84-85. a. The work associated with these invoices was performed for ten days after MS24E. Please explain how the Company verified the work resulted from event MS24E. b. Please refer to p. 84. Please explain how replacing a rotten pole was attributed to MS24E. Response: a. Referring to Exhibit ACCT-2(CLP-5A-02)(MS24E) line 112, p. 71-85, invoice totaling in the amount of $7,749. In response to subparts a and b, The Company determined during the preparation of this response that these costs are not associated with the event. Accordingly, The Company will supplement ACCT-2 (CLP-5) (MS24E), to remove the cost. b. Please refer to the response to subpart (a), above.
  7. Page 35 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-633 Page 1 of 1 Date Filed: September 24, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to Exhibit ACCT-2(CLP-5A-02)(MS24E) p. 115, which lists in the description of work communication line down. a. Did the Company reinstall/repair a communication line? b. If yes to a, did the Company recover this cost from the communications company? Response: a. The Company does not reinstall or repair any communications lines. A crew was dispatched due to the customer reporting low wires in their driveway. At the point they determined it was not Company equipment, the crew communicated the information back to the Company and was available for another assignment. b. N/A
  8. Page 36 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-634 Page 1 of 3 Date Filed: September 28, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (Storm MN25K - Timesheets) Refer to Exhibit ACCT-2 (CLP-13A-16) (MN25K). The following pertains to invoices #3634R, 3635R, 3633R, 3648R, 3646R, and 3644R (p. 30-173) and invoices #3630R, 3643R1, 3639R2, and 3636R1 (208-285): a. Several timesheets (ex. p. 38) contain missing information within the ‘Work Distribution’ section. Explain how the Company verified and justified the work performed for the hours stated in box 12 (Work Time) without event information to indicate time worked. b. Several timesheets (ex. p. 37) contain a difference in hours worked in boxes 6 and 7 (start time and end time) compared to boxes 24 and 25 (event start time and event end time). Explain what work occurred during the time differential including the event details, the event start time, the event end time, and any documentation over the work performed. Cite to the contract provision contained in the contracts provided in Response to OCC-44 explaining that the tasks noted should be logged as work and not standby. Response: a. Reviewing the specified timesheets, there is no significant missing information within the “Work Distribution” section. The timesheets are not live documents that can be used to track the crews on a minute-by-minute basis, nor is the timesheet the method by which the Company manages the crews or assures that the crew is working how and where they are supposed to be. The timesheets are used to track the time spent on the system primarily from a work status perspective and are typically filled out after the day’s work is done with reference to the major work assignments. It is not realistic to expect that the crews will record every activity that they have engaged in during the day with specificity because this would detract severely from the job at hand, which is the emergency response and restoration of power while maintaining paramount attention to the personal safety of these critical resources. The Company manages the crews through the oversight of the employee dispatching the crews and the External Field Resource Coordinator (EFRC), who is physically in the field with the crews, each assuring that the crews are properly engaged and assigned work to restore the system from storm damage. The linemen who are filling out the timesheets are primarily focused on ensuring that their crews are working safely in a dynamic
  9. Page 37 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-634 Page 2 of 3 environment that is full of potentially lethal hazards. The EFRC is the Company representative that is responsible for signing the timesheets and they have personal knowledge of the work that the crews have performed and the activities they have engaged in, particularly in relation to the hours stated in boxes 6 and 7. The Company also verifies that crews were actively engaged in storm restoration activities through operational oversight, dispatch records, crew assignments, and direct EFRC field supervision. As a result, the Company is able to confirm that the hours recorded in Box 12 reflect time during which the crews were performing restoration-related work or restoration-support activities, regardless of whether a specific event number was recorded within the Work Distribution section. Importantly, the crews are on a working status from the time they are directed to report for duty until restoration activities are completed and they are released from duty at the end of the shift. They do not get paid by the specific restoration “event” that they are assigned to and they will not be actively working an “event” every hour of a work shift. There is time that must be taken at the start and end of the day and between active restoration “events” to complete all of the steps necessary to assure safe conditions in the field while they work the event. These activities include, but are not limited to, receiving work assignments, conducting safety briefings, performing required vehicle inspections, obtaining and staging materials, traveling to and between work locations, assessing damage, coordinating switching activities, establishing safe work zones, and completing job site closeout activities. For the Resource Management Teams identifying jobs and deploying crews, and for the EFRC, the critical focus is to follow procedures, keep the crews safe, and keep them moving efficiently throughout the working shift. In this context, there is no bright line that separates one event from another and dissects the day from an “event” perspective. All activities, whether in preparation for restoration work or actively performing restoration work, are proper work activities undertaken during the work shift and will not necessarily be specified on the timesheet. Accordingly, the absence of detailed event information within portions of the Work Distribution section does not indicate that work was not performed during those hours. b. Please refer to subpart (a), above. Further, all contractor crews and non-Connecticut based Company employees working storm restoration in Connecticut are required to be lodged in hotel rooms. Prior to beginning their first job of the day, the crews eat a meal, conduct safety briefings, perform U.S. Department of Transportation mandated pre-trip inspections on their trucks, and restock their trucks as necessary with material needed for their day. This takes time and
  10. Page 38 of 148

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-16 Date Issued September 10, 2026 OCC-634 Page 3 of 3 the crews are methodical because they don’t want to get out into the field without the right equipment or materials. The crews may start the work shift by driving from their hotel rooms to the job site and depending on the availability of hotel rooms, that can add an additional 30 minutes or more. During this period, the crews remain under Company direction, available for assignment, and engaged in activities necessary to support restoration operations. At the end of their last job of the day, the crews are required to clean up their job site, properly store all equipment and tools, eat a meal after performing physical labor all day in situations where their personal safety is continually at risk and often in unforgiving conditions; and drive back to their hotel rooms, which again, could be 30 minutes or more away from the jobsite. Therefore, intervals of time at the start and end of the work shift and between restoration “events” are an expected and necessary part of the work shift, for which the crews are paid. Within a work shift, the crews do not get paid differently for different types of work. Therefore, from a field perspective, the start and stop time is the critical datapoint for the timesheet. Refer to p. 4495 of OCC-044, Attachment 2 CONFIDENTIAL, Exhibit A - Pricing Schedule. Emergency Response Working Rates for Labor are defined as the agreed labor rates payable from the commencement of applicable Emergency Response Work through to termination of such Emergency Response Work, excluding rest time during the Emergency Response Work. The crews were not in a period of rest or otherwise unavailable to perform work. During the periods reflected by the difference between Boxes 6 and 7 and Boxes 24 and 25, crews remained under Company direction and were engaged in activities such as safety briefings, vehicle inspections, travel to and between assignments, material procurement and staging, damage assessment, job site cleanup, and other restoration-support functions necessary to facilitate emergency restoration work. Accordingly, the Company considers this time to be payable Working Time, consistent with the contractual definition of Emergency Response Working Rates, rather than standby time. The event start and end times recorded on the timesheet identify a particular restoration assignment and do not capture the full range of restoration-support activities performed during the shift. Because the crews remained in working status from the time they reported for duty until they were released from duty, the differential is payable as working time and not standby time.

As listed on the current system

Corres. 10/01/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (0CC Set 16).