Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Discovery Compilation (EOE Set 5 and UCONN Set 2)

Files3

Search terms highlighted
Eversource rate increase is on 11 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
9 pages match
  1. Page 101 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-232 Page 2 of 2 requirements. “Vine” does not represent a specific work location or activity; rather, it is an administrative entry used when crews are engaged in storm-related work but are not responding to a particular ticket. The Company verifies storm-related work using additional records, including timesheets, dispatch information, and field oversight, and therefore does not rely solely on the placeholder entry for validation purposes. b. New Rd is the location of the Madison Area Work Center (AWC). It signifies the tree crew was on shift and located at the work center. “Nt-Nt” is a default blank field for pole numbers. If there are no pole numbers recorded, the system prints “Nt-Nt”. c. The tree crew’s work hours are not broken down by event locations so this time cannot be separated out. d. The tree crews referred to in Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-16 on pages 135-151 were non-local tree crews from South Carolina (pages 138, 146, 148, and 150) and North Carolina (140, 142, and 144). The tree crews were mobilizing and travelling from South Carolina and North Carolina to Connecticut on January 7-8, 2024. e. Contractor tree crews receive meals or meal per diems during active storm response per contract agreements. Lucas Tree’s contract for non-local tree crews includes a per diem of $25 per meal per day (up to 3 meals per day). The $75 per diem charged is appropriate per the contract provisions.
  2. Page 102 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-233 Page 1 of 1 Date Filed: September 25, 2026 Witness: John P. Dipaola-Tromba, Sean D. Redding, Jenna M. Turner, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-TREE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-16, pp. 185-187. The Company reported an incremental charge of $599 for the Lucas Tree Experts vendor. The charge was related to hotels for the evening of January 7, 2024, several days prior to the MS24A event. Explain how the charges relate to the MS24A event and provide documentation to support the applicability of the charges. Response: The contractor tree crews were mobilized from South Carolina to support the anticipated storm event beginning on January 9, 2024. Due to the distance involved, multiple days of travel were required for the crews to reach Connecticut. The hotel charges incurred on January 7, 2024, reflect an overnight stop in Virginia to satisfy required rest periods during transit. The crews traveled on January 7 and January 8 to ensure they arrived in Connecticut rested and prepared to begin restoration work on January 9. The Eversource Arborist's approval of the timesheet confirmed that this travel was necessary to support and was appropriately charged to the MS24A event.
  3. Page 103 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-234 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-16, pp. 193-212. The Company reported two incremental charges in the combined amount of $153,711 for the M J Electric LLC vendor. Respond to the following: a. Explain why the equipment was charged at 50% for standby. If applicable, cite the applicable contract provisions. Additionally, identify the remaining amount ($) of equipment that was charged for standby. b. Referring to p. 207, confirm that the Company included a charge applicable to “car vs pole”. If confirmed, identify the total impact of this activity and explain why this amount was not eliminated from the storm recovery request. As part of the response, please provide an unlocked Excel spreadsheet supporting applicable calculations. Response: Please refer to Exhibit ACCT-2 (CLP-1)(MS24A), Outside Line Contractors, Lines 443-444, MJ Electric LLC, in the combined amount of $153,711. a. Per the COC contract provisions in Exhibit B “Pricing Schedule” and within Appendix PS5, the contractor is required to charge 50% of the equipment rates while on standby. Additionally, the remaining amount of equipment charged for standby was $4,896.75. b. During the internal review process, it was determined that the work associated with Event 5234191 was related to storm-induced tree damage to equipment and not a car vs pole incident as indicated on the timesheet. Therefore, the associated charges were retained as storm-related costs and were not removed. The incorrect work description appears to have been a documentation error. During storm restoration activities, personnel are often managing multiple work orders simultaneously and recording information in the field, including handwritten notes when necessary. Based on the review of the supporting documentation, the Company determined that the work performed was storm-related and that the discrepancy was limited to the description recorded on the timesheet. In addition, please refer to EOE-234, Attachment 1, for the OMS details related to Event 5234191 to validate repairs were due to tree damage.
  4. Page 104 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-235 Page 1 of 2 Date Filed: September 25, 2026 Witness: Leanne M. Landry and John G. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-FOOD) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-16, p. 213. The Company reported an incremental charge of $31,432 for the Madison Lakota Oaks FB LLC vendor. The charges included 160 meals (e.g., “To Go Breakfast” and “sandwich To Go Lunch”) for January 12, 2024. Identify if all of the referenced meals were utilized in support of the MS24A event, and if so, by which vendor(s). If not all used, explain why they could not be canceled. Response: Referring to Exhibit ACCT-2 CLP-1A-16 (MS24A), Madison Lakota Oaks, for charges of $31,432, which included dinner for Wednesday, January 10, 2024, ‘to go’ breakfast, lunch and buffet dinner for Thursday, January 11, 2024, and ‘to go’ breakfast and lunch for Friday, January 12, 2024. Under the Company’s ERP for a severe weather event, resource and logistical acquisitions such as hotel rooms and food, must be undertaken ahead of time based on the expected severity and complexity of an event. Expected complexity and the associated resource and logistical requirements are analyzed based on considerations of numerous factors including, but not limited to, forecasted weather conditions; certainty of the weather forecast, size of the anticipated incident and expected impacts to personal safety and property, outage prediction modeling, anticipated extent of potential or known damage, and historical experience with other events. The Company cannot wait until a predicted weather event actually reaches its service territory to formulate its response plan and secure needed resources, as PURA has established pursuant to Conn Gen. St. §§16-32e, 16-32h and PURA’s performance standards, as well as the structure and implementation of the ERP. If the Company were to wait until a storm’s actual impact to secure mutual aid and contractor crews, hotels, food services and other logistics necessities, critical resources may not be available when needed, or, even if available, would be significantly more expensive than if procured earlier. The Company makes every effort to cancel rooms that are unused if known within the timeframe for allowed cancellation according to the hotel policy. However, based on the shifting restoration needs or priorities, crews are often relocated within regions of the service territory to work on restoration well after the cancellation period has expired and may have to be re-assigned to other
  5. Page 105 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-235 Page 2 of 2 hotel rooms that are closer to their physical work location (the Company focuses on locating crews as close as possible to their assigned restoration jobs to minimize the need for travel, thus freeing them up for actual restoration work). The Company must meet its contractual obligations with each hotel to pay for rooms reserved post the cancellation time frame. It is also important to note that, in times of service outages, there are other demands on hotel space from displaced residents that are experiencing service outages. As a result, the Company needs to be able to have adequate facilities to house the crews that are required to be on-site at the outset of an event, and the Company does that through contractual and logistical commitments made ahead of the event. In preparation for the storm event, the Company had booked rooms at the Madison Lakota Oaks for Wednesday, January 10, 2024 and Thursday, January 11, 2024 nights and ordered all meals as noted previously. On January 8, 2024, the Madison Lakota Oaks confirmed that food had been ordered to accommodate all meals and could not be cancelled. Due to changes in food and lodging needs for the storm event, the Company had to cancel the rooms. The cancellation notification was sent via email on Wednesday, January 10, 2024, at 11:37am. The Company did not incur any charges for the cancelled rooms, but did incur the cost of the ordered food.
  6. Page 106 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-236 Page 1 of 2 Date Filed: October 01, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE; WIRE GUARDS) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-16, pp. 214-225. The Company reported four incremental charges in the combined amount of $60,030 for the Maverick Construction Corp vendor for Wire Guards. Respond to the following: a. Confirm that the wire guards were not utilized for remediation services (i.e., guarding downed wires). If not confirmed, cite the supporting documents demonstrating the actual services that were rendered. b. Identify the billings attributed to mobilization, demobilization, and standby. If response to subsection (a) identifies actual remediation, please also include the billings attributed to work. c. Referring to pp. 216, 219, 222, and 225, the Company provided Eversource Contractor Storm Mobilization & Demobilization Time Reports that billed eight hours of mobilization and four hours of demobilization for every vendor employee with a general location reference of “Various locations throughout the northeast, NY, PA, Boston MA”. Explain how vendor employees could have mobilized/demobilized from “various locations” but were permitted to bill the same number of hours. Additionally, explain how the Company was able to validate the accuracy of the billed hours given the lack of locations for each billed individual. d. Provide documentation to support the specific efforts performed by the Company to obtain local wire down guard crews in lieu of those “throughout the northeast”. e. Cite the location of the specific contract and pricing schedule supporting the rates charged for the services (i.e., wire down guards) provided. Response: a. Wire Guards procured from Maverick Construction Corp were hired to perform wire guard functions exclusively. Due to the storm not materializing as forecasted, Maverick resources were not deployed to the field. The associated charges were related to mobilization, time awaiting potential deployment and demobilization. b. All charges are attributed to mobilization, demobilization, and standby.
  7. Page 107 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-236 Page 2 of 2 c. The contractors are hired from a specific hiring location. The agreements pay for mobilization from that location. The individual resources are not paid for their specific locations. For this invoice the contractor mobilized from Boston MA to be staged in CT and traveled during a weather event. d. Eversource seeks to secure the most commercially competitive suppliers with the closest available qualified wire down guard resources to support storm response activities. The resource acquisition process begins with outreach to available local and regional resources and expands geographically as necessary to satisfy forecasted staffing requirements, with priority given to qualified suppliers under existing agreements. Resource availability is often impacted by the geographic scope of the weather event and competing demand across affected utilities. Accordingly, Eversource attempts to utilize local resources where available and supplements those resources with regional crews when local availability is insufficient to meet operational needs. For MS24A, the Company contacted available resources within the region and expanded its requests as necessary to obtain the required staffing levels. Due to storm-related demand and resource availability constraints, regional resources were utilized to supplement locally available wire down guard personnel. e. The rates charged for the Wire Down Guard services are supported by the Maverick Construction Corp. Agreement for Wires Down Guards for Electric Utility Distribution Emergency Response Program Work, provided in OCC-044, Attachment 2, Page 3982.
  8. Page 108 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-237 Page 1 of 3 Date Filed: September 29, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 41-64. The Company reported an incremental charge of $97,518 for the McPhee Electric LTD vendor. Respond to the following: a. Explain why the vendor billed at DT rates from 6:00am on January 10, 2024, when it didn’t receive its first work assignment until 10:00am, four after the vendor’s start time. As part of the response, identify the incremental impact of billing four hours at DT rates in lieu of OT rates applicable during standby. b. Referring to pp. 50-58 and 60-64, the documents appear to be corrupt (i.e., too small to inspect). Please provide legible copies of the referenced documents. c. Cite the location of the vendor’s contractual Pricing Schedule Exhibit (i.e., typically referred to as Exhibit A). The contract provided at OCC-044, Att.2 (Confidential), starting at p. 3989 includes a List of Exhibits at d. p. 3995 which references the Pricing Schedule as Exhibit B which could not be located in the document. e. Referring to pp. 46-47, explain why the equipment was charged during standby when the Company’s Master Service Agreement omits billing of equipment during standby. Additionally, identify the amount ($) of equipment that was charged for standby. (Note, please assess all invoices to include the illegible ones referenced in subsection b.) Response: Please refer to Exhibit ACCT-2 (CLP-1)(MS24A), Outside Line Contractors, at Line 453, McPhee Electric LTD, in the amount of $97,518. a. Based on the Company’s review of the specified timesheets, there is no significant missing information within the “Work Distribution” section. The timesheets are not intended to be an exhaustive record of every minute, task or discrete activity undertaken by a crew in the course of performing its work. Nor is the timesheet the method by which the Company manages the crews or assures that the crew is working in the manner and location that they are supposed to be. The timesheets are used to document the time worked and general nature of the work performed. Given the nature of storm restoration work, it would be impractical and inconsistent with the crews’ primary responsibility of safely and efficiently
  9. Page 109 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-237 Page 2 of 3 restoring electric service to require personnel to record every work task or discrete activity performed throughout the workday. The Company manages the crews through the oversight of the employee dispatching the crews and the External Field Resource Coordinator (EFRC), who is physically in the field with the crews, ensuring that the crews are properly engaged and assigned work to restore the system from storm damage. The linemen who are filling out the timesheets are primarily focused on working safely in a dynamic environment that is full of potentially lethal hazards. The EFRC is the Company representative who is responsible for signing the timesheets and they have personal knowledge of the work that the crews have performed and the activities they have engaged in, particularly in relation to the hours stated in Boxes 24 and 25. Importantly, the crews are in “working” status for the entire duration of their shift – from start to finish. The Company does not compensate crews based on the specific restoration event to which they are assigned, nor are crews expected to be actively engaged in an “event” every minute of their shift. Time must be allocated at the start and end of each day, as well as between restoration “events,” to complete all necessary steps to ensure safe working conditions in the field. For the Resource Management Teams identifying the jobs and deploying crews and the EFRC, the critical focus is to follow procedures, keep the crews safe, and keep them moving efficiently throughout the working shift. In this context, there is no bright line that separates one event from another, precisely segmenting the day from an “event” perspective. All activities, whether in preparation of, or “on the pole,” are proper work activities that are undertaken during the work shift and will not be specified on the timesheet. b. Please refer to EOE-237, Attachment 1 CONFIDENTIAL, for legible copies of expense receipts from McPhee invoice number 21327RR. c. The vendor’s contractual Exhibit B Pricing Schedule was inadvertently omitted from the materials originally submitted due to a clerical error during the submission process. The Exhibit B Pricing Schedule is now being provided as EOE-237, Attachment 2 CONFIDENTIAL. d. The vendor’s contractual Exhibit B Pricing Schedule is provided as EOE-237, Attachment 2 CONFIDENTIAL. e. Under the applicable Master Service Agreement, contractors are entitled to payment for equipment at 50% of the applicable equipment rate while on standby, as provided in Section 3.6, page 5 of EOE-237, Attachment 2 CONFIDENTIAL, (Exhibit B Pricing Schedule). Accordingly, the equipment charges during standby were billed pursuant to the applicable contractual standby provisions. In addition, the total amount of $3,857.28 was charged for equipment.
  10. Page 110 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-237 Page 3 of 3 With respect to field crew timekeeping, a field crew may characterize time during a shift as “standby,” reflecting the physical status of the crew at a particular point in time. However, this characterization does not indicate that the crew or associated equipment was inactive or demobilized. During these periods, contractor resources may remain fully mobilized at the designated work or staging location, with personnel and equipment committed to Company operations and prepared to perform work immediately upon assignment. For example, resources may be awaiting the next ticket or work assignment, further direction from the Company, or otherwise transitioning between assignments, while supporting ongoing operations. Although the field crew may characterize this time as “standby” on its timesheet, the resources remain deployed and available only to Eversource for work purposes. Therefore, the working rate contractually applies.
2 pages match

As listed on the current system

Corres. 10/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (EOE Set 5 and UCONN Set 2)

This filing on the current system (opens in a new tab)