  1. Page 115 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-240 Page 1 of 1 Date Filed: September 25, 2026 Witness: John P. DiPaola-Tromba, Sean D. Redding and Jenna Turner Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-FOOD) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 176-177. The Company reported an incremental charge of $484 for the Orems Diner of Wilton LLC vendor for meal services. Confirm that these meals were provided to vegetation crews. If confirmed, identify if the meal costs were included in the Company’s Frontier Billing. Response: The meal services on January 10, 2024, were provided to vegetation crews during the MS24A restoration event. The meal services were collected through meal tickets and were not a meal expense on the vegetation crews timesheets. As the cost was not incurred through Vegetation Management, it was not included in the Company’s Frontier reimbursement.
  2. Page 116 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-241 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 215-235. The Company reported an incremental charge of $219,637 for the Premium Utility Contractor Inc vendor. Respond to the following: a. Referring to pp. 217-221, explain why the vendor billed at DT rates from 6:00am on January 10, 2024, when the crews didn’t receive their first work assignment until 9:00am, three hours after the vendor’s start time. As part of the response, please identify the incremental impact of billing three hours at DT rates in lieu of the OT rates, as well as the corresponding equipment charges that would otherwise be excluded during standby. b. Referring to pp. 222-224, explain why the vendor billed at DT rates from 6:00am on January 10, 2024, when the crews didn’t receive their first work assignment until 10:00am, four hours after the vendor’s start time. As part of the response, please identify the incremental impact of billing four hours at DT rates in lieu of the OT rates, as well as the corresponding equipment charges that would otherwise be excluded during standby. Response: a. Contractually, when the Company instructs a contractor to be on shift, ready for work, that automatically places the contractor on “Work Time” rates, regardless of when their first event is assigned. As such, the contractor billed the Company correctly as they were assigned to begin working at 6:00am on January 10, 2024. Although not relevant since the contractor billed the Company appropriately, the incremental variance between DT rates and OT rates that were charged for labor hours is $4,604.85 and $1,443.58 for equipment. b. As explained in part a, the contractor was assigned to be on shift, ready to work at 6:00am on January 10, 2024, thereby placing them on “Work Time” rates. Although not relevant since the contractor billed the Company appropriately, the incremental variance between DT rates and OT rates that were charged for labor hours is $3,438.16 and $805.08 for equipment.
  3. Page 117 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-242 Page 1 of 2 Date Filed: September 28, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-EQUIPMENT) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, p. 236. The Company reported an incremental charge of $12,361 for the PRIME Power Rental Inc vendor. Respond to the following: a. Provide screenprints of the vendor’s website. b. Provide copies of any service level agreements (SLAs) between the Company and the vendor detailing the amount of time permitted for the vendor to provide a generator upon request. If SLAs do not exist, explain why. c. Confirm that the Company allocated the invoiced amount between the MS24A and MS24B events. If not confirmed, explain why the invoice is approximately double the amount allocated to MS24A. d. Identify if any of the generators were utilized in support of storm response. For any generators not used, explain why the Company rented the generators. Additionally, identify if there were any specific outages that warranted the rental of the generators that were resolved before usage. Response: Referring to Exhibit ACCT-2 (CLP-1)(MS24A), Outside Line Contractors, at Line 469, Prime Power Rental LLC, in the amount of $12,361.00 a. Please refer to EOE-242, Attachment 1, for a screenprint of the vendor’s website. b. At the time the services were required, the Company did not have an existing contract or service level agreement (SLA) with the vendor that specifically established a required response time for the provision of generators. The vendor was engaged on an emergency basis to support customer needs during outage restoration. The availability of portable generators provided the Company with an additional resource to support customers for the duration of extended outages, including vulnerable customers who rely on a continuous source of power for individual needs.
  4. Page 118 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-242 Page 2 of 2 Given the emergent nature of the need, the services were retained in accordance with the Company’s Procurement Policy, which permits the Company to secure necessary resources during emergency conditions without an existing contract specifically established for that scope of work. Accordingly, no formal SLA establishing a prescribed generator delivery timeframe was in place for these services. c. The Company confirms that the invoiced amount is allocated between the MS24A and MS24B events. Please reference Exhibit ACCT-2 (CLP-1)(MS24A), line 469 for the amount of $12,361. Please reference Exhibit ACCT-2 (CLP-2)(MS24B), line 492 for the amount of $12,361. d. None of the generator units referenced in Confidential Exhibit ACCT-2 CLP-1A-17, p. 236 were deployed during the two storm events. In both cases, the Company was faced with credible forecasts of severe weather and widespread power outages (Exhs. CLP-STORMIMT-1; CLP-STORM-IMT-3 (Event 01-MS24A); CLP-STORM-IMT-3 (Event 02MS24B)). Under these circumstances, the Company secured these generators to ensure system reliability and protect public safety.
  5. Page 119 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-243 Page 1 of 3 Date Filed: October 02, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 238-301. The Company reported seven incremental charges in the total amount of $1,321,356 for the Quality Lines Inc vendor. Respond to the following: a. Referring to pp. 243, 249-252, 258-261, 267-270, 276-283, 289-292, and 298-301, explain why the vendor was permitted to bill for travel time prior to the commencement of work when the vendor was subject to a flat rate for Mobilization/Demobilization? As part of the response, identify the amount of travel that was billed and provide documentation supporting the billed travel hours for each crew (i.e., starting/ending locations) and identify the incremental travel costs (i.e., for both vendor employees and equipment) that were included within the recovery request. b. Identify who owned the equipment used by the various crews that were flown in. c. Referring to pp. 258-261, explain how the vendor was permitted to bill for 13 hours when they recorded a total of 11 hours within boxes 6 and 7 (i.e., 4am to 3pm) and failed to record any hours within boxes 24 and 25 (i.e., Event Start Time and Event End Time). As part of the response, identify the incremental impact of the two hours of additional billing (i.e., for both employees and equipment) that were included in the recovery request. d. Comparing pp. 274-275 with pp. 276-279, explain how the vendor could have mobilized as of 8pm on January 9, 2024 (see e.g., p. 274, box 22) and then commenced additional billing at 6pm on the same day (see e.g., p. 276, box 6). To be clear, the documentation supports that duplicate billing occurred between the hours between 6pm and 8pm. As part of the response, identify the incremental impact of the duplicate hours billed. e. Referring to pp. 280-283, confirm that the vendor failed to include details regarding the work start and end times (i.e., boxes 24 and 25) for January 10, 2024. If confirmed, explain how the Company was able to derive the correct treatment of travel (box 10), standby (box 11), and work (box 12) hours. As part of the response, provide documentation to support the timing for the actual commencement of work. Response: a. As these crews were on Eversource property and working restoration activities, it is typical for contractors to travel from one job work site to another as they address multiple restoration jobs. The timesheets referenced in this question reflect the contractors
  6. Page 120 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-243 Page 2 of 3 travelling from one working location to another working location. This is all part of normal work and restoration activities. The flat rate mobilization was complete and unrelated to the travel on the Working Time Sheets. b. Quality Lines owned and maintained a yard located near the airport during this time. Quality Lines utilized their own equipment. c. The variance for the additional two hours billed is $11,649.94 in labor and $1,762.00 in equipment. Upon further review in drafting this response, the Company determined that these costs will be reduced. The Company will supplement Exhibit ACCT-2 CLP-1 (MS24K), line 470 to reflect the new total of $164,841.06. d. The Mobilization timesheet was based on a “Fly-In” Flat rate crew rate. Traveling from Nashville, Tennessee, to East Windsor, Connecticut, is only 2 hours and 15 minutes. Based on this travel time, the Company has determined that the start and end times on the Mobilization Timesheets were entered incorrectly and should have been revised. However, this clerical error did not result in an upcharge or duplicate charge as this was charged as a “Flat Rate”. The Company reviewed the State Resource Acquisition’s Report and confirmed that this crew did arrive on site at 6PM. Therefore, based on the information above and the confirmation from the report, there were no “duplicate” hours billed and the Working Timesheet hours are correct and invoice was billed correctly. e. Yes. Eversource confirms that the vendor did not complete boxes 24 and 25 on the referenced timesheets for January 10, 2024, and therefore did not separately identify the start and end times associated with each activity on each individual timesheet. Although the activity details were not repeated on each timesheet, the supporting timesheet package was reviewed collectively. The personnel reflected on the related timesheets reported consistent hours and were supporting the same restoration activities. Based on the documentation provided, it appears the vendor included the applicable activity detail within the overall timesheet package rather than duplicating the same information across each individual timesheet. The treatment of the reported hours was also supported by the mobilization and worklocation information contained in the documentation. The mobilization records reflect the crews arriving at their designated reporting location, while the subsequent work records identify assignments in other service-area locations. The travel hours reported are consistent with the geographic distance between the applicable reporting location and the
  7. Page 121 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-243 Page 3 of 3 assigned work areas, and the remaining reported work hours are consistent with the documented restoration activities performed during the applicable period. The vendor should have provided the specific start and end times and corresponding activity detail on the individual timesheets. However, the omission of those fields does not, by itself, establish that the categorization of the hours was incorrect. The Company relied on the complete supporting package, including mobilization information, worklocation information, crew hours, documented restoration activities, and the review and approval of the applicable Eversource representative. Eversource representatives responsible for approving contractor timesheets are expected to validate that the reported labor activities and hours are consistent with the work performed and the information available to them prior to approving the timesheet. The supporting documentation, when reviewed collectively, provides validation for the reported travel, standby, and work hours despite the vendor’s omission of the detailed start and end times from the individual timesheets.
  8. Page 122 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-244 Page 1 of 2 Date Filed: September 28, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 302-316. The Company reported an incremental charge of $64,884 for the Riggs Distler & Company Inc vendor. Respond to the following: a. Referring to pp. 306-316, explain why the vendor was permitted to use a different Eversource Contractor Storm Daily Time & Work Report than is outlined within the Eversource Contractor Storm Daily Time & Work Report Procedure (Procedure) provided at EOE-022, Att.5. Additionally, referring to pp. 309, 314-316, explain why the vendor was not required to complete the information within boxes 24-26 (i.e., tracked hours per OMS event) as outlined within the Procedure. b. Cite the location of the vendor’s contractual Pricing Schedule Exhibit (i.e., typically referred to as Exhibit A). The contract provided at OCC-044, Att.2 (Confidential), starting at p. 5472 includes a List of Exhibits at p. 5478 which references the Pricing Schedule as Exhibit B but was unable to locate the document. c. Referring to pp. 306-308, 310-313, explain why the equipment was charged during standby when the Company’s Master Service Agreement omits billing of equipment during standby. Additionally, identify the amount ($) of equipment that was charged for standby. Response: a. Although the contractor did not utilize the Eversource Contractor Storm Daily Time & Work Report referenced in the applicable procedure, the documentation provided contained the key information necessary to support the billed charges, the majority of which consisted of standby hours. The supporting records included contractor details, hours worked, job locations, and required signatures. In conjunction with the Company's internal review controls and verification procedures, this documentation provided a sufficient basis for the invoice approver to validate the accuracy, reasonableness, and appropriateness of the charges. b. The vendor’s contractual Exhibit B Pricing Schedule was inadvertently omitted from the materials originally submitted due to a clerical error during the submission process. The Exhibit B Pricing Schedule is now being provided as EOE-244, Attachment 1, CONFIDENTIAL.
  9. Page 123 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-244 Page 2 of 2 c. Under the applicable Master Service Agreement, contractors are entitled to payment for equipment at 50% of the applicable equipment rate while on standby, as provided in Section 3.6, page 5 of EOE-244, Attachment 1 CONFIDENTIAL (Exhibit B Pricing Schedule). Accordingly, the equipment charges associated with standby were billed pursuant to the applicable contractual standby provisions. For purposes of contractor timekeeping, a “standby” designation may reflect the operational status of the crew at a particular point in time and does not necessarily indicate that the crew or associated equipment was inactive or demobilized. During these periods, contractor resources may remain fully mobilized at the designated work or staging location, with personnel and equipment committed to Company operations and prepared to immediately perform assigned work. For example, resources may be awaiting the next ticket or work assignment, awaiting further direction from the Company, or transitioning between assignments while remaining available to support ongoing operations. Although the contractor’s crew may refer to this time as “standby” on the timesheet, the resources remain deployed and unavailable for other work. Consistent with the contract, a total of $9,528 was charged for equipment associated with labor hours categorized as standby.
  10. Page 124 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-245 Page 1 of 2 Date Filed: September 30, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin, Leanne M. Landry, Craig Dikeman and Matthew J. Correia Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-OTHER) Refer to Exhibit ACCT-2 CLP-1, and Confidential Exhibit ACCT2 CLP-1A-17, pp. 326-327. The Company reported an incremental charge of $6,599 for the Sky Scape Industries LLC vendor. Respond to the following: a. Identify the specific services that this vendor provides. b. Confirm that the vendor was only utilized for standby. If not confirmed, provide documentation to support the services performed and explain why the invoice referred to each bill line as standby. c. Cite the section of the ERP that requires the staging (i.e., standby) of the vendor’s services discussed in subsection (a). If not included in the ERP, explain why this vendor was engaged without actual services being required. d. Provide documentation that supports both the standby hours charged (i.e., signed timesheets) and the miles incurred (i.e., mileage logs). To the extent that there are no supporting documents, explain how the Company validated the accuracy of the billing. e. Cite to the applicable contract and pricing schedule for this vendor. Response: a. Skyscape Industries has a contract with the Drone ERP team at Eversource to support the company with Drone Patrols to look for and assess damage. b. Skyscape was only needed for Standby for this storm. c. Drone services are secured as part of the damage assessment team. Per Section 2.10.1, Pre-Event Preparedness in the ERP, Damage Assessment resources are prestaged to ensure the required resources are in place in the event that they are needed for assessing critical infrastructure that cannot be easily accessed. Drone Patrols are used as a more efficient means of damage assessment and are onboarded as a supplement to the damage assessment team to ensure timely patrols are conducted in support of storm restoration efforts. d. Accuracy of billing was verified against documented minimum of 4 hours standby time if activated as part of their contract (they were on standby for 4 hours of less). Mileage was estimated against where they were staged at the time (within CT).
2 pages match

As listed on the current system

Corres. 10/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (EOE Set 5 and UCONN Set 2)

This filing on the current system (opens in a new tab)