Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Discovery Compilation (EOE Set 5 and UCONN Set 2)

Files3

Search terms highlighted
Eversource rate increase is on 11 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
9 pages match
  1. Page 159 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-262 Page 2 of 2 • Please refer to EOE-262, Attachment 3, for Union contract supporting details for milage of personal vehicles and expense plans. Please refer to Article XII, Expense Allowance, Sections 2 and Section 4, pg. 73- 75. Within this exhibit, the charges consist of a combination of incremental mileage reimbursements for employees utilizing personal vehicles outside of their normal work schedule and Expense Plan payments that are contractually earned by union employees when assigned to a reporting location other than their designated home base. Employees seeking mileage reimbursement are required to deduct their normal commuting distance and may only request reimbursement for mileage incurred in excess of their customary commute. All mileage reimbursement requests are subject to supervisory review and approval to verify compliance with Company policy. Expense Plan payments are provided pursuant to the applicable collective bargaining agreements when the Company directs an employee to report to a work location other than their regularly assigned home base. During storm restoration and emergency response efforts, the Company routinely reallocates personnel throughout its service territory to ensure that areas experiencing the greatest impact have sufficient staffing resources available to support restoration activities and maintain operational effectiveness. Accordingly, the mileage reimbursements and Expense Plan payments reflected in this exhibit were incurred as a direct result of the Company's storm response and restoration efforts and represent necessary and reasonable incremental costs associated with deploying personnel to locations where their services were required. In addition, upon further review of drafting this response, the Company determined that the total cost of $226 is associated with MS24B, thus the cost that is associated with MS24A will be adjusted to reflect the below amount within Exhibit ACCT-2 CLP-1: a. Line 35, amount will be adjusted to reflect $82. b. Line 84, amount will be adjusted to reflect $62. c. Line 271, amount will be adjusted to reflect $25.
  2. Page 160 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-263 Page 1 of 2 Date Filed: September 28, 2026 Witness: Leanne M. Landry and John G. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (MEAL POLICY) Provide any internal employee guidelines detailing the maximum cost(s) per meal that the Company would reimburse, to include the Eversource Restaurant Meal Policy provided in response to EOE-014, within Docket No. 25-12-13. As part of the response, please identify any changes to the policy since Docket No. 25-12-13. Response: Please refer to EOE-058 i, for the Company’s response regarding internal employee policies, procedures, or guidelines detailing the maximum cost(s) per meal that the Company would reimburse. The Company has not made any changes to the policy since Docket No. 25-12-13. Prior Referenced Responses: i EOE-058 Question: (EMPLOYEE MEALS) Provide any internal employee policies, procedures, or guidelines detailing the maximum cost(s) per meal that the Company would reimburse for employees. If minimum guidelines do not exist, please explain why and provide the maximum monetary threshold that the Company would determine to be 'reasonable and customary'. EOE-058 Response: Eversource’s Corporate Policy on Reimbursable Expenses for Business meals states, “Reimbursement for business meals is limited to reasonable and customary amounts as determined by the designated approver.” There are no policies, procedures, or guidelines detailing a maximum cost per meal that the Company would use to reimburse employees. The Company relies on the supervisor’s good judgment, review of the receipts, and approval of the transaction to meet the requirements of its Corporate Policy. During an ERP event, Eversource’s centralized ERP crew-care logistics, food, and lodging procedures have been recognized as an industry best-practice. All line crews, tree crews, damage assessment patrollers, and other field staff, along with support staff, are provided meals as close as possible to their work locations to minimize travel time and maximize working hours and productivity. During a storm event, the Company is required to feed the crews and staff supporting the storm restoration effort and will ensure that obligation is met while making prudent decisions on the cost per meal. To support this best practice, the Company has preferred restaurants that are used to order meals during a storm event. These agreements ensure that the Company has reliable meal providers and also provides a reasonable cost structure
  3. Page 161 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-263 Page 2 of 2 for each meal. The agreement provides “not to exceed” amounts per meal and also provides tax and tip amounts to be included in the total cost. There are circumstances and situations when preferred restaurants are at capacity or not available and other establishments are used to secure food. In some cases, the cost per meal may exceed the amounts listed in the preferred restaurants agreement but are still subject to review and expected to be reasonable and customary as established in the Company’s Corporate Policy. Please refer to EOE-058, Attachment 1 CONFIDENTIAL, for the Company Meal Agreement letter used with employees and preferred restaurants during an ERP event.
  4. Page 162 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-264 Page 1 of 1 Date Filed: September 28, 2026 Witness: Leanne M. Landry and John G. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-ACCRUAL) Refer to Exhibit ACCT-2 CLP-1. The Company reported an incremental charge of $63,628 for a Tree Accrual. Explain why the Company is reporting an accrual for Tree costs that occurred over two years ago and provide documentation supporting the amount. Response: The Company has Vegetation Management unvouchered liabilities (“UVL”) for the MS24A storm costs and is working to reconcile and confirm the anticipated charges with the appropriate vendors. The anticipated charges have not been invoiced against the storm and will not be until the charges are reconciled and confirmed.
  5. Page 163 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-265 Page 1 of 4 Date Filed: September 28, 2026 Witness: Christopher E. Colorio and Mark P. Baldwin Request from: Office of Education, Outreach, and Enforcement Question: (STORM RESTORATION) Refer to Response to EOE-020, Att. 1. Respond to the following: a. Referring to column C (EVENT COUNT), explain what this column represents and identify the situations where a ‘1’ versus a ‘0’ would be reported. b. Referring to column D (DEVICENAME), explain what information has been provided and provide a description for each type of item reported. For example, the Company appears to have reported approximately three dozen types of line items to include FUSE_OH, SCADA_REC, SS_T_CS, etc. c. Referring to column F (EVENT TYPE), explain what this column represents and specifically identify what “OUT” versus “NON” represents. d. Referring to column K (ACT-CUST-OUT), explain what this column represents and specifically identify what a “0” represents. e. Explain how the Company aligns outages to the different storm events and provide any relevant policies or procedures. As part of the response, using the MS24A event as an example, explain how the Company determined that the various new outages on January 11, 2024, would be aligned to the MS24A event when the Company’s response to EOE-19, Att. 2, identified that demobilization occurred on January 9, 2024. Response: a. Column C (EVENT COUNT) identifies whether a record represents a unique outage event. A value of 1 denotes the initial outage event and is included in the total event count. A value of 0 denotes a subsequent restoration segment, switching operation, or additional restoration activity associated with a previously counted outage event. OMS stores these restoration activities as separate records to document the progression of restoration efforts; however, they are not considered separate outage events. Accordingly, only the initial record for a given outage event is assigned an Event Count of 1, while all subsequent records related to that same outage event are assigned an Event Count of 0.
  6. Page 164 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-265 Page 2 of 4 Column D (DEVICENAME) identifies the electric system device associated with the outage or operational event. The field consists of a device-type code followed by a unique identifier used within the Company's OMS system to distinguish individual assets. The device-type code identifies the category of equipment involved in the event, while the remaining portion of the field identifies the specific asset. Common device-type codes reported in the attachment include, but are not limited to: Device Type Description XF_OH Overhead transformer XF_UG Underground transformer XF_NET_POS Network transformer FUSE_OH Overhead fuse FUSE_UG Underground fuse REC_1P Single-phase recloser REC_3P Three-phase recloser SCADA_REC SCADA-controlled recloser SCADA_REC_3P SCADA-monitored three-phase recloser LB_SW_OH Overhead load-break switch LB_DSC_OH Overhead load-break disconnect switch SS_D_CB Distribution substation circuit breaker SS_D_SW Distribution substation switch SS_D_REC Distribution substation recloser SS_D_XF Distribution substation transformer SS_T_CS Transmission/substation circuit switcher SS_T_SW Transmission/substation switch ELB_DB Underground dead break elbow device ELB_LB Underground load break elbow device 1P_TS Single-phase trip saver 2P_TS Two-phase trip saver 3P_TS Three-phase trip saver
  7. Page 165 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-265 Page 3 of 4 b. Column F (EVENT TYPE) identifies the type of OMS event record associated with the incident. “OUT” indicates an outage event that resulted in one or more customer’s being interrupted and requiring restoration. “NON” indicates an event that did not result in a customer outage but still required utility response, investigation, switching, equipment inspection, repair, or other operational actions. These events are recorded in OMS because they represent actual system incidents or operating conditions that required company attention; however, they are not considered customer outage events because no customers lost electric service as a result of the event. c. Column K (ACT-CUST-OUT) represents the number of customers who were actually without electric service for the event record. A value greater than 0 indicates the number of customers who were confirmed to be without power as a result of the event. A value of 0 indicates that no customers were actually without power for that event record. A value of 0 can occur for several reasons. For example, a customer may contact the Company to report a service outage, but subsequent investigation determines that the customer has electric service and no interruption exists. In those cases, an OMS record is still created to document the reported condition and the Company's response; however, because no customer was actually without power, the ACT-CUST-OUT value is 0. Similarly, OMS records may be generated for operational investigations, switching activities, equipment conditions, repairs, or restoration-related actions where customers are not without service. In these situations, the ACT-CUST-OUT value of 0 indicates that there were no customers out of service for that specific record. Additionally, records classified as EVENT TYPE = NON do not represent customer outage events and therefore will have an ACT-CUST-OUT value of 0. While these events may require utility response, investigation, repair, or other operational actions, they do not result in customers losing electric service. Accordingly, ACT-CUST-OUT reflects the number of customers who actually did or did not have power for a given OMS record, rather than the number of outage reports received. d. The Company aligns outages to storm events based on the cause of the outage and its relationship to storm-related damage or conditions, rather than solely on the status of contractor or mutual assistance resources. Outages may continue to be associated with a
  8. Page 166 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-265 Page 4 of 4 storm event after external resources have been demobilized if the outage is determined to have resulted from damage or conditions created by that storm. The Company reviews outage information, field observations, damage assessments, cause codes, repair records, and other operational information when determining whether an outage should be attributed to a storm event. This review may identify outages that occur after the peak restoration period but are nevertheless attributable to storm-related damage. With respect to MS24A, the Company's response to EOE-19, Attachment 2, identified January 9, 2024, as the date external storm-response resources were demobilized. The demobilization of contractor, mutual assistance, or other external resources does not necessarily indicate that all storm-related restoration activities were complete. Following demobilization, the Company may continue to perform repair work, corrective maintenance, damage remediation, and storm-related cleanup using internal resources. Accordingly, restoration and repair activity that occurred on January 11, 2024, remained aligned with the MS24A event because they were determined to be associated with damage or conditions resulting from the January 9-10, 2024 storm event. Although those outages may have occurred after external resource demobilization, the Company determined they were storm-related and therefore appropriately remained assigned to the MS24A storm event for reporting purposes. In summary, the date of external resource demobilization is not the sole criterion used to determine whether an outage is attributed to a storm event. Storm attribution is based on the relationship between the outage and the storm-related damage or conditions that caused the outage, regardless of whether restoration and repair activities are being performed by external or internal resources.
  9. Page 167 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-266 Page 1 of 1 Date Filed: September 28, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (STORM RESTORATION) Refer to Response to EOE-020, Att. 1. Explain if the Company can associate the individual outages (i.e., relevant rows within EOE-020, Att. 1) with the reported incremental costs. If costs can be associated, please supplement EOE-020, Att. 1, to include a column detailing the incremental costs for each row. Response: No. The Company does not track incremental storm restoration costs at the individual outage level identified in EOE-020, Attachment 1. Incremental storm costs are tracked and reported at the overall storm-event level in accordance with the Company's established accounting practices. Storm restoration resources may respond to multiple outage locations throughout an event, and many incremental costs are incurred in support of the overall restoration effort rather than a specific individual outage. As a result, the Company does not maintain an outage-by-outage association of the incremental costs reported for the event. Accordingly, the Company is unable to supplement EOE-020, Attachment 1, with incremental costs for each individual outage as requested.
  10. Page 168 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-267 Page 1 of 2 Date Filed: September 29, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (LINE CREWS) For each storm in the Company’s recovery request, identify the total amount of equipment that was billed by line crew vendors during standby activities. Please provide the information in an unlocked excel spreadsheet allocating each cost to a specific vendor by storm event. Response: There is no contractual, operational or other prohibition that bars the payment of equipment rates during standby time and these costs are not tracked separately from a vendor’s crew time for invoicing purposes. Information regarding equipment charges is contained within the underlying vendor invoices and supporting documentation submitted as part of the Company’s filing. The Company has consistently explained that, in the years 2018 through 2023, the Company’s contractual terms provided that standby rates were charged only to labor rates, not to equipment. This policy followed from the fact that, when vendor crews commit to perform work for the Company, their equipment is dedicated for the duration of the engagement, preventing the use of that equipment somewhere else. This commitment of vendor equipment extends beyond working hours, as vendors must remain ready and available so long as they are committed to the Company’s restoration effort. This policy also reflects the fact that labor rates vary depending on the demands and associated risk placed on the field crews for their performance (i.e., standby rates are lower than work rates), where vendor equipment is tied up regardless of the work status of the vendor’s crews. Specifically, the contract language “Standby Rates apply to labor resources only” was applied so that there was no separate standby rate for equipment and equipment was, instead, billed at the same rate regardless of the crew’s work status (e.g. travel, standby, or work time). The Company’s policy acknowledged that it was paying for exclusive access to the vendor’s equipment throughout the event, compensating vendors for their lost opportunity cost. Not paying for equipment during standby would discourage vendors from committing their resources to the Company in storms with competitive procurement of crews among regional utilities. In January 2022, Eversource Energy received the final report of an independent assessment of the “Eversource ERP Capability,” prepared by Accenture LLC. This assessment was undertaken by
2 pages match

As listed on the current system

Corres. 10/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (EOE Set 5 and UCONN Set 2)

This filing on the current system (opens in a new tab)