Words on different pages
9 pages match
  1. Page 62 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-207 Page 1 of 2 Date Filed: September 28, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-9, pp. 251-304. The Company reported six incremental charges in the total amount of $787,502 for the Elecnor Energy Services LLC vendor. Respond to the following: a. Referring to pp. 256-260, pp. 268-271, pp. 279-283, pp. 291-294, and pp. 300-304, explain if the Eversource Contractor Storm Daily Time & Work Reports were fully completed as required by the Eversource Contractor Storm Daily Time & Work Report Procedure provided at EOE-022, Att.5. If not fully completed, explain why the Eversource reviewer did not require the information to be completed prior to approval. b. Referring to OCC-044, Att. 2 (Confidential), p. 1449-1491, confirm that the vendor’s Exhibit A Pricing Schedule contains the Company’s standard provisions, including “Standby Rates apply to labor resources only” (i.e., p. 1456). If not confirmed, cite the revised Exhibit A Pricing Schedule that was executed (signed) for 2024 and 2025 that revised the standard provisions. c. Referring to pp. 256-260, pp. 268-271, pp. 279-283, pp. 291-294, and pp. 300-304, explain how the Eversource reviewer was able to determine that the billed activity related to Work (i.e., box 12) in lieu of standby time (i.e., box 11) given the lack of any work details in boxes 20-25 (i.e., pp. 256-260) or the lack of start times in box 24 (i.e., pp. 268-271, pp. 279-283, pp. 291-294, and pp. 300-304). d. Provide the billed equipment costs applicable for January 10, 2024, as derived from the six invoices resulting from pp. 256-260, pp. 268-271, pp. 279-283, pp. 291-294, and pp. 300-304. As part of the response, please identify the amount per invoice. Response: Please refer to Exhibit ACCT-2 (CLP-1)(MS24A), Outside Line Contractors, at Lines 250-254, Elecnor Energy Services LLC, for five incremental charges in the total amount of $787,502. a. The ESS contractor crews were directed to begin their work shift on January 10, 2024, at 6:00am. As the storm did not materialize as predicted, the Company began releasing contractor crews, with the ESS crews among the first released at 10:30am. There are no notes in Block 23 as the crews received no assignments prior to being released.
  2. Page 63 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-207 Page 2 of 2 b. Yes. Eversource confirms that the vendor’s Exhibit A Pricing Schedule contains the Company’s standard provisions, including the provision that “Standby Rates apply to labor resources only,” as referenced in OCC-044, Attachment 2 (Confidential), p. 1456. The Company notes that the term “standby” may also appear on a contractor’s timesheet as a description of the activity or status of a resource during a particular period. For example, a contractor may use “standby” to describe time between assigned tickets, time prior to receiving a ticket, or time following completion of a ticket while awaiting further direction from the Company. The use of the term “standby” on a timesheet does not, by itself, indicate that the contractor is entitled to bill that time at the contractual standby rate. In many such instances, the contractor’s crews have already mobilized to an assigned on-set or staging allocation; are fully prepared and available to perform work; and are awaiting further assignment or other direction from Eversource. This time may therefore be compensable at the applicable working rate depending on the circumstances, notwithstanding the crew’s use of the word “standby” as a descriptive notation on their timesheet. c. Contractually when a contractor is told to be on shift and ready for work, they are on “Work Time,” per contract regardless of when the work assignment is first made. In this case, the ESS contractor crews were told to be ready at 6:00am on January 10, 2024, and were on “Work Time,” accordingly. d. The billed equipment costs applicable to January 10, 2024, as derived from the five invoices are as follows: Ex. ACCT-2 CLP-1 Line 250 Line 251 Line 252 Line 253 Line 254 Invoice 10298 10299 10300 10304 10306 Billed Equipment Costs 1/10 $10,770.08 $8,953.36 $12,288.14 $14,881.05 $14,098.56 These costs were billed in accordance with contractual provisions.
  3. Page 64 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-208 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-9, pp. 305-312, 315, 320. The Company reported an incremental charge of $13,062 for the Elecnor Hawkeye LLC vendor for activity referenced as ‘Dock Work’ and reported the activity under Work Order # 80290578 (pp. 305-306). The description of work completed identified the daily activity as “26 Round Hill Dr, Danbury – Crew Completed Job, and Removed Old Pole” and then referenced “see storm sheets for the remaining hours” (p. 310). Finally, each of the employees were separately included within a different invoice (compare p. 310 with p. 315) where a separate Eversource Contractor Storm Daily Time & Work Report included a description of work that stated “standby after regular work, report back at 0600 next day” (p. 320). Respond to the following: a. Confirm that the $13,062 cost was incorrectly included within the storm recovery request. b. If subsection a is not confirmed, explain why the Company included the same individuals within two different invoices for the same day. c. If subsection a is not confirmed, explain why the Company did not use the correct storm Work Order #. d. If subsection a is not confirmed, provide documentation supporting the specific hours worked associated with the storm versus the non-storm activities for January 9, 2024, including a breakdown of hours between standby and work. Response: a. Please refer to Exhibit ACCT-2 CLP-1 (M24A), Outside Contractors, line 255, vendor Elecnor Hawkeye LLC, invoices totaling in the amount of $13,062. Upon further review in drafting this response, the Company determined that these costs are not associated with the event. The Company will supplement ACCT-2 CLP-1 (M24A), to remove lines 255 in the amount of $13,062. b. Please refer to the response to subpart a. c. Please refer to the response to subpart a. d. Please refer to the response to subpart a.
  4. Page 65 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-209 Page 1 of 2 Date Filed: September 28, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin, Leanne M. Landry, Craig Dikeman and Matthew J. Correia Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-9, pp. 313-330. The Company reported an incremental charge of $187,949 for the Elecnor Hawkeye LLC vendor. Respond to the following: a. Cite the location of the vendor’s contractual Pricing Schedule Exhibit (i.e., typically referred to as Exhibit A). The contract provided in OCC-044, Att.2 (Confidential), starting at p. 1492 includes a List of Exhibits at p. 1498 which references the Pricing Schedule as Exhibit B but was unable to locate the document. b. Referring to pp. 318-323, 327, 328, 330, explain why the equipment was charged during standby when the Company’s Master Service Agreement omits billing of equipment during standby. Additionally, identify the amount ($) of equipment that was charged for standby. Response: Please refer to Exhibit ACCT-2 CLP-1 (MS24A), Outside Contractor-Vendor, line 256, vendor Elecnor Hawkeye LLC, totaling invoice in the amount of $187,949. a. The Company confirms that, due to a clerical error during the submission process, the vendor’s contractual Exhibit B Pricing Schedule was inadvertently omitted from the materials provided at OCC-044, Att. 2 (Confidential). The Exhibit B Pricing Schedule is now provided as EOE-209, Attachment 1 CONFIDENTIAL. b. Under the applicable Master Service Agreement, the contractor is entitled to receive payment for equipment at 50% of the applicable equipment rate while the contractor is on standby, as expressly provided in Section 3.6, page 5 of EOE-209, Attachment 1 CONFIDENTIAL, (Exhibit B Pricing Schedule). Accordingly, the equipment charges during standby were billed pursuant to the specific standby provisions contained in the vendor’s contractual Pricing Schedule. In addition, the total amount of equipment charged for standby is $11,447.38. For purposes of contractor timekeeping, a “standby” designation may reflect the operational status of the crew at a particular point in time and does not necessarily indicate that the crew or associated equipment was inactive or demobilized. During these periods, contractor resources may remain fully mobilized at the designated work or staging location, with personnel and equipment committed to Company
  5. Page 66 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-209 Page 2 of 2 operations and prepared to immediately perform assigned work. For example, resources may be awaiting the next ticket or work assignment, awaiting further direction from the Company, or transitioning between assignments while remaining available to support ongoing operations. Although the contractor crew may refer to this time as “standby” on the timesheet, the resources remain deployed and unavailable for other work.
  6. Page 67 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-210 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-TRAFFIC) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT2 CLP-1A-10, pp. 1-3. The Company reported an incremental charge of $1,173 for the Elite Flaggers LLC vendor. The supporting documents detail flagging activities from January 8, 2024 (prior to the storm event) and January 11, 2024 (after the storm event), and detail unrelated workorder numbers. Identify which of the two services apply to the MS24A event and provide documentation supporting the applicability of the services. If an error occurred, confirm that the amount will be removed from the recovery request. Response: Please refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-10, Outside Contractors, line 257, vendor Elite Flaggers, invoice totaling in the amount of $1,173. Upon further review in drafting this response, the Company determined that $1,173 costs are not associated with the event. The Company will supplement ACCT-2 (CLP-1) (MS24A), to remove cost from line 257 in the amount of $1,173.
  7. Page 68 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-211 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-TRAFFIC) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT2 CLP-1A-10, pp. 26-44. The Company reported an incremental charge of $8,500 for the Elite Flaggers LLC vendor. The supporting documents detail various flagging activities from January 8, 2024 (prior to the storm event) through January 13, 2024 (during a different storm event), and detail multiple unrelated workorder numbers. Identify the specific assignments that derive the $8,500 amount and, where applicable, explain why the supporting documents did not detail the correct workorder number. If applicable, provide documentation supporting the applicability of the services to the MS24A event. Response: Please refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-10, Outside Contractors, line 259, vendor Elite Flaggers, invoice totaling in the amount of $8,500. Upon further review in drafting this response, the Company determined that $1,100 of the costs is not associated with the event. The Company will supplement ACCT-2 (CLP-1) (MS24A), to remove this partial cost from line 259 in the amount of $1,100. In addition, pursuant to the Company's internal invoice review and approval procedures, all vendor invoices are reviewed to verify that the charges are properly attributable to the specific event, work activity, and accounting classification for which reimbursement or cost recovery is sought. The Company verifies the nature and purpose of the services through supporting documentation and consultation with Company personnel responsible for requesting, overseeing, or receiving the services. Although the Company endeavors to provide contractors with accurate accounting information at the time services are requested, circumstances may arise in which accounting references provided at initiation require subsequent correction or refinement. In such instances, the invoice review process serves as a control mechanism to ensure that costs are assigned to the appropriate accounting and work order based on the underlying documentation and facts. The review further confirms that the services were procured, performed, and charged in connection with the specific event and applicable service period. Such determinations are supported by documentation and corroborated by the Company personnel with direct knowledge of the work performed.
  8. Page 69 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-212 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-OTHER)Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-10, p. 63. The Company reported an incremental charge of $658 for the Expressway Courier & Freight LLC vendor. Discuss the specific services provided and explain why it was necessary to incur these costs for storm recovery purposes. As part of the response, identify any non-incremental cost options the Company pursued to include the use of employees Response: Please refer to Exhibit ACCT-2 CLP-1 (MS24A), Outside Contractors-Vendors, line 262, vendor Expressway Courier & Freight LLC, invoice totaling in the amount of $658. This vendor was utilized to transport and deliver circuit maps to Damage Assessors assigned to patrol and assess storm-related damage. Providing circuit maps prior to the commencement of restoration activities enabled Damage Assessors and field personnel to have the necessary system information readily available, thereby preventing delays associated with obtaining maps and allowing crews to safely initiate restoration efforts as soon as conditions permitted. By utilizing an external service, the Company was able to ensure the timely delivery of circuit maps to Damage Assessors and area work centers while allowing internal personnel to remain focused on storm response responsibilities. Additionally, making the use of a dedicated delivery service is a cost-effective means of supporting restoration operations across the affected service territory.
  9. Page 70 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-213 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-TRAFFIC) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT2 CLP-1A-10, pp. 64-89. The Company reported an incremental charge of $17,491 for the Extra Duty Solutions vendor. Explain the Company’s practices regarding the engagement of police officers for standby. As part of the response, identify if there are cities, towns, or municipalities that require the use of police officers during storm restoration versus other flagging providers. Response: Many municipalities across Connecticut require the hiring of police officers for traffic control, regardless of the specific work location. Specific to this question, the three towns serviced by the Stamford Area Work Center (AWC) of Stamford, Greenwich, and Darien all require the Company to hire police for traffic control. As the Stamford AWC has the majority of their work in Stamford and Greenwich, they have a standing request to have three police officers in both towns available for use daily.
  10. Page 71 of 169

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-05 Date Issued September 11, 2026 EOE-214 Page 1 of 1 Date Filed: September 25, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-PURCHASED) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-10, p. 95. The Company reported an incremental charge of $954 for the Grainger vendor. The charge related to the purchase of a Fiberglass Ladder and two racks. Explain if this charge was included in the Company’s capitalization offset for the MS24A event. If included, please demonstrate where. If not included, explain why the purchase was a necessary incremental storm expense for the MS24A event and explain if the equipment was available for post-storm usage. Response: Please refer to Exhibit ACCT-2 CLP-1 (MS24A), Outside Contractors- Vendors, line 268, vendor Grainger, invoices totaling in the amount of $954. Upon further review in drafting this response, the Company determined that these costs are not associated with the event. The Company will supplement ACCT-2 CLP-1 (MS24A), to remove lines 268 in the amount of $954.
2 pages match

As listed on the current system

Corres. 10/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (EOE Set 5 and UCONN Set 2)

This filing on the current system (opens in a new tab)

Correspondence, docket 26-05-10 | Connecticut utility dockets