Discovery Compilation (ALLCO Set 8)
Filed by Keegan Werlin LLP2 files
Part of docket 26-05-10Files2
Docket No. 26-05-10 Discovery Compilation October 13 2026.pdf
PDF · 150 KB · 1 pageText searchable
Download Docket No. 26-05-10 Discovery Compilation October 13 2026.pdfRead the text of Docket No. 26-05-10 Discovery Compilation October 13 2026.pdf
ALLCO Set 8_COMBINED.pdf
PDF · 522 KB · 36 pagesText searchable
Download ALLCO Set 8_COMBINED.pdfRead the text of ALLCO Set 8_COMBINED.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 16 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-080 Page 3 of 4 the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding.1 Without waiving said objection, Eversource provides this information in its March 1st annual RAM filings2 in compliance with Order No. 5 of PURA’s November 22, 2019, 3rd Interim Decision in Docket No. 18-05-04. The Millstone PPA, inclusive of pricing per MWh for Products purchased under that agreement, is publicly available on PURA’s Docketed Database Filings website under Docket No. 18-05-04.3 Regarding the sale of Millstone products, please refer to Eversource’s response to ALLCO-037. ii ALLCO-038 Question: For each year 2019 through 2025: state (a) the Company’s total standard service and supplier of last resort service load (MWh) and the average all-in supply cost per kWh the Company paid to wholesale suppliers for that load; (b) the average cost per kWh of energy purchased under the Millstone PPA; and (c) the net amount charged to customers through the NBFMCC in respect of the Millstone PPA for that year; and produce data sufficient to calculate, for each such year, the net impact on customers had the Company used Millstone PPA energy to serve standard service and supplier of last resort service load up to the lesser of the Millstone PPA quantities or that load (accounting for the residual quantities that would still have been resold into the market), including hourly standard service load data and hourly Millstone PPA delivery quantities in native format. ALLCO-038 Response: PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested proceeding to review Eversource’s application. Eversource objects to Allco’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding. Without waiving said objection, the Company’s Standard Service loads can be found on the following website: https://www.eversource.com/residential/about/doing-business-with-us/energy-suppliers/connecticut-wholesalesupply. The supply costs paid to suppliers can be found in the following dockets: 2019-01-01; 2020-01-01; 2021-0101; 2022-01-01; 2023-01-01; 2024-01-01; 2025-01-01. As noted in the Millstone PPA, “The Price for the Buyer’s Percentage Entitlement of Delivered Products up to the Contract Maximum Amount shall be USD $49.99/MWh,” which is equivalent to $0.0499/kWh. Eversource provides the net amount charged to customers through the NBFMCC for the Millstone PPA in its March 1st annual RAM filings. iii ALLCO-037 Question: In its September 18, 2019, Interim Decision in Docket No. 18-05-04, the Authority stated that "the manner in which these Products are resold can impact the value of the Agreements to ratepayers" and directed the EDCs "to thoughtfully consider their options in this area and to pursue those options that maximize such value." Describe each action the Company has taken in response to that directive from 2019 to the present; state whether the Company has ever changed its method of reselling Millstone PPA products; and state whether the disposition of Millstone PPA products is addressed in the Company’s current procurement plan or any pending or planned procurement-plan update.Page 17 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-080 Page 4 of 4 ALLCO-037 Response: PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested proceeding to review Eversource’s application. Eversource objects to Allco’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding. Without waiving said objection, Eversource does not resell the energy from the Millstone PPA; instead, the facility bids the energy into the ISO-NE wholesale market, and it is settled via ISO-NE. Eversource receives its buyer’s percentage entitlement of that settlement. Eversource sells qualified Clean Energy Standard for Existing resources (“CES-E’s”) from the Millstone facility, and the net benefit of those sales is credited to ratepayers via the NBFMCC.Page 18 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-081 Page 1 of 2 Date Filed: October 01, 2026 Witness: Justin Pelkowski Request from: ALLCO Question: (Follow-up to ALLCO-036.) The response identified two dockets but did not answer the question. State, yes or no, whether the Company has at any time since 2019 analyzed, evaluated, or considered using the energy purchased under the Millstone PPA to serve its standard service or supplier of last resort load in whole or in part; if yes, identify and produce each analysis, evaluation, memorandum, presentation, or communication, and identify by title each person who participated in the decision regarding disposition; if the presentations in Docket Nos. 17-12-03RE10 and 1206-02RE04 are the only responsive materials, produce them in this docket and confirm that no analysis has been performed since. Response: PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested proceeding to review Eversource’s application. Eversource objects to Allco’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding. 1 Without waiving said objection, as stated in ALLCO-036 i, yes, the Company has presented information regarding the use of energy from the Millstone PPA to serve Standard Service load, the results of which are captured in presentations filed in Docket Nos. 17-12-03RE10, 12-0602RE04, and in an exhibit in 18-05-04. The presentations filed in Docket Nos. 17-12-03RE10 and 12-06-02RE04 are attached as ALLCO-081, Attachment 1, and ALLCO-081, Attachment 2, respectively to this response while the exhibit from Docket No. 18-05-04 is not as it was filed confidentially. No subsequent analysis has been performed. Allco previously litigated the Millstone PPA in the Company’s Docket No. 24-01-03 Revenue Adjustment Mechanism proceeding. See, Docket No. 24-01-03, Eversource responses to Q-ALLCO-02, Q-ALLCO-03, QALLCO-05, Q-ALLCO-06, Q-ALLCO-07, and Q-ALLCO-21. Eversource objected to each of these questions. 1Page 19 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-081 Page 2 of 2 Prior Referenced Response: i ALLCO-036 Question: State whether the Company has at any time since 2019 analyzed, evaluated, or considered using the energy purchased under the Millstone PPA to serve its standard service and/or supplier of last resort service load, in whole or in part, rather than reselling that energy into the ISO-New England markets; produce every such analysis, evaluation, memorandum, presentation, or communication; identify, by title, each person who participated in the decision regarding the manner of resale; and state each reason for the disposition method chosen. If no such analysis exists, so state. ALLCO-036 Response: PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested proceeding to review Eversource’s application. Eversource objects to Allco’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding. Without waiving said objection, the Company has previously presented information related to utilizing PPAs for Standard Service in Docket Nos. 17-12-03RE10 and 12-06-02RE04.Page 20 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-082 Page 1 of 2 Date Filed: October 01, 2026 Witness: Laura E. Perbeck Request from: ALLCO Question: (Follow-up to ALLCO-037.) The response described the current arrangement but not the actions the interrogatory asked about. Describe each action the Company has taken from 2019 to the present in response to the Authority’s September 18, 2019 directive in Docket No. 18-05-04 to “thoughtfully consider their options in this area and to pursue those options that maximize such value”; state whether the Company has ever changed the manner of disposition of Millstone PPA products, and if not, whether any change was ever evaluated; and state whether the disposition of Millstone PPA products is addressed in the Company’s current procurement plan or any pending or planned update, identifying the relevant section or stating that it is not addressed. Response: PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested proceeding to review Eversource’s application. Eversource objects to Allco’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding. 1 Without waiving said objection, each year since the PPA term began in 2019, Eversource has not resold the energy from the Millstone PPA; instead, the facility bids the energy into the ISONE wholesale market, and it is settled via ISO-NE. Eversource receives its buyer’s percentage entitlement of that settlement. Since 2021 Eversource has also sold qualified Clean Energy Standard for Existing resources (“CES-E’s”) from the Millstone facility, and the net benefit of those sales is credited to ratepayers via the NBFMCC. 2 In July 2019, in Docket No. 18-05-04, CT DEEP requested a late file (LFE No. 15) titled: 1 Allco previously litigated the Millstone PPA in the Company’s Docket No. 24-01-03 Revenue Adjustment Mechanism proceeding. See, Docket No. 24-01-03, Eversource responses to ALLCO-02, ALLCO-03, ALLCO-05, ALLCO-06, ALLCO-07, and ALLCO-21. Eversource objected to each of these questions. 2 As noted in the April 8, 2020, annual RAM filing in Docket No. 20-03-01, Exhibit 3 page 18, Eversource did not purchase nor sell any CES-E’s in 2019; As noted in the March 1, 2021, annual RAM filing in Docket No. 21-0103, Exhibit 3 page 17, Eversource did not sell any CES-E’s in 2020.Page 21 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-082 Page 2 of 2 Quantification and examples of the impact to the market and the procurement process of using the output from the Millstone PPA as the basis for a full services standard service product in CT (EDC's- Mr. Levitan) In its confidential July 11, 2019, response to LFE No. 15 in Docket No. 18-05-04, Eversource explained the impact on the Standard Service marketplace and price as a result of taking the output under the Millstone PPA and using it for Standard Service. The Company does not maintain a procurement plan; rather, the State’s Procurement Plan is maintained by PURA. PURA is currently reviewing recommendations made by the PURA Procurement Manager’s in Docket No. 12-06-02RE05. PURA posted a draft decision in Docket No. 12-06-02RE05 on September 11, 2026. As part of their draft decision, PURA addressed the use of PPAs for Standard Service.Page 22 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-083 Page 1 of 2 Date Filed: October 01, 2026 Witness: Edward A. Davis and Kimberly R. Parsons Request from: ALLCO Question: (Follow-up to ALLCO-043.) The response described the calculation of net metering amounts but did not answer subparts (b) and (c). State, yes or no, whether the amounts charged to customers through the NBFMCC for net metering and virtual net metering are reduced or offset by the corresponding reductions in regional transmission charges (RNS, LNS, TAC), capacity obligations, and standard service procurement quantities attributable to the same behind-the-meter generation; if no such offset is made, explain why not; and state the annual amount charged to customers through the NBFMCC for net metering and virtual net metering for each calendar year 2020 through 2025, in native format. Response: PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested proceeding to review Eversource’s application. Eversource objects to ALLCO’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding. 1 Without waiving said objection, the Company’s response to ALLCO-043 i is responsive to the question. The amounts charged to the NBFMCC for net metering and virtual net metering for each calendar year 2020 through 2025 are part of the public record in the respective Revenue Adjustment Mechanism proceedings in which they are included. Net metering affects wholesale loads, which could impact peak loads. Please refer to the Company’s response to ALLCO-095 which requests information on how behind the meter generation impacts wholesale settlements. Please note that ALLCO-095 will be filed on October 5, 2026. Allco previously litigated renewable energy projects as load reducers in the Company’s Docket No. 24-0103 Revenue Adjustment Mechanism proceeding. See, Docket No. 24-01-03, Eversource responses to ALLCO-04 and ALLCO-027. Eversource objected to both of these questions. 1Page 23 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-083 Page 2 of 2 Prior Referenced Response: i ALLCO-043 Question: Describe how amounts associated with net metering and virtual net metering are calculated and recovered from other customers through the NBFMCC (including the "avoided bill" methodology described by Company witnesses in Docket No. 20-01-01), and state whether the amounts so charged to customers are reduced or offset by the corresponding reductions in regional transmission charges (RNS, LNS, TAC), capacity obligations, and standard service procurement quantities attributable to the same behind-the-meter generation; if no such offset is made, explain why not, and quantify the annual amount charged to customers through the NBFMCC for net metering for each year 2020 through 2025 without any such offset. ALLCO-043 Question: PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested proceeding to review Eversource’s application. Eversource objects to ALLCO’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding Without waiving said objection, net metering and virtual net metering amounts included in the NBFMCC are calculated and recorded for inclusion in the NBFMCC, as part of each customer’s monthly bill, in accordance with the tariff rider under which each customer is enrolled. Monthly net metering amounts for the net metering rider involving banked kWh (e.g., Rider N) are calculated by multiplying the portion of a customer’s net metering facility’s energy produced and not used, but that is netted against the energy delivered to that customer from the distribution system by the customer’s prevailing per kWh rates. Any excess monthly energy production not so netted over the course of 12 months is multiplied by the annual average LMP rate to determine a residual amount included in the NBFMCC. For net metering facilities that do not involve kWh banking (e.g., RRES), the amount included in the NBFMCC for each month is calculated by multiplying total energy produced and not used by the customer by the rate set forth pursuant to the net metering tariff rider under which they are enrolled. For virtual net metering (“VNM”), net metering amounts included in the NBFMCC are determined by multiplying the monthly energy production by the prevailing general service rates under which the customer receives electric service, calculated on a per kWh basis, pursuant to the VNM rider.Page 24 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-084 Page 1 of 2 Date Filed: October 08, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: ALLCO Question: (Follow-up to ALLCO-032.) The table provided as ALLCO-032, Attachment 1, addresses subpart (c) only as to “Customer Deposits.” Complete the response as to the remaining categories the interrogatory identified: for (a) deposits, prepayments, and security provided by developers and interconnection customers (including amounts paid for interconnection studies, system modifications, and upgrades held pending final accounting), (b) unpaid or unrefunded interconnection final-accounting balances, and (c) over-recovered rate adjustment mechanism balances held prior to return to customers — state, for each: the amounts held as of December 31, 2025 and as of the most recent date available; the interest rate the Company pays or credits on each (or confirm that the rate is zero); the accrual and compounding convention; and the FERC account(s) in which each is recorded. If the Company pays or credits no interest on any category, state the basis for accruing carrying charges at its pre-tax WACC, compounded monthly, on balances customers owe the Company while paying nothing on balances the Company holds for customers. Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, the Company notes that interconnection-related funds are not held in customer deposits. Please refer to the Company’s responses to ALLCO-002 i and ALLCO-044 ii. Further, the Company does not and has not requested deposits, prepayments or security from developers and distribution generation interconnection customers. Prior Referenced Response: i ALLCO-002 Question: State the total dollar amount of CIAC and interconnection-related payments collected from DER and QF interconnection customers in each year 2018 through 2025, and explain precisely how those amounts are reflected inPage 25 of 36
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-08 Date Issued September 17, 2026 ALLCO-084 Page 2 of 2 (a) rate base, (b) the Test Year revenue requirement, and (c) the Rate Year revenue requirement proposed in this docket, identifying the specific schedules and workpapers. ALLCO-002 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, please refer to the Company’s response to ALLCO-001i for CIAC year-end balances from 2018 through 2025. CIAC and interconnection-related payments received by the Company reduce the cost of construction or plant placed in service. CIAC is recognized as an offset to the underlying capital project. CIAC would not be considered a component of rate base until the underlying capital project is placed in service. At that time, the underlying capital project costs in rate base would be wholly offset by CIAC at the time of final project billing and reconciliation. In the Company’s next cost of service update, the rate base and the Rate Year revenue requirement will reflect the CIAC and the underlying capital project cost for projects placed in service. ii ALLCO-044 Question: With respect to each cost category included in the percentage overhead or “CIAC” rates applied to interconnection upgrade, study, and construction costs charged to distributed generation, qualifying facility, and other interconnection customers (including, without limitation, project management, engineering and supervision, administrative and general expense, employee benefits or compensation loaders, insurance, and Eversource Energy Service Company charges): (a) identify each such cost category and its share of the overhead rate in effect in each year 2018 through 2025; (b) state whether the costs in each such category were included, in whole or in part, in the test-year cost of service and revenue requirement approved in the Company’s most recent prior general distribution rate proceeding, Docket No. 17-10-46, and therefore recovered from all ratepayers through base distribution rates during 2018 through the present; (c) if the answer to any part of subpart (b) is affirmative, explain why applying overhead rates that include the same cost categories to amounts charged to interconnection customers does not result in the Company recovering the same costs twice — once from ratepayers generally and again from interconnection customers; (d) quantify, for each year 2018 through 2025, the total dollar amount of overheads collected from interconnection customers in cost categories that were also reflected in base rates; and (e) state whether amounts collected from interconnection customers through overhead rates are recorded as a credit or offset to the corresponding expense or plant accounts recovered in base rates and, if not, where those amounts are recorded, consistent with the Company’s description of its netting treatment of third-party attacher billings in its response to RRU-002. ALLCO-044 Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, please note that capital expenditures (direct costs and overheads applied to those amounts) are entirely billed to the interconnection customer and reimbursed through the CIAC process; therefore, these asset additions are not included in rate base. Please refer to ALLCO-064i for additional discussion on the CIAC rate and ALLCO-003ii where the Company goes into more detail on the CIAC Tax Adder.
As listed on the current system
Corres. 10/13/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (ALLCO Set 8)