  1. Page 2 of 98

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-815 Page 1 of 1 Date Filed: October 06, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Consumer Counsel Question: Uncollectibles. Refer to WP C-3.30. a. Explain why the uncollectible expense is calculated including the revenues and uncollectibles for the RAMs and not just distribution revenues. b. Update the schedule to provide the information on a distribution only basis. c. Identify each RAM that recovers uncollectible expense. Response: a. The uncollectible expense in schedule WP C-3.30 reflects only bad-debt cost on customer rates that is not collected in other recovery mechanisms. The only portion of non-hardship bad debt cost that is recovered in other mechanisms is the uncollectible costs on GSC energy supply revenues that are recovered in FMCC rates. Non-hardship bad debt incurred on all other rate revenues, including all RAM components, is recovered in distribution rates consistent with prior rate case proceedings. 1 b. As outlined above, the Company separately tracks non-hardship uncollectible costs on the GSC energy supply portion of customer bills, which is recovered in FMCC rates. As a result, the total non-hardship uncollectible expense reflected within WP C-3.30 represents the total nonhardship distribution or delivery uncollectible expense. c. The Company recovers GSC non-hardship uncollectible costs in the FMCC and hardship uncollectible costs within the System Benefits Charge (“SBC”). These costs are not included in schedule WP C-3.30 and are segregated from the uncollectible costs described above. Distribution rates are designed to collect non-hardship customer uncollectibles only (excluding GSC energy supply revenues). Lastly, please refer to Footnote 1 in this response for additional information regarding the roll in of uncollectible costs previously recovered in RAM rates. Note, there are currently incremental revenue requirements on certain capital recoveries within the System Benefits Charge (“SBC”) and Non-Bypassable Federally Mandated Congestion Charges (“NBFMCC”) that include limited non-hardship uncollectible expense calculations that are incremental to what is included in current base distribution rates. The Company’s proposal is to roll those capital recoveries into base distribution rates and therefore the associated uncollectible expense will also be rolled into base distribution rates. 1
  2. Page 3 of 98Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-816 Page 1 of 2 Date Filed: October 06, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Consumer Counsel Question: Uncollectible Expense. Refer to Schedule C-3.0. a. Explain the reason for the significant increase in uncollectible expense in 2024 and 2025 over the prior year amounts and why this level is expected to continue in the rate year. b. Explain the company’s efforts to reduce base distribution uncollectibles. Response: a. The increase in uncollectible expense in 2024 and 2025 is consistent with the increase in customer electric bills, primarily driven by significant increases in supply prices and public benefits related charges. Total residential rates increased beginning in 2022 and peaking in January 2023 at approximately 34.4 cents per kWh for residential Rate 1 customers, compared to approximately 20.6 cents per kWh in January 2021. While supply costs declined from peak 2023 levels, overall customer bills remained elevated in 2024 and 2025 due to continued increases in public benefits charges. It is important to note, the projected rate year uncollectible expense calculated within the Company’s filing (see Exhibit CLP-REVREQ-2 Schedule C-3-30) is based on a five-year (2021 – 2025) average uncollectible percentage. The uncollectible percentage is calculated by dividing the total uncollectible expense each year by the applicable billed revenues. The average uncollectible expense percentage is then applied to the total rate year revenues in order to calculate the total rate year uncollectible expense. As a result, while there was an increase in uncollectible expense in 2025 for example, the uncollectible percentage calculated for that year was below prior periods and the five-year average. b. The Company continually evaluates its collection practices and has sought regulatory approval to implement measures intended to improve collections and reduce the accumulation of delinquent balances. In Dockets 24-05-01, 25-05-01, and 26-05-01, the Company proposed modifications to collection policies that were implemented during the COVID-19 pandemic and that have limited certain traditional collection activities. These proposed changes are intended to enhance the effectiveness of the Company’s collection processes and reduce future uncollectible expense. The Company’s Proposal to Reduce Arrears in Docket 26-05-01 is provided in OCC-816, Attachment 1.
  3. Page 4 of 98

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-816 Page 2 of 2 The Company uses collection practices available for non-hardship customers (residential and businesses) allowed by PURA orders, regulations and Connecticut statutes to minimize uncollectible balances. For example, the Company performs the following collection practices to reduce arrears and, ultimately, uncollectibles: 1. Deposits – o For businesses, deposits are taken at the time of account setup and following a disconnection for non-payment as a condition of reconnection. o For residential customers, deposits are no longer allowed for Residential customers, per PURA Order No. 1 in Docket No. 23-05-01. This eliminated a collections best practice in preventing uncollectibles because nearly 50% of write-offs are driven by customers who resided at a location for two years or less. 2. Skip-Tracing – to identify and transfer unpaid balances from inactive customer accounts to their active service account when they move within the Connecticut service territory. 3. Late Payment Charges – to encourage timely payments. 4. Payment Reminder - Notifications (available via email and/or text) – to notify customers before their payment is due. 5. Missed Payment - Notifications (available via email and/or text) to notify customers that their payment is past due. 6. Payment Plans – up to 18 months duration while making minimum required payment requirements (versus past practices included in OCC-816, Attachment 1). 7. Payment Plan - Payment Reminder (available via email and/or text) to remind customers of their upcoming monthly required payment amount due date. 8. Payment Plan – Missed Payment Notification (available via email and/or text) to remind customers of their upcoming monthly required payment amount due date. 9. Disconnect Notices – (sent via U.S.P.S. mail and available via email and/or text) an initial and final notifications is sent to customers who have a past due balance eligible for disconnection. 10. Disconnections for Non-Payment – for customers who have not taken action to make minimum required payments. 11. Legal Collections – for active service customers who the Company is unable to disconnect for non-payment, for reasons including medical protection and nursing homes. 12. Third Party Collections – to collection on inactive service accounts from former customers.
  4. Page 5 of 98

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-817 Page 1 of 1 Date Filed: October 06, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Consumer Counsel Question: Long Term Director Stock. Refer to the response to OCC-041. Provide the amount of long term director stock expense included for recovery in the rate year. Response: The Company has proposed $1.483 million of Long-Term Director Stock for recovery in the Rate Year.
  5. Page 6 of 98Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-818 Page 1 of 2 Date Filed: October 06, 2026 Witness: John P. DiPaola-Tromba, Sean D. Redding and Jenna Turner Request from: Office of Consumer Counsel Question: Frontier Reimbursements. Does the Company bill Frontier for blue sky vegetation management work? If not, explain why not. If so, provide the amounts billed and the amounts collected for blue sky work for each year 2021, 2022, 2023, 2024, 2025, as well as the amounts included in the test year and rate year. Response: Please refer to Exhibit CLP-VMP-1, page 12, at lines 4-7: “Under the Joint Operating Agreement with Frontier, Frontier is required to contribute 15% of the annual vegetation management expense amount. Consequently, Frontier’s contribution for 2027 will increase to approximately $13.5 million, annually, based on an overall program cost of approximately $90 million.” Please refer to EOE-026, Attachment 1 CONFIDENTIAL, which covers the Joint Line Agreement and Intercompany Operating Procedures. Please refer to the Company’s response to RRU-005 i, part c, which provides the annual O&M expense reimbursements from 2017-2025. Prior Referenced Response: i RRU-005 Question: (PFAFF-Vegetation Management) Application, Ex. CLP-VMP-1 (Prefiled Testimony of Vegetation Management Panel). Refer to page 11 and 12, including the statement, “Under the Joint Operating Agreement with Frontier, Frontier is required to contribute 15% of the annual vegetation management expense amount.” a. b. c. d. Provide the Joint Operating Agreement with Frontier, as well as any predecessor Joint Operating Agreements with Frontier that address vegetation management costs. Does the Joint Operating Agreement require Frontier to contribute 15% of the annual vegetation management capitalized amount? If not, explain why there is asymmetric treatment for expensed and capitalized amounts. Quantify the annual contributions from Frontier for 2017 through 2025. Were the quantified amounts in subpart (c) applied against capitalized vegetation management costs?
  6. Page 7 of 98

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-818 Page 2 of 2 RRU-005 Response: a. Please refer to EOE-026, Attachment 1 CONFIDENTIAL, that covers the Joint Line Agreement and Intercompany Operating Procedures for years 2017-2025. b. All non-capital Operations and Maintenance (“O&M”) costs are allocated pursuant to the confidential settlement and amendment agreement filed as EOE-026, Attachment 1 CONFIDENTIAL. In accordance with the confidential settlement and amendment agreement, Frontier is not required to reimburse the Company for 15% of annual Vegetation Management capitalized costs. c. The annual O&M expense reimbursements from 2017 through 2025 are below: Year 2017 2018 2019 2020 2021 2022 2023 2024 2025 d. Frontier Vegetation Management O&M Expense Reimbursement $4,500,000 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $5,100,000 $5,037,750 $5,100,000 $4,365,000 The quantified amounts in subpart (c) were not applied against capitalized vegetation management costs.
  7. Page 8 of 98Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-819 Page 1 of 1 Date Filed: October 06, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: Robotic Process Automation Cost Savings. Refer to the response to EOE-029. Did the implementation of the Robotic Process Automation reduce base distribution labor as it automated a time consuming process? If so, please quantify the savings reflected in the rate year and the specific schedules where the savings are reflected. If not, explain why not. Response: Robotic Process Automation (RPA) is highly effective because it automates repetitive, rules-based tasks, improving speed, accuracy, consistency, and productivity while reducing the risk of human error. However, successful RPA initiatives do not necessarily lead to employee reductions. Instead, organizations often redeploy employees from manual, transactional activities to highervalue work such as analysis, customer engagement, process improvement, decision-making, and innovation. As businesses grow, automation can also help absorb increasing workloads without requiring proportional increases in staffing, allowing employees to focus on more strategic responsibilities. In this case, RPA served as a tool that augmented the workforce rather than replacing it, enabling the Company to improve operational performance while enhancing employee contributions and job satisfaction.
  8. Page 9 of 98Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-820 Page 1 of 3 Date Filed: October 08, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: Drone Costs. Refer to the response to EOE-033. a. Provide an explanation of the Creative Surveying Cost in 2025 and 2026. b. Explain the large increase in this cost in 2025 and 2026 over the prior years. c. State whether this cost is included in base rates or in the storm docket. If it is in base rates provide the amount included in the rate year and the revenue requirement schedule where it is located and explain why this expense is expected to occur annually. Response: Please refer to the Company’s response to EOE-033-SP01 i. Regarding part c, the original response to EOE-033 ii incorrectly showed that Creative Surveying provided drone services in the test year. Prior Referenced Responses: i EOE-033-SP01 Question: (STORM – DRONE USAGE) Discuss the Company’s use of drones in support of storm remediation efforts. As part of the response, identify when the Company first started using drones, explain the nature of these services as performed by either internal or external parties, and explain how these costs have impacted (i.e., reduced) other offsetting costs (i.e., patrols). Finally, provide a detailed listing of drone expenses by year (2018 through present), identify any dronerelated capital additions (i.e., drone purchases), and identify where in the Company’s application those costs are included. EOE-033-SP01 Response: The Company’s original submission included a chart with inaccurate information. This supplemental answer provides corrected information. Eversource has utilized drones for storm restoration support of electric distribution assets since 2019, when the Company first hired drone contractors. In 2020, the Company created an internal drone team and, since that time, the Company has utilized both contracted and internal resources for storm support. The Company’s drone teams aid in storm restoration efficiency by delivering detailed images of aerial assets quickly and in a level of detail not typically
  9. Page 10 of 98

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-820 Page 2 of 3 viewable from the ground, or in areas that cannot be traversed due to environmental factors. This capability allows the Company to better assess the circumstances of a particular damage location and to identify the work and materials that will be needed to address the damage, thereby improving the efficiency of the overall damage repair. The chart below provides a listing of expenses and capital additions by year. The expenses in the test year were recorded to storm workorders and are, therefore, either deferred for future recovery ($293,774) or included in Exhibit CLP-REVEQ-2-A,B,C,D, Schedule C-3.28 (Storms: Non-Catastrophic / Pre-Staging Incremental Storm Expenses) ($153,000). Purchases by the Service Company and the associated capital costs are billed to the Company as operating expense through: (1) EESCO Capital Return (Exhibit CLP-REVREQ-2-A,B,C,D, Schedule C-3.11; and (2) EESCO Depreciation expense (Exhibit CLP-REVREQ-2-A,B,C,D, Schedule C-3.35). Expenses 2018 lnternaI Labor Creative Surveying Pinnaclx VHB Skyscape TotalExpenses ii 2019 2020 19,605 18,084 5,366 43,054 2021 202.2 10,082 18,588 29,709 1,950 13,099 3,209 15,847 41,741 50,744 2023 2024 2025 54,771 50,157 29,704 2026 7,556 11,872 11,259 5,943 12,993 6,924 28,827 73,567 90,243 35,647 20,549 Total 190,463 47,792 62,482 3,209 51,598 355,545 EOE-033 Original Response: Eversource has utilized drones for storm restoration support of electric distribution assets since 2019 when the Company hired drone contractors. In 2020, the Company created our internal drone team and since then, the Company has utilized both contracted and internal resources for storm support. The Company’s drone teams aid in storm restoration efficiency by quickly delivering detailed images of aerial assets to a decision maker and identifying potential issues not typically seen from the ground, or in areas that cannot be traversed due to environmental factors. This in turn reduces costs by increasing reliability and reducing outages for our customers. Refer to the charts below for a listing of expenses and capital additions by year. The expenses in the test year were recorded to storm workorders and are therefore either deferred for future recovery ($293,774) or included in Exhibit CLP-REVEQ-2-A,B,C,D, Schedule C-3.28 (Storms: Non-Catastrophic / Pre-Staging Incremental Storm Expenses) ($153,000). The assets are purchased by the Service Company and those capital costs are billed to the Company as operating expenses though (1) EESCO Capital Return (Exhibit CLP-REVREQ-2-A,B,C,D, Schedule C-3.11) and (2) EESCO Depreciation expense (Exhibit CLP-REVREQ-2-A,B,C,D, Schedule C-3.35). Expenses Internal labor Creative Surveying Pinnaclx VHB Skyscape Total Expenses 2018 2019 2020 2021 2022 19,605 18,084 10,082 29,709 18,588 5,366 1,950 43,054 41,741 13,099 3,209 15,847 50,744 2023 2024 2025 Jun YTD Total 2026 54,771 50,157 29,704 7,556 190,463 446,774 555,644 1,050,210 11,872 11,259 5,943 12,993 62,482 3,209 6,924 28,827 51,598 73,567 90,243 482,421 576,193 1,357,963
  10. Page 11 of 98

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-20 Date Issued September 22, 2026 OCC-820 Page 3 of 3 Capital Additions Drones 2018 2019 2020 2021 2022 2023 2024 583,392 291,391 173,095 2025 459,639 Jun YTD 2026 Total 1,507,517

As listed on the current system

Corres. 10/14/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (ALLCO Set 9, OCC Set 19, OCC Set 20).

This filing on the current system (opens in a new tab)