Text of CLF-AC Set 2_COMBINED.pdf

Extracted from the file · 18 pages · 32,497 characters

60 pages match
  1. Page 74 of 150

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-366 Page 25 of 26 (b) How will the Company’s proposed treatment of capital expenditures be expected to produce customer cost savings or otherwise improve customer affordability relative to including capital expenditures within a revenue cap formula. There are three main opportunities for customer benefit in the PBR framework, which are: (1) the opportunity to leverage the stay-out term to drive operational efficiency and cost savings; (2) the opportunity to spread rate changes out over time to smooth impacts for customers and employ the concept of gradualism rather than promoting the cost and inefficiency of a traditional rate-case cycle; and (2) the opportunity to develop a systematic investment plan that promotes operational efficiency and cost-saving procurement strategies, while taking advantage of the smoothing impacts of the PBR framework to mitigate cost impacts. The Company has submitted substantial testimony and documentation in this proceeding to provide insight into the level of capital investment that is needed on the system to provide adequate service to customers and to support the economic vitality of the State of Connecticut. Customers benefit directly when investment can be undertaken on a planned, systematic and consistent basis over time because (1) it is consistently more expensive to complete infrastructure projects tomorrow rather than today due to price inflation and other factors; and (2) the Company’s process inputs (i.e., primarily labor and materials) cost less when procured on a planned and systematic basis rather than on an emergent basis. Although difficult to define in terms of the overall cost trends, there are significant benefits for customers in an operating approach that is consistent, systematic, planned and carefully managed, which is an outcome that the Company is hoping to promote with its proposals in this proceeding. Bottomline – the Company is looking to establish a ratemaking framework that will promote efficiency of operations for the benefit of customers and the F-Factor is the optimal mechanism for that purpose. Assuming that OCC’s referenced alternative for a capital-cost mechanism “within a revenue cap formula,” means that the PBMRP would rely exclusively on an “I-X” revenue cap formula, with or without X defined with a negative factor, the Company’s experience is that it is not adequate to support necessary capital investment, while raising issues for stakeholders. With the negative X factor, there is no direct link between the actual cost of capital plant additions and the revenue collection through customer rates, leaving it to be insufficient to support necessary capital investments and unsatisfactory for stakeholders that want transparency between the costs collected in rates and the rates that customers pay. As a result, achieving the efficiency needed to support a cost-effective capital plan is illusory in this model. (c) How does the proposed F-Factor mitigate or avoid any incentive to favor capital expenditures over O&M solutions, including in circumstances where either a capital or O&M solution could be used to address the same system need? In the Company’s experience, implementation of the X factor mechanism (with a negative X factor) to cover capital investment was thought to be a mechanism that would promote efficient solutions between capital and O&M because the revenue allowance was not predicated on actual plant additions; rather, was simply formulaic. In 2017, the Massachusetts Department of Public Utilities (“MDPU”) approved a negative X factor within a revenue cap for NSTAR Electric Company d/b/a Eversource Energy – and it remained operative for the five-year term of the plan. However, the fact is that – during an extended stay-out period, there is no incentive to incur any greater level of expense than is absolutely necessary to run the business. Therefore, there is no greater impetus than would exist in any event to make the optimal choice between expense and capitalization, where such a choice exists. And again, with the negative X factor, the MDPU felt it had no line of sight as to whether funds allowed to NSTAR Electric through the annual PBR allowance were, indeed, being leveraged for system investment.
  2. Page 75 of 150

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-366 Page 26 of 26 Therefore, in 2022, the MDPU instituted the K-Bar providing an allowance for system infrastructure projects, coupled with reporting requirements on investment levels. The MDPU maintained the I-X formula to cover the O&M portion of the approved revenue requirement, which is what the Company is proposing in this case. In reality, there are very few instances when system needs can be easily transitioned between a capital-work solution or a work solution that can be expense. The prudence review is the primary and most effective tool that regulators possess for evaluating these situations.
  3. Page 76 of 150

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-367 Page 1 of 6 Date Filed: October 15, 2026 Witness: Douglas P. Horton Request from: Office of Education, Outreach, and Enforcement Question: (PBMRP CAPITAL SUPPORT MECHANISM) Refer to Response to EOE-156, pp. 10-12. The Company’s response argues that the proposal will require O&M savings of $29 million by Rate Year 4 to achieve the authorized rate of return (pp. 10-11) and then details an assumption of “v. O&M cost pressure is assumed to be 1% greater than inflation, annually” (p. 12). All else equal, confirm that the $29 million amount was driven by the O&M assumption within the broader revenue cap formula and was not driven by the F-Factor proposal. If not confirmed, provide the updated analysis excluding the O&M assumption (i.e., assume O&M costs equal inflation) and separately discuss why there would be a shortfall driven by the proposed F-Factor. Response: The analysis presented in EOE-156, Attachments 1 and 2, demonstrated that, under the cost projections presented in that response, projected revenues under the proposed framework do not fully recover projected costs in order to produce adequate net income over the course of the PBR term, with assumptions outlined in that response. In addition to the assumption identified in this question, the Company also assumed that going-in rates established in this proceeding are approved as filed and requested by the Company, with no adjustments or disallowances. Having said that, the $29 million gap reflected in EOE-156, Attachment 1, is predominantly attributable to the O&M assumptions rather than the proposed F-Factor, since Attachment 1 assumes that the Company’s actual spending is identical to the spending within the TSP, and thus that capital is reflected in the F-Factor revenue support presented in that response. Conversely, EOE 156, Attachment 2, presents analysis assuming spending exceeds the amount allowable in the F-Factor by 5 percent. As a result, the larger gap identified in Attachment 2, relative to Attachment 1, is driven by capital related costs rather than O&M, since O&M assumptions are the same in both attachments. As discussed in the Company’s responses to EOE-372 i and OCC-857 ii, the F-Factor is subject to a downward-only annual reconciliation based on actual capital investment. As a result, the mechanism cannot produce earnings in excess of those supported by actual plant investment. If actual capital investment is lower than forecast, F-Factor recovery is reduced through the reconciliation process. Conversely, if actual capital investment exceeds forecast levels, the Company will incur the additional capital-related costs without corresponding F-Factor revenue until such investment is reflected prospectively through future ratemaking proceedings.
  4. Page 77 of 150Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-367 Page 2 of 6 Accordingly, the F-Factor does not provide a structural opportunity for over-recovery and is not responsible for the earnings shortfall reflected in the EOE-156 analysis. Further, even if O&M costs were assumed to increase only at the rate of inflation, the proposed PBR-O mechanism would continue to preserve cost-efficiency incentives. Because the mechanism includes a minimum customer dividend of 30 basis points, revenue growth is designed to trail inflation. As a result, achieving the authorized return on equity would remain dependent upon the Company’s ability to manage costs effectively and operate efficiently. The proposal therefore does not guarantee earnings recovery and continues to place meaningful performance risk on the Company. Consequently, the analysis demonstrates that the proposal maintains robust incentives for cost containment, operational efficiency, and prudent management while continuing to protect customers through the proposal’s sharing and reconciliation mechanisms. Prior Referenced Responses: i EOE-372 Question: (TIMING OF ANNUAL FILINGS; F-FACTOR) Provide both a discussion and a visual representation of the timeline detailing key components of the Company’s proposed annual filings for each year of the MRP. As part of the response, identify the cutoff date(s) for capital additions, the annual filing date(s), and rate change date(s). This request attempts to understand the amount of time needed for the Company to close its books and prepare the filing, along with the amount of time for the Authority’s approval, and the Company’s subsequent processing of the rate increases within its system. Additionally, this request attempts to understand relevant cutoff dates whereby the F-Factor capital additions would be applicable from the end of the evidentiary record through the first annual cutoff date. EOE-372 Response: Please refer to the Company’s response to OCC-857,i which responds to a similar question. The Company proposes to align the Performance Based Multi-Year Rate Plan (PBMRP) with the Rate Year, with PBMRP adjustments occurring on July 1 each year. For each year that the PBMRP mechanism is in effect, the Company would submit an Annual PBR Plan Compliance Filing to PURA in the annual RAM proceeding. The annual compliance filing would include, among other things: (1) the calculation of the annual revenue-cap adjustment; (2) the new proposed rate using the PBR formula; (3) an earnings-sharing computation; (4) cost documentation for the Company’s capital investments; (5) the calculation and reconciliation of the annual capital-cap adjustment; (6) documentation of metric performance and resulting penalties or incentives; (7) bill impacts of the new rate by rate class; and (8) any request for exogenous rate change, if applicable. With respect to the capital support mechanism or “F” factor in the formula, the Company proposes a mechanism based on a fixed annual capital investment level for each year of the PBMRP, with reconciliation through PURA’s annual RAM proceedings. The fixed, annual investment level will be set at the Company’s capital forecast, as approved in this proceeding. As described in its Exhibit CLP-ELP-1 testimony, the Company has presented different investment trajectories in the Company’s 5-Year targeted system performance (TSP) and is proposing to establish the capital support mechanism of the PBR adjustment consistent with the annual capital funding requirements presented in Figure 7 of the Exhibit CLP-ELP-1 testimony. As part of the Company’s annual RAM compliance filing, actual plant additions placed in service during the applicable plan year will be reconciled against the approved forecast. As
  5. Page 78 of 150

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-367 Page 3 of 6 described in the response to OCC-857, the fixed annual investment level would initially be set at the Company’s capital forecast, as approved in this proceeding, and would be subject to downward-only reconciliation in the event that either i) the Company’s actual plant in service is lower than projected and utilized in establishing the initial FFactor for that Rate Year or ii) PURA ultimately denies as imprudent a level of investment that was initially included in the F Factor allowance. In this way, customers are assured that rates ultimately reflect the costs of system investments that are actually in service, and have been found prudently incurred by PURA. If the Company’s actual capital spending exceeds the forecasted amount approved in this proceeding, the Company will not be permitted to seek recovery of the incremental investment during the initial four-year PBMRP Term. Any such investment would instead remain subject to review and consideration in a subsequent base rate proceeding or successor PBMRP Term. The Company’s proposed capital funding mechanism sets a defined cap on capital recovery during the plan term, providing customers with greater rate certainty and placing the risk of excess capital spending on the Company. The annual reconciliation further protects customers by blocking recovery of investments that are delayed, deferred, canceled, or not placed in service, since those costs would not be reflected in the “F” factor, since, although the Ffactor will initially be established based on the capital expenditure forecast presented in this proceeding, it will ultimately be reconciled based on plant in service, but only to the extent actual plant in service is less than (not more than) contemplated in the original F-Factor. For these reasons, the proposal aligns cost recovery with prudent investment, promotes accurate capital forecasting, and incentivizes efficient execution of the capital program, all while ensuring that customers do not provide revenues that support capital that is not in-service and used and useful to customers, and that is not found prudent by PURA. Based on the above framework, an exhibit that reconciles actual plant additions placed in service during the applicable plan year against the approved forecast will be filed on or about March 1st of each year consistent with the timing of all other RAM component reconciliations. Further, under the Company’s proposed timeline, the revenue requirement resulting from the reconciliation of the prior year’s F-factor allowance and the new Rate Year’s F-factor allowance will go into effect on July 1, following the March 1st filing. As part of the RAM process, PURA performed prudence reviews of capital documentation filed for the ESI, including discovery, between March 1st and September 1st, the date on which additional RAM rate changes were made. Even though PBMRP rates would go into effect on July 1st, the Company proposes that this timeline continues to be used for capital prudence reviews under the PBMRP. To the extent PURA’s prudence review warrants any adjustment to the revenue requirement that went into effect on July 1, the Company will calculate the excess revenue collected from customers over the period of July 1 through August 31 and include this amount, plus carrying costs for those 2 months, in the RDM’s allowed revenue target for the July 1 through June 30th Rate Year. Annual reconciliation, including the prudence reviews involved, is a critical element of the Company’s PBMRP proposal. As part of each annual PBMRP adjustment effective July 1 each year of the PBMRPi, the Company’s actual capital additions for the Prior Year are allowed for inclusion in the calculation of the F factor to the extent that the actual capital additions do not exceed the Forecasted Budget (referred to as the F-factor allowance). To the extent that the cumulative actual capital costs in-service through the Prior Year, in aggregate, exceeds the Forecasted Budget through the Prior Year, then the F Factor allowance is capped at the cumulative Forecasted Budget. This downwardonly reconciliation will ensure that, in the end upon reconciliation, customer bills reflect the costs associated only with projects that are in service to customers and no more, and that if the Company invests more than the Forecasted Budget, customer bills will not reflect amounts above the Forecasted Budget, until such time as those capital investments are allowed into rates at the time of the Company’s next rate case. The prior-period reconciliation will be reflected in the F-Factor, in addition to the revenue requirement associated with the Forecasted Budget for the upcoming Rate Year, effective July 1 annually. The F Factor allowance will be calculated to determine the revenue requirement (inclusive of depreciation expense, property tax expense, return on rate base, and income tax) on actual plant additions (including plant additions, cost of removal, plant retirements, accumulated depreciation, and plantrelated accumulated deferred income taxes (“ADIT”)) up to the Forecasted Budget amount, and to reflect the revenue requirement for the Prior Year and through the Rate Year on in service capital additions placed in service in the Prior
  6. Page 79 of 150

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-367 Page 4 of 6 Year, provided that those in service capital additions are not reflected in base rates or in another rate mechanism. In addition, the F Factor allowance will reflect the revenue requirement for Rate Year capital, established at the Forecasted Budget, subject to downward-only reconciliation in the subsequent F Factor filing. As noted above, annual reconciliation will consider plant-related ADIT on the Company’s books through the end of the calendar year, prior to a given annual filing. To the extent the Company has recorded cumulative plant additions in excess of the capital expenditure forecast provided in this docket or supported by a mechanism other than the FFactor, the plant-related ADIT will be adjusted in the Company’s annual reconciliation to avoid overstating the ADIT relevant to the F-Factor. In total, the Company’s proposed F-Factor will provide revenue support for, and ultimately reconcile, the capital investment placed into service from the cutoff date for inclusion in base rates through the effective date of the Company’s subsequent rate case at the conclusion of the proposed PBMRP term. Per the Company’s proposal the FFactor would ultimately reconcile capital investments made up to July 1, 2031 (the effective date of the subsequent rate case). Should the subsequent rate case be effective later than the July 1, 2031, illustrative date, the F-Factor would continue to reconcile capital investments placed into service until such time as that rate case does take effect. ii OCC-857 Question: (Capital Support Mechanism) On p. 101 of Exhibit CLP-ELP-1, the Company states that, “As part of the Company’s annual RAM compliance filing, actual plant additions placed in service during the applicable plan year will be reconciled against the approved forecast.” In the Company’s response to EOE-156, Witness Horton states that prudence reviews would be included in the annual reconciliation process. a. Provide a detailed plan for how the Company envisions the annual reconciliation process would proceed and how long the process would take both as a whole, and for each step. Please identify what filings would be made, whether and how discovery would be allowed, and what types of determinations would be required by the Authority. b. Where in the reconciliation process will the distinction and differences be identified between realized annual plant addition costs and the associated rate base, and the return, taxes, and deprecation on rate base that are included in the going-in revenues? c. Will the annual PBR reconciliations be assessments of the whole Company’s rate base with calculations of commensurate return, tax and depreciation, or will it be an incremental adjustment based on annual plant additions? Please explain. d. Provide one or more examples, as appropriate, showing how the annual capital recovery process, including reconciliation, would function, including detailed calculations in the form to be used in the annual adjustment filings. e. Provide a list of all types of costs that will be included in the capital recovery reconciliations. OCC-857 Response: a. The Company has given this process a lot of thought based on discussions throughout the PBR dockets. Based on input from those sessions, the Company’s proposal is to align the Performance Based Multi-Year Rate Plan (PBMRP) with the Rate Year, and as much as possible, aligns with the existing annual RAM ratemaking process. As such, the Company proposes that PBMRP adjustments occur on each July 1, starting with July 1, 2027, and annually thereafter. For each year that the PBMRP mechanism is in effect, the Company would submit an Annual PBR Plan Compliance Filing to PURA in the annual RAM proceeding. The annual compliance filing would include, among other things:
  7. Page 80 of 150Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-367 Page 5 of 6 (1) the calculation of the annual revenue-cap adjustment; (2) the new proposed rate using the PBR formula; (3) an earnings-sharing computation; (4) cost documentation for the Company’s capital investments; (5) the calculation and reconciliation of the annual capital-cap adjustment; (6) documentation of metric performance and resulting penalties or incentives; and (7) bill impacts of the new rate by rate class. (8) as applicable, any request for exogenous cost recovery. With respect to the capital-support mechanism or “F” factor in the formula, the Company proposes a mechanism based on a fixed annual capital investment level for each year of the PBMRP, with reconciliation through PURA’s annual RAM proceedings. The fixed annual investment level would initially be set at the Company’s capital forecast, as approved in this proceeding, and would be subject to downward-only reconciliation1 in the event that either i) the Company’s actual plant in service is lower than projected and utilized in establishing the initial F-Factor for that Rate Year or ii) PURA ultimately denies as imprudent a level of investment that was initially included in the F Factor allowance. In this way, customers are assured that rates ultimately reflect the costs of system investments that are actually in service, and have been found prudently incurred by PURA. As described in its Exhibit CLP-ELP-1 testimony, the Company has presented different investment trajectories in the Company’s 5-Year targeted system performance (TSP) and is proposing to establish the capital support mechanism of the PBR adjustment consistent with the annual capital funding requirements presented in Figure 7 of the Exhibit CLP-ELP-1 testimony. As part of the Company’s annual RAM compliance filing, actual plant additions placed in service during the applicable plan year would be reconciled against the approved forecast that would have been utilized in the prior PBMRP filing to establish the F-Factor initially. Following PURA’s determination that the Company’s actual plant additions are prudent, used and useful, the Company’s allowed rate base and associated revenue requirement for that year will be limited to the lesser of (1) the total revenue requirement for the forecasted capital approved in this proceeding; or (2) the total revenue requirement for the actual plant in service. As described previously, if the Company’s actual capital additions exceeds the forecasted amount approved in this proceeding, the Company would not be permitted to seek recovery of the incremental investment during the initial four-year PBMRP Term. Any such investment would instead remain subject to review and consideration in a subsequent base rate proceeding or successor PBMRP Term. The Company’s proposed capital funding mechanism sets a defined cap on capital recovery during the plan term, providing customers with greater rate certainty and placing the risk (and cost) of increased capital spending on the Company during the course of the PBMRP. The annual reconciliation further protects customers by blocking recovery of investments that are delayed, deferred, canceled, or not placed in service, since those costs would not be reflected in the “F” factor upon reconciliation, which is based on plant in service. For these reasons, the proposal aligns cost recovery with prudent investment and incentivizes efficient execution of the capital program, all while minimizing customer over-collection. Based on the above framework, an exhibit that demonstrates a revenue requirement consisting of: (1) a reconciliation of actual plant additions placed in service during the previous calendar year against the approved forecast (also referred to as the F-factor allowance) for that calendar year, and (2) the F-factor allowance for the new Rate Year beginning July 1st, would be filed on or about March 1st of each year consistent with the timing of all other RAM component reconciliations. Concurrent with that timing, all plant additions documentation for the previous calendar year included in the above reconciliation will also be filed on or about March 1st as part of the same filing.
  8. Page 81 of 150Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-367 Page 6 of 6 Further, under the Company’s proposed timeline, the revenue requirement resulting from the reconciliation of the prior year’s F-factor allowance and the new Rate Year’s F-factor allowance will go into effect on July 1, following the March 1st filing. As part of the RAM process, PURA performed prudence reviews of capital documentation filed for the ESI, including discovery, between March 1st and September 1st, the date on which additional RAM rate changes were made. Even though PBMRP rates would go into effect on July 1st, the Company proposes that this timeline continues to be used for capital prudence reviews under the PBMRP. To the extent PURA’s prudence review warrants any adjustment to the revenue requirement that went into effect on July 1, the Company will calculate the excess revenue collected from customers over the period of July 1 through August 31 and include this amount, plus carrying costs for those 2 months, in the RDM’s allowed revenue target for the July 1 through June 30th Rate Year. b. Please refer to subpart (d) of this question. c. Please refer to subpart (d) of this question. d. Please refer to the example shown in EOE-156, Attachment 1, pages 4 through 12, showing how the annual capital recovery process, including reconciliation, would function, including detailed calculations in the form to be used in the annual adjustment filings. Please note that pages 4, through 12, show an illustrative example for all four Rate Years contemplated for the duration of the PBMRP; however, the annual filing would only be for a single year of the PBMRP. As part of this example, please refer to the differences between realized annual plant addition costs and the associated rate base, and the return, taxes, and depreciation on rate base that are included in the going-in revenues found in EOE-156, Attachment 1, worksheet “PBR-7 Going-In Capital RR”, Lines 13-16. Additionally, the detailed calculations shown in EOE-156, Attachment 1, pages 4 through 12, demonstrate that the annual PBR reconciliations will be an assessment of the Company’s total accumulated depreciation included in base distribution rates (i.e., customers will be receiving credit for the increase in the Company’s accumulated depreciation for all capital included in base distribution rates), as opposed to the Company’s entire rate base (the Company considers its entire rate base to include other rate base items such as deferred assets and liabilities, etc.). e. The revenue requirement for capital recovery will include appropriate recovery of net plant in service, accumulated deferred income taxes (“ADIT”) and accumulated depreciation for the cumulative additional plant additions and will include a pre-tax return on investment (i.e. return on rate base including income taxes), return of investment (i.e. depreciation), property taxes, gross earnings tax and uncollectible expense.
  9. Page 82 of 150Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-368 Page 1 of 16 Date Filed: October 14, 2026 Witness: Douglas P. Horton, Brendan J. O’ Brien, Garrett J. Murray, and Timothy J. Griffin Request from: Office of Education, Outreach, and Enforcement Question: (F-FACTOR; PROPERTY TAXES O&M) Confirm that both the Company’s proposed F-Factor calculation and the proposed revenue cap formula calculation increase the revenue requirements for property taxes. If confirmed, provide an analysis detailing the estimated property tax increase that would result within the revenue cap formula for each of the four Rate Years. As part of the increase, please account for the impact of the gross earnings tax (GET) and allowance for uncollectible amounts (i.e., the 7.63% and .63% included within the PBR-3 F-Factor Summary tab). If not confirmed, explain how the property tax expense would be excluded from the revenue cap formula to include the corresponding reduction in the property tax basis used after accounting for depreciation. Response: The premise of this interrogatory is incorrect. The Company’s proposal does not increase revenue requirements for normal property taxes through both the F-Factor as well as another component of its PBMRP proposal, such as I-X. Unlike the framework outlined in the 2021-05-15RE01 Proposed Final Decision (“PFD”), which would have resulted in overlapping treatment of property-taxrelated revenue requirements, the Company’s proposal was specifically designed to avoid that outcome by separating capital cost recovery from O&M cost recovery. As described in the Company’s response to EOE-156 i, the I-X-CD adjustment is applied only to O&M expense. This is demonstrated in EOE-156, Attachment 1, Worksheet “PBR-1 Total PBRA,” Line 21, which identifies its source as “Exhibit CLP-REVREQ-2, Schedule C-3.0, Column F, Line 51.” Property taxes, by contrast, are reflected on Line 61 of that same schedule and are not included in the O&M expense amount to which I-X-CD is applied. Accordingly, the Company’s proposal does not apply I-X-CD to a revenue requirement that includes property taxes. Under the Company’s proposal, any incremental revenue requirement associated with property taxes arises solely through operation of the F-Factor. The PFD, however, not only does not offer that separation, it clearly results in overlap. Specifically, Step 6 of the CT-Bar mechanism expressly incorporated property taxes into the capital-related revenue requirement calculation:
  10. Page 83 of 150Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-07 Date Issued September 26, 2026 EOE-368 Page 2 of 16 Step 6: The Authority will calculate the amount of revenue the EDC may recover through the CT-Bar for CT-Bar Projects by taking the CT-Bar Projects identified in Step 5 and allocating the costs associated with those projects equally to each month of Rate Year 1. The Authority will then multiply each month’s CT-Bar Project costs by the depreciation, property tax, and GET rates approved in the EDC’s rate amendment decision and add those costs together to determine an aggregated monthly amount. The Authority will then use the aggregated monthly amount to determine the annual revenue requirement impact. A similar approach will be taken for each respective Rate Year of the MRP, i.e., Rate Years 2 through 4. (PFD, Appendix Page x, emphasis added). Thus, under the PFD, property taxes were expressly embedded within CT-Bar revenue requirements. At the same time, the PFD further discusses application of the I-Factor to all variables of the revenue cap formula: “The Authority will apply the I-Factor to all variables within the Revenue Cap Formula, capital funding mechanisms, (i.e., CT-Bar and any potential Capital Cost Trackers), PIMs, SSMs, and regulatory assets and liabilities.” (PFD, Appendix Page vi, emphasis added). Accordingly, the PFD not only included property taxes within CT-Bar revenue requirements, but also subjected those CT-Bar amounts to the application of the I-Factor through the broader revenue cap framework. As a result, the PFD’s approach would have increased revenues related to property taxes through multiple mechanisms, which, at a minimum, obscures the degree to which property taxes are reasonably accounted for in its framework. The Company’s proposal intentionally avoids that result. Rather than embedding property-tax recovery within a capital mechanism as well as the revenue base to which inflation is applied, the Company separates revenues supporting O&M from those driven by system investment. O&M expense alone is subject to the I-X-CD adjustment, while capital-related revenue requirements, including associated property taxes, are recovered exclusively through the F-Factor. This structure ensures a clear delineation between O&M and capital cost recovery and prevents the overlapping result outlined in the PFD. Prior Referenced Response: i EOE-156 Question: (PBMRP CAPITAL SUPPORT MECHANISM) Refer to Exhibit CLP-ELP-1, pp. 101-103. Provide a working, unlocked Excel spreadsheet that would serve as a representative tool used to calculate the Company’s incremental revenue requirements resulting from the proposed capital support mechanism (F-Factor) for each year of the MRP. As part of the submission, discuss the calculations and separately identify and explain all critical assumptions, using cited information from the Company’s rate case submission where relevant (e.g., depreciation rate from the Company’s depreciation study). In support of the request, please use the Company’s

Text of NECTA Set 4_COMBINED.pdf

Extracted from the file · 14 pages · 26,843 characters

Text of NECTA Set 5_COMBINED.pdf

Extracted from the file · 27 pages · 51,321 characters

Text of OCC Set 22_COMBINED.pdf

Extracted from the file · 40 pages · 63,151 characters

Text of OCC Set 23_COMBINED.pdf

Extracted from the file · 8 pages · 12,023 characters

Text of OCC Set 25_COMBINED.pdf

Extracted from the file · 33 pages · 57,780 characters

Text of OCC Set 26_COMBINED.pdf

Extracted from the file · 11 pages · 14,212 characters

Text of PURA Set 6_COMBINED.pdf

Extracted from the file · 82 pages · 163,601 characters

Text of PURA Set 7_COMBINED.pdf

Extracted from the file · 141 pages · 373,939 characters

Text of UCONN Set 1_COMBINED.pdf

Extracted from the file · 45 pages · 105,510 characters

Text of UCONN Set 2_COMBINED.pdf

Extracted from the file · 19 pages · 40,074 characters

As listed on the current system

Corres. 10/21/2026 [26-05-10] (Keegan Werlin LLP) - Compilation of Discovery Responses