Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Compilation of Discovery Responses

Files15

Search terms highlighted
Eversource rate increase is on 113 pages across 8 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of CLF-AC Set 2_COMBINED.pdf

Extracted from the file · 18 pages · 32,497 characters

Text of EOE Set 7_COMBINED.pdf

Extracted from the file · 150 pages · 432,851 characters

Text of NECTA Set 4_COMBINED.pdf

Extracted from the file · 14 pages · 26,843 characters

Text of NECTA Set 5_COMBINED.pdf

Extracted from the file · 27 pages · 51,321 characters

2 pages match
  1. Page 1 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-867 Page 1 of 1 Date Filed: October 09, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-06)(MS24E), p. 25-27. Did this crew perform any work on March 12 or were they on standby at the Cheshire Work Center that day? If they performed work, please indicate where they worked and how the Company knows about and validated that work. Response: The individual referred to in Exhibit ACCT-2(CLP-5A-06)(MS24E), pages 25-27, is providing contractor tree crew supervision and dispatching to support storm restoration. The contractor’s supervisory personnel do not maintain records of specific crew dispatch locations during storm events because they are not personally responding to each work site. Their role is to supervise operations and dispatch the tree crews performing the work to locations identified through the Company’s restoration process.
  2. Page 2 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-868 Page 1 of 1 Date Filed: October 09, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-06)(MS24E), p. 56. It appears that someone crossed out “MN24F” from the invoice and instead allocated the storm to “MS24E011.” Please explain who did this and how they validated that the work should be attributed to MS24E and not MN24F. Response: From March 6, 2024, through March 13, 2024, the Company completed three separate storm restoration events (MN24E, MN24F, and MS24E). The storm code was corrected from MN24F to MS24E after the Company Arborist reviewed the police detail invoices and determined that the work was performed in support of the MS24E, rather than the MN24F. The original entry was a vendor administrative error. The Company Arborist verifies the correction using their personal crew assignment, scheduling, and operational knowledge, which confirmed the work was associated with MS24E. The revised invoice reflects this correction and aligns the record with the appropriate storm event. The Company Arborist’s signature is the verification the work was billed correctly.
  3. Page 3 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-869 Page 1 of 1 Date Filed: October 09, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-07)(MS24E), p. 1-16. This vendor included receipts for hotel accommodations, but no travel time was indicated on the timesheets. Was this vendor based in Connecticut? If not, please explain why no travel time was noted. Response: MJ was a dock crew currently working in CT on Eversource property. As a result the crew did not require travel to reach the Company’s system. However, as it was a multiple day storm, the contractors were lodged so that they were located near the work that they would be assigned to and so that they would be available to the Company as needed.
  4. Page 4 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-870 Page 1 of 1 Date Filed: October 09, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-07)(MS24E), p. 61-67. a. Please explain why the sole charge attributed to this vendor is for vehicle rentals. b. What vehicles were rented? c. For what were the vehicles used? Response: Referring to ACCT-2(CLP-5A-07)(MS24E), Outside Contractor- Vendors, lines 262, vendor Mears Group Inc, invoice total amount of $1,590. Upon further review in drafting this response, the Company determined that these costs are not associated with the event. The Company will supplement ACCT-2(CLP-5A-07)(MS24E), to remove line 262 in the amount of $1,590.
  5. Page 5 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-871 Page 1 of 2 Date Filed: October 09, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-07)(MS24E), p. 92-94. a. Box 12 on the timesheet indicates 15 or 16 hours worked on March 12, but boxes 24 and 25 show the earliest work time starting at 6:45 am and the latest end time at 7 pm. Please explain this discrepancy. b. Boxes 24 and 25 contain overlapping work times, such that every member of the crew could not have worked each of the times indicated. Please explain how the Company confirmed that every member of the crew worked for 15 or 16 hours that day. Response: a. All contractor crews and non-Connecticut based Company employees working storm restoration in Connecticut are required to be lodged in hotel rooms. Prior to beginning their first job of the day, the crews eat a meal, conduct safety briefings, perform U.S. Department of Transportation mandated pre-trip inspections on their trucks, and restock their trucks as necessary with material needed for their day. This takes time and the crews are methodical because they don’t want to get out into the field without the right equipment or materials. The crews start the work shift by driving from their hotel rooms to the job site and depending on the availability of hotel rooms, that can add an additional 30 minutes or more. At the end of their last job of the day, the crews are required to clean up their job site, properly store all equipment and tools, eat a meal after performing physical labor all day in situations where their personal safety is continually at risk and often in unforgiving conditions; and drive back to their hotel rooms, which again, could be 30 minutes or more away from the jobsite. Therefore, intervals of time at the start and end of the work shift and between restoration “events” is an expected and necessary part of the work shift, for which the crews are paid. Within a work shift, the crews do not get paid differently for different types of work. Therefore, from a field perspective, the start and stop time is the critical datapoint for the timesheet. b. The timesheets on p. 92-94 are not for a single crew. The size of a line crew is dependent upon the work being performed. For a lot of jobs that have minimal damage, a single two-
  6. Page 6 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-871 Page 2 of 2 person crew in one bucket can accomplish the job on their own. On other events with extensive damage (broken poles, many spans of wire down, etc.) it can require several twoperson crews working as a team to make the repairs and re-energize the area. When the Company onboards contractor crews, it is identified how many crews the contractor contingent is bringing onboard. The Company employee dispatching the crews and the ERFC physically in the field with the crews both confirm that all crews are properly engaged and working throughout the duration of the storm.
  7. Page 7 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-872 Page 1 of 2 Date Filed: October 16, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-07)(MS24E), p. 117-121. a. Box 12 on the timesheet indicates 9 hours worked on March 12, but boxes 24 and 25 show the earliest work time starting at 8 am and the latest end time at 12:15 pm. Please explain this discrepancy. b. Boxes 24 and 25 contain overlapping work times, such that every member of the crew could not have worked each of the times indicated. Please explain how the Company confirmed that every member of the crew worked for 9 hours that day. Response: a. All contractor crews and non-Connecticut based Company employees working storm restoration in Connecticut are typically lodged in hotel rooms. Prior to beginning their first job of the day, the crews eat a meal, conduct safety briefings, perform U.S. Department of Transportation mandated pre-trip inspections on their trucks, and restock their trucks as necessary with material needed for their day. This takes time and the crews are methodical because they do not want to get out into the field without the right equipment or materials. The crews start the work shift by driving from their hotel rooms to the job site and depending on the availability of hotel rooms, that can add an additional 30 minutes or more. The intervals of time at the start of the work shift and between restoration “events” is an expected and necessary part of the work shift, for which the crews are paid. Within a work shift, the crews do not get paid differently for different types of work. Therefore, from a field perspective, the start and stop time is the critical data point for the timesheet. b. The referenced timesheets are not for a single crew. The size of a line crew is dependent upon the work being performed. For a lot of jobs that have minimal damage, a single two-person crew in one bucket, or possibly two bucket trucks, can accomplish the job. On other events with extensive damage (broken poles, many spans of wire down, etc.), it can require several two-person crews working as a team to make the repairs and re-energize the area. When the Company onboards contractor crews, it is identified how many crews the contractor contingent is bringing onboard. The Company employee dispatching the crews and the ERFC physically in the field with the crews both confirm that all crews are properly engaged and working throughout the duration of the storm.
  8. Page 8 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-872 Page 2 of 2 March 12 was the final day of the storm event. At the end of any event, restorations are down to the last individual outages, and the Company is focused on returning the system to its steady state, deploying available crews to the stack of single or small outage events and non-outage events that have to be completed before the resources are demobilized. As crews are working in the field, the Company is working through its systems to assess what’s left to do, in what locations and which resources are needed before individual crews or groups of crews are demobilized and sent away from the system. The crews on the referenced timesheets started their time at 0600 and arrived at their first job at 0800, finished work on certain identified events at 12:20 p.m. and then were in the field until 3 p.m. when they were demobilized. Because it was the very end of the restoration effort, the multiple crews were functioning in a team, splitting up to cover multiple jobs throughout the day coordinated through this group. All crews worked for nine hours, 6 a.m. till 3 p.m. and properly billed the Company for that time. The listed OMS events are just the time that crews were working on specific events tracked for completion. During other hours, these crews were completing other tasks not recorded as “events” in the system and were present on the system until demobilized.
  9. Page 9 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-873 Page 1 of 1 Date Filed: October 09, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-08)(MS24E), p. 21. a. Please cite to the provision of the vendor’s contract in the record that permits the vendor a six hour rest period. b. The timesheet allocates four hours as “Return to Windsor Locks” after the rest period. Where was the crew before it returned to Windsor Locks? Response: a. The contract does not permit a vendor to bill for rest time. “Emergency Response Working Rates for Labor” are the agreed labor rates payable from the commencement of applicable Emergency Response Work through the termination of such Emergency Response Work, excluding rest time during that Emergency Response Work. Rates are all inclusive of wages, insurance, taxes, overhead, profit and shall be in effect for the term of this Agreement. In this instance, the crews worked overnight into the following morning. Accordingly, their rest period occurred during the morning/early afternoon hours, consistent with the rest period that would occur overnight for a crew working a typical daytime schedule. The crews were not compensated during this rest period. b. Prior to returning to Windsor Locks, the crew was at its hotel in Newtown, Connecticut. The submitted timesheets reflect travel from the crew’s last job in Guilford, Connecticut, at approximately 0900 to the Newtown hotel, followed by the crew’s rest period. Following release, the 1500–1900 period included checkout from the hotel and return travel from Newtown to Windsor Locks, as well as associated demobilization activities, including returning or disposing of unused or spent materials, conducting a safety debrief, taking a meal, and securing and demobilizing equipment upon arrival at the contractor’s yard. Based on these activities, travel/demobilization hours were reviewed and approved by the Company.
  10. Page 10 of 40

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-22 Date Issued September 28, 2026 OCC-874 Page 1 of 1 Date Filed: October 09, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (Storm MN25K – Invoice) Refer to Exhibit ACCT-2 (CLP-13A-17) (MN25K). The following pertains to Invoice #252417001R (p. 6-22). Per review of the documentation, it was noted that a breakout of the items within the invoice was not included relating to the labor, equipment, meals, and lodging charged and their associated rates per item. Explain how the Eversource reviewer reconciled the work performed by these crews without this breakout and rates. If the vendor provided a breakdown of the invoice, please provide to ensure the appropriate rates were applied based on the contract provided as part of OCC-44. Response: Referring to Exhibit ACCT-2 (CLP-13A-17) (MN25K), Outside Contractor-Vendor, line 559, vendor Nooter Construction LLC, invoice total amount of $392,655. As part of the Company’s invoice review and approval process, contractor invoices are reconciled against the supporting timesheets submitted by the contractor and verified against the applicable contract rates in effect at the time the services were performed. This reconciliation includes a review of labor classifications, equipment charges, lodging expenses, meal allowances, and any applicable per diem amounts. Where discrepancies or variances are identified, the Company contacts the contractor to investigate and resolve such differences prior to approval and payment. In this instance, the contractor provided a detailed breakdown of labor, equipment, meal, and lodging charges. The Company reviewed this supporting documentation as part of its reconciliation process and verified that the charges were consistent with the applicable rates and supporting records. Based on that review, the Company confirmed that the invoice reflected the appropriate charges for the services provided. Please refer to OCC-874, Attachment 1 CONFIDENTIAL, detailing labor, equipment, meals, and lodging charges.

Text of OCC Set 23_COMBINED.pdf

Extracted from the file · 8 pages · 12,023 characters

Text of OCC Set 25_COMBINED.pdf

Extracted from the file · 33 pages · 57,780 characters

Text of OCC Set 26_COMBINED.pdf

Extracted from the file · 11 pages · 14,212 characters

Text of PURA Set 6_COMBINED.pdf

Extracted from the file · 82 pages · 163,601 characters

Text of PURA Set 7_COMBINED.pdf

Extracted from the file · 141 pages · 373,939 characters

Text of UCONN Set 1_COMBINED.pdf

Extracted from the file · 45 pages · 105,510 characters

Text of UCONN Set 2_COMBINED.pdf

Extracted from the file · 19 pages · 40,074 characters

As listed on the current system

Corres. 10/21/2026 [26-05-10] (Keegan Werlin LLP) - Compilation of Discovery Responses

This filing on the current system (opens in a new tab)