  1. Page 1 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 05, 2026 OCC-901 Page 1 of 4 Date Filed: October 19, 2026 Witness: Douglas P. Horton Request from: Office of Consumer Counsel Question: (SCRAF Mechanism) Please quantify the savings and benefits, if any, in carrying charges that the Company expects to result from implementation of the proposed SCRAF as compared with recovery under the current storm cost recovery framework. Provide all assumptions, calculations, and workpapers supporting the response. Response: The Company assumes that the reference to “the current storm cost recovery framework” is a reference to the following framework: 1. The Company is authorized to defer incremental expenses incurred to restore power following a storm event, where those incremental expenses exceed $4 million, or where the Company has notified PURA of its intent to pre-stage a potential event and those incremental expenses do not exceed $4 million. 2. The cost of “minor” events, or events where less than $4 million in incremental cost is incurred to restore power to customers, is recovered through base rates, with a representative amount included in rates in a rate proceeding based on historical experience. 3. DISPUTED. No carrying charges are allowed on deferrals to the Catastrophic Storm or PreStaging Event Reserves unless and until a prudence review is completed – and then only on the deferred balance determined to be prudently incurred. 4. DISPUTED. The prudence review can only occur in the context of a rate proceeding, unless required by approved settlement provision or as a matter of PURA discretion. 5. DISPUTED. Carrying charges commencing on the date of the prudence review are recoverable in a rate proceeding only prospectively, as applied to the unamortized balanced over the amortization period, collected through distribution rates (but not through rate base). 6. Actual recovery of storm costs or associated carrying costs cannot occur outside of a distribution rate proceeding. The Company’s proposal for establishment of a revised storm mechanism in this case seeks to resolve these disputes and to create a framework that is fair, efficient, lawful, provides timely and
  2. Page 2 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 05, 2026 OCC-901 Page 2 of 4 adequate recovery for prudently incurred costs and mitigates cost impacts for customers to the maximum extent feasible for administrative proceedings. As the Company discussed in detail in response to OCC-522 i, the reduction of carrying costs is a primary benefit of a systematic approach. Accordingly, the Company’s framework employs a systematic mechanism that would operate outside of base rates with an annual funding contribution collected through distribution rates to mitigate carrying costs for catastrophic storms and prestaging events. In this framework, the reduction of carrying costs is an important tool to mitigate costs for customers, although the Company does not agree that PURA has lawful authority to simply bar the application of carrying costs unless or until a prudence review is completed. The Company does agree that carrying costs may only be recovered on costs that are ultimately determined to be prudently incurred and this would require the refund of any carrying costs accrued on deferred costs from the date of cost incurrence (if collected), in the event that costs are declared to be imprudent. In this context, a critical feature of a new storm-cost recovery mechanism is for it to operate on a shorter-term cycle, so that prudence reviews are systematically performed; deferred costs are not allowed to accumulate for a multi-year period; and recovery is timely and efficient, so that carrying costs can be minimized and the Company is not impaired by the fact that customer obligations are allowed to remain outstanding for long periods. Also, with a more timely, systematic format for storm-cost review and recovery, the carrying cost rate can approximate a debt rate instead of the weighted average cost of capital (“WACC”), which is necessary, appropriate and lawful where the periods that deferred amounts must be carried are relatively longer. To illustrate the savings and benefits that would result from the Company’s proposed framework, as compared to the current framework, lawfully applied, the Company is building a model to compare a SCRAF mechanism (operating annually outside of base rates) to a framework that relies on rate-case intervals. Carrying costs will be greater as the timeframe for deferral and recovery is extended. However, the Company’s model will demonstrate the results that would be achieved with more systematic recovery and will be provided as a supplement to this response. Prior Referenced Response: i OCC-522 Question: Leadership Panel Exhibit CLP-ELP-1 – Storm Cost Recovery (Carrying charges applied to SCRAF) In its proposal, the Company notes, “should PURA implement the SCRAF, which provides for more timely review and recovery of storm and pre-staging costs, the Company accepts the Prime rate from the date of cost incurrence, applied to the net balance of the storm fund and pre-staging reserve fund 6 for storms occurring after March, 2025.” (p.143) Did the company consider or analyze setting carrying charges on costs recovered through SCRAF to be equal to the commercial paper index or the utility's actual cost of short-term debt, rather than the prime rate?
  3. Page 3 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 05, 2026 OCC-901 Page 3 of 4 a. If yes, provide the analysis conducted and the rationale for proposing the use of the Prime rate instead. b. If not, explain why the Company did not consider proposing that the carrying charges on SCRAF recovery to be set at either the commercial paper index or actual cost of short-term debt. OCC-522 Response: a. and b. Carrying costs are the mechanism by which the Company recovers its cost of money. Thus, carrying costs must be tied to the actual cost that the Company is incurring to carry the storm deferral. When the storm deferral is relatively larger and carried for a relatively extended time period, then the Company’s weighted average cost of capital (“WACC”) is its actual carrying cost. If PURA establishes a ratemaking mechanism that provides more systematic reviews and more timely recovery, then the cost of money may be susceptible to approximation with lower cost sources of funds. The relationship between time and quantity and the cost of capital is clearly demonstrated through a utility’s cost of service whereby a utility’s rate base (comprised mainly of the Company’s plant which is paid back by customers over many years) receives a return at the Company’s authorized WACC. Applying the Company’s WACC to long-term assets aligns the carrying charge calculation with the manner in which comparable longterm assets are reflected for ratemaking purposes. Similarly, the WACC is the appropriate rate for calculating carrying charges on long-term funded regulatory assets because it reflects the Company’s actual cost of funding those customer “debts,” including storm restoration costs, over an extended period of time. Financing obligations – certainly obligations of this magnitude – cannot be supported exclusively through debt financing, whether short-term or long-term. Instead, the Company must balance its capital requirements through a reasonable mix of both debt and equity to ensure financial stability and continued access to reasonably priced capital. With respect to the appropriate carrying charge rate to utilize for the Storm Cost Recovery Adjustment Factor (“SCRAF”), the Company provided a thorough response to this question in response to LFE-031, in Docket No. 25-12-13. The Company is providing that response as OCC-522, Attachment 1. The analysis shows that: (1) necessary uses of cash routinely exceed available sources of cash, creating a persistent funding gap; (2) commercial paper is a tool to maintain liquidity, not to finance investments or deferred expenses; and (3) short-term borrowing capacity is limited, and the Company cannot plan to operate at or near its short-term debt capacity without putting its ability to operate the system in severe jeopardy. Given all of the considerations elucidated by Attachment 1, the Company recognizes that the appropriate treatment of carrying charges may vary based on the regulatory framework established within each jurisdiction. Different regulatory constructs reflect differing policy objectives and mechanisms designed to balance the Company’s financing needs with customer impacts. In establishing a going-forward framework for storm cost recovery, the Company agrees that it would be within PURA’s discretion to strike a balance between the Company’s costs of financing storm costs while ensuring that the Company is not ‘profiting’ on a force majeure event like a storm. This is the Company’s experience in Massachusetts, as well, where the MDPU has authorized a carrying charge rate that is different from and generally less than the Company’s WACC, but that still recognizes that the Company is using its longer-term capital resources to finance storm costs (not its shorter term commercial paper source of liquidity). Thus, the Company stated that “should PURA implement the SCRAF, which provides for more timely review and recovery of storm and pre-staging costs, the Company accepts the Prime rate from
  4. Page 4 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 05, 2026 OCC-901 Page 4 of 4 the date of cost incurrence, applied to the net balance of the storm fund and pre-staging reserve fund for storms occurring after March, 2025.”
  5. Page 5 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 02, 2026 OCC-902 Page 1 of 3 Date Filed: October 21, 2026 Witness: Donald J. Scacco Jr., Digaunto Chatterjee and Douglas P. Horton Request from: Office of Consumer Counsel Question: (SCRAF Mechanism) Has the Company considered limiting SCRAF eligibility to storm events that also satisfy an objective storm-magnitude criterion, such as a Major Event Day designation under the IEEE Major Event Day methodology (2.5 Beta Method), a minimum number of customers interrupted, or a specified ERP tier or level, in addition to the proposed dollar-cost threshold? a. If the Company didn’t consider such criteria, please explain why. If the Company considered and rejected such criteria, please provide any analysis performed and explain the basis for relying solely on a cost-based threshold. b. If one or more of the three additional objective criteria in this question were to be adopted for the Company to be eligible for SCRAF recovery, if approved, discuss the implications and changes to storm preparation and response that the Company would consider adopting going forward? c. Are there any other objective criteria that the Company would be comfortable adopting, in addition to the cost per event threshold, to be eligible for SCRAF recovery? Response: The Company considered whether additional objective criteria can reasonably and workably be used in conjunction with the proposed cost threshold for SCRAF eligibility because introducing objective criteria would help to eliminate controversy and provide clarity to all parties, including the Company. However, criteria such as an IEEE Major Event Day ("MED") designation, a minimum number of customers interrupted, or a specified ERP tier do not necessarily provide an valid and reliable indication for determining that incremental storm restoration costs are in excess of the level included in base rates and should be recoverable. The proposed cost threshold is intended to identify events that require restoration efforts at a level that is above and beyond the level set in base rates for non-catastrophic storms and for which it is not possible to establish a ‘representative level’ in base rates due to the magnitude and inability to accurately predict the frequency of events of this magnitude.
  6. Page 6 of 41Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 02, 2026 OCC-902 Page 2 of 3 a. Additional Criteria The Company did not recommend a MED-based criterion because the MED designation is based on system reliability performance rather than restoration cost for outages caused by operating circumstances not recognized by MED. Under the IEEE 2.5 Beta methodology, the MED threshold changes over time based on historical reliability performance. As the Company continues to invest in automation, sectionalizing, and other reliability improvements, outage impacts measured through SAIDI may decrease even though the underlying damage and restoration effort remain substantial. Consequently, the use of an MED threshold could produce the unintended result that a storm requiring significant incremental restoration resources, including external crews and their associated costs, would be ineligible for a prudence review under the SCRAF simply because customer outage impacts were reduced through prior reliability investments, even in situations where the costs were incremental and prudently incurred in accordance with the PURA approved ERP. Similarly, a minimum customer interruption threshold is not an appropriate criterion because restoration costs are driven by the nature and extent of system damage rather than solely by the number of customers affected. For example, a fault on a heavily automated circuit may affect fewer customers than a similar event on a circuit without such automation, or on the same circuit in prior years prior to installation of automation, while still requiring the same field resources, equipment, and repair activities to restore service. As system automation expands, the relationship between customer interruptions and restoration costs becomes increasingly disconnected, even in situations where the costs are still determined to be incremental and prudently incurred. Also, a major component of storm response is the clearing of blocked roads and other public-safety necessities, which are not reflected in customer outages. Similarly, a fixed ERP tier would similarly not be an appropriate criterion because ERP classifications are operational tools used to manage Company resources and may be influenced by factors such as forecast uncertainty, geographic scope, and restoration complexity. ERP levels are not designed to determine whether costs are incremental to normal operations or suitable for regulatory cost recovery. Accordingly, the primary indicator of whether an event exceeds normal operating conditions and should be eligible for recovery under the SCRAF is the magnitude of incremental restoration costs, which is a function of external crew utilization. Catastrophic storm costs are impossible to predict with accuracy and are therefore not possible to reflect in rates on a representative level. Moreover, incremental costs may still be prudently incurred in accordance with the ERP even if the triggers discussed in this response are not met, and therefore cost should be the determining factor of SCRAF cost recovery eligibility rather than another measure.
  7. Page 7 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 02, 2026 OCC-902 Page 3 of 3 b. Implications of Adopting Additional Criteria If eligibility for SCRAF recovery were conditioned on an MED designation, customer interruption count, or ERP tier, the Company would need to evaluate how those requirements could affect restoration planning and resource deployment decisions. For example, an MED or customer-count criterion could create a situation where investments that reduce outage impacts also reduce the likelihood that an event qualifies for recovery, even when restoration costs remain substantial. This could create a disconnect between reliability objectives and cost recovery mechanisms. The Company's objective during storm response is to restore customers as quickly and safely as possible, and cost recovery criteria should not eliminate the potential for cost recovery without a prudence review. Likewise, if a specific ERP tier were required, the Company would need to consider the interaction between operational activation decisions and regulatory recovery treatment. The Company's ERP classifications are intended to support safe and effective storm response and should remain focused on operational needs rather than cost recovery outcomes. c. Alternative Objective Criteria If an additional objective criterion were required, the Company would be more comfortable with a criterion tied to the need for external restoration resources. In the Company's view, the clearest indication that an event exceeds normal operating conditions is that internal resources are insufficient and external mutual assistance or contract crews must be mobilized to support restoration efforts. In essence, evaluating the need for additional crew assistance encompasses concerns relating to both customer outages and public-safety demands. The need for external resources reflects the scale and complexity of the event and is directly related to the incremental costs the SCRAF is intended to address. Unlike MED designations or customer interruption thresholds, which are based primarily on outage outcomes, the use of external resources is more closely aligned with the underlying restoration effort and associated incremental costs. In addition, the Company is often required to procure crews in advance of a weather event, based on forecasted information which may or may not materialize as expected. The incremental costs associated with those events should still be eligible for recovery, based on a prudence review and determination by PURA, even if the weather does not materialize as forecast, meaning that designated MED or customer interruption thresholds are not triggered.
  8. Page 8 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 02, 2026 OCC-903 Page 1 of 2 Date Filed: October 16, 2026 Witness: Donald J. Scacco Jr., Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (Storm costs) Please provide an excel workbook with all of the following data points for each of the 14 catastrophic storm events in the 2025-2025 period the Company is seeking recovery for in this proceeding, as well as all the catastrophic storm events that were authorized for recovery in Docket 25-12-13 for the 2018-2023 time period: a. Did the storm qualify as a Major Event Day designation under the IEEE Major Event Day methodology (2.5 Beta Method)? (yes or no) b. What was the corresponding ERP level (Level 1-5) for each storm event as outlined in the Company’s Emergency Response Plan? c. What was the count of customers whose service was interrupted by the storm event? d. Would the storm have met the 1% materiality threshold as calculated in OCC-6(a) (yes or no)? e. The total cost of each storm event. Response: The Company calculates the annual IEEE 1366 TMED (Threshold Major Event Day) value in accordance with the methodology prescribed by IEEE Std. 1366. The annual TMED threshold values for the 2018-2025 period are presented in the table below. A calendar day is classified as an IEEE Major Event Day (MED) if the daily SAIDI exceeds the applicable annual TMED threshold for that year. Historical TMED Thresholds YEAR 2018 2019 2020 2021 2022 2023 2024 2025 TMED Threshold 2.4653 2.8369 3.0301 4.0733 4.0468 3.9719 3.3314 3.1844
  9. Page 9 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 02, 2026 OCC-903 Page 2 of 2 Please refer to OCC-903, Attachment 1, for a listing of storm events along with the requested data.
  10. Page 10 of 41

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-24 Date Issued October 02, 2026 OCC-904 Page 1 of 1 Date Filed: October 16, 2026 Witness: Donald J. Scacco Jr., Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Consumer Counsel Question: (Storm Cost Recovery) Please state what proportion of the catastrophic storms for which the Company is seeking recovery of costs in this proceeding were classified as Major Event Days under the IEEE Major Event Days methodology (2.5 Beta Method). In your response, provide all assumptions, calculations, and workpapers to support the following calculations: a. Provide the cost of each storm event and the average cost of all catastrophic storm events that are classified as Major Event Days, b. provide the cost of each storm event and the average cost of all the catastrophic storms that are not classified as Major Event Days. Response: Please refer to OCC-904, Attachment 1, for the requested information.

As listed on the current system

Corres. 10/22/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilations (ALLCO Set 11, CLF-SC Set 3, OCC Set 24).

This filing on the current system (opens in a new tab)