  1. Page 11 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-952 Page 1 of 2 Date Filed: October 19, 2026 Witness: Mark P. Baldwin, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to OCC-713. Is the Company stating in this response that it could not secure double hotel rooms for the invoices in question? If so, please provide evidence thereof. Response: In preparation for this response, the Company confirmed with the Hampton by Hilton, as referenced in the Company’s response to OCC-713 i, p. 129, that the reservations were made through the hotel's online booking system. At the time the reservations were made, D&D Power did not indicate that multiple occupants would be assigned to the rooms. The Hampton by Hilton further confirmed that the rooms provided to the contractor were double-occupancy rooms. Additionally, the Company confirmed with the Holiday Inn Express Hartford South, as referenced in OCC-713, p. 157, that rooms with double beds were not available at the time the reservations were booked. As a result, the contractor could not be accommodated in double-bed rooms due to the hotel's room availability limitations at the time of booking. Based on the information provided by both hotels, the lodging accommodations were secured based on the room inventory available at the time of reservation and the occupancy information supplied during the booking process. Prior Referenced Response: i OCC-713 Question: (MS24E) Please refer to Exhibit ACCT-2 (CLP-5A-02) (MS24E), p. 129-144, 157-158. Many of the hotel receipts indicate one adult/guest in the room. Please provide the Company’s policy and/or contractual provision with these vendors indicating the provision of individual hotel rooms. OCC-713 Response: Referring to Exhibit ACCT-2 (CLP-5A-02) (MS24E), Outside Contractors-Vendors, Line 114, vendor D&D Power LLC, invoice total amount of $324,466.
  2. Page 12 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-952 Page 2 of 2 During storm restoration events, the Company initially utilizes hotels with which it maintains contractual lodging agreements and works to secure all available accommodations within those facilities. When sufficient lodging cannot be obtained through these contracted vendors, the Company will secure accommodations at other available hotels within the affected area to ensure personnel have adequate lodging during the event. Consistent with past practice, the Company generally requests separate hotel rooms for supervisory personnel, separate accommodations for female employees, and double occupancy arrangements for line crews where practical. However, room availability and hotel capacity constraints are often beyond the Company's control, particularly during widespread storm events when lodging demand is elevated. As a result, hotels may be unable to accommodate all rooming preferences requested by the Company. In circumstances where double occupancy or other preferred lodging arrangements cannot be accommodated, the Company is responsible for the cost of any room assigned by the hotel to an employee at the time of check-in. The Company's primary objective is to ensure that all personnel responding to the storm event are provided with suitable accommodation and the opportunity to obtain adequate rest between shifts. Providing lodging to restoration personnel is a necessary component of the Company's storm response efforts, as it enables employees to receive proper rest and safely return to work for their subsequent assignments.
  3. Page 13 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-953 Page 1 of 2 Date Filed: October 21, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to OCC-714(a). Please explain how the Company verifies the additional amount of time billed but not indicated as worked on the timesheet. Response: The premise of this question is suggesting that the lower section of the timesheet (“Work Distribution” section) represents the amount of hours a contractor should be paid, which is incorrect. Part of the Company’s review process is to verify the accuracy and reasonableness of contractor labor charges using the billable hours per day (Timesheet boxes 10, 11, and 12), dates and times of service (Timesheet boxes 2, 6, and 7), crew information (Timesheet boxes 8 and 9), validation from field supervision overseeing the contractors work, and through consultation with supervisory personnel, as necessary. This review process serves as a key control to ensure that contractor invoices are reasonable, supported, and accurately associated with the applicable event. Boxes 20 through 25, on the timesheet (“Work Distribution”) serve as supporting information but are not representative of the total hours the contractors are entitled to be paid. Contractors are paid for their full shift regardless of whether they are working a specific OMS event. Many required work activities are performed outside of specific OMS event times. For instance, prior to beginning their first job of the day, the crews eat a meal, conduct safety briefings, perform U.S. Department of Transportation mandated pre-trip inspections on their trucks, and restock their trucks as necessary with material needed for their day. This takes time and the crews are methodical because they do not want to get out into the field without the right equipment or materials. The crews start the work shift by driving from their hotel rooms to the job site and depending on the availability of hotel rooms, that can add an additional 30 minutes or more. At the end of their last job of the day, the crews are required to clean up their job site, properly store all equipment and tools, eat a meal after performing physical labor all day in situations where their personal safety is continually at risk and often in unforgiving conditions; and drive back to their hotel rooms, which again, could be 30 minutes or more away from the jobsite. Therefore, intervals of time at the start and end of the work shift and between restoration “events” is an expected and necessary part of the work shift, for which the crews are paid. Within
  4. Page 14 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-953 Page 2 of 2 a work shift, the crews do not get paid differently for different types of work. Therefore, from a field perspective, the start and stop time is the critical datapoint for the timesheet.
  5. Page 15 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-954 Page 1 of 1 Date Filed: October 21, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to OCC-714(b). If the crew split in two and both worked the two jobs ending at 21:30 (one of which started at 13:00 and the other at 14:30), who worked the other three jobs listed on the timesheet? Response: For the two events referenced in the question that both ended at 9:30pm, one of the two crews was assigned to both tickets. As both jobs were in approximately the same geographic location (the transformers being approximately 500’ away from each other), they were assigned to the contractor at the same time with the expectation that one crew would handle both events to maximize efficiency by reducing travel time between jobsites. The contractor did not separate the times between the two tickets for the crew and considered the end time the same for both jobs. The other crew handled the overlapping work listed on the timesheet.
  6. Page 16 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-955 Page 1 of 3 Date Filed: October 26, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to OCC-716. What did this crew do between 6 am and 8 am and between 8 pm and 10 pm? To the extent the Company can answer the question, please provide evidence and/or substantiation for how it knows the answer. Response: For convenience of this response, the timesheet referenced in OCC-716 i is provided here as OCC955, Attachment 1 (Exhibit ACCT-2(CLP-5A-02) (MS24E), p. 155). On this timesheet, the crew properly documented the specific trouble events assigned to them through the OMS, which show a timespan of 8am to 8pm, which is a span of time within the crew’s 16-hour workshift running between 6am and 10pm on that same day. Putting all else aside, the two hour increments referenced in the question between 6am and 8 am, and 8pm and 10pm, have to contemplate travel time. Note that the seven jobs listed on the timesheet were located in five different towns, starting in Canaan and Cornwall, CT and ending in Sharon, CT – all located in the remote Northwest section of Connecticut, on the border of New York State, where the closest Eversource work center is at least 25 miles away in Torrington, CT (almost one hour’s drive). Typically, the Company does not house crews in that remote location and, instead, the crew would have been working out of a work location and/or hotel further south near the Company’s work centers. In the two-hour intervals at the start and end of the work shift, the crews would have had to travel from their “show up” location to this area to perform work throughout the day and then would have had to travel back to an Eversource work location and/or to their hotel, which in itself would have consumed the better part of the two-hour interval on each end. Note also, that the timesheet indicates that the crews are from Wallingford, CT and may have dispatched directly to, or from, that location, which is 65 miles away, or at least 90 minutes by bucket truck. In addition, crews cannot just show up at a job site and undertake work on high-voltage equipment without preparation of their truck at the report-in location, a safety instruction, or food – or without then cleaning up their worksite, cleaning up their trucks, potentially reporting back to the Company’s work site to check in and grabbing a meal. Given the location of the work performed, the two-hour intervals at each end of the shift are exactly what is expected of the crews, which is
  7. Page 17 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-955 Page 2 of 3 that – in a 16-hour shift – it would be completely routine for the crews to complete 12 hours of “wrench” work directly on the system with a lead time and finish time on each end to complete other work tasks and travel between locations. Prior Referenced Response: i OCC-716 Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-02) (MS24E), p. 155. Box 12 indicates a total work time of 16 hours, but boxes 24 and 25 appear to total a maximum work time of 12 hours. a. Was this crew on standby from 6 a.m. to 8 a.m.? If yes, please explain why this time was billed as work time and not standby time? If no, please explain what occurred in those two hours and how Eversource is now aware of what occurred. b. Please explain why the crew ended work at 8 p.m. but billed until 10 p.m. OCC-716 Response: a. Based on the Company’s review of the specified timesheets, there is no significant missing information within the “Work Distribution” section. The timesheets are not a contemporaneous record of every minute, task, or discrete activity undertaken by a crew in the course of performing its work. Nor is the timesheet the method by which the Company manages the crews or assures that the crew is working how and where the crews are supposed to be. The timesheets are used to document the time worked and general nature of the work performed. Timesheets are typically completed at the end of each workday, with time allotted to the major work assignments completed that day. Given the nature of storm restoration work, it would be impractical and inconsistent with the crews’ primary responsibility of safely and efficiently restoring electric service to require personnel to contemporaneously record every minute task or discrete activity performed throughout the workday. The Company manages the crews through the oversight of the employee dispatching the crews and the External Field Resource Coordinator (EFRC), who is physically in the field with the crews, ensuring that the crews are properly engaged and assigned work to restore the system from storm damage. The linemen who are filling out the timesheets are primarily focused on ensuring that their crews are working safely in a dynamic environment that is full of potentially lethal hazards. The EFRC is the Company representative that is responsible for signing the timesheets and have personal knowledge of the work that the crews have performed and the activities the crews have engaged in, particularly in relation to the hours stated in boxes 24 and 25. Importantly, the crews are in “working” status for the entire duration of their shift – from start to finish. The Company does not compensate crews based on the specific restoration event to which they are assigned, nor are crews expected to be actively engaged in an “event” every minute of their shift. Time must be allocated at the start and end of each day, as well as between restoration “events,” to complete all necessary steps to ensure safe working conditions in the field. For the Resource Management Teams identifying the jobs and deploying crews and the EFRC, the critical focus is to follow procedures, keep the crews safe, and keep them moving efficiently throughout the working shift. In this context, there is no bright line that separates one event from another and neatly segmenting the day from an “event” perspective – all activities whether in preparation of, or “on the pole,” are proper work activities that are undertaken during the work shift and will not be specified on the timesheet.
  8. Page 18 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-955 Page 3 of 3 b. Please refer to subpart (a), above. Further, all contractor crews and non-Connecticut based Company employees working storm restoration in Connecticut are required to be lodged in hotel rooms. Prior to beginning their first job of the day, the crews eat a meal, conduct safety briefings, perform U.S. Department of Transportation mandated pre-trip inspections on their trucks, and restock trucks as necessary with material needed for their day. This takes time and the crews are methodical because they don’t want to get out into the field without the right equipment or materials. The crews start the work shift by driving from their hotel rooms to the job site and depending on the availability of hotel rooms, that can add an additional 30 minutes or more. At the end of the last job of the day, the crews are required to clean up the job site, properly store all equipment and tools, eat a meal after performing physical labor all day in situations where the personal safety is continually at risk and often in unforgiving conditions; and drive back to the hotel rooms, which again, could be 30 minutes or more away from the jobsite. Therefore, intervals of time at the start and end of the work shift and between restoration “events” is an expected and necessary part of the work shift, for which the crews are paid. Within a work shift, the crews do not get paid differently for different types of work. Therefore, from a field perspective, the start and stop time is the critical data point for the timesheet.
  9. Page 19 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-956 Page 1 of 3 Date Filed: October 21, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G. Griffin Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to OCC-717. What did this crew do between 6am and 8am and between 6 pm and 10 pm? To the extent the Company can answer the question, please provide evidence and/or substantiation for how it knows the answer. Response: As evidenced by the approved timesheet, these crews were engaged by the Company in restoration efforts from 6:00am until 10:00pm and were paid according to their respective contract. Part of the Company’s review process is to verify the accuracy and reasonableness of contractor labor charges using the billable hours per day (Timesheet boxes 10, 11, and 12), dates and times of service (Timesheet boxes 2, 6, and 7), crew information (Timesheet boxes 8 and 9), validation from field supervision overseeing the contractors work, and through consultation with supervisory personnel, as necessary. This review process serves as a key control to ensure that contractor invoices are reasonable, supported, and accurately associated with the applicable event. Boxes 20 through 25, on the timesheet (“Work Distribution”) serve as supporting information but are not representative of the total hours the contractors are entitled to be paid. Contractors are paid for their full shift regardless of whether they are working a specific OMS event. Many required work activities are performed outside of specific OMS event times. For instance, prior to beginning their first job of the day, the crews eat a meal, conduct safety briefings, perform U.S. Department of Transportation mandated pre-trip inspections on their trucks, and restock their trucks as necessary with material needed for their day. This takes time and the crews are methodical because they do not want to get out into the field without the right equipment or materials. The crews start the work shift by driving from their hotel rooms to the job site and depending on the availability of hotel rooms, that can add an additional 30 minutes or more. At the end of their last job of the day, the crews are required to clean up their job site, properly store all equipment and tools, eat a meal after performing physical labor all day in situations where their personal safety is continually at risk and often in unforgiving conditions; and drive back to their hotel rooms, which again, could be 30 minutes or more away from the jobsite. Therefore, intervals of time at the start and end of the work shift and between restoration “events” is an expected and necessary part of the work shift, for which the crews are paid. Within
  10. Page 20 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-27 Date Issued October 07, 2026 OCC-956 Page 2 of 3 a work shift, the crews do not get paid differently for different types of work. Therefore, from a field perspective, the start and stop time is the critical datapoint for the timesheet. This crew documented the OMS tickets ranging from 8am to 6pm on their timesheet referred to in OCC-716 i. When the crew’s shift begins, they need to have a safety tailboard and prepare for their first job of the day. Then they head to their first job. When they complete their final ticket of the day, there is still work that needs to be done before they are finished with their shift. This includes cleaning up their worksite, cleaning up their trucks and grabbing a meal. This was also the final day of the storm and the crews are required to perform demobilization activities including the return of unused materials and any other Company property. Prior Referenced Response: i OCC-716 Question: (MS24E) Please refer to Exhibit ACCT-2(CLP-5A-02) (MS24E), p. 155. Box 12 indicates a total work time of 16 hours, but boxes 24, and 25, appear to total a maximum work time of 12 hours. a. Was this crew on standby from 6 a.m. to 8 a.m.? If yes, please explain why this time was billed as work time and not standby time? If no, please explain what occurred in those two hours and how Eversource is now aware of what occurred. b. Please explain why the crew ended work at 8 p.m. but billed until 10 p.m. OCC-716 Response: a. Based on the Company’s review of the specified timesheets, there is no significant missing information within the “Work Distribution” section. The timesheets are not a contemporaneous record of every minute, task, or discrete activity undertaken by a crew in the course of performing its work. Nor is the timesheet the method by which the Company manages the crews or assures that the crew is working how and where the crews are supposed to be. The timesheets are used to document the time worked and general nature of the work performed. Timesheets are typically completed at the end of each workday, with time allotted to the major work assignments completed that day. Given the nature of storm restoration work, it would be impractical and inconsistent with the crews’ primary responsibility of safely and efficiently restoring electric service to require personnel to contemporaneously record every minute task or discrete activity performed throughout the workday. The Company manages the crews through the oversight of the employee dispatching the crews and the External Field Resource Coordinator (EFRC), who is physically in the field with the crews, ensuring that the crews are properly engaged and assigned work to restore the system from storm damage. The linemen who are filling out the timesheets are primarily focused on ensuring that their crews are working safely in a dynamic environment that is full of potentially lethal hazards. The EFRC is the Company representative that is responsible for signing the timesheets and have personal knowledge of the work that the crews have performed and the activities the crews have engaged in, particularly in relation to the hours stated in boxes 24 and 25. Importantly, the crews are in “working” status for the entire duration of their shift – from start to finish. The Company does not compensate crews based on the specific restoration event to which they are assigned, nor are crews expected to be actively engaged in an “event” every minute of their shift. Time must be allocated at the start and end of each day, as well as between restoration “events,” to complete all necessary steps to

As listed on the current system