Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).

Files4

Search terms highlighted
Eversource rate increase is on 5 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
5 pages match
  1. Page 11 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-156 Page 7 of 12 In accordance with Section 10(a) of the 2018 Rate Settlement approved by PURA in Docket No. 17-10-46, earnings at the end of each calendar year above the authorized return on equity (“ROE”) of 9.25% shall be shared between customers and the Company on a 50/50 basis. The Company reports its ROE at the end of each calendar year in Docket No. 76-03-07 (2018 – 2020) or Docket No. 76-03-07RE01 (2021 – 2025) as the basis for any earnings sharing.1 The Company did not earn above the authorized 9.25% at the end of any calendar year between 2018 and 2025. Please refer to Exhibit 1(C)(1) of Attachments 1a through 5a for each actual ROE for the period 2018 through 2022. Please refer to Exhibit 1(C)(1a) of Attachments 6 through 8 for each actual ROE for the period 2023 through 2025. Please refer to Exhibit 1(C)(1) of Attachments 1b through 5b for each illustrative ROE for 2018 through 2022 utilizing the Company’s authorized equity ratio from Docket No. 17-10-46. The Company began reporting an illustrative ROE utilizing the Company’s authorized equity ratio from Docket No. 17-10-46, beginning with its year-end 2023 results. Please refer to Exhibit 1(C)(1b) of Attachments 6 through 8 for each illustrative ROE for 2023 through 2025 utilizing the Company’s authorized equity ratio from Docket No. 17-10-46. A table summarizing the results is presented below: Year Earned ROE w/ Actual Illustrative ROE Using Reference Capital Structure Authorized Capital Structure 2018 2019 2020 2021 2022 2023 2024 2025 8.98% 8.70% 9.03% 9.09% 8.33% 7.35% 6.13% 6.51% ii 9.00% 8.85% 9.26% 9.26% 8.60% 7.57% 6.23% 6.57% Attachments 1a and 1b Attachments 2a and 2b Attachments 3a and 3b Attachments 4a and 4b Attachments 5a and 5b Attachment 6 Attachment 7 Attachment 8 ALLCO-142 Question: (Credit metrics and rating thresholds.) (a) State the Company’s current long-term issuer and first mortgage bond ratings from Moody’s, S&P, and Fitch, the date of each rating action since January 1, 2020, and the outlook. (b) For each calendar year 2020 through 2025 and the Test Year, state the Company’s CFO pre-WC/debt, FFO/debt, debt-tocapitalization, and cash-flow-to-interest ratios as calculated by each rating agency (or, if the Company does not have the agency calculation, as calculated by the Company using the agency’s published methodology), and produce the calculation. (c) Identify the ratio ranges or thresholds that each rating agency has published or communicated to the Company as consistent with the Company’s current rating and with the next rating category below it, and produce each rating-agency report, credit opinion, or communication since January 1, 2023 that states such thresholds for the Company or Eversource Energy. (d) State the share of the Company’s cash flow from operations in the Test Year that consists of net income, and the share that consists of depreciation, amortization, deferred income taxes, and other noncash items. (e) Compute the Company’s CFO pre-WC/debt and FFO/debt ratios for the Rate Year at authorized returns on common equity of 10.25%, 9.25%, 8.5%, 7.5%, and 6.5%, holding all other inputs at the Company’s proposed levels, and state for each the rating category the Company contends would result and the basis for that contention. ALLCO-142 Response:
  2. Page 12 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-156 Page 8 of 12 (a) Please refer to ALLCO-142, Attachment 1, for CL&P’s ratings and outlook from S&P Global Ratings since January 1, 2020. Please refer to ALLCO-142, Attachment 2, for CL&P’s ratings and outlook from Moody’s Ratings since January 1, 2020. Please refer to ALLCO-142, Attachment 3, for CL&P’s ratings and outlook from Fitch Ratings since January 1, 2020. (b) Please refer to ALLCO-142, Attachment 4, for the metrics requested. (c) Please refer to ALLCO-142, Attachment 5, for reports from S&P Global Ratings on CL&P since January 1, 2023. As discussed on page 2 of 109, in ALLCO-142, Attachment 5, S&P expects “CL&P’s stand-alone FFO to debt will average 20%-22% over the forecast period”. Please refer to ALLCO-142, Attachment 6, for reports from Moody’s Ratings on CL&P since January 1, 2023. As discussed on page 3 of 73, in ALLCO-142 Attachment 6, “CL&P's stable outlook reflects our expectation that the utility will maintain a ratio of CFO pre-WC to debt of at least 17% over the next 12-18 months. At the same time, the stable outlook reflects the company’s ongoing effort to rebuild its relationship with key stakeholders including regulators, state leaders and customers and the potential that storm costs could be recovered through pending regulatory proceedings or securitization” and “CL&P could be downgraded if Connecticut regulatory decisions continue to be contentious or unsupportive of credit quality or if CL&P's financial performance deteriorates such that its ratio of CFO pre-WC to debt falls below 17% on a sustained basis”. Please refer to ALLCO-142, Attachment 7, for reports from Fitch Ratings on CL&P since January 1, 2023. As discussed on page 2 of 19 in ALLCO-142, Attachment 7, “Through 2027, Fitch forecast CL&P’s FFO leverage to average about 4.0x.”. Additionally on page 2 of 19 in ALLCO-142 Attachment 7, factors that could, individually or collectively, lead to a downgrade include “FFO leverage exceeds 4.3x on a sustained basis” and “An adverse implementation of the recent regulatory changes that reduces the stability and predictability of earnings and cash flow and materially weakens CL&P's financial profile”. (d) Please refer to exhibit CLP-REVREQ-2-H-1.2A for the Company’s 2025 Form 10K. Per the Company’s reported statement of cash flows: Net Income: $551,329k Non-Cash Items: $964,867k Change In Current Assets & Liabilities: $158,970k Cash from Operations: $1,675,166k “Non-Cash Items” includes Depreciation, Amortization, Deferred Income Taxes, and Other Non-Cash items, as requested. Note that Test Year Amortization expense includes recovery of substantial under-recovered prior-period costs that built up as the direct result of artificially low RAM rates established over multiple years beginning in 2022. As a result, Test Year Amortization expense may not be indicative of future amortizations, to the extent that reconciling rate adjustments maintain closer alignment with current costs better than they have in the past.
  3. Page 13 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-156 Page 9 of 12 (e) The requested computations would produce unreliable and misleading information regarding the Company's credit ratings because the computations would require broad speculation as to how independent rating agencies will evaluate hypothetical outcomes under circumstances that do not exist. In particular, the request presumes that credit ratings can be determined solely by recalculating CFO preWC/debt and FFO/debt under a series of assumed ROEs and then assigned a corresponding rating category on that basis. Rating agencies do not evaluate utility credit quality in this manner. Moody's expressly states in its methodology that a "scorecard-indicated outcome is not expected to match the actual rating for each company" and further recognizes that there are "various reasons why scorecard-indicated outcomes may not map closely to actual ratings." Thus, Moody's itself cautions against the precise type of exercise requested here, which is the use of a limited set of quantitative measures to infer a specific rating outcome. More fundamentally, Moody's does not evaluate utility credit quality through financial metrics alone. Moody's identifies the regulatory framework as "a key determinant of the credit quality of a utility" and recognizes that utilities can experience financial stress because of "a breakdown or obstacle in the regulatory framework." Consistent with that view, Moody's methodology focuses on the regulatory environment, the consistency and predictability of regulation, the utility's ability to recover its costs and earn returns, and the sufficiency and timeliness of cost recovery. As Moody's explains, the critical issue is whether rates are sufficient to allow the utility to recover its costs and earn a reasonable return, not whether a particular authorized ROE can be associated with a particular financial ratio. These facts were proven by the experience of Aquarion Company of Connecticut (“Aquarion”) during and after its general rate case, Docket No. 22-07-01, which is particularly instructive on this point because it involved the precise type of exercise requested here. In that docket, PURA purported to evaluate projected credit metrics under multiple ROE and capital structure scenarios, ultimately concluding that "[Aquarion’s] credit metrics remain in acceptable ranges set by the credit rating agencies" and that "an ROE set within the ranges presented by EOE, OCC, and [Aquarion] (i.e., 7.765% to 10.35%) would not adversely affect [Aquarion’s A3] credit rating." PURA then relied upon that conclusion in establishing the authorized ROE, opining that "[a] key determinant in setting an ROE is whether the ROE will allow the utility to maintain its current financial condition and credit rating." In its rationale, PURA asserted that it had conducted a "rigorous analysis" of the effect of various ROE levels on the company's credit rating. In that instance, PURA evaluated alternative ROE scenarios, compared projected metrics against ratingagency benchmarks, concluded that the approved ROE would not adversely affect Aquarion's credit rating, and relied upon that conclusion in setting rates. That exercise involved the same basic premise underlying this interrogatory, which is that projected credit metrics and rating-agency thresholds can be used to predict the credit implications of alternative ROE outcomes. This proposition is invalid. Despite PURA’s conclusions that Aquarion’s A3 credit rating would not be adversely impacted by the decision in Docket No. 22-07-01, approximately one year later, Moody's downgraded Aquarion Water Company of Connecticut from A3 to Baa1 and specifically attributed the downgrade to the consequences of the rate order. Moody's stated: The downgrade of Aquarion Water Company of Connecticut reflects a weakening financial profile resulting from the utility's rate order last year, which included a reduced revenue requirement as well as lower returns. The rate order was another indication that the
  4. Page 14 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-156 Page 10 of 12 Connecticut regulatory environment has become more challenging and less credit supportive for the state's regulated utilities.” Moody's further explained that Aquarion's lower rating reflected a Connecticut regulatory environment that had become less consistent and predictable, as evidenced by recent regulatory decisions affecting Connecticut utilities.7 Notably, the factors Moody's cited as driving the downgrade extended beyond the projected financial metrics on which PURA’s analysis principally relied. The requested computations suffer from the same fundamental flaw. The request assumes that all relevant rating considerations remain unchanged except for the effect of a lower ROE on two financial ratios. In reality, rating agencies do not assess utility credit quality that way. A lower ROE is not merely an input to a ratio calculation. Depending on the circumstances, the ROE may affect a rating agency's assessment of the utility's ability to earn its return, recover its costs, attract capital, maintain cash flow, and operate within a constructive regulatory framework. From a credit perspective, the relevant question is not what ROE appears in a rate order, but whether the utility can actually recover its costs, earn its authorized return, generate sufficient cash flow, and maintain access to capital. Those outcomes depend on numerous features of the regulatory framework and cannot be inferred from the authorized ROE alone. Accordingly, the Company cannot reasonably assign hypothetical rating categories to the requested ROE scenarios. More importantly, the Aquarion outcome demonstrates that doing so would not provide a reliable indication of how the rating agencies would actually evaluate the Company's credit quality. The requested exercise would therefore create an appearance of precision that is unsupported by the methodology used by the rating agencies in practice and is contradicted by the directly analogous Connecticut experience. iii ALLCO-051 Question: With respect to capital structure and expected earnings: (a) state the Company’s actual common equity ratio, per books, at the end of the Test Year and as of the most recent quarter, and reconcile any difference from the requested 53.86%; (b) state the amount of long-term debt outstanding at Eversource Energy (the parent) as of the end of the Test Year and state whether any proceeds of parent debt have been invested as common equity in CL&P, quantifying the amounts (i.e., the extent of double leverage); and (c) quantify the expected return on equity to shareholders under the proposed earnings sharing mechanism — 50/50 sharing above the authorized return with no downside adjustment — assuming the requested 10.25% authorized return, producing the distribution or scenario analysis used, and state whether the Company performed any analysis of the asymmetric value of that mechanism; if not, explain why an asymmetric mechanism does not require a lower authorized return. ALLCO-051 Response: a. In recent years, the Company has had to fund significant deferred balances relating to catastrophic storm restoration costs and the Company’s Revenue Adjustment Mechanism (“RAM”) reconciling rates, including the 2024 Non-bypassable Federally Mandated Congestion Charges (“NBFMCC”). As discussed in response to data request OCC-522i, including the attachment provided therein, the Company’s capital resources are limited. With no foreseeable recovery of the costs in the near term, the Company had to support the growing deferral balance using its limited capital resources, although the deferral offered no operating cash flow with which the Company could service additional debt. To mitigate the financial risk that would otherwise result (from additional debt), the Company took steps to preserve its credit ratings, including maintaining a higher percentage of equity in its capital structure. Consequently, the Company’s common equity ratio, per books, was considerably higher than the equity ratio in prior years. Once the artificially low RAM rates were
  5. Page 15 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-156 Page 11 of 12 corrected and the corresponding deferred balances were reduced, the need to maintain a higher equity capitalization ratio was lessened. Specifically, the Company’s common equity ratio on a 5-quarter average basis was 54.56% as of December 31, 2025, and 55.26% as of June 30, 2026. The Company anticipates issuing $1.45 billion of First Mortgage Bonds over the two-year period July 1, 2026 through June 30, 2028, to fund ongoing operations as well as upcoming maturities of $500 million. Additionally, the Company expects to retain approximately $400 million of earned equity over the same timeframe. As shown in the table below, the Company has reflected an equity ratio of 53.86% in the rate year in this proceeding, incorporating assumptions of timely recovery of past and future storm costs, among other proposals in this proceeding. Please refer to Table 1, below, as well as the Company’s filed Exhibit CLP-REVREQ-2, Schedules D-1.0, WP-D-1.1, and D-5.0. ALLCO-051 Table 1 ($ Millions) End-of-Period Balance June 30, June 30, 2027 2028 $ $ $ 5,109.2 5,751.7 6,053.8 6,769.5 6,812.8 7,171.5 117.0 117.0 117.0 June 30, 2026 Long-term Debt * Common Equity Preferred Stock Total Capital 2-Year Change $ 944.5 402.0 0.0 $ $ $ $ 11,995.7 12,681.5 13,342.3 1,346.5 Common Equity Percentage of Total Capital Average June 30, 2028 $ 5,873.0 6,992.1 117.0 $ 13,011.9 53.86% * Rate Year average balance is calculated on a 5-quarter average basis b. Eversource Energy is a public holding company that holds regulated electric, gas and water affiliates as well as unregulated affiliates. It is simply not possible to associate individual sources of funds, whether at the utility or holding company, with the uses of funds at the operating company level, nor is the business managed in that manner. The management of cash into and out of the Company is a daily undertaking that ultimately includes the passage of billions of dollars out of the Company, to suppliers and employees, as well as into the Company from various sources, including customers. Although the Parent company raises necessary capital through specific sources available, the uses are not connected to any specific source of funds. Those sources of funds include equity issuances, retained earnings, the use of treasury shares for such programs as dividend reinvestment and 401k match, long-term debt issuances, and, temporarily, short-term debt. These sources of funds as well as the eventual uses vary significantly year to year. Moreover, the Company’s credit ratings, such as those issued by Moody’s, are determined at the subsidiary level based on the riskiness of its assets, specifically, as well as the degree of financial risk resulting from the Company’s issuances of First Mortgage Bonds. Those bonds include protections, ring fencing, and covenants specific to
  6. Page 16 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-156 Page 12 of 12 the Company (i.e not Eversource Energy Parent), and are backed by the Company’s (again, not Eversource Energy Parent’s) assets in the State of Connecticut. c. iv There is no sharing of earnings caused by the setting of base rates with an authorized return incorporated into the approved revenue requirement. Further, the Company does not anticipate that it will over-earn during the term of the PBMRP. ALLCO-158 Question: Follow-up to the Company’s response to Q-ALLCO-019 (recovery of DG dispute obligations through rates). The Company’s response did not answer the final portion of Q-ALLCO-019. State whether the Company proposes, in this proceeding, to recover through rates — whether in base rates, through any rate adjustment mechanism, or through any deferral or regulatory asset — any judgment, settlement payment, refund, or interest obligation arising from any dispute with a distributed generation or qualifying facility customer, including without limitation any refund or interest obligation to Allco or its affiliates arising from overcharges for interconnection-related costs. If so, identify each such amount, the schedule and line item in which it appears, and the witness sponsoring it. If not, state the accounting treatment the Company proposes for any such judgment, settlement, refund, or interest obligation that becomes payable during the rate plan term, including the account to be charged and whether shareholders or ratepayers would bear the cost. ALLCO-158 Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, as the Company stated in response to ALLCO-019, there are no judgments and/or settlements resulting from lawsuits brought by distributed generation developers, qualifying facilities, or interconnection customers; therefore, the Company is not proposing to recover any such amounts through rates. Please refer to the Company’s response to ALLCO-006 for the accounting treatment of interconnection refunds.
  7. Page 17 of 52Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 1 of 4 Date Filed: October 27, 2026 Witness: Warren R. Boutin, Leanne M. Landry and Jeffrey D. Turano Request from: ALLCO Question: (Follow-up to OCC-676 and ALLCO-059 — customer advances and interconnection deposits.) OCC-676 states that the Company has excluded customer advances from rate base since Docket No. 14-05-06 because “they are refundable and the Company does not have use of these dollars.” ALLCO-059 states that Account 252500 held ($28,277,769) of interconnection customers’ payments at June 30, 2026. (a) State whether the funds recorded in Account 252500 and in any other customer-advance or CIAC-deposit account are held in a segregated or escrow account or are commingled with the Company’s general funds, and identify the account(s) and institution(s). (b) If commingled, state whether those funds are available to and used by the Company for working capital, construction, or any other purpose pending final accounting, and reconcile that use with the statement that the Company “does not have use of these dollars” and with OCC-677, which attributes the increase in customer advances since December 2025 to $14.5 million received from five NB-12 line-extension customers for projects that “are currently in construction.” (c) State whether any interest is paid or credited to interconnection customers on advances held pending final accounting or refund, and the tariff, agreement, or policy provision governing it. (d) State whether customer advances and CIAC deposits are reflected in the Company’s cash working capital or lead-lag analysis in this Application and, if so, where; if not, explain why customer funds held for months or years are excluded from the working-capital determination. (e) Produce the Company’s response to OCC-072 in Docket No. 14-05-06 and identify the page of the Final Decision in that docket on which the Company relies. Response: a. Please refer to the Company’s responses to ALLCO-001 i, ALLCO-002 ii, and ALLCO004 iii. b. Please refer to the Company’s response to subpart (a) and OCC-935 iv. The Company keeps enough cash on hand in order to refund customer advances if/when they come due. For primary extensions and modifications under PURA-approved New Business Policy NB-12 (“NB-12 Policy”), a customer may make the required advance payment to the Company via wire transfer or letter of credit. For advance payments made via wire transfer, per the NB-12 Policy, the Company credits advances to:
  8. Page 18 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 2 of 4 AU 1D CCC 349 In Blank Column 25201 The Company also authorizes refunds, when appropriate, charging to this same account. This advance payment is refunded in full, without interest, when the extensions and modifications are considered by the Company to have been put into full use. c. The PURA-approved Interconnection Guidelines and form of Interconnection Agreement do not authorize the payment of interest on final accountings that result in an Overpayment to be refunded to the interconnecting customer, and the PURA-approved NB-12 Policy states that advances will not accumulate interest. d. Customer advances and CIAC deposits are not reflected within the Company’s cash working capital or lead-lag analysis. e. The relevant language from the Company’s response to OCC-072 in Docket No. 14-05-06 is provided in the Company’s response to OCC-676 v. Monthly balances of customer advances between 2009 and 2014 are not relevant to the instant proceeding. To answer the remainder of the subpart, OCC-072 stated, in relevant part “The Company has not included customer advances in the test year or rate year as they are refundable and the Company does not have use of these dollars.” The Final Decision in Docket No. 14-05-06 did not comment on the treatment of customer advances. Prior Referenced Responses: i ALLCO-001 Question: Identify each FERC account in which the Company records CIAC and other amounts collected from interconnection customers for interconnection studies, upgrades, and overheads, and state the balance in each such account at the end of each year 2018 through 2025 and as of the most recent month available. ALLCO-001 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, the Company records CIAC activity from interconnection customers to FERC Account No. 252500. The table below summarizes the end of year balance in FERC Account No. 252500 from 2018 through June 2026.
  9. Page 19 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 3 of 4 Year December 2018 December 2019 December 2020 December 2021 December 2022 December 2023 December 2024 December 2025 June 2026 ii Balance ($5,569,769) ($5,038,280) ($9,076,090) ($25,399,399) ($11,263,859) ($7,796,182) ($10,334,276) ($23,605,408) ($28,277,769) ALLCO-002 Question: State the total dollar amount of CIAC and interconnection-related payments collected from DER and QF interconnection customers in each year 2018 through 2025, and explain precisely how those amounts are reflected in (a) rate base, (b) the Test Year revenue requirement, and (c) the Rate Year revenue requirement proposed in this docket, identifying the specific schedules and workpapers. ALLCO-002 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, please refer to the Company’s response to ALLCO-001i for CIAC year-end balances from 2018 through 2025. CIAC and interconnection-related payments received by the Company reduce the cost of construction or plant placed in service. CIAC is recognized as an offset to the underlying capital project. CIAC would not be considered a component of rate base until the underlying capital project is placed in service. At that time, the underlying capital project costs in rate base would be wholly offset by CIAC at the time of final project billing and reconciliation. In the Company’s next cost of service update, the rate base and the Rate Year revenue requirement will reflect the CIAC and the underlying capital project cost for projects placed in service. iii ALLCO-004 Question: State whether refund obligations owed by the Company to interconnection customers following final accounting or reconciliation of interconnection projects — including the $257,260.19 in refunds identified in the Company’s December 2024 Final Accounting Reports for the Fisk, Plainfield, Voluntown 1240, and Bilton clusters — are recorded as liabilities on the Company’s books; identify the account(s), the total balance of such unpaid refund obligations at the end of each year 2022 through 2025, and state whether and how such balances are reflected in rate base, cash working capital, or the revenue requirement in this docket. ALLCO-004 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States
  10. Page 20 of 52

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 4 of 4 District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, please refer to the Company’s response to ALLCO-002i for “whether and how such balances are reflected in rate base, cash working capital, or the revenue requirement in this docket.” The Company confirms that when a refund obligation is owed to interconnection customers following final accounting or reconciliation of interconnection projects, the refund obligation is recorded as a liability on the Company’s books until the payment is issued to the interconnection customer. iv OCC-935 Question: Customer Advances. Refer to the response to OCC-270, Attachment 2. a. b. c. Are the balances shown held in a restricted account? Describe in detail where these customer advances are held until offset to plant in service, forfeited or refunded. Identify the portion of the balances shown that are letters of credit and not actual cash deposits. Provide a copy of or link to the NB-12 policy. OCC-935 Response: a. b. c. v Cash received from customers as part of their customer advances on NB-12 projects are held in a general purpose cash account (131.010) for use by the Company. A specific liability account (252.010) tracks the advance received until it is forfeited or refunded based on specific customer agreement milestones. All amounts presented in OCC-270, Attachment 2, are cash balances. Please refer to Exhibit CLP-ADDITIONS-13 for copies of CL&P’s New Business policies. OCC-676 Question: Customer Advances. Refer to the response to OCC-270. Has the Company ever included customer advances as a reduction to rate base? If so, identify the PURA precedent relied on for no longer including these as a reduction to rate base. OCC-676 Response: The Company’s position on not including customer advances as a reduction to rate base has been consistent since at least the 2014 CL&P Rate Case, Docket No. 14-05-06. In that case the Company responded to a similar question: “The Company has not included customer advances in the test year or rate year as they are refundable and the Company does not have use of these dollars,” as stated in the Company’s response to discovery question OCC-072 in Docket No. 14-05-06. In the Final Decision in Docket No. 14-05-06 PURA did not reduce the Company’s rate base for these refundable advances and therefore the Company has treated advances consistent with this PURA precedent.
Words on different pages
Words on different pages

As listed on the current system

Corres. 11/02/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).

This filing on the current system (opens in a new tab)