Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).
Files4
Docket No. 26-05-10 Discovery Compilation November 2 2026.pdf
PDF · 133 KB · 1 pageText searchable
Download Docket No. 26-05-10 Discovery Compilation November 2 2026.pdfRead the text of Docket No. 26-05-10 Discovery Compilation November 2 2026.pdf
ALLCO Set 12_COMBINED.pdf
PDF · 661 KB · 52 pagesText searchable
Download ALLCO Set 12_COMBINED.pdfRead the text of ALLCO Set 12_COMBINED.pdf
PURA Set 9_COMBINED.pdf
PDF · 433 KB · 35 pagesText searchable
Download PURA Set 9_COMBINED.pdfRead the text of PURA Set 9_COMBINED.pdf
PURA Set 10_COMBINED.pdf
PDF · 109 KB · 4 pagesText searchable
Download PURA Set 10_COMBINED.pdfRead the text of PURA Set 10_COMBINED.pdf
Page 16 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-156 Page 12 of 12 the Company (i.e not Eversource Energy Parent), and are backed by the Company’s (again, not Eversource Energy Parent’s) assets in the State of Connecticut. c. iv There is no sharing of earnings caused by the setting of base rates with an authorized return incorporated into the approved revenue requirement. Further, the Company does not anticipate that it will over-earn during the term of the PBMRP. ALLCO-158 Question: Follow-up to the Company’s response to Q-ALLCO-019 (recovery of DG dispute obligations through rates). The Company’s response did not answer the final portion of Q-ALLCO-019. State whether the Company proposes, in this proceeding, to recover through rates — whether in base rates, through any rate adjustment mechanism, or through any deferral or regulatory asset — any judgment, settlement payment, refund, or interest obligation arising from any dispute with a distributed generation or qualifying facility customer, including without limitation any refund or interest obligation to Allco or its affiliates arising from overcharges for interconnection-related costs. If so, identify each such amount, the schedule and line item in which it appears, and the witness sponsoring it. If not, state the accounting treatment the Company proposes for any such judgment, settlement, refund, or interest obligation that becomes payable during the rate plan term, including the account to be charged and whether shareholders or ratepayers would bear the cost. ALLCO-158 Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, as the Company stated in response to ALLCO-019, there are no judgments and/or settlements resulting from lawsuits brought by distributed generation developers, qualifying facilities, or interconnection customers; therefore, the Company is not proposing to recover any such amounts through rates. Please refer to the Company’s response to ALLCO-006 for the accounting treatment of interconnection refunds.Page 17 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 1 of 4 Date Filed: October 27, 2026 Witness: Warren R. Boutin, Leanne M. Landry and Jeffrey D. Turano Request from: ALLCO Question: (Follow-up to OCC-676 and ALLCO-059 — customer advances and interconnection deposits.) OCC-676 states that the Company has excluded customer advances from rate base since Docket No. 14-05-06 because “they are refundable and the Company does not have use of these dollars.” ALLCO-059 states that Account 252500 held ($28,277,769) of interconnection customers’ payments at June 30, 2026. (a) State whether the funds recorded in Account 252500 and in any other customer-advance or CIAC-deposit account are held in a segregated or escrow account or are commingled with the Company’s general funds, and identify the account(s) and institution(s). (b) If commingled, state whether those funds are available to and used by the Company for working capital, construction, or any other purpose pending final accounting, and reconcile that use with the statement that the Company “does not have use of these dollars” and with OCC-677, which attributes the increase in customer advances since December 2025 to $14.5 million received from five NB-12 line-extension customers for projects that “are currently in construction.” (c) State whether any interest is paid or credited to interconnection customers on advances held pending final accounting or refund, and the tariff, agreement, or policy provision governing it. (d) State whether customer advances and CIAC deposits are reflected in the Company’s cash working capital or lead-lag analysis in this Application and, if so, where; if not, explain why customer funds held for months or years are excluded from the working-capital determination. (e) Produce the Company’s response to OCC-072 in Docket No. 14-05-06 and identify the page of the Final Decision in that docket on which the Company relies. Response: a. Please refer to the Company’s responses to ALLCO-001 i, ALLCO-002 ii, and ALLCO004 iii. b. Please refer to the Company’s response to subpart (a) and OCC-935 iv. The Company keeps enough cash on hand in order to refund customer advances if/when they come due. For primary extensions and modifications under PURA-approved New Business Policy NB-12 (“NB-12 Policy”), a customer may make the required advance payment to the Company via wire transfer or letter of credit. For advance payments made via wire transfer, per the NB-12 Policy, the Company credits advances to:Page 18 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 2 of 4 AU 1D CCC 349 In Blank Column 25201 The Company also authorizes refunds, when appropriate, charging to this same account. This advance payment is refunded in full, without interest, when the extensions and modifications are considered by the Company to have been put into full use. c. The PURA-approved Interconnection Guidelines and form of Interconnection Agreement do not authorize the payment of interest on final accountings that result in an Overpayment to be refunded to the interconnecting customer, and the PURA-approved NB-12 Policy states that advances will not accumulate interest. d. Customer advances and CIAC deposits are not reflected within the Company’s cash working capital or lead-lag analysis. e. The relevant language from the Company’s response to OCC-072 in Docket No. 14-05-06 is provided in the Company’s response to OCC-676 v. Monthly balances of customer advances between 2009 and 2014 are not relevant to the instant proceeding. To answer the remainder of the subpart, OCC-072 stated, in relevant part “The Company has not included customer advances in the test year or rate year as they are refundable and the Company does not have use of these dollars.” The Final Decision in Docket No. 14-05-06 did not comment on the treatment of customer advances. Prior Referenced Responses: i ALLCO-001 Question: Identify each FERC account in which the Company records CIAC and other amounts collected from interconnection customers for interconnection studies, upgrades, and overheads, and state the balance in each such account at the end of each year 2018 through 2025 and as of the most recent month available. ALLCO-001 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, the Company records CIAC activity from interconnection customers to FERC Account No. 252500. The table below summarizes the end of year balance in FERC Account No. 252500 from 2018 through June 2026.Page 19 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 3 of 4 Year December 2018 December 2019 December 2020 December 2021 December 2022 December 2023 December 2024 December 2025 June 2026 ii Balance ($5,569,769) ($5,038,280) ($9,076,090) ($25,399,399) ($11,263,859) ($7,796,182) ($10,334,276) ($23,605,408) ($28,277,769) ALLCO-002 Question: State the total dollar amount of CIAC and interconnection-related payments collected from DER and QF interconnection customers in each year 2018 through 2025, and explain precisely how those amounts are reflected in (a) rate base, (b) the Test Year revenue requirement, and (c) the Rate Year revenue requirement proposed in this docket, identifying the specific schedules and workpapers. ALLCO-002 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, please refer to the Company’s response to ALLCO-001i for CIAC year-end balances from 2018 through 2025. CIAC and interconnection-related payments received by the Company reduce the cost of construction or plant placed in service. CIAC is recognized as an offset to the underlying capital project. CIAC would not be considered a component of rate base until the underlying capital project is placed in service. At that time, the underlying capital project costs in rate base would be wholly offset by CIAC at the time of final project billing and reconciliation. In the Company’s next cost of service update, the rate base and the Rate Year revenue requirement will reflect the CIAC and the underlying capital project cost for projects placed in service. iii ALLCO-004 Question: State whether refund obligations owed by the Company to interconnection customers following final accounting or reconciliation of interconnection projects — including the $257,260.19 in refunds identified in the Company’s December 2024 Final Accounting Reports for the Fisk, Plainfield, Voluntown 1240, and Bilton clusters — are recorded as liabilities on the Company’s books; identify the account(s), the total balance of such unpaid refund obligations at the end of each year 2022 through 2025, and state whether and how such balances are reflected in rate base, cash working capital, or the revenue requirement in this docket. ALLCO-004 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United StatesPage 20 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-157 Page 4 of 4 District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, please refer to the Company’s response to ALLCO-002i for “whether and how such balances are reflected in rate base, cash working capital, or the revenue requirement in this docket.” The Company confirms that when a refund obligation is owed to interconnection customers following final accounting or reconciliation of interconnection projects, the refund obligation is recorded as a liability on the Company’s books until the payment is issued to the interconnection customer. iv OCC-935 Question: Customer Advances. Refer to the response to OCC-270, Attachment 2. a. b. c. Are the balances shown held in a restricted account? Describe in detail where these customer advances are held until offset to plant in service, forfeited or refunded. Identify the portion of the balances shown that are letters of credit and not actual cash deposits. Provide a copy of or link to the NB-12 policy. OCC-935 Response: a. b. c. v Cash received from customers as part of their customer advances on NB-12 projects are held in a general purpose cash account (131.010) for use by the Company. A specific liability account (252.010) tracks the advance received until it is forfeited or refunded based on specific customer agreement milestones. All amounts presented in OCC-270, Attachment 2, are cash balances. Please refer to Exhibit CLP-ADDITIONS-13 for copies of CL&P’s New Business policies. OCC-676 Question: Customer Advances. Refer to the response to OCC-270. Has the Company ever included customer advances as a reduction to rate base? If so, identify the PURA precedent relied on for no longer including these as a reduction to rate base. OCC-676 Response: The Company’s position on not including customer advances as a reduction to rate base has been consistent since at least the 2014 CL&P Rate Case, Docket No. 14-05-06. In that case the Company responded to a similar question: “The Company has not included customer advances in the test year or rate year as they are refundable and the Company does not have use of these dollars,” as stated in the Company’s response to discovery question OCC-072 in Docket No. 14-05-06. In the Final Decision in Docket No. 14-05-06 PURA did not reduce the Company’s rate base for these refundable advances and therefore the Company has treated advances consistent with this PURA precedent.Page 21 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-158 Page 1 of 2 Date Filed: October 22, 2026 Witness: Douglas P. Horton, Brendan J. O’Brien, Garrett J. Murray, and Matthew Fallon Request from: ALLCO Question: (Follow-up to ALLCO-048 and ALLCO-051 — affiliate returns and earnings sharing.) ALLCO048, Attachment 1, shows authorized returns of 9.50% on a 50.00% equity ratio for PSNH (DE 24-070, July 25, 2025) and 9.80% on a 53.21% equity ratio for NSTAR Electric (D.P.U. 22-22, November 30, 2022), each with an asymmetric earnings sharing mechanism, and ALLCO-048 states that the Company did not conduct any analysis comparing its business risk to those affiliates. (a) State each respect in which the Company contends that its business or regulatory risk exceeds that of NSTAR Electric and of PSNH, and identify the evidence for each. (b) State the earned return on common equity of NSTAR Electric and of PSNH for each year 2022 through 2025 and the amounts, if any, shared with customers under each affiliate’s earnings sharing mechanism. (c) ALLCO-048 states that in the Company’s experience earnings sharing mechanisms are “implemented in a one-sided manner – to the benefit of customers,” while ALLCO-051(c) states that the Company “does not anticipate that it will over-earn during the term of the PBMRP.” State whether the Company contends that the proposed earnings sharing mechanism has any expected value to customers and, if so, quantify it and produce the analysis; if the Company contends it has none, state why it is proposed. (d) State whether Ms. Bulkley or any other ROE Witness was asked to consider, or did consider, the authorized returns of the Company’s affiliates in forming her recommendation, and produce any workpaper or correspondence in which the affiliates’ returns are discussed. Response: a. The Company did not perform an analysis comparing its business or regulatory risk to that of PSNH or NSTAR Electric. Accordingly, the Company does not contend that its business or regulatory risk exceeds that of PSNH or NSTAR Electric in any specific respect based on an analysis performed in this proceeding. The Company’s recommended ROE is based on the analyses presented in its pre-filed testimony and supporting workpapers, which evaluated the Company’s required return on a stand-alone basis. Additionally, authorized returns on equity established in individual regulatory proceedings, while informative datapoints, should not be viewed as objective measures of the return required by investors. Authorized ROEs reflect the evidentiary records, issues presented, regulatory frameworks, and outcomes specific to those proceedings.Page 22 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-158 Page 2 of 2 b. Please refer to the table for both NSTAR Electric and PSNH for 2022 through 2025. Neither regulated entity earned returns that have triggered the earning sharing mechanism. c. By design, PBR plans are multi-year plans during which the utility waives its right to file a full distribution rate case in order to increase rates. As a result, earnings sharing mechanisms (ESM) are a common feature of PBR to provide a guardrail in the event that rates become misaligned with costs over the course of the plan for reasons not anticipated at the inception of the multi-year plan. As a symmetrical guardrail, ESMs serve to protect both the utility and its customers during the course of the plan in the event that rates are set too high or too low (protecting the customer from any potential over-earning and protecting the utility from earning below an established threshold without the ability to file a rate case, given its commitment to waive such right as part of the PBR framework). The Company has developed its proposed PBMRP in an effort to establish a regulatory framework that provides revenue support over the course of the PBR plan that aligns with the Company’s costs over the same period, including the cost of equity capital. The Company’s Proposed PBMRP is not designed to result in a scenario where the Company earns above its authorized ROE, thus triggering the ESM. In fact, the Company’s analysis demonstrates that the PBMRP, if approved as proposed with no modification, the Company would earn below the authorized ROE. 1 In this way, the benefit to customers of an ESM that is triggered only in cases where the company over-earns, is that it ensures that the PBR plan will not inadvertently establish rates that are ‘too high’ during the course of the PBR plan, by operation of the ESM in that event. The ESM allows for a ‘sharing’ of any over earnings, as a means to retain the overarching incentive properties of PBR as well as the other administrative benefits of PBR as a framework. d. No. Ms. Bulkley did not rely on the authorized returns of PSNH or NSTAR Electric in developing her ROE recommendation in this proceeding, nor was she asked to do so by the Company. Consequently, no such workpapers or correspondence exist. The analysis presented in EOE-156, Attachment 1, relied upon the currently authorized ROE of 9.25% and capital structure of 53% equity for illustrative purposes. As shown in EOE-156, Attachment 1, projected earned returns fall below the authorized return in each year, showing a steady decline over the course of the plan. 1Page 23 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-159 Page 1 of 2 Date Filed: October 27, 2026 Witness: Warren R. Boutin and Andrew C. Belden Request from: ALLCO Question: (Follow-up to ICC-013 and ICC-016 — application-to-agreement timing by category.) ICC013, Attachment 1, reports the business days from application receipt to issuance of an Interconnection Agreement for all applications (78,740 since January 2020; mean 17.7 business days), and ICC-016 reports agreement-to-Permission-to-Operate timing separately for four categories. (a) Provide the ICC-013 schedule (projects, mean, and median business days by month) separately for the same four categories used in ICC-016 — residential inverterbased generators of 50 kW or less; Fast Track residential above 50 kW; commercial and industrial of 2 MW or less; and study-process projects above 2 MW — and, for the last two categories, separately for applications that required electric power system modifications or upgrades. (b) For each category, state the number of applications received since January 1, 2020, for which no Interconnection Agreement has been issued as of the date of the response, the number of those that the Company has tendered but not countersigned, and the mean and maximum elapsed business days for each group. (c) Explain why ICC-013, Attachment 1, reports a monthly median that exceeds the monthly mean in numerous months (e.g., January 2020: mean 5.98, median 22.5), identify any negative or zero durations in the underlying data and their cause, and state whether the “Mean” and “Average” columns are computed differently. Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, the Company states as follows: a. Please refer to ALLCO-159, Attachment 1, through ALLCO-159, Attachment 4, for the requested information. a. ALLCO-159, Attachment 1 – Residential Less than 50kW i. Please note, in ALLCO-159, Attachment 1. The median business day column shows 0 or 1 or 2 days for some months. These numbers are correctPage 24 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-159 Page 2 of 2 as the applications were processed on the same day or within one or two days from receipt. b. ALLCO-159, Attachment 2 – Fast track Greater than 50kW c. ALLCO-159, Attachment 3 – Less than 2MW d. ALLCO-159, Attachment 4 – Greater than 2MW b. Please refer to the Company’s response to ALLCO-017 i. c. The mean and the median are derived differently. The mean is the average of the total days divided by the number of projects. Whereas the median is the middle number when the numbers are arranged from smallest to largest, or the average of the two middle numbers if it is an even number. The “Mean” and “Average” were requested by the intervenor, which are the same. Thus, the Average column repeats the information in the Mean column. Prior Referenced Response: i ALLCO-017 Question: State the average and maximum elapsed time, in each year 2019 through 2025, between the Company’s receipt of an interconnection agreement executed by a Connecticut generator and the Company’s countersignature and return of that agreement, and identify each instance exceeding 180 days, including project LEG-22708. ALLCO-017 Response: CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, the Company does not track information on the average and maximum elapsed time between the receipt of a partially-executed interconnection agreement (“IA”) from a Generator and the Company’s countersignature and return of the fully-executed IA to the Generator. Starting in early 2026, the IA execution process was enhanced to leverage automation available in PowerClerk; therefore, the execution dates are now recorded electronically in a software platform.Page 25 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-160 Page 1 of 3 Date Filed: October 22, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: ALLCO Question: (Follow-up to ALLCO-076, ALLCO-077, and ALLCO-028 — outside counsel matters in the revenue requirement.) ALLCO-076, Attachment 1 reports outside counsel expense charged to the Company of $3,834,493 (2021), $2,287,868 (2022), $4,257,622 (2023), $2,678,448 (2024), and $5,185,192 (2025), and a Rate Year amount of $5,121,457, and lists, among others, Day Pitney LLP (“Regulatory / Litigation,” direct charge: $79,724 in 2023, $204,831 in 2024, $164,213 in 2025, $174,796 in the Rate Year), Cowdery Murphy & Healy LLC (“Regulatory / Litigation,” direct charge: $147,160 in 2024, $511,973 in 2025, $544,967 in the Rate Year), and Keegan Werlin LLP (“Regulatory Matters,” direct charge: $1,210,144 in 2025, $1,288,132 in the Rate Year). ALLCO-077 states that the Rate Year legal costs “include litigation or other proceedings in which the Company is a plaintiff or defendant” and that the Company “does not track legal costs that would allow the Company to identify the portion of costs that relate to litigation or other proceedings and then separate that portion by specific matters.” (a) For each of Day Pitney LLP, Cowdery Murphy & Healy LLC, and Keegan Werlin LLP, and for each year 2023 through 2025 and the Rate Year, identify each matter (by Legal Tracker Matter # and Eversource Matter Name, or, if privilege is asserted as to a name, by category and forum) to which the amounts in ALLCO076, Attachment 1 were charged, and the amount charged to each matter. (b) State whether any portion of the amounts in subpart (a) was incurred in connection with (i) Allco Finance Limited or any of its affiliates, including the matters settled in Docket No. 16-03-08RE01, the February 2025 settlement filed in Docket No. 25-03-12, the Company’s disqualification of SCEF Year 7 bids, the retention of SCEF Year 6 bid deposits, or the interconnection, LREC/ZREC, or power purchase agreements of Allco’s affiliates; (ii) Windham Solar LLC or any affiliate; (iii) any other interconnection, net-metering, SCEF, or renewable-energy-contract dispute with a customer or developer; or (iv) any proceeding in which the Company defended the prudence or lawfulness of its own conduct — and state the amount for each. (c) State the basis on which the Company contends that the Rate Year amount of $5,121,457 is a reasonable and prudent level of outside counsel expense to be recovered from ratepayers when, by its own account in ALLCO-077, it cannot identify what portion of that amount was incurred to litigate against its own customers or to defend its own conduct, and identify every adjustment the Company made to remove such costs from the Rate Year, with the amount and workpaper reference, or state that no adjustment was made. (d) State whether any fee or disbursement of Day Pitney LLP incurred in Allco Finance Limited Inc. v. The Connecticut Light and Power Company, et al., No. 3:26-cv-01277 (D. Conn.), or in the Rule 11 and related correspondence preceding it, has been or will be charged to the Company, recorded above the line, included in any deferral, or sought in this or any future rate proceeding, and identify the account(s) used. (e) Produce the Legal Tracker matter list and budget-
As listed on the current system
Corres. 11/02/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).