Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).
Files4
Docket No. 26-05-10 Discovery Compilation November 2 2026.pdf
PDF · 133 KB · 1 pageText searchable
Download Docket No. 26-05-10 Discovery Compilation November 2 2026.pdfRead the text of Docket No. 26-05-10 Discovery Compilation November 2 2026.pdf
ALLCO Set 12_COMBINED.pdf
PDF · 661 KB · 52 pagesText searchable
Download ALLCO Set 12_COMBINED.pdfRead the text of ALLCO Set 12_COMBINED.pdf
PURA Set 9_COMBINED.pdf
PDF · 433 KB · 35 pagesText searchable
Download PURA Set 9_COMBINED.pdfRead the text of PURA Set 9_COMBINED.pdf
PURA Set 10_COMBINED.pdf
PDF · 109 KB · 4 pagesText searchable
Download PURA Set 10_COMBINED.pdfRead the text of PURA Set 10_COMBINED.pdf
Page 26 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-160 Page 2 of 3 versus-actual report for each matter identified in subpart (a) in native format. Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. CL&P further objects to this request on the ground that it is not within the scope of the proceeding to review the Company’s application to amend its existing rates schedules because the interrogatory either seeks information specific to Allco projects or seeks information that Allco views as relevant to its specific projects. (a) Only the costs incurred in 2025 are at issue in this proceeding. Costs included in the Rate Year are escalated by the rate of inflation from the test year. Day Pitney LLP assists the Company in three areas – routine business and litigation matters, regulatory matters and appellate work. Cowdery Murphy & Healy LLC assists the Company with regulatory and appellate work, and Keegan Werlin LLP assists the Company with specialized regulatory work. (b) The Company objects to this request on the ground that it is not within the scope of the proceeding to review the Company’s application to amend its existing rates schedules because the interrogatory either seeks information specific to Allco projects or seeks information that Allco views as relevant to its specific projects. (c) The Company intends to address the prudence of costs as a legal matter. In addition, the question posed in ALLCO-077 asked for a breakdown of “the proceedings in which the Company defends the prudence or lawfulness of its own conduct…,” which are false categories of legal work. The Company does not “litigate against its own customers,” nor does it incur legal costs to impermissibly, improperly or inappropriately “defend its own conduct” and the Company is able to state categorically that there are zero legal costs incurred for these stated purposes. In preparing its rate filing, the Company reviewed all of its legal costs to determine that the costs were reasonable, necessary, efficiently incurred and expected to be routinely occurring, primarily due to the need to meet increased regulatory requirements, as well as other compliance matters. The legal costs were incurred in the course of operating as a public service company in the State of Connecticut and to provide safe and reliable service to customers as a company that is rateregulated by PURA. All of the Company’s legal costs included in the revenue requirement fall within this category.Page 27 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-160 Page 3 of 3 (d) The Company objects to this request on the ground that it is not within the scope of the proceeding to review the Company’s application to amend its existing rates schedules because the interrogatory either seeks information specific to Allco projects or seeks information that Allco views as relevant to its specific projects.Page 28 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-161 Page 1 of 5 Date Filed: October 27, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: ALLCO Question: (Follow-up to ALLCO-078 and ALLCO-034 — rate-proceeding costs outside Exhibit CLPREVREQ-9.) ALLCO-078 states that the $3.1 million of rate case expense in Exhibit CLPREVREQ-9 consists solely of external vendor charges; that the Company “does not incur incremental payroll, labor or benefits costs when preparing, filing or adjudicating a rate case” because the work is performed by permanent employees of the Connecticut revenue requirements group, the Connecticut rates group, and the internal legal department; that internal rate-case work is “exclusively contained in fiscal year 2026”; and that, applying the OCC-332 payroll methodology, “there are no payroll, labor or benefit costs pertaining to the rate case in the proposed revenue requirement.” The response did not identify the positions, amounts, or accounts the interrogatory asked for. (a) Identify by title each position in the Connecticut revenue requirements group, the Connecticut rates group, the internal legal department, and any other Company or ESC group whose incumbent has recorded or is expected to record time on this proceeding in 2026, and state for each the Test Year Pro Forma and Rate Year salary, incentive compensation, and benefits included in the revenue requirement (Exhibit CLP-REVREQ-2, WP C-3.5 and related), and the percentage of 2026 working time the Company estimates each will devote to this proceeding. (b) Confirm that the Rate Year payroll, incentive compensation, and benefits of the positions identified in subpart (a) are included in the proposed revenue requirement without any adjustment to exclude time devoted to this or any other rate proceeding; if the Company contends an adjustment was made, identify it by amount and workpaper. (c) State whether the Company contends that Conn. Gen. Stat. § 16-243p(b) permits recovery through rates of the salaries, incentive compensation, and benefits of employees for the time they devote to attendance in, participation in, or preparation for a rate proceeding, and state the basis for that contention. (d) Identify every cost associated with any rate proceeding initiated on or after January 1, 2024 — including Docket Nos. 26-05-10, 24-12-01, 25-01-03, and 26-01-03, any RAM, storm-cost, or reconciliation proceeding, and any appeal — that is recorded in Test Year or Rate Year O&M, A&G, service-company charges, regulatory assets, or deferrals, stating the amount, account, and schedule or workpaper for each, and the total. (e) Produce the Company’s 2026 time records, project codes, or other records (or state that none exist) showing employee time charged to this proceeding, and identify the project or workorder code(s), if any, under which such time is recorded.Page 29 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-161 Page 2 of 5 (f) State whether the principle stated in ALLCO-078 — that the Company “does not incur incremental payroll, labor or benefits costs” when work is performed by permanent employees whose salaries are in the payroll base — applies to the time of permanent Company and ESC employees, and to the pooled supervisory, engineering, administrative, fleet, stores, and other overhead costs, that the Company charges to interconnecting customers through percentage loaders on interconnection work orders; if the Company contends it does not, explain why the same cost is not incremental when recovered from ratepayers but is incremental when recovered from an interconnecting customer, and identify every document on which that contention rests. Response: (a), (c), and (e). Please refer to the Company’s response to RRU-070 i. (b) The Company confirms no adjustment has been made to exclude labor related to this proceeding. Please refer to the Company’s responses to ALLCO-078 ii and RRU-070 for additional information regarding the internal labor specific to this proceeding. (d) Please refer to the Company’s responses to OCC-438 iii and RRU-070. (f) The Company disagrees with the characterization of subpart f in this question. There are no incremental labor costs in either scenario represented in this question. Prior Referenced Responses: i RRU-070 Question (RATE PROCEEDING SALARIES) Application, Sch. C-3.5; Interrog. Resp. OCC-199; Public Act 23-102, Sec. 2. Regarding employee salaries associated with attendance in, participation in, preparation for, or appeal of a rate proceeding: a. b. c. d. Provide the total charges to work order CT260N11 and to each other work order, cost center or account used to record labor associated with this proceeding. Show by month, by employee classification, and by hours and dollars. State whether any portion of those amounts is included in the payroll expense in Schedule C-3.5 for the Test Year or Rate Year. Identify the line on which it appears and the amount. Identify the EESCO services listed in Attachment 1 of the response to Interrogatory EOE-066 under the captions Legal and Regulation that relate to regulatory proceedings and appeals. State the amount charged to CL&P in the Test Year and Rate Year and the amount removed as non-recoverable. State the EESCO labor charged to work order PURAAN11 identified in Attachment 1 of the response to Interrogatory OCC-355 as established for employees supporting the Connecticut Management Audit in each calendar year from 2021 through 2025. State whether any portion of the charge is included in Schedule C-Page 30 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-161 Page 3 of 5 3.5 or Schedule C-3.11 while management audit cost is treated as a deferred expense in Exhibit CLPREVREQ-11. RRU-070 Response: a. Please refer to RRU-070, Attachment 1, for the total internal labor charges to work order CT260N11 by month, employee classification, hours and dollars. b. As outlined within Exhibit CLP-REVREQ-9, all rate case expenses requested for recovery in the Rate Year are from external vendors/contractors. There are no internal payroll, labor or benefits costs included within the $3.1 million rate case expense outlined in Exhibit CLP-REVREQ-9. Please note that the Company does not incur incremental payroll, labor or benefits costs when preparing, filing or adjudicating a rate case. All internal labor associated with this proceeding is staffed with current employees that work for the Company on a permanent basis, which means that there is no additional internal cost caused by the rate case. The Company’s departments handling the rate case are the Connecticut revenue requirements group; the Connecticut rates group; and the internal legal department. The Test Year for this case is fiscal year ending December 31, 2025, and the internal work on the rate case is exclusively contained in fiscal year 2026, and the Company has confirmed that there is less than $10,000 recorded in 2025 in relation to the rate case. Please refer to the Company’s response to OCC-332 for a detailed explanation as to how the Company calculates its Test Year pro-forma and Rate Year payroll expense. Applying the Company’s calculation of payroll expense, there are no payroll, labor or benefit costs pertaining to the rate case in the proposed revenue requirement. c. All of the costs identified in RRU-070, Attachment 1, are direct charged from the Service Company and represent non-incremental charges (see response part b.). The Company does not track the Service Company costs recorded to work order CT260N11 based on each category identified in EOE-066, Attachment 1. d. Please see Table 1 below for the total EESCO internal labor charges to work order PURAAN11 for each of the years 2021 through 2025. There are no internal payroll, labor or benefits costs included within the $901,194 expense outlined in Exhibit CLP-REVREQ-11. As shown in Exhibit CLP-REVREQ-11, the only Management Audit costs deferred and sought for recovery in this case are incremental costs billed to the Company by PURA for professional services provided by FTI Consulting, Inc. Consistent with the Company’s response to part b. above, the Company does not incur incremental payroll, labor or benefits costs when participating in a PURA Management Audit. All internal labor associated with that work effort is staffed with current employees that work for the Company on a permanent basis, which means that there is no additional internal cost caused by the Management Audit. Year 2021 2022 2023 2024 2025 Total Table 1 EESCO Labor Charged to PURAAN11 Calendar Years 2021 – 2025 Amount $20,446 $72,075 $107,932 $1,069 $236 $201,800Page 31 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-161 Page 4 of 5 ii ALLCO-078 Question (Follow-up to ALLCO-030.) The response cross-referenced OCC-438, which contains no itemization. Itemize the approximately $3.1 million of rate case expense in Exhibit CLP-REVREQ-9 by vendor or firm, matter or workstream, and amount; identify each Company or ESC position (by title) whose Test Year or Rate Year payroll, incentive compensation, or benefits include time associated with attendance in, participation in, or preparation for rate proceedings, and the amounts included; state whether any rate-proceeding-associated costs are recorded outside Exhibit CLP-REVREQ-9 — including in payroll, A&G, service-company charges, or any deferral — and identify the amounts and locations; and state the total of all costs associated with rate proceedings initiated on or after January 1, 2024 that are included anywhere in the proposed revenue requirement. ALLCO-078 Response: The rate case expense in Exhibit CLP-REVREQ-9 in the amount of $3.1 million is itemized by vendor and Exhibit CLP-REVREQ-2, WP C-3.36, at page 10, shows the annual amortized rate case expense proposed in the revenue requirement. Additionally, please refer to ALLCO-027, Attachment 9, for a summary of billed rate-case expenses by vendor through June 30, 2026. As outlined within Exhibit CLP-REVREQ-9, all rate case expenses requested for recovery are from external vendors/contractors. There are no internal payroll, labor or benefits costs included within the $3.1 million rate case expense outlined in Exhibit CLP-REVREQ-9. Please note that the Company does not incur incremental payroll, labor or benefits costs when preparing, filing or adjudicating a rate case. All internal labor associated with this proceeding is staffed with current employees that work for the Company on a permanent basis, which means that there is no additional internal cost caused by the rate case. The Company’s departments handling the rate case is the Connecticut revenue requirements Group; the Connecticut rates group; and the internal legal department. The Test Year for this case is fiscal year ending December 31, 2025, and the internal work on the rate case is exclusively contained in fiscal year 2026, and the Company has confirmed that there is less than $10,000 recorded in 2025 in relation to the rate case. Please refer to the Company’s response to OCC-332i for a detailed explanation as to how the Company calculates its Test Year pro-forma and Rate Year payroll expense. Applying the Company’s calculation of payroll expense, there are no payroll, labor or benefit costs pertaining to the rate case in the proposed revenue requirement. iii OCC-438 Question: Exhibit CLP-REVREQ-1 Please explain why the Company has not excluded costs associated with its participation in rate case proceedings from the revenue deficiency calculation in this proceeding. In your response, please explain how the Company's proposed treatment of such costs complies with the requirements of SB 7, An Act Strengthening Protections For Connecticut's Consumers Of Energy, concerning recovery of costs associated with participation in rate case proceedings. OCC-438 Response: The Company has not removed costs associated with the preparation and participation in this rate case proceeding from the revenue deficiency calculation as these costs are necessary operating costs ensuring that rates are set at a just and reasonable level to enable the ongoing investment into the system to maintain a safe and reliable electric system, benefiting customers. As such, these costs are appropriately recovered from customers and are therefore included in the Company’s proposed revenue deficiency. In this regard, the Company plans to provide legal argument on the plainPage 32 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-161 Page 5 of 5 language of the statute at the appropriate juncture in this proceeding. In the meantime, the Company plans to submit to the record the documentary support necessary to support recovery of the costs. The Company justifies its recovery for costs associated with the preparation and participation in this rate amendment proceeding as prudently incurred and normal operating costs to litigate this rate amendment application. The Company is entitled to a reasonable opportunity, but not a guarantee, to recover its operating costs and maintain its credit integrity. Further, the Company should be allowed to demonstrate that the costs incurred to adjudicate this rate case proceeding are just and reasonable and affording PURA the opportunity to set equitable rates and establish innovative rate mechanisms and programs for the benefit of our customers.Page 33 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-162 Page 1 of 3 Date Filed: October 27, 2026 Witness: Warren R. Boutin, Leanne M. Landry and Jeffrey D. Turano Request from: ALLCO Question: (Exhibit CLP-Additions-6 Supplemental — distributed-generation interconnection projects.) The redacted project documentation filed on October 1, 2026 as Exhibit CLP-Additions-6 Supplemental includes CS & Closing Reports and Project Approval Forms for the following projects, each of which the documentation describes as a distributed-generation interconnection or identifies by the name of a solar developer: CD01162, CD01163, CD01242, CD01244, CD01412, CD01470, CD01594, CD01682, CD01705, CD01776, CD01938, CD02028, CD02124, CD02136, CD02239, CD02244, and CD02247. The Project Approval Form for CD02239 (Verogy, Upper Road, Stafford Springs) states a Total Capital Request of $414.7K “(100% Reimbursable),” “Less Total Customer Contribution” of $414.7K and “Project Costs (Net of Reimbursement)” of $0.0, while the CS & Closing Report for the same project reports Project Actuals of $299,031 direct, $317,847 indirect and $616,877 total with no customer contribution shown. For each project listed above: (a) state the amount paid or payable by the interconnecting customer for the work, the date(s) of payment, and the account(s) in which each payment was recorded; (b) state the gross cost of the project (direct, indirect and AFUDC), the amount of the customer contribution credited against that cost, and the net amount, if any, recorded in plant in service and included in the plant additions supporting the proposed revenue requirement, with the schedule and line reference; (c) state whether any part of the Indirect/Overheads amount shown in the CS & Closing Report was recovered from the customer and, if so, how much; (d) for each project whose CS & Closing Report shows no customer contribution in the “Other” cost element, explain where the customer’s payment was recorded and why it does not appear in the closing report; and (e) state whether any project listed above, or any other project in Exhibit CLP-Additions-6 or CLP-Additions-6 Supplemental, was funded in whole or in part by an interconnecting customer and nonetheless included at its gross cost in the plant additions supporting the Application, and identify each such project and amount. Response: Please refer to Exhibit CLP-Additions-6 and the additional supplemental filings for additional information regarding project costs (direct and indirect) and associated contributions applied to the projects. Additionally, please refer to ALLCO-148 i where the Company responds to the specific timing and accounting associated with contributions. ALLCO-148 states: Plant constructed for interconnection projects is recorded in FERC accounts 106 and 101 at its gross cost when placed in service. CIAC begins in FERC account 252.500 as a credit. Every DER interconnection project is different and the interconnection process is typically characterized byPage 34 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-162 Page 2 of 3 numerous milestones over the course of construction, subject to reconciliation as the final step. The majority of customers are responsible for 100% of the project costs, customer payments may or may not align with the milestones and are often contested by the customer causing delay and requiring substantial coordination to bring to closure. Therefore, depending on the particular circumstances of the specific project, the Company generally will apply customer payments as components of the project go into service, and may not apply some or all of the payments until the final reconciliation is complete to assure correct alignment. Prior Referenced Response: i ALLCO-148 Question: (Follow-up to ALLCO-064(c), and ALLCO-059 — rate base treatment of customer-funded plant.) The response to ALLCO-064(c), states that interconnection capital expenditures “are entirely billed to the interconnection customer and reimbursed through the CIAC process; therefore, these asset additions are not included in rate base,” and that “there is no basis in the plant accounting records.” The response to ALLCO-059, states that CIAC is “an offset to the underlying capital project,” that the offset is applied “at the time of final project billing and reconciliation,” and that the underlying capital project “would not be considered a component of rate base until the underlying capital project is placed in service.” (a) Reconcile the two responses: state whether plant constructed for an interconnection customer is recorded in Accounts 106 and 101 at its gross cost when placed in service, with the CIAC recorded as a credit in Account 252500 (or elsewhere) until reconciliation, or whether the plant is never recorded at gross cost; identify the accounting policy and the journal entries for one Allco Cluster project from work-order opening to reconciliation. (b) State whether the “not included in rate base” statement in ALLCO-064(c), applies to the period between in-service and final reconciliation, and if so identify the schedule in this Application in which the corresponding CIAC or customer-advance balance is deducted from rate base. (c) State the amount of plant in service at December 31, 2025 that was funded in whole or part by interconnection-customer payments not yet reconciled, and the revenuerequirement effect of its inclusion in, or exclusion from, rate base. (d) Identify the witness whose testimony in this proceeding sponsors the treatment described in ALLCO-064(c). ALLCO-148 Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. CL&P further objects to this request on the ground that it is not within the scope of the proceeding to review the Company’s application to amend its existing rates schedules because the interrogatory either seeks information specific to Allco projects or seeks information that Allco views as relevant to its specific projects. Without waiving said objections, the Company responds as follows: a) Plant constructed for interconnection projects is recorded in FERC accounts 106 and 101 at its gross cost when placed in service. CIAC begins in FERC account 252.500 as a credit. Every DER interconnection project is different and the interconnection process is typically characterized by numerous milestones over the course of construction, subject to reconciliation as the final step. The majority of customers arePage 35 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-162 Page 3 of 3 responsible for 100% of the project costs, customer payments may or may not align with the milestones and are often contested by the customer causing delay and requiring substantial coordination to bring to closure. Therefore, depending on the particular circumstances of the specific project, the Company generally will apply customer payments as components of the project go into service, and may not apply some or all of the payments until the final reconciliation is complete to assure correct alignment. b) Responses associated with the Company’s response to ALLCO-059, subpart (f) addresses capital additions put in service more generically. The statement “not included in rate base” in ALLCO-064ii, subpart (c) applies to those interconnection projects that have completed their Final Reconciliation. c) Please refer to Exhibit CLP-ADDITIONS-4, for actual capital expenditures and in-service capital addition projects since 2017. d) Please refer to the witnesses listed in the Company’s response to ALLCO-064.
As listed on the current system
Corres. 11/02/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).