Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).
Files4
Docket No. 26-05-10 Discovery Compilation November 2 2026.pdf
PDF · 133 KB · 1 pageText searchable
Download Docket No. 26-05-10 Discovery Compilation November 2 2026.pdfRead the text of Docket No. 26-05-10 Discovery Compilation November 2 2026.pdf
ALLCO Set 12_COMBINED.pdf
PDF · 661 KB · 52 pagesText searchable
Download ALLCO Set 12_COMBINED.pdfRead the text of ALLCO Set 12_COMBINED.pdf
PURA Set 9_COMBINED.pdf
PDF · 433 KB · 35 pagesText searchable
Download PURA Set 9_COMBINED.pdfRead the text of PURA Set 9_COMBINED.pdf
PURA Set 10_COMBINED.pdf
PDF · 109 KB · 4 pagesText searchable
Download PURA Set 10_COMBINED.pdfRead the text of PURA Set 10_COMBINED.pdf
Page 32 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-161 Page 5 of 5 language of the statute at the appropriate juncture in this proceeding. In the meantime, the Company plans to submit to the record the documentary support necessary to support recovery of the costs. The Company justifies its recovery for costs associated with the preparation and participation in this rate amendment proceeding as prudently incurred and normal operating costs to litigate this rate amendment application. The Company is entitled to a reasonable opportunity, but not a guarantee, to recover its operating costs and maintain its credit integrity. Further, the Company should be allowed to demonstrate that the costs incurred to adjudicate this rate case proceeding are just and reasonable and affording PURA the opportunity to set equitable rates and establish innovative rate mechanisms and programs for the benefit of our customers.Page 33 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-162 Page 1 of 3 Date Filed: October 27, 2026 Witness: Warren R. Boutin, Leanne M. Landry and Jeffrey D. Turano Request from: ALLCO Question: (Exhibit CLP-Additions-6 Supplemental — distributed-generation interconnection projects.) The redacted project documentation filed on October 1, 2026 as Exhibit CLP-Additions-6 Supplemental includes CS & Closing Reports and Project Approval Forms for the following projects, each of which the documentation describes as a distributed-generation interconnection or identifies by the name of a solar developer: CD01162, CD01163, CD01242, CD01244, CD01412, CD01470, CD01594, CD01682, CD01705, CD01776, CD01938, CD02028, CD02124, CD02136, CD02239, CD02244, and CD02247. The Project Approval Form for CD02239 (Verogy, Upper Road, Stafford Springs) states a Total Capital Request of $414.7K “(100% Reimbursable),” “Less Total Customer Contribution” of $414.7K and “Project Costs (Net of Reimbursement)” of $0.0, while the CS & Closing Report for the same project reports Project Actuals of $299,031 direct, $317,847 indirect and $616,877 total with no customer contribution shown. For each project listed above: (a) state the amount paid or payable by the interconnecting customer for the work, the date(s) of payment, and the account(s) in which each payment was recorded; (b) state the gross cost of the project (direct, indirect and AFUDC), the amount of the customer contribution credited against that cost, and the net amount, if any, recorded in plant in service and included in the plant additions supporting the proposed revenue requirement, with the schedule and line reference; (c) state whether any part of the Indirect/Overheads amount shown in the CS & Closing Report was recovered from the customer and, if so, how much; (d) for each project whose CS & Closing Report shows no customer contribution in the “Other” cost element, explain where the customer’s payment was recorded and why it does not appear in the closing report; and (e) state whether any project listed above, or any other project in Exhibit CLP-Additions-6 or CLP-Additions-6 Supplemental, was funded in whole or in part by an interconnecting customer and nonetheless included at its gross cost in the plant additions supporting the Application, and identify each such project and amount. Response: Please refer to Exhibit CLP-Additions-6 and the additional supplemental filings for additional information regarding project costs (direct and indirect) and associated contributions applied to the projects. Additionally, please refer to ALLCO-148 i where the Company responds to the specific timing and accounting associated with contributions. ALLCO-148 states: Plant constructed for interconnection projects is recorded in FERC accounts 106 and 101 at its gross cost when placed in service. CIAC begins in FERC account 252.500 as a credit. Every DER interconnection project is different and the interconnection process is typically characterized byPage 34 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-162 Page 2 of 3 numerous milestones over the course of construction, subject to reconciliation as the final step. The majority of customers are responsible for 100% of the project costs, customer payments may or may not align with the milestones and are often contested by the customer causing delay and requiring substantial coordination to bring to closure. Therefore, depending on the particular circumstances of the specific project, the Company generally will apply customer payments as components of the project go into service, and may not apply some or all of the payments until the final reconciliation is complete to assure correct alignment. Prior Referenced Response: i ALLCO-148 Question: (Follow-up to ALLCO-064(c), and ALLCO-059 — rate base treatment of customer-funded plant.) The response to ALLCO-064(c), states that interconnection capital expenditures “are entirely billed to the interconnection customer and reimbursed through the CIAC process; therefore, these asset additions are not included in rate base,” and that “there is no basis in the plant accounting records.” The response to ALLCO-059, states that CIAC is “an offset to the underlying capital project,” that the offset is applied “at the time of final project billing and reconciliation,” and that the underlying capital project “would not be considered a component of rate base until the underlying capital project is placed in service.” (a) Reconcile the two responses: state whether plant constructed for an interconnection customer is recorded in Accounts 106 and 101 at its gross cost when placed in service, with the CIAC recorded as a credit in Account 252500 (or elsewhere) until reconciliation, or whether the plant is never recorded at gross cost; identify the accounting policy and the journal entries for one Allco Cluster project from work-order opening to reconciliation. (b) State whether the “not included in rate base” statement in ALLCO-064(c), applies to the period between in-service and final reconciliation, and if so identify the schedule in this Application in which the corresponding CIAC or customer-advance balance is deducted from rate base. (c) State the amount of plant in service at December 31, 2025 that was funded in whole or part by interconnection-customer payments not yet reconciled, and the revenuerequirement effect of its inclusion in, or exclusion from, rate base. (d) Identify the witness whose testimony in this proceeding sponsors the treatment described in ALLCO-064(c). ALLCO-148 Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. CL&P further objects to this request on the ground that it is not within the scope of the proceeding to review the Company’s application to amend its existing rates schedules because the interrogatory either seeks information specific to Allco projects or seeks information that Allco views as relevant to its specific projects. Without waiving said objections, the Company responds as follows: a) Plant constructed for interconnection projects is recorded in FERC accounts 106 and 101 at its gross cost when placed in service. CIAC begins in FERC account 252.500 as a credit. Every DER interconnection project is different and the interconnection process is typically characterized by numerous milestones over the course of construction, subject to reconciliation as the final step. The majority of customers arePage 35 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-162 Page 3 of 3 responsible for 100% of the project costs, customer payments may or may not align with the milestones and are often contested by the customer causing delay and requiring substantial coordination to bring to closure. Therefore, depending on the particular circumstances of the specific project, the Company generally will apply customer payments as components of the project go into service, and may not apply some or all of the payments until the final reconciliation is complete to assure correct alignment. b) Responses associated with the Company’s response to ALLCO-059, subpart (f) addresses capital additions put in service more generically. The statement “not included in rate base” in ALLCO-064ii, subpart (c) applies to those interconnection projects that have completed their Final Reconciliation. c) Please refer to Exhibit CLP-ADDITIONS-4, for actual capital expenditures and in-service capital addition projects since 2017. d) Please refer to the witnesses listed in the Company’s response to ALLCO-064.Page 36 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-163 Page 1 of 3 Date Filed: October 22, 2026 Witness: Warren R. Boutin, Leanne M. Landry and Jeffrey D. Turano Request from: ALLCO Question: (Exhibit CLP-Additions-6 Supplemental — overhead loading on customer-funded work.) For each project identified in Q-ALLCO-162, and for the 2026 Customer blanket (CSTMER / CDCDANNL), the 2026 Third Party Attachment Make Ready program (495802), CD02458 (New Service Amazon Plainfield) and CD02497 (New Service Uline Plainfield): (a) identify each overhead, loader, or indirect-cost rate applied to the project (by name, rate, and the base to which it was applied) and the Company policy, procedure, or accounting instruction under which it was applied; (b) state the amount of the Indirect/Overheads total in the CS & Closing Report attributable to each rate; (c) state whether the rates in subpart (a) are the same rates applied to the interconnection work orders of Allco’s affiliates for the Fisk, Plainfield, Voluntown and Bilton project clusters, and if not, identify each difference; (d) state whether the salaries and benefits recovered through those rates are also included in the Test Year Pro Forma and Rate Year payroll and benefits in the proposed revenue requirement, and if so, identify the adjustment, if any, that removes amounts capitalized to customer-funded projects, by amount and workpaper; and (e) reconcile subpart (d) with the statement in ALLCO-078 that the Company “does not incur incremental payroll, labor or benefits costs” when work is performed by permanent employees. Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. CL&P further objects to this request on the ground that it is not within the scope of the proceeding to review the Company’s application to amend its existing rates schedules because the interrogatory either seeks information specific to Allco projects or seeks information that Allco views as relevant to its specific projects. Without waiving said objections, please refer to the Company’s response to ALLCO-102 i and ALLCO-102, Attachment 1, for the development of the requested rates. The Company also notes all payroll and overhead-related components are adjusted for capitalization within the cost of service. Please refer to Schedules C-3.5, C-3.6, C-3.11, C-3.12, C-3.25, C-3.35 and C-3.38. Also, please note the Company’s response to ALLCO-078 ii was specific to rate-case expense incurredPage 37 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-163 Page 2 of 3 by internal employees, which is not being discussed here. Given the topics discussed are different, there is no amount to reconcile. Prior Referenced Responses i ALLCO-102 Question: For the percentage overhead loaders applied to interconnection cost estimates, invoices, and contributions in aid of construction (“CIAC”) for distributed-generation and qualifying-facility interconnections at any time from 2017 through the present: (a) identify each person who established, calculated, approved, or revised the loader percentages, and each person or group with authority to approve deviations from them; (b) identify the written policy, procedure, methodology document, or workpaper in which each loader percentage and its derivation is recorded, and produce each; (c) state, for each loader, whether it was developed by CL&P, ESC, Burns & McDonnell Engineering Company, Inc. (“Burns & McDonnell”), or another entity, and identify the entity and organizational unit; and (d) state whether any loader percentage applied to interconnection charges was ever reviewed for consistency with actual incurred costs before December 2024, and if so, identify each review, its date, its author, and its conclusion, and produce it. ALLCO-102 Response: CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery in that lawsuit. Without waiving said objection, the ESC Investment Planning, Corporate Accounting, Plant Accounting and Accounts Payable departments are responsible for creating and maintaining the rates. The Company uses either historical costs or budgeted information to develop its overhead rates. The rates are calculated annually and maintained by the Investment Planning, Corporate Accounting, Plant Accounting and Accounts Payable departments and updated as needed. The overhead charges are calculated by applying the applicable overhead rate to the direct charged cost elements applicable for that overhead (i.e., Labor, Material, Contractors, etc.). Therefore, for a project to be eligible to receive overheads, it must have direct spending. ii ALLCO-078 Question: (Follow-up to ALLCO-030.) The response cross-referenced OCC-438, which contains no itemization. Itemize the approximately $3.1 million of rate case expense in Exhibit CLP-REVREQ-9 by vendor or firm, matter or workstream, and amount; identify each Company or ESC position (by title) whose Test Year or Rate Year payroll, incentive compensation, or benefits include time associated with attendance in, participation in, or preparation for rate proceedings, and the amounts included; state whether any rate-proceeding-associated costs are recorded outside Exhibit CLP-REVREQ-9 — including in payroll, A&G, service-company charges, or any deferral — and identify the amounts and locations; and state the total of all costs associated with rate proceedings initiated on or after January 1, 2024 that are included anywhere in the proposed revenue requirement.Page 38 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-163 Page 3 of 3 ALLCO-078 Response: The rate case expense in Exhibit CLP-REVREQ-9 in the amount of $3.1 million is itemized by vendor and Exhibit CLP-REVREQ-2, WP C-3.36, at page 10, shows the annual amortized rate case expense proposed in the revenue requirement. Additionally, please refer to ALLCO-027, Attachment 9, for a summary of billed rate-case expenses by vendor through June 30, 2026. As outlined within Exhibit CLP-REVREQ-9, all rate case expenses requested for recovery are from external vendors/contractors. There are no internal payroll, labor or benefits costs included within the $3.1 million rate case expense outlined in Exhibit CLP-REVREQ-9. Please note that the Company does not incur incremental payroll, labor or benefits costs when preparing, filing or adjudicating a rate case. All internal labor associated with this proceeding is staffed with current employees that work for the Company on a permanent basis, which means that there is no additional internal cost caused by the rate case. The Company’s departments handling the rate case is the Connecticut revenue requirements Group; the Connecticut rates group; and the internal legal department. The Test Year for this case is fiscal year ending December 31, 2025, and the internal work on the rate case is exclusively contained in fiscal year 2026, and the Company has confirmed that there is less than $10,000 recorded in 2025 in relation to the rate case. Please refer to the Company’s response to OCC-332, for a detailed explanation as to how the Company calculates its Test Year pro-forma and Rate Year payroll expense. Applying the Company’s calculation of payroll expense, there are no payroll, labor or benefit costs pertaining to the rate case in the proposed revenue requirement.Page 39 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-164 Page 1 of 2 Date Filed: October 22, 2026 Witness: Christopher Leigh and Sean P. Noonan Request from: ALLCO Question: (AI Tools in use.) Identify each AI Tool that the Company, ESC, or any affiliate acting for the Company has licensed, deployed, piloted, or used at any time since January 1, 2024, stating for each: (a) the vendor and product; (b) whether it is licensed under enterprise, commercial, or consumer terms, and the date first used; (c) the business functions and departments that use it (including, without limitation, legal, regulatory, rates and revenue requirements, customer service, engineering, distribution planning, grid operations, storm response, procurement, information technology, and human resources); (d) whether Company confidential information, customer information, or CEII is or may be entered into it; (e) the contractual terms governing the vendor’s retention of inputs and outputs, use of inputs to train or improve models, ownership of inputs and outputs, and access by the vendor or any other third party, producing the governing agreement or terms; (f) whether it is hosted on Company premises, in a Company-controlled cloud tenancy, or in the vendor’s environment, and in what country; and (g) the annual cost, the account(s) in which that cost is recorded, and the amount, if any, included in the Test Year, Test Year Pro Forma, and Rate Year cost of service, with the schedule and workpaper reference. Response: Please refer to the Company’s response to CIEC-023 i for a discussion of Eversource’s use of AI system tools. As described in that response, Eversource is exploring the enterprise use of AI on a limited, deliberate basis with appropriate safeguards in place. While that exploration occurs to identify methods for the safe use of AI as a productivity tool, it is imperative to ensure a high level of cybersecurity and protection of customer information remains a paramount objective for the Company. The Company takes its obligations in this regard very seriously and is taking appropriate measures to guard against cyber threats, further harden information systems relied on throughout the organization and ensure continuing vigilance. The Company employs robust security controls, technologies and training strategies to defend against cyberattacks. The Company’s IT Security Policies establish a comprehensive framework to safeguard information assets, ensure operational resilience, and maintain compliance with recognized cybersecurity standards.Page 40 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-164 Page 2 of 2 Prior References Response: CIEC-023 Question: Does Eversource utilize any artificial intelligence (“AI”) system in any part of its electric distribution business? If the answer is in the affirmative, then: a. b. c. specify each AI system utilized; describe the use case(s) for each AI system; and provide the policies, procedures, and protocols that govern the utility’s use of each AI system. For purposes of responding to this question, an AI system is defined as a machine-based system that can, for a given set of human-defined objectives, make predictions, recommendations, or decisions influencing real or virtual environments. Such systems include but are not limited to systems that use machine learning, large language models, natural language processing, and computer vision technologies including generative AI. CIEC-023 Response: a. The Company is unable to provide a comprehensive list of “AI systems” utilized. This is because AI can run under the hood of various applications and software with or without the user’s knowledge or ability to choose or not to use it. Eversource, consistent with other utilities and industries, can use AI in two main ways; first, use AI as a tool for coding and analytics support and second, build or buy software tools and applications that have AI embedded. Regarding the first type of AI use, as a workforce assistance tool, at the time of this response, the Company has enabled business users to use Microsoft Copilot, as an overall personal productivity enhancing tool. Microsoft Copilot is not connected to any Company databases or software systems. As a simple example, a search in a web browser still results in an AI-generated response. Regarding AI-embedded tools, there is a limited number of internally developed tools that run AI, currently utilized at CL&P. For example, the Control Room Call Analytics Dashboard is used by System Operations Management to efficiently flag training opportunities by analyzing calls between operators and field crews. b. Please refer to the Company’s response to subpart (a) above. While the AI-embedded applications have use cases as listed in (a) above, since Microsoft Copilot is widely accepted as a general personal productivity tool, the applications of the tool are broad and user specific and cannot be listed comprehensively. Copilot in its current form is a chat only system and does not have direct integrations into other Company systems. c. The Company has allowed all business users access to Microsoft Copilot. Users need to complete an AI training that defines the business-appropriate uses of this tool. This is a very standard approach, leaning on the cautious side, of all industries and peer utilities around AI. The Company's AI strategy emphasizes cybersecurity, data privacy, oversight, and responsible application of emerging technologies. AI initiatives are evaluated through established corporate governance processes, including appropriate business and technical review.Page 41 of 52
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-12 Date Issued October 08, 2026 ALLCO-165 Page 1 of 1 Date Filed: October 22, 2026 Witness: Christopher Leigh and Sean P. Noonan Request from: ALLCO Question: (AI in the Application and in this proceeding.) State whether any AI Tool was used in the preparation of any part of the Application, its exhibits, workpapers, or testimony; of any response to an interrogatory in this docket; of the redactions applied to any confidential exhibit or attachment, including the redactions to Exhibit CLP-ADDITIONS-6 and CLP-ADDITIONS-6 Supplemental and the “redaction and e-discovery services” billed by TCDI (ALLCO-034, Attachment 1); or of the forecast of the Rate Year revenue requirement. For each such use identify the AI Tool, the task, the department or Contractor that performed it, whether confidential information, customer information, or CEII was entered into the tool, and the cost. Response: No, the Company did not use any type of AI system tool as part of its efforts to develop the Rate Application and no exhibit, workpaper or testimony was generated in that manner. Eversource has only recently begun to deploy AI across the enterprise and within the operating companies and these tools are not yet approved for this purpose.
As listed on the current system
Corres. 11/02/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (ALLCO Set 12, PURA Set 9, PURA Set 10).