Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

Files9

Search terms highlighted
Eversource rate increase is on 89 pages across 5 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
2 pages match

Text of ALLCO Set 18_COMBINED.pdf

Extracted from the file · 25 pages · 65,407 characters

Text of CIEC Set 7_COMBINED.pdf

Extracted from the file · 7 pages · 8,262 characters

48 pages match
  1. Page 105 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-025 Page 2 of 4 Prior Referenced Response: i OCC-599 Question: Refer to Exhibit CLP-TSP-3 at 22–24. a. Provide the data underlying the headroom and constrained-area presentations on pages 22–24. For each substation identified as constrained, provide its normal and emergency rating, five-year historical load and peak load data, available headroom, forecast first year of violation, and proposed project cost. b. For each constrained substation identified, provide the existing analysis of temporary and permanent load transfers. Identify the receiving substation or feeder, available transfer capacity, MW that could be transferred, required enabling work, estimated cost, and reason any transfer was rejected. Please confirm if no transfer analysis was performed. c. Provide a summary of each actual substation capacity violation and stranded-load event experienced from 2016 through the present. Identify the substation, date, maximum loading, applicable rating, duration, contingency, customers at risk, customers interrupted, and whether load transfer prevented or reduced an outage. OCC-599 Response: a. The graphic depicted in CLP-TSP-3, at 22, is derived from headroom data for substations with actual values, time series data, and ratings shown on our public maps using the Eversource CT Grid Connection Navigator. Loads are based on our most recent summer peak year, 2025. Please refer to OCC-599, Attachment 1 CONFIDENTIAL, for project forecast violation year and the 5-year historical peak load data for each respective project. The table contains the LCC rating of each substation which is the planning criteria identified within the DSPG, please refer CLF-SC-023, Attachment 1. The following substations have projects initiated and have obtained at a minimum a conceptual level estimate: Substation West Brookfield 14H Beacon Falls 11N Franklin Drive 1B Southington 4C Berlin 6A_13.8kV Westside 7A Hopewell 22R Estimated Project Cost $16,900,000 $12,632,000 $17,986,000 $9,772,600 $23,199,000 $18,399,000 $17,518,000 All other substations within the attachment have not had a comprehensive evaluation to identify possible solutions and the costs associated with those solutions. The table below depicts a high-level tabletop analysis for possible projected cost of a substation solution. These costs will be refined as these projects progress through the funding process and receive full engineering analysis for solutions and conceptual level estimates.
  2. Page 106 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-025 Page 3 of 4 b. Substations High Level Estimate Project Status Waterside 22M Flax Hill 24A Rocky Hill 12Y $600,000 $500,000 Less than $250,000 Investigating Project Need Investigating Project Need Investigating Project Need – Anticipating Permanent Load Transfer from West Brookfield 14H with settings changes only Triangle 11A Middle River 28M $4,800,000 $500,000 Initial Funding Approved Investigating Project Need Rockville 14W Campville 14R Baldwin 13F Tracy 14M Frybrook 13B Brooklyn 30Y $10,000,000 $52,300,000 $20,250,000 $9,900,000 $20,000,000 Less than $250,000 Initial Funding Approved Partial Funding Initial Funding Submitted Initial Funding Approved Initial Funding Approved Investigating Project Need – Anticipating Permanent Load Transfer from Tracy 14M or Frybrook 13B with settings changes only Prior to initiating a funding project, permanent load transfers are, in many cases, a preferred solution if the conditions at the constrained substation and the adjacent area support this as these are typically substantially lower cost than substation investments and have a much more rapid deployment timeline. Historically these load transfers were not explicitly tracked, and the Company does not possess historical data as it pertains to deferrals by means of permanent load transfer. As of 2024 the Company identified this opportunity to begin having a detailed record of load transfers, partly in response to increasingly constrained regional capacity. The Company is now prepared to track these transfers in the Step Load Tracker as a load transfer on the receiving substation and a negative load transfer to the originally constrained station. This tracker will not only allow the forecasted load transfer to be visible but will also allow for historical reporting of deferred major capital upgrades through completed load transfers. The newly identified projects are in early stages of development and have not yet completed the solution selection process yet. Therefore, these projects would not yet have any tracked load transfers or analyses completed to date. Following initial funding of these projects, all available solutions including permanent load transfers, non-wires solutions, and traditional solutions are identified and evaluated for suitability and for viability. No potential solutions have been rejected at this time from these newly identified projects. Temporary transfers are reserved for substations anticipating overload during a current planned peak event, planned or unplanned outages, or other transient system events. Temporary solutions place the system in an abnormal condition which can impact operations, protections and controls, and automations within the system and are not used as a long-term solution except where necessary to address real-time operational needs that do not have a permanent solution placed into service. c. All substation forecasted violations are mitigated by using pre-contingent load transfers to adjacent substations with remaining capacity. In accordance with planning criteria in the Distribution System Planning Guide (CLFSC-023, Attachment 1), the Company plans and designs its system to avoid overload of major substation assets such as transformers during an N-1 event. During real-time operation, these overload scenarios are avoided
  3. Page 107 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-025 Page 4 of 4 through the use of monitoring technology and planned mitigation measures. However, the Company’s substation planning group recreates a normalized substation load to aid in the process of forecasting for future years.
  4. Page 108 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 1 of 5 Date Filed: October 26, 2026 Witness: David L. Gladey, Lavelle Freeman, John P. Dipaola-Tromba, Jennifer A. Schilling and Elli Ntakou Request from: Department of Energy and Environmental Protection Question: (Integrated Distribution System Plan) Refer to Exhibit CLP-TSP-1, Exhibit CLP-TSP-1, p. 69. Please explain further the Company’s statement that “the Companies have provided their version of the IDSP with reduced scope”. Provide specifics on where the Company’s TSP differs in scope from the Authority’s Version in Docket No. 21-05-15RE03. Response: Based on the question, the Company clarifies the comment referenced in Exhibit CLP-TSP-1, at page 69. The “reduced scope” version of the IDSP referenced here refers to the Company’s response to a proposal issued by PURA on what the IDSP should include, not the TSP submitted in this filing. The Company submitted a proposal for a reduced scope version of the IDSP 1 for PURA to consider in Docket No. 21-05-15RE03, in order to focus on customer affordability and delivering benefits at a lower cost, with the key focus on: 1. A more contained and streamlined stakeholder process; 2. A reduced number of scenarios for the Company to consider and develop as part of planning; and 3. A more limited granularity of system modeling and forecasting. PURA, in its most recent proposed final decision, made certain modifications to the requirements (with the exception of the stakeholder process) that align with the Company’s request ask for two incremental FTEs as part of this filing (please refer to the Company’s response to OCC-835 i). 1 The Company filed this proposal as written exceptions in response to the draft decision for Docket 21-052025. Please see the link to the document: 15RE03 on Aug 28th https://www.dpuc.state.ct.us/dockcurr.nsf/8e6fc37a54110e3e852576190052b64d/6ec4c362aab351ff85258cf400701 215/$FILE/Docket%20No.%2021-05-15RE03%20%20UI%20CLP%20Joint%20Written%20Exceptions%208.28.25.pdf
  5. Page 109 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 2 of 5 In the Company’s response to OCC-566 ii, the Company has provided a more detailed mapping of its TSP content (which is not the IDSP) to the IDSP proposed outline. Prior Referenced Responses: i OCC-835 Question: Payroll. Refer to the response to OCC-333 which states that of the 41 new positions requested, 21 vegetation management, 5 power quality positions and 2 distribution planning and forecasting positions are contingent on PURA’s approval in this case. If they are contingent on PURA’s approval, explain how these positions are necessary. OCC-835 Response: For the 21 vegetation management positions, all but one (1) of these are already included in the current vegetation management operations and are necessary for the accomplishment of the vegetation programs. The Company is proposing a shift from contract to internal resources in this case. As noted in the Company’s response to OCC-333: “The Vegetation Management positions allow the Company the opportunity to improve the system’s reliability and improve cost-efficiency by transitioning more work in-house to restructure vegetation management performance for the benefit of our customers. While the twenty-one (21) Vegetation Management positions appear to be incremental, in reality there is only 1 incremental resource. Of the twenty-one (21), eight (8) of the FTEs are the result of 16 employees who currently split their time 50%/50% between O&M and capital work shifting to solely working on the proposed combined O&M program, if approved, results in the equivalent of 8 incremental employees working on the O&M program; twelve (12) resources would be converted from contracted resources to internal resources of which the Company’s proposed vegetation management expenses in Exhibit CLP-REVREQ-2, Work Paper C-3.31 reflect the reduction in outside contractor services; and one (1) resource would be truly incremental.” The five (5) power quality positions allow the Company to better serve our customers with dedicated resources that can troubleshoot, analyze, and identify power quality problems. Power Quality is typically a deviation from sinusoidal voltage or frequency and encompasses a wide variety effects, ranging from voltage sags and swells, surges, transients, low power factor, harmonics and other phenomena that disrupt service or damage customer and utility equipment. The causes of these issues can be failing equipment, lightning, equipment operation or installation as well as customer loads and DER, identifying the causes and mitigation requires specialized skills, field data and analytics. Currently within the Company there is no dedicated group responsible for resolving customer power quality issues This group will take ownership of these complaints and problems and troubleshoot customer power quality issues by taking actual field measurements at both the Company and customer premises. With field measurement and further engineering analysis, the power quality group will be able to identify the source of power quality concerns which could be at the utility side or at the customer side. Based on the group’s assessment the Company will be able to improve response to customer power quality concerns and improve customer service. The two (2) distribution planning and forecasting positions are designated resources for forecasting and modeling in distribution planning to comply with PURA’s requirements outlined in the IDSP for advanced forecasting, 8760 forecasting, and larger number of scenarios, as well as to manage the stakeholder input, verification, and data sharing efforts associated with the IDSP docket. As stated by the Company in 21-05-15 RE03, compliance with an IDSP as
  6. Page 110 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 3 of 5 outlined by the Authority will require significant additional efforts. Not adding these incremental positions would severely hamper the Company’s ability to: - Meaningfully engage with the stakeholder process, review recommendations, data sets, and provide adequate responses and justifications to stakeholders Limit the ability to develop more than the currently staffed and resourced for single scenario peak load forecast Jeopardize the 8760 model delivery at circuit levels as envisioned by the Authority and Stakeholders Supporting this effort would in turn provide the Company with these abilities, which would provide the Authority and stakeholders with more granular data as envisioned by the IDSP to better understand investment decisions. ii OCC-566 Question: In Exhibit CLP-TSP-1, Page 13, Eversource notes the following: “The purpose of our joint testimony is to present CL&P’s 5-Year Targeted System Performance Plan (the “TSP Plan” or the “Plan”), covering the planning horizon for operations and investment on the Company’s distribution system over the timeframe of January 1, 2027, through December 31, 2031. A summary narrative of CL&P’s State of the System report providing a foundational perspective on the 5-Year Plan is provided herewith as Exhibit CLP-TSP-2. In addition, a detailed presentation of the 5-Year TSP framework is presented as Exhibit CLP-TSP-3.” The proposed decision issued on July 17, 2026, in docket 21-05-15RE03 lists the following content items for inclusion in an IDSP document: a. b. c. d. e. f. g. h. i. j. k. Executive Summary - identifies key points from each section of the document; Planning Policy – discusses relevant state and local goals and policies that inform grid planning; Current State of the System – provides an overview of existing grid conditions including but not limited to capacity, reliability, and DER integration issues; IDSP Methodology – explains the planning methods used to produce the IDSP; Stakeholder Engagement and Social Equity – specifies how stakeholders participate in the IDSP process, as well as social and environmental equity considerations; Load Forecasting – consists of all components of peak load; Grid Needs Assessment – consists of various capacity, reliability, and resiliency analyses substantiating investment needs; Solution Selection Process – provides the criteria and methods used to identify, assess, compare. and select both traditional and non-traditional grid capital investments for implementation; Capital Investment Plan – lists, prioritizes, and describes all planned investments for a ten-year planning horizon; and Long-Term Strategic Plan – provides an overview of strategic plans for the grid beyond a ten-year planning horizon. For each of the content items above, please share what aspects of the submitted TSP Plan represent information that would be included in each of the proposed IDSP sections. Please include exhibit and slide or page numbers for any content that would belong in each of the content sections.
  7. Page 111 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 4 of 5 OCC-566 Response: For the purpose of answering this question, the Company is assuming that the IDSP referenced in the question is as described in PURA’s proposed final decision issued on July 17, 2026, in Docket No. 21-05-15RE03, and as proposed and discussed by the EDCs in Technical Meetings #10 to #12. As designed therein, the IDSP is intended to be a cohesive, strategic plan for ensuring safe, reliable and resilient electric service for all customers while supporting state clean energy and decarbonization goals. Given the scope of the proposed IDSP, with expanded requirements for analytics, stakeholder engagement and review, the EDCs expressed concerns about the timeline, process and specific elements in Written Comments and Technical Sessions. Consequently, the TSP Plan aligns generally with the IDSP content, particularly in terms of the state of the system and investment plans to address current and projected needs, while also reflecting practical differences. More specifically, the TSP aligns with proposed IDSP sections, as follows: a. Executive Summary - identifies key points from each section of the document; Please refer to: Exhibit CLP-TSP-1 Exhibit CLP-TSP-3: Page 3-7 b. Planning Policy – discusses relevant state and local goals and policies that inform grid planning; Please refer to: Exhibit CLP-TSP-2: Page 20-21 c. Current State of the System – provides an overview of existing grid conditions including but not limited to capacity, reliability, and DER integration issues; Please refer to: Exhibit CLP-TSP-2 Exhibit CLP-TSP-3: Page 13-38 d. IDSP Methodology – explains the planning methods used to produce the IDSP; Please refer to: Exhibit CLP-TSP-2: Page 9-20, 24-28 Exhibit CLP-TSP-3: Page 33-34, 83-92, 96-120, 138-139, 141-149 e. Stakeholder Engagement and Social Equity – specifies how stakeholders participate in the IDSP process, as well as social and environmental equity considerations; Please refer to: Exhibit CLP-ELP-1: Page 19, 29 f. Load Forecasting – consists of all components of peak load; Please refer to: Exhibit CLP-TSP-2: Page 20-24 Exhibit CLP-TSP-3: Page 18-20, 91-92, 138 g. Grid Needs Assessment – consists of various capacity, reliability, and resiliency analyses substantiating investment needs; Please refer to: Exhibit CLP-TSP-3: Page 51, 56-81, 93-95, 102-106, 114-120, 142-149
  8. Page 112 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 5 of 5 h. Solution Selection Process – provides the criteria and methods used to identify, assess, compare. and select both traditional and non-traditional grid capital investments for implementation; Please refer to: Exhibit CLP-TSP-3: Page 88-90 i. Capital Investment Plan – lists, prioritizes, and describes all planned investments for a ten-year planning horizon. Please refer to: Exhibit CLP-TSP-1: Page 40-72; Exhibit CLP-TSP-2: Page 46-48; Exhibit CLP-TSP-3: Page 7-12, 45-81, 102-105, 107-149 j. Long-Term Strategic Plan – provides an overview of strategic plans for the grid beyond a ten-year planning horizon. Please refer to: Exhibit CLP-TSP-2: Page 20-21
  9. Page 113 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 1 of 8 Date Filed: October 26, 2026 Witness: John P. DiPaola-Tromba Request from: Department of Energy and Environmental Protection Question: (Substation Transformers) Refer to Exhibit CLP-TSP-1, Exhibit CLP-TSP-1, pp. 55-56. Please explain the Company's rationale for targeting an average age of approximately 35 years when substation transformers typically have a design life of 40 years. Furthermore, please define "design life" and discuss whether there are any actions that can be taken to extend the life of these assets and whether the Company has taken such actions. Response: Based on industry experience, transformers can operate beyond their typical design life of 40 years, although the risk of failure exponentially increases after 70 years of service life, due to paper insulation degradation. OCC-596, Attachment 1 CONFIDENTIAL, provides a CIGRE study from 2024, showing the failure rate of transformers has a noticeable increase starting at 40 years and exponentially increases as the asset exceeds 65 years old. This study reviewed analysis of thousands of transformers including many voltage classes from around the world to build depth into the data available. OCC-596, Attachment 2 CONFIDENTIAL, is an EPRI paper discussing “Large Transformer End-of-Expected Life” that notes “the useful life of a large, oil-filled transformer is between 30 and 40 years with insulation or bus supports being the most likely to fail due to age. For the insulation, thermal aging of the paper insulation is the likely cause of failure.” OCC-596, Attachment 3, is a Department of Energy report from 2024, citing that large power transformers “are typically considered to have a design lifetime on the order of 40 years. In 2014, a DOE report estimated that the average age of LPTs in the North American grid was 38–40 years, indicating that a substantial fraction of those LPTs are at, or over, that design lifetime and that these LPTs will ultimately need to be replaced or refurbished. These industry research groups and others have provided basis within their published studies to support the concerns of failure with any transformer over 40 years in-service. Based on this industry knowledge base, Eversource’s Asset Health philosophy for transformers is to operate transformers to their maximum useful life, but plan to maintain a transformer fleet that does not exceed 70 years of age and maintains an average age of approximately 35 years. The objective is to find the balance between affordability and preventing an aged transformer fleet that approaches the “knee of the curve,” resulting in failure rates that increase significantly. With a large portion of the transformer fleet being between 50 and 80 years old, as these transformers
  10. Page 114 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 2 of 8 continue to approach and exceed 70 years, the rate of failure will increase rapidly. Due to the complexity and time duration of procuring and replacing transformers, a significant increase in failures would result in the inability to maintain reliability by reactively replacing an increased volume of transformer failures. Please refer to the response and attachments to OCC-596 i, for additional information on this topic. In addition, Eversource employs several methods to both actively and passively monitor the health of all power transformers within its service area. Active and continuous monitoring methods include out-of-specification alarming. Remote alarming (if applicable) is conducted through the Eversource SCADA system with alarms existing for bushing monitoring, LTC trouble, dissolved gas, oil level alarms, and oil temperature alarms, among others. Per industry best practices, local alarming is performed through panel indication lamps with corresponding nameplate alarm descriptions and annunciation technologies such as bulb annunciators and Human Machine Interfaces (HMI’s). The preventive maintenance procedures for power transformers are documented within the Eversource Maintenance Program (EMP) 5.58 Station Transformers and Oil-Filled Shunt Reactors. The inspection and maintenance tasks are catalogued into three (3) categories which include a list of asset conditions for real-time condition monitoring, time-based regular inspections, and condition-based maintenance activities. These are described in more detail below: Condition Monitoring: Various parameters related to power transformer health are actively monitored as applicable. The monitoring is performed both locally and remotely with local monitoring performed by individual equipment alarms and station annunciators. Remote monitoring is performed via Supervisory Control and Data Acquisition (SCADA) to enable realtime asset parameter output and SCADA equipment alarms. Such parameters include temperature, oil level, pressure, and load tap changer (LTC) status. Time-Directed Maintenance and Inspections: Eversource has established multiple routine maintenance activities required to be performed for all power transformers within specific time intervals. These activities include monthly visual inspections, annual oil sampling including dissolved gas analysis (DGA), thermographic readings, LTC maintenance, and major maintenance activities. Major maintenance activities include power factor testing, bushing testing, excitation testing, confirmation of proper operation and integrity of pressure relief devices and ensuring all alarms operate properly. Condition-Based Maintenance: These activities are on an as-needed basis when identified upon visual inspection, when performing time-directed maintenance activities, and when output from condition monitoring devices indicate outside normal operating values. Such activities include, but are not limited to, acoustic measurements, core grounding tests, leak repairs, and chassis repair.

Text of NECTA Set 6_COMBINED.pdf

Extracted from the file · 22 pages · 43,545 characters

Text of OCC Set 29_COMBINED.pdf

Extracted from the file · 30 pages · 65,312 characters

Text of PURA Set 8_COMBINED.pdf

Extracted from the file · 230 pages · 511,861 characters

As listed on the current system

Corres. 11/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

This filing on the current system (opens in a new tab)