Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

Files9

Search terms highlighted
Eversource rate increase is on 89 pages across 5 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
2 pages match

Text of ALLCO Set 18_COMBINED.pdf

Extracted from the file · 25 pages · 65,407 characters

Text of CIEC Set 7_COMBINED.pdf

Extracted from the file · 7 pages · 8,262 characters

48 pages match
  1. Page 110 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 3 of 5 outlined by the Authority will require significant additional efforts. Not adding these incremental positions would severely hamper the Company’s ability to: - Meaningfully engage with the stakeholder process, review recommendations, data sets, and provide adequate responses and justifications to stakeholders Limit the ability to develop more than the currently staffed and resourced for single scenario peak load forecast Jeopardize the 8760 model delivery at circuit levels as envisioned by the Authority and Stakeholders Supporting this effort would in turn provide the Company with these abilities, which would provide the Authority and stakeholders with more granular data as envisioned by the IDSP to better understand investment decisions. ii OCC-566 Question: In Exhibit CLP-TSP-1, Page 13, Eversource notes the following: “The purpose of our joint testimony is to present CL&P’s 5-Year Targeted System Performance Plan (the “TSP Plan” or the “Plan”), covering the planning horizon for operations and investment on the Company’s distribution system over the timeframe of January 1, 2027, through December 31, 2031. A summary narrative of CL&P’s State of the System report providing a foundational perspective on the 5-Year Plan is provided herewith as Exhibit CLP-TSP-2. In addition, a detailed presentation of the 5-Year TSP framework is presented as Exhibit CLP-TSP-3.” The proposed decision issued on July 17, 2026, in docket 21-05-15RE03 lists the following content items for inclusion in an IDSP document: a. b. c. d. e. f. g. h. i. j. k. Executive Summary - identifies key points from each section of the document; Planning Policy – discusses relevant state and local goals and policies that inform grid planning; Current State of the System – provides an overview of existing grid conditions including but not limited to capacity, reliability, and DER integration issues; IDSP Methodology – explains the planning methods used to produce the IDSP; Stakeholder Engagement and Social Equity – specifies how stakeholders participate in the IDSP process, as well as social and environmental equity considerations; Load Forecasting – consists of all components of peak load; Grid Needs Assessment – consists of various capacity, reliability, and resiliency analyses substantiating investment needs; Solution Selection Process – provides the criteria and methods used to identify, assess, compare. and select both traditional and non-traditional grid capital investments for implementation; Capital Investment Plan – lists, prioritizes, and describes all planned investments for a ten-year planning horizon; and Long-Term Strategic Plan – provides an overview of strategic plans for the grid beyond a ten-year planning horizon. For each of the content items above, please share what aspects of the submitted TSP Plan represent information that would be included in each of the proposed IDSP sections. Please include exhibit and slide or page numbers for any content that would belong in each of the content sections.
  2. Page 111 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 4 of 5 OCC-566 Response: For the purpose of answering this question, the Company is assuming that the IDSP referenced in the question is as described in PURA’s proposed final decision issued on July 17, 2026, in Docket No. 21-05-15RE03, and as proposed and discussed by the EDCs in Technical Meetings #10 to #12. As designed therein, the IDSP is intended to be a cohesive, strategic plan for ensuring safe, reliable and resilient electric service for all customers while supporting state clean energy and decarbonization goals. Given the scope of the proposed IDSP, with expanded requirements for analytics, stakeholder engagement and review, the EDCs expressed concerns about the timeline, process and specific elements in Written Comments and Technical Sessions. Consequently, the TSP Plan aligns generally with the IDSP content, particularly in terms of the state of the system and investment plans to address current and projected needs, while also reflecting practical differences. More specifically, the TSP aligns with proposed IDSP sections, as follows: a. Executive Summary - identifies key points from each section of the document; Please refer to: Exhibit CLP-TSP-1 Exhibit CLP-TSP-3: Page 3-7 b. Planning Policy – discusses relevant state and local goals and policies that inform grid planning; Please refer to: Exhibit CLP-TSP-2: Page 20-21 c. Current State of the System – provides an overview of existing grid conditions including but not limited to capacity, reliability, and DER integration issues; Please refer to: Exhibit CLP-TSP-2 Exhibit CLP-TSP-3: Page 13-38 d. IDSP Methodology – explains the planning methods used to produce the IDSP; Please refer to: Exhibit CLP-TSP-2: Page 9-20, 24-28 Exhibit CLP-TSP-3: Page 33-34, 83-92, 96-120, 138-139, 141-149 e. Stakeholder Engagement and Social Equity – specifies how stakeholders participate in the IDSP process, as well as social and environmental equity considerations; Please refer to: Exhibit CLP-ELP-1: Page 19, 29 f. Load Forecasting – consists of all components of peak load; Please refer to: Exhibit CLP-TSP-2: Page 20-24 Exhibit CLP-TSP-3: Page 18-20, 91-92, 138 g. Grid Needs Assessment – consists of various capacity, reliability, and resiliency analyses substantiating investment needs; Please refer to: Exhibit CLP-TSP-3: Page 51, 56-81, 93-95, 102-106, 114-120, 142-149
  3. Page 112 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-026 Page 5 of 5 h. Solution Selection Process – provides the criteria and methods used to identify, assess, compare. and select both traditional and non-traditional grid capital investments for implementation; Please refer to: Exhibit CLP-TSP-3: Page 88-90 i. Capital Investment Plan – lists, prioritizes, and describes all planned investments for a ten-year planning horizon. Please refer to: Exhibit CLP-TSP-1: Page 40-72; Exhibit CLP-TSP-2: Page 46-48; Exhibit CLP-TSP-3: Page 7-12, 45-81, 102-105, 107-149 j. Long-Term Strategic Plan – provides an overview of strategic plans for the grid beyond a ten-year planning horizon. Please refer to: Exhibit CLP-TSP-2: Page 20-21
  4. Page 113 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 1 of 8 Date Filed: October 26, 2026 Witness: John P. DiPaola-Tromba Request from: Department of Energy and Environmental Protection Question: (Substation Transformers) Refer to Exhibit CLP-TSP-1, Exhibit CLP-TSP-1, pp. 55-56. Please explain the Company's rationale for targeting an average age of approximately 35 years when substation transformers typically have a design life of 40 years. Furthermore, please define "design life" and discuss whether there are any actions that can be taken to extend the life of these assets and whether the Company has taken such actions. Response: Based on industry experience, transformers can operate beyond their typical design life of 40 years, although the risk of failure exponentially increases after 70 years of service life, due to paper insulation degradation. OCC-596, Attachment 1 CONFIDENTIAL, provides a CIGRE study from 2024, showing the failure rate of transformers has a noticeable increase starting at 40 years and exponentially increases as the asset exceeds 65 years old. This study reviewed analysis of thousands of transformers including many voltage classes from around the world to build depth into the data available. OCC-596, Attachment 2 CONFIDENTIAL, is an EPRI paper discussing “Large Transformer End-of-Expected Life” that notes “the useful life of a large, oil-filled transformer is between 30 and 40 years with insulation or bus supports being the most likely to fail due to age. For the insulation, thermal aging of the paper insulation is the likely cause of failure.” OCC-596, Attachment 3, is a Department of Energy report from 2024, citing that large power transformers “are typically considered to have a design lifetime on the order of 40 years. In 2014, a DOE report estimated that the average age of LPTs in the North American grid was 38–40 years, indicating that a substantial fraction of those LPTs are at, or over, that design lifetime and that these LPTs will ultimately need to be replaced or refurbished. These industry research groups and others have provided basis within their published studies to support the concerns of failure with any transformer over 40 years in-service. Based on this industry knowledge base, Eversource’s Asset Health philosophy for transformers is to operate transformers to their maximum useful life, but plan to maintain a transformer fleet that does not exceed 70 years of age and maintains an average age of approximately 35 years. The objective is to find the balance between affordability and preventing an aged transformer fleet that approaches the “knee of the curve,” resulting in failure rates that increase significantly. With a large portion of the transformer fleet being between 50 and 80 years old, as these transformers
  5. Page 114 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 2 of 8 continue to approach and exceed 70 years, the rate of failure will increase rapidly. Due to the complexity and time duration of procuring and replacing transformers, a significant increase in failures would result in the inability to maintain reliability by reactively replacing an increased volume of transformer failures. Please refer to the response and attachments to OCC-596 i, for additional information on this topic. In addition, Eversource employs several methods to both actively and passively monitor the health of all power transformers within its service area. Active and continuous monitoring methods include out-of-specification alarming. Remote alarming (if applicable) is conducted through the Eversource SCADA system with alarms existing for bushing monitoring, LTC trouble, dissolved gas, oil level alarms, and oil temperature alarms, among others. Per industry best practices, local alarming is performed through panel indication lamps with corresponding nameplate alarm descriptions and annunciation technologies such as bulb annunciators and Human Machine Interfaces (HMI’s). The preventive maintenance procedures for power transformers are documented within the Eversource Maintenance Program (EMP) 5.58 Station Transformers and Oil-Filled Shunt Reactors. The inspection and maintenance tasks are catalogued into three (3) categories which include a list of asset conditions for real-time condition monitoring, time-based regular inspections, and condition-based maintenance activities. These are described in more detail below: Condition Monitoring: Various parameters related to power transformer health are actively monitored as applicable. The monitoring is performed both locally and remotely with local monitoring performed by individual equipment alarms and station annunciators. Remote monitoring is performed via Supervisory Control and Data Acquisition (SCADA) to enable realtime asset parameter output and SCADA equipment alarms. Such parameters include temperature, oil level, pressure, and load tap changer (LTC) status. Time-Directed Maintenance and Inspections: Eversource has established multiple routine maintenance activities required to be performed for all power transformers within specific time intervals. These activities include monthly visual inspections, annual oil sampling including dissolved gas analysis (DGA), thermographic readings, LTC maintenance, and major maintenance activities. Major maintenance activities include power factor testing, bushing testing, excitation testing, confirmation of proper operation and integrity of pressure relief devices and ensuring all alarms operate properly. Condition-Based Maintenance: These activities are on an as-needed basis when identified upon visual inspection, when performing time-directed maintenance activities, and when output from condition monitoring devices indicate outside normal operating values. Such activities include, but are not limited to, acoustic measurements, core grounding tests, leak repairs, and chassis repair.
  6. Page 115 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 3 of 8 Substation Technical Engineering leverages data collected by the CASCADE, PTX Analysis, and substation equipment databases to perform asset condition assessments of power transformers. The reports are based on the following six (6) parameters with recommendations for replacement by the Substation Technical Engineering team being based upon whether two (2) of the six parameters are considered high risk: • Oil Analysis Results o DGA o Fluid Quality Analysis o Furan Analysis on Main Tanks • Age • Loading • Maintenance History • Historical Test Data • Physical Inspection Findings The above practices are applicable to all power transformers. Asset age and condition will prompt enhanced inspection, testing, monitoring, and maintenance as noted in the EMP toward the goal of maximizing the usable life of a transformer. Historically the Company has effectively maximized the life of Transformers by extensive maintenance and monitoring practices, evidenced by the age demographics of the fleet which far exceed the typical design life of 40 years. While this practice continues, the risk profile of an aging fleet compounded by longer lead times and more challenging outage constraints has resulted in a need to initiate planned replacements, beyond the historical average of 1-2 transformer replacements per year, to minimize overall impact of a failed transformer and maximize efficiency. A typical transformer replacement can take from 2 to 5 years to plan and execute. From the time of identification of deteriorating health, the transformer will continue to degrade over the course of the project execution time period. While spares are an effective mitigation plan for emergent failures, it is not a “one-size fits all” long-term mitigation plan to address the fleet risk because depending on when the failure or urgent replacements occur, it may happen at a high-risk period of the year which cannot be controlled exposing the system and customers to a much higher risk. Allowing transformers to run to failure also poses a serious safety risk to both the public and utility
  7. Page 116 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 4 of 8 workers. Additionally, a failed transformer could cause damage to adjacent healthy equipment compounding the negative impact. Prior to initiation of a transformer replacement project, the various subject matter experts (SMEs) will confer and review the nameplate data, maintenance records, and PTX scores of the unit. If a transformer is reviewed and a capital project is not to be initiated, the transformer is typically recommended to have further evaluation for maintenance mitigation of the found issue. This may include repairs or minor refurbishment actions that enable the power transformer to be reenergized and placed back in-service. If the transformer is identified as requiring a capital project an initial funding is established and a project team assembled. The project team includes a team of SMEs and they are required to review the technical and financial feasibility of transformer replacement, transformer refurbishment, load transfer options, and usage of existing spare transformer inventory for a replacement. After the feasible options are developed, the project team will proceed with a formal review of the multiple feasible options within the procedures of the Eversource Solution Design Committee. Please refer to the response and attachments to OCC-597 ii, for additional information on this topic. Prior Referenced Responses: i OCC-596 Question: Refer to Exhibit CLP-TSP-1, at 55, “…plan to maintain a transformer fleet that does not exceed 70 years of age.” Identify every law, regulation, manufacturer requirement, or mandatory engineering standard that requires a substation transformer to be retired at 40 years, 70 years, or any other specified age. If no such requirement exists, please confirm. a. b. Provide all existing studies, analyses, and historical data relied upon by the Company to conclude that transformer failure risk increases rapidly as transformers approach or exceed 70 years of age. If the Company has not performed an empirical analysis using its transformer-failure experience, please justify. Provide the Company data and analyses used to establish the transformer age thresholds or replacement criteria in the TSP, including the stated 40-year useful life and increased failure risk near 70 years. Include the age and cause of failure for each Company transformer that failed during the period covered by the analysis. If the criteria are not based on the Company’s actual failure experience, identify the source on which they are based. OCC-596 Response: There are no laws, regulations, manufacturer requirements, or mandatory engineering standards that require substation transformers to be retired at a specific age. The age of a power transformer is one of the most important factors in assessing asset condition. Although actual service life varies widely depending on the manufacturer’s design, quality of assembly, materials used, operating history, current operating conditions, and maintenance history, the average
  8. Page 117 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 5 of 8 expected life for an individual transformer is approximately 40 years according to industry consortiums, and manufacturers. International reliability surveys (i.e., CIGRE) report major failure rates on the order of ~0.3% per transformer-year across large populations, with failure behavior influenced by aging and asset condition. Industry asset-management guidance supports risk-based decision-making that balances failure risk and cost. Eversource employs several methods to both actively and passively monitor the health of distribution power transformers within its service area. Active and continuous monitoring methods include out of specification alarming. Alarms may include indications for bushing monitoring (if applicable), LTC trouble, dissolved gas (if applicable), oil level alarms, and oil temperature alarms, among others. This information along with periodic maintenance and testing reports provide data into Eversource’s condition‑based asset management methodology that draws on multiple sources including: • Transformer nameplate characteristics • Oil quality and DGA trends • Abnormal thermal, electrical, or core indicators derived from PTX health modeling • Maintenance and inspection records • Power Factor Testing Eversource utilizes a detailed asset health score generated through the Electric Power Research Institute (EPRI) PTX tool to assess power transformer asset health. OCC-596, Attachment 4 CONFIDENTIAL, is a technical guide to the EPRI Power Transformer Expert System (PTX). The PTX tool evaluates normal degradation, abnormal operating conditions, oil quality, and age to produce two critical indicators: the Long-Term Health Index (LTI) and the ShortTerm Health Index (STI). The PTX health index is measured in the range of 0 to 1, with 0 meaning healthy and 1 needing immediate replacement. A value greater than 0.5 is considered poor health, such that if repair/replacement is not performed the transformer will continue to decline leading to equipment failure. Eversource has 27 transformers in CT, or about 8.6% of the fleet, that fall within the range considered to be in poor condition. This means that without repair or replacement, their condition is expected to continue declining, increasing the risk of equipment failure. As a result, Eversource continues to prioritize and initiate replacement projects for these transformers. Attachments included note that multiple industry sources discuss aging and failure rates of substation power transformers. • OCC-596, Attachment 1 CONFIDENTIAL, A2 Cigre Brochure 939 AC Transformer Reliability • OCC-596, Attachment 2 CONFIDENTIAL, 1013566 Plant Support Engineering Large Transformer End of Expected Life Considerations and the Need for Planning • OCC-596, Attachment 3, EXEC-2022-001242 - Large Power Transformer Resilience Report 7-10-24 • OCC-596, Attachment 4 CONFIDENTIAL, 3002026877_Power Transformer Expert System (PTX) Software Application Guide_ Introduction to PTX, Overview, Technical Basis and Application Information Based on industry experience, while transformers can operate beyond their typical design life of 40 years, the risk of failure exponentially increases after 70 years of service life, due to paper insulation degradation. OCC-596, Attachment 1 CONFIDENTIAL, a CIGRE study from 2024, shows the failure rate of transformers has a noticeable increase starting at 40 years and exponentially increases as the asset exceeds 65 years old. This study reviewed analysis of thousands of transformers including many voltage classes from around the world to build depth into the data available. OCC-596, Attachment 2 CONFIDENTIAL is an EPRI paper discussing “Large Transformer End-ofExpected Life” which notes “the useful life of a large, oil-filled transformer is between 30 and 40 years with insulation
  9. Page 118 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 6 of 8 or bus supports being the most likely to fail due to age. For the insulation, thermal aging of the paper insulation is the likely cause of failure.” OCC-596, Attachment 3, is a Department of Energy report from 2024, citing that large power transformers “are typically considered to have a design lifetime on the order of 40 years. In 2014, a DOE report estimated that the average age of LPTs in the North American grid was 38–40 years, indicating that a substantial fraction of those LPTs are at or over that design lifetime. These LPTs will ultimately need to be replaced or refurbished.” These industry research groups and others have provided basis within their published studies to support the concerns of failure with any transformer over 40 years in-service. As a result, Eversource’s Asset Health philosophy for transformers is to operate transformers to their maximum useful life, but plan to maintain a transformer fleet that does not exceed 70 years of age and an average age of approximately 35 years. The objective is to find the balance between affordability and preventing an aged transformer fleet that approaches the “knee of the curve” which results in failure rates that increase significantly. With a large portion of the transformer fleet being between 50 and 80 years old, as these transformers continue to approach and exceed 70 years, the rate of failure will increase rapidly. Due to the complexity and time duration of procuring and replacing transformers, a significant increase in failures would result in the inability to maintain reliability by reactively replacing an increased volume of transformer failures. The six most recent failures of transformers in CT were all attributed to internal failures of the transformer. The ages of the failed transformers were 32, 50, 52, 52, 56, and 83 years old at the time of the failure. ii OCC-597 Question: Refer to Exhibit CLP-TSP-1, at 55. For each proposed proactive replacement, identify whether the Company evaluated continued operation through enhanced inspection, testing, monitoring, maintenance, refurbishment, loading limits, load transfer, or use of a spare transformer. Provide each existing analysis and state whether it found that replacement could be deferred by one, three, or five years. If no deferral or life-extension or alternate analysis was performed, please confirm the reason. OCC-597 Response: Eversource employs several methods to both actively and passively monitor the health of all power transformers within its service area. Active and continuous monitoring methods include out-of-specification alarming. Remote alarming (if applicable) is conducted through the Eversource SCADA system with alarms existing for bushing monitoring, LTC trouble, dissolved gas, oil level alarms, and oil temperature alarms, among others. Per industry best practices, local alarming is performed through panel indication lamps with corresponding nameplate alarm descriptions and annunciation technologies such as bulb annunciators and Human Machine Interfaces (HMI’s). The preventive maintenance procedures for power transformers are documented within the Eversource Maintenance Program (EMP) 5.58 Station Transformers and Oil-Filled Shunt Reactors. The inspection and maintenance tasks are catalogued into three (3) categories which include a list of asset conditions for real-time condition monitoring, timebased regular inspections, and condition-based maintenance activities. These are described in more detail below: Condition Monitoring: Various parameters related to power transformer health are actively monitored as applicable. The monitoring is performed both locally and remotely with local monitoring performed by individual equipment alarms and station annunciators. Remote monitoring is performed via Supervisory Control and Data Acquisition (SCADA) to enable real-time asset parameter output and SCADA equipment alarms. Such parameters include temperature, oil level, pressure, and load tap changer (LTC) status.
  10. Page 119 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-027 Page 7 of 8 Time-Directed Maintenance and Inspections: Eversource has established multiple routine maintenance activities required to be performed for all power transformers within specific time intervals. These activities include monthly visual inspections, annual oil sampling including dissolved gas analysis (DGA), thermographic readings, LTC maintenance, and major maintenance activities. Major maintenance activities include power factor testing, bushing testing, excitation testing, confirmation of proper operation and integrity of pressure relief devices and ensuring all alarms operate properly. Condition-Based Maintenance: These activities are on an as-needed basis when identified upon visual inspection, when performing time-directed maintenance activities, and when output from condition monitoring devices indicate outside normal operating values. Such activities include, but are not limited to, acoustic measurements, core grounding tests, leak repairs, and chassis repair. Substation Technical Engineering leverages data collected by the CASCADE, PTX Analysis, and substation equipment databases to perform asset condition assessments of power transformers. The reports are based on the following six (6) parameters with recommendations for replacement by the Substation Technical Engineering team being based upon whether two (2) of the following (6) parameters are considered high risk: • Oil Analysis Results o DGA o Fluid Quality Analysis o Furan Analysis on Main Tanks • Age • Loading • Maintenance History • Historical Test Data • Physical Inspection Findings The above practices are applicable to all power transformers. Asset age and condition will prompt enhanced inspection, testing, monitoring, and maintenance as noted in the EMP toward the goal of maximizing the usable life of a transformer. Historically the Company has effectively maximized the life of Transformers by extensive maintenance and monitoring practices, evidenced by the age demographics of the fleet which far exceed the typical design life of 40 years. While this practice continues, the risk profile of an aging fleet compounded by longer lead times and more challenging outage constraints has resulted in a need to initiate planned replacements, beyond the historical average of 1-2 transformer replacements per year, to minimize overall impact of a failed transformer and maximize efficiency. A typical transformer replacement can take from 2 to 5 years to plan and execute. From the time of identification of deteriorating health, the transformer will continue to degrade over the course of the project execution time period. While spares are an effective mitigation plan for emergent failures, it is not a “one-size fits all” long-term mitigation plan to address the fleet risk because depending on when the failure or urgent replacements occur, it may happen at a high-risk period of the year which cannot be controlled exposing the system and customers to a much higher risk. Allowing transformers to run to failure also poses a serious safety risk to both the public and utility workers. Additionally a failed transformer could cause damage to adjacent healthy equipment compounding the negative impact. Prior to initiation of a transformer replacement project, the various subject matter experts (SMEs) will confer and review the nameplate data, maintenance records, and PTX scores of the unit. If a transformer is reviewed and a capital project is not to be initiated, the transformer is typically recommended to have further evaluation for maintenance

Text of NECTA Set 6_COMBINED.pdf

Extracted from the file · 22 pages · 43,545 characters

Text of OCC Set 29_COMBINED.pdf

Extracted from the file · 30 pages · 65,312 characters

Text of PURA Set 8_COMBINED.pdf

Extracted from the file · 230 pages · 511,861 characters

As listed on the current system

Corres. 11/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

This filing on the current system (opens in a new tab)