Utility Dockets and Filings

Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

Files9

Search terms highlighted
Eversource rate increase is on 89 pages across 5 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
2 pages match

Text of ALLCO Set 18_COMBINED.pdf

Extracted from the file · 25 pages · 65,407 characters

Text of CIEC Set 7_COMBINED.pdf

Extracted from the file · 7 pages · 8,262 characters

48 pages match
  1. Page 44 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-003 Page 16 of 16 deployment. If PURA were to approve an AMI deployment before or during the PBMRP term, the Company would need to increase the forecasted budget to incorporate those investments. b. c. Please refer to the Company’s detailed response to information request OCC-423. The Company’s proposed F-Factor is an annual adjustment taking effect July 1 of each year that reflects an allowance based on the annual revenue requirement on the capital expenditures budgeted for the current calendar year (per Exhibit TSP-3), plus a downward-only reconciliation comparing the actual plant additions placed in service as of December 31 of the calendar year prior to rates taking effect. In this way, the FFactor provides an allowance for capital investment in the rate year based on the expected capital expenditures projected in this proceeding (same as the CT-Bar), but is reconciled such that in the end the F Factor measures the actual capital investment, including plant additions, plant retirements, accumulating depreciation, cost of removal, and plant-related accumulated deferred income taxes, cumulatively from the investment allowed in base rates. Yes, that is correct. Prior-year capital additions are subject to the same annual downward-only reconciliation and Forecasted Budget cap as capital additions placed in service during the applicable Rate Year. d. The Company’s proposal to implement an F Factor allowance based on the forecasted budget presented in this proceeding, subject to a downward only adjustment upon reconciliation of prior-year capital additions is consistent with the Company's characterization of the Forecasted Budget as a cap on capital recovery during the PBMRP term because the F Factor reconciliation will only reconcile downward, meaning that if, in the end, the Company’s actual costs in a given year are more than it has forecasted in this proceeding, the Company would not be entitled to reconcile the F Factor to reflect the higher (i.e., above the cap) level of spending. It will only be reconciled downward, which will occur if the Company invests less than the amounts budgeted in this proceeding, and used in establishing the F Factor in a given year. e. Rate stability is enabled by prescribed, annual adjustments, consistent with the Company’s experience during the first four years following settlement of Docket No. 17-10-46. By providing the Company with incremental revenues to cover a portion of the rising costs of service, the rate increase requested in the subsequent rate case (for rates effective July 2031) would be significantly reduced both in dollar amount and in percentage change relative to then-effective rates. Moreover, the adoption of the PBMRP will enable the Company to stay-out of a rate case for the duration of the PBMRP, whereas in the absence of a properly designed PBR plan and adequate cast-off rates, the Company will not be in a position to stay out for any period of time and will require more frequent filing of base rate cases, resulting in larger and more choppy rate changes for customers than would be experienced under the PBMRP. The Company’s proposed PBMRP incorporates multiple customer protections, including the effect of the cap on capital investment eligible to be supported by the F-Factor, the earnings sharing mechanism, and the consumer dividend.
  2. Page 45 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-004 Page 1 of 2 Date Filed: October 27, 2026 Witness: Douglas P. Horton Request from: Department of Energy and Environmental Protection Question: (PBMRP- Z factor) Refer to Exhibit CLP-ELP-1 p. 99. Define (1) State Initiated Cost Change; (2) Federally Initiated Cost Change; (3) Regulatory Cost Reassignment; and (4) Externally Imposed Accounting Rule Change as it pertains to Exogenous Events in the Company’s proposal. For each category, provide specific examples of potential events the Company expects would and would not qualify for recovery as an Exogenous Event. Response: Below, the Company has provided illustrative examples of the types of events or changes that could qualify for exogenous factor consideration, subject to satisfaction of the applicable Z-Factor criteria: 1. State Initiated Cost Change • A new Connecticut statutory mandate requiring a distribution-system capital investment program or activity that was not contemplated in the revenue requirement used to establish the PBMRP. • A new or materially changed PURA or other Connecticut agency requirement imposing material incremental compliance, operational, or infrastructure requirements on electric distribution companies. • A change in Connecticut tax law that imposes a new or materially different tax obligation specific to utilities or electric distribution operations. 2. Federally Initiated Cost Change • A new or materially revised federal reliability or cybersecurity requirement that requires incremental distribution-system investment or operating expenditures. • A new federal environmental requirement requiring remediation, equipment modifications, monitoring, or other incremental expenditures associated with distribution assets or operations.
  3. Page 46 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-004 Page 2 of 2 • A new or materially revised federal safety or physical-security standard requiring changes to distribution facilities, equipment, systems, or operating practices. 3. Regulatory Cost Reassignment • A change in jurisdictional cost responsibility between federal and state regulation that causes a category of costs to become, or cease to be, the responsibility of distribution customers. • A regulatory determination that moves responsibility for a material cost into or out of distribution rates when that cost had previously been recovered through another regulatory mechanism. 4. Externally Imposed Accounting Rule Change • A new or amended FASB accounting standard that requires a material change in the recognition or measurement of distribution-related costs. • A mandatory regulatory-accounting change that requires costs previously capitalized to be expensed, or costs previously expensed to be capitalized. • A mandatory accounting change that creates, eliminates, or materially changes the accounting treatment of a regulatory asset or regulatory liability.
  4. Page 47 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-005 Page 1 of 1 Date Filed: October 27, 2026 Witness: Douglas P. Horton Request from: Department of Energy and Environmental Protection Question: (PBMRP Z- factor) Refer to Exhibit CLP-ELP-1 p. 99. Discuss whether the proposed Z-factor would apply only to increases and decreases in distribution costs resulting from qualifying exogenous events. Response: Yes, the proposed Z-factor would apply only to increases and decreases in distribution costs resulting from qualifying exogenous events. The proposed Z-factor would apply equally to both qualifying cost increases as well as qualifying cost decreases. A qualifying event would be reflected through the Z-Factor only to the extent its impact is appropriately borne by distribution customers and is not otherwise captured through another PURA-approved rate mechanism. The positive or negative distribution revenue impact of qualifying events would also need to satisfy the proposed 0.5 percent materiality threshold.
  5. Page 48 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-006 Page 1 of 2 Date Filed: October 27, 2026 Witness: Donald J. Scacco Jr., Digaunto Chatterjee and Douglas P. Horton Request from: Department of Energy and Environmental Protection Question: (PBMRP Z- factor) Refer to Exhibit CLP-ELP-1 pp. 24-25, 99. Discuss any interaction of the proposed PBMRP and the Leadership Panel's discussion of enabling utility ownership of generation. Response: There is no direct interaction under the proposal currently before PURA. As the Company explained in CIEC-001 i, the Company is not advancing a specific proposal in this proceeding to authorize or implement utility ownership of generation. The Leadership Panel instead identified utility ownership as one potential resource option that should be considered as part of a broader resource-planning assessment. Accordingly, no generation investment or related cost is included in the proposed PBMRP merely as a result of that discussion. If future legislation, regulation, or another binding governmental action were to impose a new distribution cost on the Company during the PBMRP term, any request for Z-Factor treatment would be evaluated under the Z-Factor criteria then applicable, including whether the cost is beyond the Company’s control, is not reflected in the I-Factor or another recovery mechanism, and satisfies the materiality threshold. The Leadership Panel’s policy discussion, standing alone, does not trigger the Z-Factor. Prior Referenced Response: i CIEC-001 Question: (Executive Leadership Panel) With reference to page 21 of the Executive Leadership Panel’s Direct Testimony, state whether the Company is advancing any proposal in this proceeding that would promote, allow, or otherwise enable utility ownership of generation. If the Company is advancing any such proposal in this proceeding, provide a reference to the testimony where the proposal(s) may be found. CIEC-001 Response: No, the Company is not advancing any specific proposal in this proceeding to promote, allow, or enable utility ownership of generation. The Company’s point is that it is time to consider all alternatives to solving the energy affordability conundrum in Connecticut (and the broader New England region). This should start with development of a comprehensive independent integrated resource planning assessment that projects the state of resource adequacy under a range of scenarios – ten years out. This is the type of study completed with robust stakeholder participation
  6. Page 49 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-006 Page 2 of 2 and input – including EDCs, LDCs, the legislature, and advocates for all customer segments (residential, commercial, and industrial) – that is essential to formulate an informed view of the comprehensive solution set necessary to meet the future resource adequacy needs within Connecticut. The Company is open to consideration of what would essentially be customer-owned generation through the utility operating model, if it would be the most cost-effective solution to meet reliability needs of Connecticut customers.
  7. Page 50 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-007 Page 1 of 1 Date Filed: October 27, 2026 Witness: Donald J. Scacco Jr., Digaunto Chatterjee and Douglas P. Horton Request from: Department of Energy and Environmental Protection Question: (PBMRP Z- factor) Refer to Exhibit CLP-ELP-1 pp. 22-24, 99. Discuss any interaction of the proposed PBMRP and the Comprehensive Independent Integrated Resource Plan (“CIIRP”) stakeholder process described by Leadership Panel. Response: The CIIRP discussion does not itself create a PBMRP adjustment. The Leadership Panel proposed a comprehensive, independent stakeholder process to evaluate supply options, associated costs and implementation issues and to provide a longer-term framework for future resource decisions. No specific resource selected through such a future process is embedded in the proposed PBMRP by virtue of that discussion. The PBMRP and the CIIRP concept therefore operate at different levels. The PBMRP is a distribution ratemaking framework for the four-year stay-out term. The CIIRP is described as a broader resource-planning process. If a future CIIRP process ultimately results in legislation, regulation, or another binding action that imposes a qualifying distribution cost change during the PBMRP, the Company would evaluate that discrete cost change under the Z-Factor criteria. The CIIRP process itself would not automatically qualify as an Exogenous Event.
  8. Page 51 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-008 Page 1 of 1 Date Filed: October 27, 2026 Witness: Donald J. Scacco Jr., Digaunto Chatterjee and Douglas P. Horton Request from: Department of Energy and Environmental Protection Question: (PBMRP Z- factor) Refer to Exhibit CLP-ELP-1 pp. 24-25, 99. Discuss any interaction of the proposed PBMRP and the Leadership Panel’s discussion of opportunities to coordinate upgrades to the gas distribution and transmission systems to increase firm gas supply in southeast Connecticut, facilitating either the buildout of a new natural gas combined-cycle generation unit or firming up an equivalent amount of gas supply for existing generation. Response: There is no direct interaction under the proposal presently before PURA. The Leadership Panel identified a potential opportunity to coordinate gas distribution and transmission upgrades in southeast Connecticut to increase firm gas supply, either to facilitate new combined-cycle generation or to firm gas supply for existing generation. That discussion does not place any such investment or cost into CL&P’s proposed distribution PBMRP. To the extent a future policy or project were approved through legislation, a regulatory order, or another binding action, the ratemaking treatment would depend on the nature of the approved project and the entity and jurisdiction to which the resulting costs are assigned. A cost would not become eligible for CL&P distribution Z-Factor treatment merely because the Leadership Panel discussed the concept. Any future request would have to satisfy the Z-Factor criteria, including that the distribution cost change is beyond the Company’s control, not otherwise reflected in the I-Factor or another recovery mechanism, and meets the applicable materiality threshold.
  9. Page 52 of 174Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-009 Page 1 of 1 Date Filed: October 27, 2026 Witness: Douglas P. Horton Request from: Department of Energy and Environmental Protection Question: (PBMRP Z- factor) Refer to Exhibit CLP-ELP-1 p. 100. For the purposes of determining the threshold significance of 0.5 percent of CL&P’s total distribution revenue, please explain whether that threshold would be fixed at the Company's allowed base distribution revenue for the Rate Year, the current annual base distribution revenue inclusive of PBMRP Adjustments, or some other amount. Response: The 0.5 percent significance threshold would initially be calculated based on the Company’s allowed total base distribution revenue requirement as established by PURA in this proceeding. Thereafter, the revenue amount used to calculate the threshold would increase by operation of the PBMRP, including the I-X and F-Factor adjustments. Accordingly, the dollar amount of the 0.5 percent significance threshold would not remain fixed throughout the PBMRP term.
  10. Page 53 of 174

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-010 Page 1 of 8 Date Filed: November 03, 2026 Witness: Douglas P. Horton Request from: Department of Energy and Environmental Protection Question: (PBMRP Z- factor) Refer to Exhibit CLP-ELP-1 p. 100. Compare and contrast the Company's PBMRP proposal with the performance based ratemaking mechanisms allowed for Eversource's electric operations in other jurisdictions. Response: As described below, the Company’s proposed Z-Factor is generally consistent with the exogenouscost mechanisms applicable to Eversource’s electric operations in Massachusetts and New Hampshire. Although the mechanisms differ in their eligibility criteria and materiality thresholds, each distinguishes ordinary cost variation subject to the incentives and risks of a multi-year plan from material changes outside utility management’s control that may warrant separate regulatory treatment. In this proceeding, the Company has proposed to implement an exogenous cost recovery adjustment for qualifying positive or negative cost changes that are beyond the Company’s control, are not reflected in the I-Factor, and are not otherwise addressed through another PURA-approved cost recovery mechanism. Potential changes include State Initiated Cost Changes, Federally Initiated Cost Changes, Regulatory Cost Reassignments, and Externally Imposed Accounting Rule Changes. The Company proposes an aggregate materiality threshold equal to 0.5 percent of total distribution revenues. Please refer to the Company’s response to BETP-004 i for additional discussion of these categories. 1 In Massachusetts, NSTAR Electric’s exogenous mechanism provides for rate changes for qualifying industry-specific tax, accounting, regulatory, judicial, and legislative changes that are beyond the company’s control and not reflected in the applicable inflation factor. It applies a $4 million individual-event threshold in the first PBR year, adjusted annually by GDP-PI, which equates to approximately 0.37 percent of distribution revenues. 2 Exhibit CLP-ELP-1, p. 100; Company response to BETP-004. PURA Docket No. 21-05-15RE01, Eversource Energy Comments on Revised Straw Proposal (Mar. 26, 2025), pp. 34-41. 1 2

Text of NECTA Set 6_COMBINED.pdf

Extracted from the file · 22 pages · 43,545 characters

Text of OCC Set 29_COMBINED.pdf

Extracted from the file · 30 pages · 65,312 characters

Text of PURA Set 8_COMBINED.pdf

Extracted from the file · 230 pages · 511,861 characters

As listed on the current system

Corres. 11/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

This filing on the current system (opens in a new tab)