Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8
Files9
Docket No. 26-05-10 Discovery Compilation November 6 2026.pdf
PDF · 134 KB · 1 pageText searchable
Download Docket No. 26-05-10 Discovery Compilation November 6 2026.pdfRead the text of Docket No. 26-05-10 Discovery Compilation November 6 2026.pdf
ALLCO Set 13_COMBINED.pdf
PDF · 801 KB · 49 pagesText searchable
Download ALLCO Set 13_COMBINED.pdfRead the text of ALLCO Set 13_COMBINED.pdf
ALLCO Set 16_COMBINED.pdf
PDF · 642 KB · 22 pagesText searchable
Download ALLCO Set 16_COMBINED.pdfRead the text of ALLCO Set 16_COMBINED.pdf
ALLCO Set 18_COMBINED.pdf
PDF · 306 KB · 25 pagesText searchable
Download ALLCO Set 18_COMBINED.pdfRead the text of ALLCO Set 18_COMBINED.pdf
CIEC Set 7_COMBINED.pdf
PDF · 230 KB · 7 pagesText searchable
Download CIEC Set 7_COMBINED.pdfRead the text of CIEC Set 7_COMBINED.pdf
DEEP Set 1 (BETP)_COMBINED.pdf
PDF · 1.9 MB · 174 pagesText searchable
Download DEEP Set 1 (BETP)_COMBINED.pdfRead the text of DEEP Set 1 (BETP)_COMBINED.pdf
NECTA Set 6_COMBINED.pdf
PDF · 446 KB · 22 pagesText searchable
Download NECTA Set 6_COMBINED.pdfRead the text of NECTA Set 6_COMBINED.pdf
OCC Set 29_COMBINED.pdf
PDF · 499 KB · 30 pagesText searchable
Download OCC Set 29_COMBINED.pdfRead the text of OCC Set 29_COMBINED.pdf
PURA Set 8_COMBINED.pdf
PDF · 2.5 MB · 230 pagesText searchable
Download PURA Set 8_COMBINED.pdfRead the text of PURA Set 8_COMBINED.pdf
Text of ALLCO Set 18_COMBINED.pdf
Extracted from the file · 25 pages · 65,407 characters
Text of CIEC Set 7_COMBINED.pdf
Extracted from the file · 7 pages · 8,262 characters
Page 81 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-021 Page 3 of 6 Prior Referenced Responses: i OCC-596 Question: Refer to Exhibit CLP-TSP-1 at 55, “…plan to maintain a transformer fleet that does not exceed 70 years of age.” Identify every law, regulation, manufacturer requirement, or mandatory engineering standard that requires a substation transformer to be retired at 40 years, 70 years, or any other specified age. If no such requirement exists, please confirm. a. Provide all existing studies, analyses, and historical data relied upon by the Company to conclude that transformer failure risk increases rapidly as transformers approach or exceed 70 years of age. If the Company has not performed an empirical analysis using its transformer-failure experience, please justify. b. Provide the Company data and analyses used to establish the transformer age thresholds or replacement criteria in the TSP, including the stated 40-year useful life and increased failure risk near 70 years. Include the age and cause of failure for each Company transformer that failed during the period covered by the analysis. If the criteria are not based on the Company’s actual failure experience, identify the source on which they are based. OCC-596 Response: There are no laws, regulations, manufacturer requirements, or mandatory engineering standards that require substation transformers to be retired at a specific age. The age of a power transformer is one of the most important factors in assessing asset condition. Although actual service life varies widely depending on the manufacturer’s design, quality of assembly, materials used, operating history, current operating conditions, and maintenance history, the average expected life for an individual transformer is approximately 40 years according to industry consortiums, and manufacturers. International reliability surveys (i.e., CIGRE) report major failure rates on the order of ~0.3% per transformer-year across large populations, with failure behavior influenced by aging and asset condition. Industry asset-management guidance supports risk-based decision-making that balances failure risk and cost. Eversource employs several methods to both actively and passively monitor the health of distribution power transformers within its service area. Active and continuous monitoring methods include out of specification alarming. Alarms may include indications for bushing monitoring (if applicable), LTC trouble, dissolved gas (if applicable), oil level alarms, and oil temperature alarms, among others. This information along with periodic maintenance and testing reports provide data into Eversource’s condition‑based asset management methodology that draws on multiple sources including: • • • • • Transformer nameplate characteristics Oil quality and DGA trends Abnormal thermal, electrical, or core indicators derived from PTX health modeling Maintenance and inspection records Power Factor Testing Eversource utilizes a detailed asset health score generated through the Electric Power Research Institute (EPRI) PTX tool to assess power transformer asset health. OCC-596, Attachment 4 CONFIDENTIAL, is a technical guide to the EPRI Power Transformer Expert System (PTX). The PTX tool evaluates normal degradation, abnormal operating conditions, oil quality, and age to produce two critical indicators: the Long-Term Health Index (LTI) and the Short-Page 82 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-021 Page 4 of 6 Term Health Index (STI). The PTX health index is measured in the range of 0 to 1, with 0 meaning healthy and 1 needing immediate replacement. A value greater than 0.5 is considered poor health, such that if repair/replacement is not performed the transformer will continue to decline leading to equipment failure. Eversource has 27 transformers in CT, or about 8.6% of the fleet, that fall within the range considered to be in poor condition. This means that without repair or replacement, their condition is expected to continue declining, increasing the risk of equipment failure. As a result, Eversource continues to prioritize and initiate replacement projects for these transformers. Attachments included note that multiple industry sources discuss aging and failure rates of substation power transformers. • • • • OCC-596, Attachment 1 CONFIDENTIAL, A2 Cigre Brochure 939 AC Transformer Reliability OCC-596, Attachment 2 CONFIDENTIAL, 1013566 Plant Support Engineering Large Transformer End of Expected Life Considerations and the Need for Planning OCC-596, Attachment 3, EXEC-2022-001242 - Large Power Transformer Resilience Report 7-10-24 OCC-596, Attachment 4 CONFIDENTIAL, 3002026877_Power Transformer Expert System (PTX) Software Application Guide_ Introduction to PTX, Overview, Technical Basis and Application Information Based on industry experience, while transformers can operate beyond their typical design life of 40 years, the risk of failure exponentially increases after 70 years of service life, due to paper insulation degradation. OCC-596, Attachment 1 CONFIDENTIAL, a CIGRE study from 2024, shows the failure rate of transformers has a noticeable increase starting at 40 years and exponentially increases as the asset exceeds 65 years old. This study reviewed analysis of thousands of transformers including many voltage classes from around the world to build depth into the data available. OCC-596, Attachment 2 CONFIDENTIAL is an EPRI paper discussing “Large Transformer End-ofExpected Life” which notes “the useful life of a large, oil-filled transformer is between 30 and 40 years with insulation or bus supports being the most likely to fail due to age. For the insulation, thermal aging of the paper insulation is the likely cause of failure.” OCC-596, Attachment 3, is a Department of Energy report from 2024, citing that large power transformers “are typically considered to have a design lifetime on the order of 40 years. In 2014, a DOE report estimated that the average age of LPTs in the North American grid was 38–40 years, indicating that a substantial fraction of those LPTs are at or over that design lifetime. These LPTs will ultimately need to be replaced or refurbished.” These industry research groups and others have provided basis within their published studies to support the concerns of failure with any transformer over 40 years in-service. As a result, Eversource’s Asset Health philosophy for transformers is to operate transformers to their maximum useful life, but plan to maintain a transformer fleet that does not exceed 70 years of age and an average age of approximately 35 years. The objective is to find the balance between affordability and preventing an aged transformer fleet that approaches the “knee of the curve” which results in failure rates that increase significantly. With a large portion of the transformer fleet being between 50 and 80 years old, as these transformers continue to approach and exceed 70 years, the rate of failure will increase rapidly. Due to the complexity and time duration of procuring and replacing transformers, a significant increase in failures would result in the inability to maintain reliability by reactively replacing an increased volume of transformer failures. The six most recent failures of transformers in CT were all attributed to internal failures of the transformer. The ages of the failed transformers were 32, 50, 52, 52, 56, and 83 years old at the time of the failure. ii OCC-597 Question:Page 83 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-021 Page 5 of 6 Refer to Exhibit CLP-TSP-1 at 55. For each proposed proactive replacement, identify whether the Company evaluated continued operation through enhanced inspection, testing, monitoring, maintenance, refurbishment, loading limits, load transfer, or use of a spare transformer. Provide each existing analysis and state whether it found that replacement could be deferred by one, three, or five years. If no deferral or life-extension or alternate analysis was performed, please confirm the reason. OCC-597 Response: Eversource employs several methods to both actively and passively monitor the health of all power transformers within its service area. Active and continuous monitoring methods include out-of-specification alarming. Remote alarming (if applicable) is conducted through the Eversource SCADA system with alarms existing for bushing monitoring, LTC trouble, dissolved gas, oil level alarms, and oil temperature alarms, among others. Per industry best practices, local alarming is performed through panel indication lamps with corresponding nameplate alarm descriptions and annunciation technologies such as bulb annunciators and Human Machine Interfaces (HMI’s). The preventive maintenance procedures for power transformers are documented within the Eversource Maintenance Program (EMP) 5.58 Station Transformers and Oil-Filled Shunt Reactors. The inspection and maintenance tasks are catalogued into three (3) categories which include a list of asset conditions for real-time condition monitoring, timebased regular inspections, and condition-based maintenance activities. These are described in more detail below: Condition Monitoring: Various parameters related to power transformer health are actively monitored as applicable. The monitoring is performed both locally and remotely with local monitoring performed by individual equipment alarms and station annunciators. Remote monitoring is performed via Supervisory Control and Data Acquisition (SCADA) to enable real-time asset parameter output and SCADA equipment alarms. Such parameters include temperature, oil level, pressure, and load tap changer (LTC) status. Time-Directed Maintenance and Inspections: Eversource has established multiple routine maintenance activities required to be performed for all power transformers within specific time intervals. These activities include monthly visual inspections, annual oil sampling including dissolved gas analysis (DGA), thermographic readings, LTC maintenance, and major maintenance activities. Major maintenance activities include power factor testing, bushing testing, excitation testing, confirmation of proper operation and integrity of pressure relief devices and ensuring all alarms operate properly. Condition-Based Maintenance: These activities are on an as-needed basis when identified upon visual inspection, when performing time-directed maintenance activities, and when output from condition monitoring devices indicate outside normal operating values. Such activities include, but are not limited to, acoustic measurements, core grounding tests, leak repairs, and chassis repair. Substation Technical Engineering leverages data collected by the CASCADE, PTX Analysis, and substation equipment databases to perform asset condition assessments of power transformers. The reports are based on the following six (6) parameters with recommendations for replacement by the Substation Technical Engineering team being based upon whether two (2) of the following (6) parameters are considered high risk: • Oil Analysis Results • DGA • Fluid Quality Analysis • Furan Analysis on Main Tanks • AgePage 84 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-021 Page 6 of 6 • • • • Loading Maintenance History Historical Test Data Physical Inspection Findings The above practices are applicable to all power transformers. Asset age and condition will prompt enhanced inspection, testing, monitoring, and maintenance as noted in the EMP toward the goal of maximizing the usable life of a transformer. Historically the Company has effectively maximized the life of Transformers by extensive maintenance and monitoring practices, evidenced by the age demographics of the fleet which far exceed the typical design life of 40 years. While this practice continues, the risk profile of an aging fleet compounded by longer lead times and more challenging outage constraints has resulted in a need to initiate planned replacements, beyond the historical average of 1-2 transformer replacements per year, to minimize overall impact of a failed transformer and maximize efficiency. A typical transformer replacement can take from 2 to 5 years to plan and execute. From the time of identification of deteriorating health, the transformer will continue to degrade over the course of the project execution time period. While spares are an effective mitigation plan for emergent failures, it is not a “one-size fits all” long-term mitigation plan to address the fleet risk because depending on when the failure or urgent replacements occur, it may happen at a high-risk period of the year which cannot be controlled exposing the system and customers to a much higher risk. Allowing transformers to run to failure also poses a serious safety risk to both the public and utility workers. Additionally a failed transformer could cause damage to adjacent healthy equipment compounding the negative impact. Prior to initiation of a transformer replacement project, the various subject matter experts (SMEs) will confer and review the nameplate data, maintenance records, and PTX scores of the unit. If a transformer is reviewed and a capital project is not to be initiated, the transformer is typically recommended to have further evaluation for maintenance mitigation of the found issue. This may include repairs or minor refurbishment actions that enable the power transformer to be reenergized and placed back in-service. If the transformer is identified as requiring a capital project an initial funding is established and a project team assembled. The project team includes various SMEs and they are required to review the technical and financial feasibility of transformer replacement, transformer refurbishment, load transfer options, and usage of existing spare transformer inventory for a replacement. After the feasible options are developed, the project team will proceed with a formal review of the multiple feasible options within the procedures of the Eversource Solution Design Committee. Using the nameplate data with age and ratings combined with the PTX scores, the power transformers noted in Exhibit CLP-TSP-1 at 55 have been identified to proceed with the initial capital project evaluation within the Targeted System Plan. As these evaluations are completed, the power transformers will be prioritized and projects initiated as confirmed. The project sequencing and deferral options will be evaluated within this review. The two active and ongoing projects for transformer replacements included within the Targeted System Plan followed the processes noted above, were prioritized within the project portfolio, and are planned to be placed in-service in 2028.Page 85 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-022 Page 1 of 16 Date Filed: November 05, 2026 Witness: David L. Gladey, Lavelle Freeman, John P. Dipaola-Tromba, Jennifer A. Schilling and Elli Ntakou Request from: Department of Energy and Environmental Protection Question: Please provide a reconciliation, by year for 2027–2031 and by major program category, of the approximately $3.985 billion Targeted System Performance Plan to the Company’s capitaladditions forecast. Please identify the following in this reconciliation: a. forecasted expenditure; b. expected in-service amount; c. primary investment driver; d. and proposed recovery mechanism for each category. Please identify which amounts are authorized, under design, conceptual, or contingent on a future event. Separately identify IT, Facilities, and Basic Business capital expenditures excluded from the engineering plan. Response: Plant additions and capital expenditures are two different perspectives on the same underlying investment. Capital expenditures are generally organized and managed around specific business objectives, programs, projects, or asset installation efforts, such as substation expansions, feeder rebuilds, pole replacement programs, or other distribution system investments. Capital expenditures are incurred over the course of project execution and may span multiple months or years depending on project scope, complexity, and construction schedules. Plant additions, by contrast, are recognized when utility assets are placed in service and meet the applicable accounting criteria for recording as utility plant. Accordingly, a plant addition is generally recorded at a specific point in time, whereas the associated capital expenditures may have been incurred over an extended period. The Company develops its forecast of plant additions using its capital investment plans, project schedules, anticipated in-service dates when possible, and historical experience. However, actual in-service dates may differ from forecasted in-service dates (where available) due to changes in project scope, construction sequencing, permitting, material availability, operational considerations, weather, or other factors. Consequently, the timing of annual plant additions may differ from the timing of annual capital expenditures. While such timing differences may occur inPage 86 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-022 Page 2 of 16 any given year, over a multi-year period it is reasonable to expect that plant additions, together with associated cost of removal, will generally track with capital expenditures. Please refer to the Company’s responses to OCC-423 i, OCC-857 ii, OCC-858 iii, and EOE-371 iv for further discussion on the reconciliation of capital expenditures and capital additions and the rate recovery mechanisms for these investments. Prior Referenced Responses: i OCC-423 Question: Exhibit CLP-ELP-1 Please explain in detail why the Company believes its proposed treatment of capital expenditures under the PBMRP, including the use of forecasted capital expenditures and the F-Factor, is preferable to including capital expenditures within the Revenue Cap Formula framework as proposed in the Docket No. 21-0515RE01 Proposed Final Decision. In your response, a. Please explain why the Company believes O&M expenses are appropriately subject to an externally indexed revenue cap, while capital expenditures require separate recovery through an F-Factor based on a fixed annual capital investment forecast. b. Please explain how the Company's proposed treatment of capital expenditures is expected to produce customer cost savings or otherwise improve customer affordability relative to including capital expenditures within a revenue cap formula. c. Please explain how the proposed F-Factor mitigates or avoids any incentive to favor capital expenditures over O&M solutions, including in circumstances where either a capital or O&M solution could be used to address the same system need. OCC-423 Response: The Company appreciates OCC’s thoughtful and analytical questions on the Company’s proposed performance based multi-year rate plan (“PBMRP”) and looks forward to further discussion on the development of a workable PBR framework for the Company’s customers. To cover the issues raised in the question, the Company’s response is organized as follows: 1. 1. Review of relevant aspects of the Company’s PBMRP. 2. Considerations on the design of capital-driven revenue support. 3. Specific responses to parts (a), (b) and (c), above. Review of the Relevant Aspects of the Company’s PBMRP Ultimately, the Company’s goal in this proceeding is to establish a sustainable, cohesive ratemaking framework that advances electric utility service in the State of Connecticut in an affordable manner for customers, over a long term. This is the Company’s goal because the CL&P system needs investment for reliability, resiliency and modernization. For this investment to be affordable for customers, a coherent ratemaking plan needs to be instituted that will consider the interests of customers over a longer term than just the next rate case. That framework needs to balance: (1) thePage 87 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-022 Page 3 of 16 reliability and performance requirements of the Company’s customers and the broader State of Connecticut; (2) customer rate stability and affordability; (3) incentives for cost efficiency in utility operations; and (4) implementation of a revenue support mechanism sufficient to cover the cost of delivering these objectives to customers. The Company’s PBMRP is designed to address these objectives in a holistic, balanced way. To do this, the Company started with the ratemaking framework under discussion in PURA’s PBR docket (Docket No. 21-05-15RE01), while also introducing certain new elements to remediate the flaws that would ultimately hinder PURA’s (draft) PBR model from supporting the necessary stay-out terms. For any multi-year rate plan to be successful, it needs to be grounded in the reality of the utility’s costs, while also incorporating features that innately push the utility to be more efficient. That is not to say every dollar of the utility’s costs will be (or should be) recovered. Rather, the allowed revenues need to be sufficient to afford the utility a reasonable opportunity to cover its cost of service to customers, including a reasonable rate of return on equity (“ROE”) where the utility is operating prudently and efficiently, as required by state law. A framework in which the utility has no reasonable opportunity to earn its ROE, regardless of how hard it strives for efficiency, simply becomes self-defeating because the utility will exercise its statutory rights to a distribution rate proceeding, thereby muting the most powerful efficiency feature of a multi-year rate plan, which is the stay-out term. A framework that underestimates the actual cost to run the system and/or affords the utility no reasonable chance to earn its allowed ROE, year after year, also results in under-investment and a system that not only lacks innovation, but falls further and further behind at a significant – albeit potentially unseen – cost to customers. As a result, a lasting, productive framework is one that is soundly informed by – not detached from – the drivers of the utility’s real cost of service, including its cost of capital. In this context, the two most critical features of the Company’s PBMRP are as follows: • • A going-in revenue requirement that reasonably reflects the Company’s actual operating expenses and cost of investment in the Rate Year, so that through effective management and prudent decision making, the Company can achieve the true efficiency gains that will be needed to stretch the approved revenue requirement over the stay-out term. Without a reasonable opportunity to maintain financial integrity over a stay-out period, as measured by the authorized ROE, the utility cannot focus on innovation and efficiency gains – and will instead file for the next rate case to make up ground. To accomplish this goal, the overall paradigm must “hang” together, making the base revenue requirement a pivotal element. The many components of a PBR plan, including going-in rates, as well as the subsequent rate adjustments, must work in concert with performance objectives and the capital investment requirements expected of the Company – for the benefit of customers, i.e., the entire framework must work to the benefit of customers, not only in relation to the price they will pay, but also in relation to supporting the level of service that they need and expect. Revenue support for incremental capital investment to support long-term system goals. The Company operates in a capital-intensive industry and has a substantial need to acquire cash on a systematic basis to operate its business. As annual capital investments regularly exceed net cash from operations (i.e. cash receipts from customers net of operating cash outflows), the Company must look to other capital sources to fund those investments. Those sources are the debt and equity investors supplying the cash to capital markets. This means the Company must compete with all other entities participating in those markets to attract capital. It is simply not possible for the Company to go to those markets and demand cash for free, or at belowmarket rates relative to the investor’s risk when other entities participating in the same capital markets offer compensation for the use of funds over time.Page 88 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-022 Page 4 of 16 The Company provided extensive analysis and discussion on the cost of capital throughout Docket No. 21-05-15RE01, including specifically as it relates to CT-Bar. PURA’s treatment with respect to going-in revenue requirements as well as any ongoing capital-driven revenue support mechanism, such as CT-Bar, is paramount to whether the Company, with effective management and sound decision-making, can responsibly cede its right to file for a rate amendment, whereas that is otherwise the only tool the utility has to align its revenues and costs and have a reasonable chance at earning its authorized ROE, which, over time, is necessary in order to attract the capital necessary to meet the standards of service expected of the Company’s customers. The lack of a valid revenue requirement component within the CT-Bar that would allow recovery of the cost of capital associated with incremental capital investment over the term of the PBMRP is a non-starter from a policy perspective, creating an obstacle that would block a utility from giving up its right to file for rate modifications over the multi-year period in question. This is particularly accurate in the present environment in which significant increases in the level of necessary system investments are expected (and planned). Simply put, the CT-Bar, as previously envisioned in PURA’s draft PBR decision, fully prevented the Company from having any practical chance at staying out of a rate case, and therefore, would never work to create a reasonable PBR framework. The Company’s proposed PBMRP in this docket is designed to track the design of the CT-Bar as closely as possible, given that this was PURA’s developing framework. However, the Company’s PBMRP addresses the two primary faults in PURA’s RE01 framework that would prevent the implementation of a workable PBR framework, which are (1) the deviations from ratemaking fundamentals that grossly understate the “going in” revenue requirement; and (2) modification of the CT-Bar to reflect the revenue requirement applicable to capital investment, which would include recovery of the cost of capital and the cost of removal over the course of the PBMRP term. The Company’s F-Factor also corrects for the mechanical error of deducting depreciation expense from new plant additions, rather than from rate base. In particular, the Company’s proposed F-Factor is designed to recover no more than the revenue necessary to support a discrete amount of ongoing system investment, recognizing that the cost of capital is a lawful and factual cost of service that must be incorporated into the revenue requirement calculation for the Company, as it is for any utility. 2. Considerations on the Design of Capital-Driven Revenue Support CT-Bar, as defined in PURA’s Proposed Final Decision, issued in Docket No. 21-05-15RE01, on July 14, 2025 (the “RE01-PFD”), had several sensible qualities that the Company supported. However, those “sensible” qualities were overcome by certain critically flawed concepts that would need to be modified or eliminated in order for the Company to consider committing to a stay-out. The positive and negative CT-Bar qualities are outlined briefly here and discussed in greater detail below, including with respect to similarities or differences to the Company’s proposed FFactor. Summary of constructive features of PURA’s RE01-PFD: 1) Acknowledgement that current revenue support for ongoing investment is essential; 2) No category of capital investment was summarily or preemptively excluded from CT-Bar; 3) CT-Bar takes effect with Rate Year 1; and 4) CT-Bar aligns capital revenue support with the capital investments of the DSP. Summary of unworkable features of PURA’s RE01-PFD:Page 89 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-022 Page 5 of 16 1) Exclusion of the recognition in the CT-Bar of the cost of capital between rate cases. 2) Exclusion of cost of removal in the CT-Bar. 3) Application of depreciation expense as a reduction to plant additions rather than rate base. Constructive features of PURA’s RE01-PFD: 1) Positive #1: Acknowledgement that current revenue support for ongoing investment is essential to the integrity of the PBR framework. First, that the CT-Bar even existed in PURA’s RE01-PFD is genuine acknowledgement that some form of revenue support for rate year investment is essential to support a PBR framework. As discussed at length in that docket, the Company anticipates significant system investment over the next five years to advance the state’s clean energy and reliability goals. Revenue support for ongoing system investment is crucial for any multi-year rate plan, whether in the form of the Company’s proposed PBMRP, step increases, or any other ratemaking framework. CT-Bar’s inclusion in RE01-PFD is a clear indication that incremental revenue support for ongoing system investments is a necessity. 2) Positive #2: No category of capital investment was summarily or preemptively excluded from CT-Bar. Second, the RE01-PFD did not exclude particular categories of capital investment. For example, capital investments in facilities, fleet and information technology are viewed as permissible categories for revenue support in the CT-Bar framework. This is consistent with the Company’s proposed F-Factor in this proceeding. 3) Positive #3: CT-Bar takes effect as of Month 1 of Rate Year 1. The Company provided extensive discussion and analysis throughout Docket No. 21-05-15RE01 technical sessions and data responses regarding the “going-in” revenue requirement and the detrimental financial consequences of limiting capital investments to a period of time removed from the rate year. Ignoring for a moment the CT-Bar’s deficiencies, having the mechanism take effect Month 1 of Rate Year 1 minimizes or eliminates those detrimental timing consequences, particularly in light of the fact that PURA has in recent years moved away from its prior practice of implementing future-test years in base rate proceedings, instead favoring a strict historical test year practice as it relates to plant additions. Revenue decoupling is a factor to consider here because the revenue decoupling mechanism (“RDM”) subsumes all sales growth to the extent that it is occurring, funneling incremental sales revenues back to customers. RDM is supported by valid policy reasons; however, the fact is that there are capital costs associated with adding new customers. Historically, when consistent and steady levels in the range of ~3$ per year of annual growth in sales and revenues was available to a utility to help offset the cost of incremental capital additions between rate cases, the pressing need for incremental revenue support was mitigated. Without the ability to capture that sales growth, and combined with the absence of an ongoing revenue support mechanism such as an F Factor taking effect on Month 1 of Rate Year 1, the Company would not be in a position to commit to a stay-out of any duration. This is because the Company would never be in a position to cover its cost of service (inclusive of its authorized cost of capital) because its rates would be set on a historical level of plant additions, despite the fact that its capital expenditures are higher than historical levels of depreciation, and because revenue decoupling ensures that even if load growth exists (and even if such load growth is enabled by the Company’s increased level of capital expenditures) the Company is unable to retain additional revenues contributed by new customers, or new load.Page 90 of 174
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set DEEP-01 Date Issued October 06, 2026 BETP-022 Page 6 of 16 4) Positive #4: CT-Bar was designed to align capital revenue support with the DSP. Ignoring its deficiencies, the CT-Bar’s connection to the Distribution System Plan (“DSP”) constituted an essential link between ongoing system investments necessary to meet the objectives of the DSP with the revenues necessary to support those investments. Throughout Docket No. 21-05-15RE01, the Company advocated strongly for clearly defined linkages across all three tracks (RE01, RE02 and RE03), including proposing what would be the final technical session touching upon revenue requirements, in which those linkages were discussed. The Company’s F-Factor is similarly aligned with the capital investment forecast provided in this proceeding for the DSP. The Company’s capital investment forecast serves as the basis for a cap on the level of investment for the F-Factor. Unworkable Features of PURA’s RE01-PFD: 1) Negative #1: No recovery of cost of capital in the revenue requirement for capital investment between rate cases. The single-most problematic feature of the CT-Bar was its intentional exclusion of the cost of capital associated with completing capital plant additions to the benefit of customers. Costs of capital are real costs of providing electric distribution service to customers in the State of Connecticut (or anywhere) and are recognized in statute. Although the cost of capital may be a more challenging cost to conceptualize, it is nonetheless as real as vegetation management, insurance, customer service, or any other cost of service. Cash is not free, a fact arising from its scarcity. Fundamentally, capital markets are where people, banks, corporations and other institutions provide their surplus of cash -- which is limited, to those entities that have cash needs -- which are generally unlimited. Consequently, and unsurprisingly, those entities providing the cash for some period of time expect to be compensated for providing it, thus establishing real cost to acquire capital. The Company, operating in the capital-intensive industry of regulated utilities, is one of those entities that needs to acquire cash to operate its business. As annual capital investments regularly exceed its net cash from operations (i.e. cash from customers), the Company must look to other sources to fund those investments. Those sources are the debt and equity investors supplying the cash to capital markets. This means the Company must compete with ALL other entities participating in those markets. It is simply not possible for the Company to go to those markets and demand cash for free (or for below-market rates, relative to market expectations of risk and reward) when other entities participating in those capital markets offer adequate compensation for the use of funds over time. Therefore, there is a real and tangible cost to acquiring that capital. Please refer to the Company’s pre-filed cost of capital testimony for in-depth discussion of the cost of capital. The Company provided extensive analysis and discussion on the cost of capital throughout Docket No. 21-05-15RE01, including specifically as it relates to CT-Bar. PURA’s treatment with respect to going-in revenue requirements as well as any ongoing capital revenue support mechanism, such as CT-Bar, is paramount to whether the Company, with effective management and sound decision-making, has the opportunity, but not a guarantee, to cover its cost of service to customers, and to earn its allowed return. The absence of the cost of capital from the CT-Bar, particularly in the present environment where significant increases in the level of necessary system investments are expected, prevents the Company from having any practical opportunity to commit to a stay-out to avoid the next rate case. As discussed in the Company’s response to OCC-435, based on the Company’s current assessment of system investment needs in the near future, the revenue requirement associated exclusively with the cost of capital pertaining to future capital additions (excluding GET and Uncollectible) would amount to an incremental $15.6 million for Rate Year 1; an incremental $32.8 million for Rate Year 2; an incremental $36.4 million for Rate Year 3; and an incremental $39.5 million for Rate Year 4, or $124.1 million in total.
Text of NECTA Set 6_COMBINED.pdf
Extracted from the file · 22 pages · 43,545 characters
Text of OCC Set 29_COMBINED.pdf
Extracted from the file · 30 pages · 65,312 characters
Text of PURA Set 8_COMBINED.pdf
Extracted from the file · 230 pages · 511,861 characters
As listed on the current system
Corres. 11/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8