Eversource rate increase is on 89 pages across 5 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
2 pages match

Text of ALLCO Set 18_COMBINED.pdf

Extracted from the file · 25 pages · 65,407 characters

Text of CIEC Set 7_COMBINED.pdf

Extracted from the file · 7 pages · 8,262 characters

Text of DEEP Set 1 (BETP)_COMBINED.pdf

Extracted from the file · 174 pages · 446,641 characters

Text of NECTA Set 6_COMBINED.pdf

Extracted from the file · 22 pages · 43,545 characters

Text of OCC Set 29_COMBINED.pdf

Extracted from the file · 30 pages · 65,312 characters

35 pages match
  1. Page 156 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-084 Page 4 of 9 Audit Report # Audit Report Title Report Recommendations (iii) 24-49 Project Support Services and Engineer of Choice Staff Augmentation (4.1) Management should consider standardizing the background check attestation form for PSS/EOC workers to ensure all suppliers complete the necessary checks in compliance with the applicable contract. It is recommended these documents be requested from the Suppliers for all new hires to ensure contract compliance. These documents can then be uploaded to Fieldglass, as is done by Allegiance for their contingent worker base. (iii) 24-49 Project Support Services and Engineer of Choice Staff Augmentation (4.2) Each Supplier is responsible to conduct a background check on workers they on-board for Eversource. Should a worker switch suppliers after a tenure break, the new supplier is expected to Management Responses be implemented by February 1, 2025. The requirement for worker attestation is not currently a requirement under the existing contract. Contract Controls will work with Procurement to modify the existing contract language to explicitly require the attestation form to be completed and provided with each worker during onboarding. In coordination with Procurement, this contractual requirement is being added to the EOC contracts that are being negotiated currently and will be included in the upcoming Project Support Services category re-bid (current contracts expire June 28, 2025 but may be extended to accommodate appropriate time to complete the re-bid cycle). Once Procurement has successfully negotiated that language with each Supplier to make it contractually obligated in the new agreements, Contract Controls will enforce the requirement with each Supplier Worker that is onboarded by adding it as a required activity to be completed and attached as part of the on-boarding checklist in the Fieldglass system. This will be completed by December 31, 2025. Contract Controls will ensure Supplier compliance of reconducting a background check on a previous PSS or EOC worker that switches suppliers during on-boarding. Additionally, a banner Status Complete (12/2/2025) Complete (12/4/2024)
  2. Page 157 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-084 Page 5 of 9 (iii) (iv) Audit Report # Audit Report Title 24-49 Project Support Services and Engineer of Choice Staff Augmentation 26- 10 Defined Pension Audit Benefit Plan Report Recommendations Management Responses perform their own background check on the worker. Human Resources Talent Acquisition provided that if Project Contract and Controls is able to verify that prior background checks did not result in any derogatory information related to prior employment, education, social security trace, or military history, the current Supplier should perform the Criminal and Sex Offender Registry screening and drug test, at a minimum. (5) Appropriate individuals of Suppliers PFE (Planet Forward Energy) and PMA Consultants should be counseled accordingly. Going forward, FG records should go through an integrity check after a person is on-boarded to ensure accuracy and completeness. reminder has been posted and communicated to Suppliers via the Fieldglass tool to reinforce the current contractual obligation under the Agreement. Effective May 26, 2023, the Randstad/Allegis Fieldglass vendor management system was modified to instruct suppliers to enter the worker's legal name upon submission. A pop-up confirms they are doing so. There is also a verification box at the bottom of the submission page requiring a response that the legal name was entered. Management should evaluate the potential of implementing a similar control in the PSS/EOC Fieldglass module. The Investment Management team and the RPIC (Eversource Retirement Plan and Investment Committee) Status In Q3 2024, a communication went out via email to all PSS and EOC supplier worker contract representatives to reinforce the requirement to enter full legal names in Fieldglass as outlined in the Supplier Quick reference & user guide training. Additionally, a banner was posted in Fieldglass on the home page to reinforce the reminder. Lastly, Contract Controls worked with IT and SAP Fieldglass support to implement the pop-up enhancement described above. This functionality was implemented and effective as of October 25, 2024. Complete (12/4/2024) Charter and IPS Alignment We will review and update the Investment Policy Statement (IPS) to ensure alignment with Complete (5/26/2026)
  3. Page 158 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-084 Page 6 of 9 Audit Report # Audit Report Title Report Recommendations Management Responses should collaborate, with guidance from legal counsel, as to what administrative activities should be routinely performed and the cadence for those activities. Once determined, those activities should be documented and scheduled. Meeting minutes should document that the activities were performed. Examples of administrative activities include, at a minimum, the following: the RPIC Charter regarding member appointment authority. Target Completion: February 23, 2026 • Charter and IPS alignment, periodic review, and approval by the RPIC Review of Meeting Materials We will target one week prior to RPIC meetings for distributing meeting materials to allow adequate review time. Target Completion: Quarterly, beginning February 15, 2026 • RPIC acknowledgement of the Charter and IPS when new members join the RPIC • Calendaring meeting dates for the year and scheduling delivery of meeting materials • Schedule for reviewing/approving consultants that support the Plan • Periodic assessment of activities against applicable ERISA (Employee Retirement Income Security Act) requirements (v) 26-14 Energy Efficiency Time Allocation Audit (1.1) Management from EE (Energy Efficiency) should perform the following: Status Quarterly Meeting Calendar and Meeting Materials An annual calendar for RPIC meetings will be established and communicated at the start of each year. Target Completion: Every calendar year beginning January 2026 [Completed for 2026] RPIC Member Acknowledgement Process A review of Charter and IPS will be implemented for new RPIC members and a review of the IPS will be conducted annually. Target Completion: Annually, and as needed, beginning February 23, 2026 Administrative Checklist We will work with outside counsel to develop and maintain a checklist of key administrative activities, including consultant review/approval, and ERISA compliance assessments. Target Completion: May 31, 2026 Management agrees and will conduct the following: a. Energy Efficiency management will review Complete (5/28/2026)
  4. Page 159 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-084 Page 7 of 9 (v) Audit Report # Audit Report Title 26-14 Energy Efficiency Time Allocation Audit Report Recommendations Management Responses • Review the time charged to EE programs by the 16 non-EE employees and amend their time using WorkForce or through journal entry adjustments • Implement a process to review non-EE employees’ time on a regular basis going forward • Update the Time Charging & Cost Allocation Process Memo to detail guidance around time charging for non-EE employees and communicate to appropriate employees the time charged by the 16 non-EE employees and will enter a journal entry adjustment as appropriate for the MA and CT charges in the PowerPlan system to reverse the time charged to Energy Efficiency. [To be completed by May 31, 2026] b. Energy Efficiency management will implement a quarterly review process to review time charged by nonEnergy Efficiency employees to ensure it is appropriate. [To be completed by May 31, 2026] c. Energy Efficiency management will review the time charging memo to detail guidance around time charging for non-EE employees and communicate to appropriate employees. [To be completed by May 31, 2026] Management agrees with the recommendation and will update the Time Charging & Cost Allocation Process Memo to include the items identified in the recommendation above. [To be completed by May 31, 2026] (1.2) Review the Time Charging and Cost Allocation Process Memo and update the following items as appropriate: • Include details regarding the advisory boards and regulatory bodies involved • Further define the reallocation of program cost codes process (through journal entries or a manual Excel workbook that are sent to the regulatory bodies) • Describe the monitoring/SOX (Sarbanes Status Complete (5/28/2026)
  5. Page 160 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-084 Page 8 of 9 Audit Report # Audit Report Title (vi) 25-08 (vi) 26-07 Work Order Life Cycle Project Work Order Life Cycle Project Report Recommendations Management Responses Status Oxley) processes in place and the responsibilities of those facilitating the processes • Define acronyms • Describe when the memo was last reviewed, who performed the review, and revision history N/A – No recommendations N/A N/A N/A – No recommendations N/A N/A b. For the privileged and confidential review of the procurement organization completed on June 4, 2026, 117 total hours were spent by the Internal Audit manager and staff . Because this work was performed at the direction of legal counsel to enable the Company to prepare for the contested rate case in this docket, Internal Audit appropriately charged the 117 hours to the work order for this rate case. In response to the portion of subpart (b) of this interrogatory that asks about whether costs the Company incurred to prepare for and participate in this rate case are recoverable under Section 2 of Public Act 23-102, please see the Company’s response to OCC-438 i, and RRU-070. c. Please refer to the table below for Eversource Internal Audit Department allocated costs to CL&P for each year 2021 through 2025 and in the Rate Year. The historical values in each year 2021 through 2024 use the 2025 ESC percentages as a proxy to estimate Internal Audit Department costs allocated to CL&P. $ i 2021 278,885 $ 2022 318,383 $ 2023 319,799 $ 2024 329,714 $ Rate Year 2025 340,946 $ 376,630 OCC-438 Question: Exhibit CLP-REVREQ-1 Please explain why the Company has not excluded costs associated with its participation in rate case proceedings from the revenue deficiency calculation in this proceeding. In your response, please explain how the Company's proposed treatment of such costs complies with the requirements of SB 7, An Act Strengthening Protections For Connecticut's Consumers Of Energy, concerning recovery of costs associated with participation in rate case proceedings. OCC-438 Response:
  6. Page 161 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-084 Page 9 of 9 The Company has not removed costs associated with the preparation and participation in this rate case proceeding from the revenue deficiency calculation as these costs are necessary operating costs ensuring that rates are set at a just and reasonable level to enable the ongoing investment into the system to maintain a safe and reliable electric system, benefiting customers. As such, these costs are appropriately recovered from customers and are therefore included in the Company’s proposed revenue deficiency. In this regard, the Company plans to provide legal argument on the plain language of the statute at the appropriate juncture in this proceeding. In the meantime, the Company plans to submit to the record the documentary support necessary to support recovery of the costs. The Company justifies its recovery for costs associated with the preparation and participation in this rate amendment proceeding as prudently incurred and normal operating costs to litigate this rate amendment application. The Company is entitled to a reasonable opportunity, but not a guarantee, to recover its operating costs and maintain its credit integrity. Further, the Company should be allowed to demonstrate that the costs incurred to adjudicate this rate case proceeding are just and reasonable and affording PURA the opportunity to set equitable rates and establish innovative rate mechanisms and programs for the benefit of our customers.
  7. Page 162 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-085 Page 1 of 2 Date Filed: October 13, 2026 Witness: Sasha Lazor Request from: Public Utilities Regulatory Authority Question: (COMPENSATION BENCHMARKING) Lazor, Eichler and O'Connor Pre-Filed Test., pp. 2129; Interrog. Resp. OCC-193, Atts. 1-8 and Interrog. Resp. OCC-195. Regarding the market position reported for CL&P and EESCO compensation: a. Identify the data relied upon for each benchmarked year in Tables 3 through 7 before 2024. State how the Company verified the reported market position for each of those years without the survey data, which the response to Interrogatory OCC-193 states is retained for two years. b. Provide the Company's position-matching output derived from the Willis Towers Watson surveys, including the peer set, the matching methodology, the data effective dates, and the resulting market percentile for each benchmarked position. c. For each employee group, provide actual total compensation against the market median in dollars and as a percentage. Distinguish base pay from each variable component and from benefits. Reconcile the total cash compensation position for CL&P shown in Table 3 as negative 0.09% with the narrative description of 99.1%. d. Provide turnover data for each calendar year from 2021 through 2025 by union, exempt and non-exempt classification and by department, distinguishing voluntary resignations, retirements and involuntary separations. Provide any workforce, staffing, succession or organizational study supporting the requested staffing complement. Response: a. As described in CLP-EMPLOYEE-1, p. 18, Eversource partners in the compensation benchmarking process with Willis Towers Watson (“Towers Watson”), which is a global human resources consulting firm. Towers Watson assists Eversource in setting competitive salary ranges and variable pay levels, so that compensation levels at Eversource remain competitive with other employers in the marketplace. As such, we have participated in their surveys for many years. Therefore, Eversource utilized Towers Watson surveys prior to 2024. Survey data is no longer current after two years which is why it is not retained. b. Please refer to RRU-085, Attachment 1, through RRU-085, Attachment 3, which provide more detailed information on Towers Watson Survey methodology and participant list.
  8. Page 163 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-085 Page 2 of 2 c. Please refer to RRU-085, Attachment 4, which provides total compensation vs the market the market median, as downloaded from our Workday HRIS system. This exhibit compares current base salaries along with market variable compensation (at median). Section (b) requests that data be presented as a “market percentile”. Our current methodology is to present compensation elements as a “percent of market”, such as the 99.1% referenced is question (c). d. Please refer to RRU-085, Attachment 5, for turnover information. Please note, turnover data by department is not readily available. The Company will endeavor to provide the requested data as soon as practicable. The Company conducts workforce planning on an annual basis to in support of budget preparation. This review considers turnover and retention, incremental staffing needs, skills needed and organizational structure.
  9. Page 164 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-086 Page 1 of 5 Date Filed: October 19, 2026 Witness: Donald J. Scacco Jr., Digaunto Chatterjee, Douglas P. Horton, Brendan J. O'Brien, Garrett J. Murray and Julia Frayer Request from: Public Utilities Regulatory Authority Question: (UNIT COST) Application, Sch. G-2.14 and Ex. CLP-PBR-3; Interrog. Resp. EOE-123, Att. 1. Regarding the compensation and staffing levels measured on a unit cost basis: a. For each calendar year from 2021 through 2025, the interim year and the Rate Year, provide, the number of customers, circuit miles, the year-end full-time equivalent count, total operating and maintenance expense, total compensation expense, and total payroll expense. b. For each calendar year from 2021 through 2025, provide an exhibit that shows customers per full-time equivalent, circuit miles per full-time equivalent, total compensation per customer, operating and maintenance expense per customer, and payroll expense per customer. c. Provide the average of each ratio for 2021 through 2025 and compare the Test Year and Rate Year values to that average. Explain each variance exceeding five percent. d. Reconcile the Test Year and Rate Year operating and maintenance cost per customer to the finding in Exhibit CLP-PBR-3 that operating and maintenance cost per customer averaged 22.9% above the industry average. Response: a. Please refer to RRU-086, Attachment 1, for the requested data for historical years 2021-2025, and Rate Year data elements. Historical data has been provided for: • # of Customers (12-month Average) – Previously provided in response to CIEC-010 i; • # of Line Miles (as of December 31st) – Data from Form 10-K, Item 2. Properties; • Year-End Full Time Equivalent (FTE) Count – The FTE Count provided in this response is for CL&P Distribution; previously provided in OCC-042, Attachment 1; • Core Operating Expenses ($K) – Core Operating Expenses excludes expenses recovered separately or not subject to management annual control; previously provided in OCC-432, Attachment 1;
  10. Page 165 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-086 Page 2 of 5 • Total Compensation Expense ($K) – The Company defines Total Compensation Expense as Payroll Expense plus Variable Compensation plus Employee Benefits. Previously provided as part of Exhibit CLP-REVREQ-3, lines 21, 22, 23 and 28; • Total Payroll Expense ($K) – Previously provided as part of Exhibit CLP-REVREQ3, line 21. Rate Year data has been provided for: • # of Customers – Previously provided in OCC-514, Attachment 1. • Year-End Full Time Equivalent (FTE) Count – Sum of 2025 YE plus CLP incremental FTEs as provided in OCC-333, Attachment 1; • Total Compensation Expense ($K) and Total Payroll Expense ($K) – Previously provided in Exhibit CLP-REVREQ-2, lines 22, 23, 24, and 29 of Schedule C-3.0. The Company does not have the requested data for the remaining Rate Year data elements and Interim Year data. The Company does not forecast these data points and does not necessarily agree that all of the computations and comparisons set forth herein are generally reliable indicators of performance or operational trending. b. Please refer to RRU-086, Attachment 1, for the following ratios for 2021-2025: Customers per FTE; Line Miles per FTE; Core Operating Expenses per Customer (previously provided in OCC-432, Attachment 1); Total Compensation Expense per Customer; and Total Payroll Expense per Customer. c. Please refer to RRU-086, Attachment 1, for the 5-year average of all data and ratios provided for subparts (a) and (b). Regarding variances between the 5-year average ratios and the Test Year (2025 YE) ratios, those variances are provided in the referenced attachment and are generally within five percent. Total Compensation Expense per Customer and Total Payroll Expense per Customer are slightly outside the 5.0% variance at 5.1% and 5.6% respectively. The primary driver for these variances is a function of the fact that the 5-year averages are lower due to variation in 2022 actuals for Total Payroll Expense and Total Compensation Expense. The 2022 Total Compensation Expense per Customer ratio is 26% lower than the 5year average and the 2022 Total Payroll Expense per Customer ratio is 10% lower than the 5year average. For Total Compensation Expense ($K), the primary driver is the Employee Benefits reported for 2022 (Line 28 of Exhibit CLP-REVREQ-3). The Company provided an explanation of the variances for expenses between 2022 and 2025 in OCC-069 Attachment 1.

As listed on the current system

Corres. 11/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

This filing on the current system (opens in a new tab)