Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

Files9

Search terms highlighted
Eversource rate increase is on 89 pages across 5 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
2 pages match

Text of ALLCO Set 18_COMBINED.pdf

Extracted from the file · 25 pages · 65,407 characters

Text of CIEC Set 7_COMBINED.pdf

Extracted from the file · 7 pages · 8,262 characters

Text of DEEP Set 1 (BETP)_COMBINED.pdf

Extracted from the file · 174 pages · 446,641 characters

Text of NECTA Set 6_COMBINED.pdf

Extracted from the file · 22 pages · 43,545 characters

Text of OCC Set 29_COMBINED.pdf

Extracted from the file · 30 pages · 65,312 characters

35 pages match
  1. Page 33 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-051 Page 8 of 11 Recent meteorological data reviewed by the Company provides additional context for these observed operational trends. UtiliWeather analyzed four wind-profile parameters over a recent five-year period: average mean sustained winds, average maximum sustained winds, average mean wind gusts, and average maximum wind gusts. UtiliWeather found increasing linear trends across these wind parameters, with sustained winds exhibiting a modest increase and wind gusts exhibiting a somewhat more robust increase over the period analyzed. While the five-year period is not, standing alone, sufficient to establish a long-term climatological trend, these observations provide additional recent meteorological context that is consistent with the Company’s operating experience and the longer-term regional climate information discussed above.
  2. Page 34 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-051 Page 9 of 11
  3. Page 35 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-051 Page 10 of 11 A look at the average amount of daily outage events also indicates a clear increase that the system is seeing increased outage activity on a daily basis.
  4. Page 36 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-051 Page 11 of 11 At the same time, this operating trend, standing alone, does not necessarily prove that weather systems have become stronger or that climate change is responsible for any particular outage. Electric-system impacts are affected by multiple variables, including weather, vegetation, antecedent environmental conditions, infrastructure exposure and system configuration. Accordingly, the Company’s operating data are appropriately considered together with, rather than as a substitute for, independent meteorological and environmental information. Relationship to System Resilience An increase in operationally significant weather impacts should also not be interpreted, by itself, as evidence of declining system resilience. Reliability and resilience investments can reduce the consequences of weather events, but they do not eliminate the underlying exposure of an overhead distribution system to weather and vegetation. In fact, system-impact data reflect the combined effect of the hazard to which the system is exposed and the system’s ability to withstand and recover from that hazard. For that reason, it is important to evaluate the trend in system impacts together with independent evidence regarding changes in the external environment rather than attempting to infer either weather severity or system resilience solely from outage counts. This is also consistent with the broader treatment of infrastructure risk in the Fifth National Climate Assessment, which recognizes that additional climate-related loads and stressors can interact with infrastructure and its operational constraints to produce cascading impacts. Conclusion Weather, vegetation, antecedent environmental conditions and electric-system impacts are interrelated and changes in outage activity cannot reasonably be attributed to any single variable. However, in addition to the Company’s actual operational experience, multiple independent lines of evidence point in the same general direction. Scientific assessments document changes in Connecticut and the Northeast’s climate, including increases in heavy precipitation and other extreme-weather characteristics relevant to electric infrastructure. Connecticut-specific observations demonstrate changing precipitation patterns, while broader assessments identify increasing risks to infrastructure from extreme weather. Those weather conditions interact with Connecticut’s vegetation and antecedent environmental conditions, meaning that similar meteorological events do not necessarily produce similar electric-system impacts. Added to this context, the Company’s own operating experience demonstrates an increasing frequency of days on which weather-related impacts are significant enough to exceed approximately 100 outage events and require the Company to begin adjusting its normal operating posture. Recent meteorological data reviewed by the Company also identifies increasing trends in sustained winds and wind gusts over the five-year period analyzed, with the increase in wind gusts being somewhat more pronounced Viewed collectively, this data provides a more complete picture than any individual measure could provide: the weather and environmental conditions affecting Connecticut are changing; those conditions can increase the stresses placed on an overhead electric distribution system; and the Company is experiencing an increasing frequency of operationally significant weather-related system impacts. Accordingly, the Company’s statement is made on the basis of the increasing frequency and operational severity of weather-related impacts experienced by the Company’s electric system, considered in the context of independent scientific evidence documenting changes in the weather and environmental conditions affecting Connecticut.
  5. Page 37 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-052 Page 1 of 3 Date Filed: October 09, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray and Erin M. Travassos Request from: Public Utilities Regulatory Authority Question: (TEMPORARY STAFFING) Interrog. Resp. OCC-309, Att. 1, Interrog. Resp. OCC-321, Att. 2, and Interrog. Resp. OCC-359, Att. 1. Regarding temporary and contract staffing costs and its treatment in the cost of service: a. OCC-359, Attachment 1, provides a Rate Year temporary help amount of $1,158,401 which the Company states in response to OCC-321 is not reflected in payroll expense. Identify each schedule and line on which any portion of the $1,158,401 is recorded and the amount on each. b. OCC-359, Attachment 1, equals the operating and maintenance line of OCC-321, Attachment 2 for each of calendar years 2021 through 2025. State whether Allegis Global Solutions and Randstad are the only temporary staffing vendors. Identify other temporary staffing vendors and the amount paid to each vendor in each of calendar years 2021 through 2025. Identify the schedule and line on which the capital and other portion of temporary staffing is recorded. c. State the services provided by Allegis Global Solutions and the basis for recording $179,046 paid in 2025 as outside legal counsel expense in OCC-309, Attachment 1, and for including $94,338 in the Rate Year. Response: a. Please refer to the table below identifying the schedules that include portions of the $1,158,401 of Rate Year temporary staffing expenses. Schedule Reference C-3.3 Bank Fees and Debit Service Charges C-3.8 Computer Services C-3.9 Corporate Communications C-3.10 Customer Services C-3.12 Employee Benefits C-3.16 Field Operations OHL C-3.17 Field Operations UGL C-3.18 Human Resources C-3.20 Legal C-3.33 O&M Residual Rate Year Amount $7,416 $180,403 $5,788 $109,611 $10,767 $422,069 $113 $40,575 $190,584 $191,074
  6. Page 38 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-052 Page 2 of 3 Total $1,158,400 Please note as the costs associated with temporary help are embedded in multiple SFRs utilizing different methodologies to estimate the Rate Year level of costs, therefore, the Company used GDP-PI as a proxy to estimate the amount included in the Rate Year. b. Allegis Global Solutions and Randstad are the only two temporary staffing vendors, as explained in the Company’s response in EOE-125 i. c. The $179,046 represents costs paid in the 2025 Test Year for legal support including coverage for an Eversource attorney that transitioned to part-time employee status, and coverage for an Eversource attorney on authorized medical leave. The Company included 52% of the Test Year expense (which is $94,338) in the Rate Year because legal support will continue to be needed in the Rate Year to provide coverage for a part-time attorney and other additional legal support. Prior Referenced Response: i EOE-125 Question: (EXTERNAL STAFFING) Provide an unlocked Excel spreadsheet detailing the Company’s ‘external’ average staffing levels for each year starting from 2018 through present, along with the overall gross costs. To the clear, this request is looking to identify the roles, counts, applicable external vendors, costs, and any other relevant details that could assist in minimizing follow-up interrogatories. This request is applicable to all types of external staffing including, but not limited to, vendors supporting line crew activities, customer service activities, IT development activities, etc. EOE-125 Response: The Company began tracking external staffing counts on a systematic, reportable basis starting in 2023. As a result, the system has data as of December 2023, and December 2024 and then by month starting in 2025 and 2026. Please refer to EOE-125, Attachment 1, for a headcount by Business Area using the respective December counts. Please note that external staffing counts are not associated with a specific operating company. Therefore in EOE-125, Attachment 1, the Company provides the requested data in relation to any business area that could potentially support CL&P. This includes Shared Services Organizations such as CFO and Customer Group, as well as operational organizations such as Engineering and Safety, Training, and Fleet. “External Staffing” referenced above is generally held to mean short-term temporary staffing that can include administrative/clerical, accounting/financial, technological, and project support. External staffing is hired through staffing agencies (i.e., temp agencies) or can been contracted directly with firms. During the period requested, the Company had two outside vendor companies that acted as staffing agencies, Randstad and Allegis Global Solutions. During the requested period, the Company directly contracted with 30 outside vendor companies. These vendors are Burns & McDonnell, TRC Engineers, Progressive Global Energy, United Utility Power Services, CHA Consulting, Capital Staffing Solutions, Leidos, RLC Engineering, Plant Forward Energy Services, Qualus, Ironhouse, Qualus
  7. Page 39 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-052 Page 3 of 3 Consulting, AI Engineers, ESPii, EN Specialty Services, PMA Consultants, Watkins Strategies, Airswift, WunderlichMalec, Power Engineers, Cascade, RCM Technologies, Global Technical Talent, Shermco Industries, EPST-A Voltyx Company, Parsons, Asplundh Engineering Services, BHI Energy, Saybrook Associates Inc., and Control Point Technologies. The Overhead Line Department has kept internal reporting on counts for CL&P Distribution Overhead Line crews, as shown in EOE-125, Attachment 2. This includes headcounts by vendor with the averages from 2018 to June 2026. The Company does not track staffing counts for any other types of Contractors. “Contractors” are vendors used to supplement the Company’s internal work force for specific functions and projects to respond to the increase of work during peak need times including the seasonal demand of the work plan, repairs, and project management. The gross costs on all Outside Services are included in EOE-125, Attachment 3, including all Outside Services provided to the Company by vendor. This includes the External Staffing, CL&P Overhead Line Crews and all other Contractors, as described above.
  8. Page 40 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-053 Page 1 of 4 Date Filed: October 16, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray and Danielle Munson Request from: Public Utilities Regulatory Authority Question: (EESCO CAPITAL FUNDING) O'Brien and Murray Pre-Filed Test., pp. 83-84; Application, Sch. WP C-3.11; Interrog. Resp. OCC-373. Regarding the EESCO capital funding reflected in Schedule C-3.11 and the return on equity applied: a. Provide (1) the weighted average of the Eversource operating companies' return on equity as calculated in January of each of the years 2021 through 2026 and (2) the allowed return of each operating company used, the allocation methodology, and the plant balances used as weights. b. The Company’s response to Interrogatory OCC-373 states that EESCO charges billed to CL&P in the Rate Year will be based on the weighted average of the Eversource operating companies’ return on equity. Provide an exhibit that shows Schedule C-3.11 recomputed on that basis for the Test Year pro forma and the Rate Year. State the basis for filing a schedule that does not reflect the return the Company states will be billed. c. Provide the capitalized proportion of EESCO capital funding for each of calendar years 2021 through 2025. d. Identify the EESCO capital projects on which the Rate Year charge is based and for each capital project, provide in an unlocked Excel spreadsheet the (i) plant balance, (ii) in-service date, and (iii) amount allocated to CL&P. e. Identify the FERC account to which the reference 930RAX on Schedule WP C-3.11 corresponds. Response: a. Please refer to RRU-053, Attachment 1, for 2021 return on equity calculation, RRU-053, Attachment 2, for 2022 return on equity calculation; RRU-053, Attachment 3, for 2023 return on equity calculation; RRU-053, Attachment 4, for 2024 return on equity calculation; RRU-053, Attachment 5, for 2025 return on equity calculation; and RRU-053, Attachment 6, for 2026 return on equity calculation. b. Please refer to RRU-053, Attachment 7, for Schedule C-3.11 recomputed reflecting the 2026 weighted-average Eversource operating company return on equity for the Test Year pro forma and the Rate Year.
  9. Page 41 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-053 Page 2 of 4 The premise that Schedule C-3.11 should reflect the weighted-average Eversource operating company return on equity rather than CL&P's proposed return on equity is misplaced. The weighted-average return used by EESCO is an administrative costallocation mechanism designed to allocate service company costs among affiliate utilities. It is not a determination of the cost of equity applicable to CL&P, nor is it intended to establish CL&P's authorized return for ratemaking purposes. Schedule C-3.11 appropriately reflects CL&P's proposed return on equity of 10.25%, which is the return the Company seeks authorization to earn in this proceeding based on the evidence presented in its cost of capital testimony. The fact that EESCO bills capitalrelated costs using a weighted-average return derived from multiple operating companies does not change the return required by investors to provide capital to CL&P and therefore does not provide an appropriate basis for establishing CL&P's revenue requirement. Moreover, the weighted-average EESCO return is inherently dependent on the existing authorized returns of the various affiliated operating companies and therefore does not necessarily reflect current capital market conditions or contemporaneous regulatory determinations. Because CL&P is presently the only Eversource operating company seeking updated rates, the weighted-average EESCO return reflects legacy authorized returns for other affiliates rather than a current assessment of the cost of equity. The existence of those historical returns does not diminish or modify the return on equity that is appropriate for CL&P in this proceeding. As explained in response to OCC-373 i, EESCO makes capital investments on behalf of the operating companies it serves. The costs of those investments are ultimately borne by utility customers because the investments support utility operations and functions that would otherwise need to be performed directly by each operating company. Had CL&P made these investments directly and recorded the associated assets in its own rate base, those assets would earn CL&P's authorized return on equity in the same manner as any other utility investment. Accordingly, reflecting CL&P's proposed 10.25% return on equity in Schedule C-3.11 appropriately recognizes the economic substance of the investment and provides the proper basis for establishing the Company's revenue requirement in this proceeding. The service company structure is intended to achieve efficiencies and economies of scale by centralizing functions, personnel, systems, and technology investments that would otherwise need to be duplicated across multiple operating companies. The relevant regulatory question is therefore not whether EESCO bills using a weighted-average return on equity, but whether the underlying investments support utility operations and provide benefits to CL&P customers. They do. Recomputing Schedule C-3.11 using the weightedaverage EESCO return would substitute an administrative allocation convention for the Company's actual cost of equity and would fail to reflect the return associated with
  10. Page 42 of 230

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-08 Date Issued September 25, 2026 RRU-053 Page 3 of 4 comparable investments had those same assets been owned directly by CL&P. Indeed, absent the service company model, CL&P would be required to make many of these investments itself, resulting in additional standalone costs and operational duplication. The service company structure therefore produces a lower-cost and more efficient means of providing these capabilities while preserving the fundamental economic reality that the investments are made for the benefit of, and ultimately support service to, CL&P customers. c. Please see the below table for the capitalized proportion of EESCO capital funding for each of calendar years 2021 through 2025: EESCO Capital Funding - Capitalized Portion 2021 4,373,292 2022 6,041,810 2023 6,531,398 2024 4,961,042 2025 5,093,797 d. The Company is pursuing the necessary details and will supplement this response as soon as the information is available. e. The reference to “930RAX” is denoting the specific FERC Account. As outlined in Title 18, Chapter I, Subchapter C, Part 101 of the Code of Federal Regulations, Federal Energy Regulatory Commission (“FERC”) Account No. 930.2 Miscellaneous general expenses, compensation for the use of capital is recorded to this account as it is the cost from the shared services company incurred in the general management of the utility not provided for elsewhere. Prior Referenced Response: OCC-373 Question: ESC Capital Funding. to Exhibit CLP-REVREQ-1, page 83 lines 1-21 through page 84 lines 1-2 and lines 11-15. i a. b. Explain why the Company replaced the weighted average of Eversource operating companies ROE with the Company's proposed ROE in this case. Confirm that the ESC charge billed to CL&P in the rate year will be based on the weighted average of Eversource operating companies ROE.

As listed on the current system

Corres. 11/06/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation ALLCO Set 13, 16, 18, CIEC Set 7, DEEP Set 1, NECTA Set 6, OCC Set 29, PURA 8

This filing on the current system (opens in a new tab)