  1. Page 96 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-415 Page 2 of 3 via written lists, emails, texts or phone calls and work to address issues in an efficient manner. Reviewing the associated work locations, the Company Arborist may have approved the use of the chipper and chip truck on January 8-9, 2024, and January 11-12, 2024, due to the roadside topography of the properties, limited drop zone areas available, and roadside snow load at the time of mitigation. This would have required storm debris to be placed in the roadway, resulting in a public safety hazard, or introduced risk to the tree crew’s safety. The total incremental amount associated with the disk chipper and chip truck is $1,010.52. Please note that these charges are itemized directly on the invoice. Please refer to Exhibit ACCT-2 (CLP-1A-15)(MS24A), at page 53. c. Please refer to the response to EOE-231 i, (emphasis added): It is an established practice for contractor tree crews to bill for larger chainsaws during storm restoration activities. The use of larger-bar chainsaws when removing large-diameter trees improves operational efficiency and enhances worker safety by allowing the work to be performed quicker and with less risk to the operator. The chainsaws billed on the referenced invoices are larger than the standard chainsaws provided on each bucket truck, consistent with the applicable contract provisions. Because tree crews cannot determine the size and removal requirements of a tree until they arrive at the work location, requiring a separate trip to obtain a larger chainsaw could delay restoration efforts and result in additional travel costs. Pre-authorization for utilizing a larger chainsaw during storm-response activities is not required as it is an established practice. Requiring pre-authorization would hinder storm restoration activities as the tree crew would not know that a larger chainsaw was needed until they arrived at the outage location and evaluated the situation. If a larger chainsaw was required, the tree crew would need to leave the outage event, drive to a centralized location where chainsaws would be stored, select and inspect the chainsaw, and drive back to the outage event before the tree crew was able to start their job briefing and perform the associated tree work. Pre-authorization to utilize larger chainsaws would not be operationally efficient or beneficial to our customers. The total incremental amount associated with the larger chainsaws is $80.91. Please note that these charges are itemized directly on the invoice. Please refer to Exhibit ACCT-2 (CLP-1A-15)(MS24A), at page 58. Prior Referenced Response:
  2. Page 97 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-415 Page 3 of 3 EOE-231 Question: i (MS24A-VENDOR-TREE) Refer to Exhibit ACCT-2 CLP-1, and Confidential Exhibits ACCT-2 CLP-1A-15 through CLP-1A-16, Rows 373-376, 393. The Company reported various incremental charges for the Lewis Tree Service Inc vendor. Each of the invoices included billing for extra chainsaws. Identify if the extra chainsaws were pre-authorized by the Eversource arborist and identify the total incremental amounts. If pre-authorization occurred, please provide documentation, along with explanations for why the extra equipment was necessary. EOE-231 Response: It is an established practice for contractor tree crews to bill for larger chainsaws during storm restoration activities. The use of larger-bar chainsaws when removing large-diameter trees improves operational efficiency and enhances worker safety by allowing the work to be performed quicker and with less risk to the operator. The chainsaws billed on the referenced invoices are larger than the standard chainsaws provided on each bucket truck, consistent with the applicable contract provisions. Because tree crews cannot determine the size and removal requirements of a tree until they arrive at the work location, requiring a separate trip to obtain a larger chainsaw could delay restoration efforts and result in additional travel costs. Accordingly, billing for a larger chainsaw is permitted for the entire shift when utilized, as that equipment resource is dedicated to the assigned crew and is therefore unavailable for use on other work during that period. The associated chainsaw charges were reviewed and approved by the Eversource Arborist through the timesheet approval process, confirming that use of the equipment was appropriate for the work performed.
  3. Page 98 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-416 Page 1 of 4 Date Filed: October 27, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Response to EOE-239, Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 100-151. Respond to the following: a. Provide a redacted version of the referenced documentation. b. Referring to subsection ‘a’ and pp. 118-121 and pp. 134-136, explain why the vendor was permitted to submit Eversource Contractor Storm Daily Time & Work Reports without completing any Event Start Times (box 24) and Event End Times (box 25). c. Referring to subsection ‘a’ and pp. 118-121 and pp. 134-136, explain how the “number of tickets and the various locations and the various locations that these crews had to travel to and from” would support the hours billed. As part of the response, please provide copies of OMS tickets or other documentation and demonstrate how this information verifies the accuracy of the hours billed for each vendor employee. d. Referring to subsection ‘b’, and p. 150-151, clarify the Company’s response where the Company referenced “4 hours of travel” for the referenced example but the documentation depicts 6.5 hours. Does the increased number of hours billed for mobilization change the Company’s position? Response: a. Please refer to the Redacted Bulk Material filed on September 1, 2026 as Supplement for New Applications to locate the redacted Exhibit CLP-STORM-ACCT-2(CLP-1A17)(MS24A). b. Boxes 24 and 25 should have been filled out. However, the reviewer was able to independently verify the reported start time of 6:00 a.m. from the documentation submitted and confirm the reported end time of 12:30 p.m. through Eversource’s original response to EOE-239 i, subpart (a). Because the Timesheets contained sufficient information and evidence to validate the hours worked, the reviewer determined that the omission of Boxes 24 and 25 did not deprive the Company of information necessary to substantiate the claimed work time and the Company therefore approved the invoice. c. Please refer to EOE-416, Attachment 1 for the events that were covered by Midcon during the MS24A event. These crews covered events inside the Norwalk Area Work Center
  4. Page 99 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-416 Page 2 of 4 ranging well within the times that their timesheet specified. The crews did not complete their final work assignment until 1:09pm on 1/10/2024. After cleaning up the work site, this lines up with their time sheet end time. d. Please refer to EOE-239-RV01 ii. There was an error in the Company’s response and 4 hours should have been typed as 6.5 hours. Prior Referenced Responses: i EOE-239 Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 100151. The Company reported an incremental charge of $1,285,629 for the Midcon Energy Services Inc vendor. The charge applies to travel (i.e., mobilization and demobilization), standby, and work. Respond to the following: a. b. c. d. Referring to pp. 118-121 and pp. 134-136, explain why the vendor was permitted to submit Eversource Contractor Storm Daily Time & Work Reports without completing any Event Start Times (box 24) and Event End Times (box 25). As part of the response, explain how the Company was able to verify the accuracy of the reported travel time (box 10), standby time (box 11), and work time (box 12). Referring to p. 150-151 (as a 1st example), explain why the vendor was permitted to bill for 6.5 hours of mobilization from Beacon Falls CT to Windsor CT and four hours for demobilization when that commute would typically take less than 1 hour, or less than 1.5 hours after applying a 1.3 factor increase. As part of the response, provide any communication between the Company and the vendor that occurred prior to the approval of the invoice substantiating the travel hours billed. Referring to p. 137-138 (as a 2nd example), explain why the vendor was permitted to bill for four hours of demobilization from Norwalk CT to Windsor CT when that commute would typically take less than 1.5 hours, or less than 2 hours after applying a 1.3 factor increase. As part of the response, provide any communication between the Company and the vendor that occurred prior to the approval of the invoice substantiating the travel hours billed. Referring to pp. 101-105, provide the information within an unlocked Excel spreadsheet and supplement each of the travel hours billed to the Company (i.e., mobilization on 1/9/24, travel on 1/10/24, and demobilization, on 1/10/24) with details for the starting and ending locations, the number of miles between the two locations, and provide any communication between the Company and the vendor that occurred prior to the approval of the invoice substantiating the travel hours billed. EOE-239 Response: a. The Company confirmed that this crew arrived onsite for their first shift on 01/10/2024 at 6:00am. These crews traveled from Windsor, CT to their first location, which was to Norwalk, CT confirming that the stated travel time of 2 hours was well within the approved travel time. There was no standby time submitted on these timesheets. Based on the number of tickets and the various locations that these crews had to travel to and from, the 6.5 hours of working time would be appropriate and was therefore approved. b. The Mobilization timesheets from Beacon Fall, CT to Windsor, CT were submitted at 4 hours of travel. This travel did occur during rush hour traffic and it was communicated via the Mobilization timesheet that they
  5. Page 100 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-416 Page 3 of 4 encountered trouble locating hotels to accommodate the large contingent and then drove to East Granby, CT to be on standby. Based on these conditions and the time of day, the number of travel hours was not considered excessive and was therefore approved. c. The Demobilization timesheets were from Hartford, CT to Beacon Falls, CT which would allow for an acceptable travel time of 1.5 hours. Communication was received during the Demobilization travel that these crews encountered a major traffic accident during the travel home and therefore the 4 hours of travel were approved. d. Please refer to EOE-239, Attachment 1, for requested travel breakdown. There were no additional discussions with the Contractor regarding travel during the invoice review process. All hours were considered acceptable and were therefore approved. Please note that the travel mileage was not captured for timesheets under the working tab because crews traveled between multiple work locations during their shifts. Although mileage was not separately tracked within the timesheet, the invoice review process included an assessment of the work locations to validate the travel incurred. Based on that review, the travel charges were found to be consistent with the locations where the work was performed. Included in the referenced attachment are the job locations and the total number of work assignments. ii EOE-239-RV01 Question: (MS24A-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 100151. The Company reported an incremental charge of $1,285,629 for the Midcon Energy Services Inc vendor. The charge applies to travel (i.e., mobilization and demobilization), standby, and work. Respond to the following: a. b. c. d. Referring to pp. 118-121 and pp. 134-136, explain why the vendor was permitted to submit Eversource Contractor Storm Daily Time & Work Reports without completing any Event Start Times (box 24) and Event End Times (box 25). As part of the response, explain how the Company was able to verify the accuracy of the reported travel time (box 10), standby time (box 11), and work time (box 12). Referring to p. 150-151 (as a 1st example), explain why the vendor was permitted to bill for 6.5 hours of mobilization from Beacon Falls CT to Windsor CT and four hours for demobilization when that commute would typically take less than 1 hour, or less than 1.5 hours after applying a 1.3 factor increase. As part of the response, provide any communication between the Company and the vendor that occurred prior to the approval of the invoice substantiating the travel hours billed. Referring to p. 137-138 (as a 2nd example), explain why the vendor was permitted to bill for four hours of demobilization from Norwalk CT to Windsor CT when that commute would typically take less than 1.5 hours, or less than 2 hours after applying a 1.3 factor increase. As part of the response, provide any communication between the Company and the vendor that occurred prior to the approval of the invoice substantiating the travel hours billed. Referring to pp. 101-105, provide the information within an unlocked Excel spreadsheet and supplement each of the travel hours billed to the Company (i.e., mobilization on 1/9/24, travel on 1/10/24, and demobilization, on 1/10/24) with details for the starting and ending locations, the number of miles between the two locations, and provide any communication between the Company and the vendor that occurred prior to the approval of the invoice substantiating the travel hours billed. EOE-239-RV01 Response: There was an error in the number of hours typed (4 hours vs. 6.5) in the original response to EOE-239 part b. The response should have stated the following:
  6. Page 101 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-416 Page 4 of 4 The Mobilization timesheets from Beacon Fall, CT to Windsor, CT were submitted at 6.5 hours of travel. This travel did occur during rush hour traffic and it was communicated via the Mobilization timesheet that they encountered trouble locating hotels to accommodate the large contingent and then drove to East Granby, CT to be on standby. Based on these conditions and the time of day, the number of travel hours was not considered excessive and was therefore approved.
  7. Page 102 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-417 Page 1 of 2 Date Filed: October 27, 2026 Witness: Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M. Landry Request from: Office of Education, Outreach, and Enforcement Question: (MS24A-VENDOR-LINE) Refer to Response to EOE243, Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pp. 238-301. Referring to subsection ‘d’, the Company’s response deduced that there was a clerical error with the hours reported on pp. 274275 but asserted that there was no duplicate billing. The Company also referenced its review of the “State Resource Acquisition’s Report and confirmed that this crew did arrive on site at 6PM.” Provide the referenced report that was contemporaneously available to the invoice reviewer and explain how this report can be relied upon in lieu of the signed Eversource Contractor Storm Mobilization & Demobilization Time Report. As part of the response, identify the incremental impact of the two hours billed. Response: In reference to the Company’s response to EOE-243, Exhibit ACCT-2 CLP-1 and Confidential Exhibit ACCT-2 CLP-1A-17, pages 238-301, specifically subsection (d), Eversource's review confirmed that the discrepancy identified on pages 274-275 was the result of a clerical error in the reported hours and that no duplicate billing occurred. The response further referenced the reviewing team's use of the “State Resource Acquisition Report” to confirm that the crew arrived on site at 6:00 p.m. The reviewer and drafting team cited this document in error. The “State Resource Acquisition Report” is not a formal report; rather, it is an interactive spreadsheet utilized by multiple groups as a communication and coordination tool during storm response operations. The information reviewed in connection with the invoice dispute was the portion of the interactive spreadsheet that mirrors the resource information maintained in Arcos. Arcos contains the official resource management records and confirms the crew's arrival time of 6:00 p.m. As previously stated, members of the State Resource Acquisition team are responsible for communicating with crews regarding arrival times, crew status, and other operational details. That information, together with hiring and deployment details, is used by Eversource personnel to populate and maintain the Arcos records. Accordingly, the Arcos records served as the source data relied upon during the invoice review and approval process. Because the data reflected in the interactive spreadsheet is derived from
  8. Page 103 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-417 Page 2 of 2 and consistent with the Arcos records, the arrival time documented in Arcos was appropriately relied upon to validate the invoice. Therefore, the Arcos records provided a reliable basis for invoice review and approval, notwithstanding the absence of a signed Eversource Contractor Storm Mobilization & Demobilization Time Report.
  9. Page 104 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-418 Page 1 of 2 Date Filed: October 27, 2026 Witness: Brendan J. O’Brien, Garrett J. Murray, Leanne M. Landry and Jeffrey D. Turano Request from: Office of Education, Outreach, and Enforcement Question: (EMERGENCY RESPONSE SPECIALIST) Refer to Response to OCC-829. Respond to the following: a. Identify the average Emergency Response Specialist staffing levels for each year 2021-present. b. Provide an unlocked Excel spreadsheet detailing the following information for both each year 2021-2025: i. Number of Emergency Response Specialists ii. Average Base Pay iii. Average Annual Overtime Pay iv. Average Annual Premiums v. Average Overhead or Other Costs vi. Fully Loaded Labor Costs vii. Hourly Equivalent Rate Response: a. Please refer to the table below for the average Response Specialist staffing levels by year. CT Response Specialists Average Staffing Levels by Year Year 2021 2022 2023 2024 2025 2026 Avg. Staffing 123 121 125 125 125 124 b. Please refer to EOE-418 Attachment 1. Please note that this data includes both non-storm and storm pay. The hourly equivalent rates are an average rate for the year as rates get updated on
  10. Page 105 of 105

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-418 Page 2 of 2 June 1 of each year per the union contract. There are no hourly equivalent rates included for premiums because the corresponding hours are included with base pay. Also, pursuant to the collective bargaining agreement, Response Specialists are entitled to overtime as part of their normal schedules, averaging out to approximately two hours of overtime each week. Response Specialists are the highest skill workforce resource that the Company has and the Company relies on these resources heavily under both normal operating conditions and storm response.