Discovery Compilation (PURA Set 13, EOE Set 8)
Files3
Docket No. 26-05-10 Discovery Compilation November 16 2026.pdf
PDF · 133 KB · 1 pageText searchable
Download Docket No. 26-05-10 Discovery Compilation November 16 2026.pdfRead the text of Docket No. 26-05-10 Discovery Compilation November 16 2026.pdf
EOE Set 8_COMBINED.pdf
PDF · 1012 KB · 105 pagesText searchable
Download EOE Set 8_COMBINED.pdfRead the text of EOE Set 8_COMBINED.pdf
PURA Set 13_COMBINED.pdf
PDF · 1.5 MB · 144 pagesText searchable
Download PURA Set 13_COMBINED.pdfRead the text of PURA Set 13_COMBINED.pdf
Page 7 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-379 Page 2 of 5 Prior Referenced Responses: i EOE-093 Question: (HARDSHIP) Describe the process(es) that the Company uses to educate customers regarding hardship designation and associated benefits and payment arrangements. Please include copies of all material currently provided to customers regarding hardship and its corresponding payment arrangements. EOE-093 Response: The Company educates customers regarding hardship designation and associated benefits and payment arrangements in a variety of channels. For example, the Company’s communications strategy and implementation are outlined annually in the Joint Arrears Management Plan, Communication Plan in Docket No. 26-05-01, Annual Review of Affordability Programs and Offerings. See EOE-093, Attachment 1. The following outreach materials are included as attachments: Financial Hardship Letters • • • Heating w/50% low-income discount rate (“LIDR”) Welcome Letter: EOE093, Attachment 2 5%, 15%, 20%, 40% LIDR Heating Welcome Letter: EOE-093, Attachment 3 Non-Heating w/50% LIDR Welcome Letter: EOE-093, Attachment 4 5%, 15%, 20%, 40% LIDR Non-Heating Welcome Letter: EOE-093, Attachment 5 60- & 30-Day Renewal Letter: EOE-093, Attachment 6 15-Day Renewal Letter: EOE-093, Attachment 7 Expired: EOE-093, Attachment 8 • • • Welcome: EOE-093, Attachment 9 Renewal Reminder: EOE-093, Attachment 10 Expired: EOE-093, Attachment 11 • • • • • • • Initial Claim: EOE-093, Attachment 12 Welcome: EOE-093, Attachment 13 Payment Reminder: EOE-093, Attachment 14 Renewal Reminder: EOE-093, Attachment 15 2nd Reminder to Renew: EOE-093, Attachment 16 Removal: EOE-093, Attachment 17 Infant Protection Claim: EOE-093, Attachment 18 • • • • Financial Hardship Notifications Digital Medical Protection LettersPage 8 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-379 Page 3 of 5 Matching Payment Program (“MPP”) Letters • • • • • • • Welcome: EOE-093, Attachment 19 Monthly Required Payment Change: EOE-093, Attachment 20 Missed Payment Reminder: EOE-093, Attachment 21 Removal due to Financial Hardship Expiration: EOE-093, Attachment 22 Removal due to Missed Payments: EOE-093, Attachment 23 Program Reinstatement: EOE-093, Attachment 24 Program Completion: EOE-093, Attachment 25 MPP Digital Notifications • EOE-093, Attachment 26 (email and text) Connecticut Energy Assistance Program (“CEAP”) • • EOE-093, Attachment 27 (email) EOE-093, Attachment 28 (letter) Heating Assistance Awareness Month • • EOE-093, Attachment 29 (bill insert) EOE-093, Attachment 30 (email) Targeted Community Outreach Campaign • EOE-093, Attachment 31 (email) Additionally, the Company promotes hardship designation and associated benefits and payment arrangements alongside other programs, like the non-hardship payment arrangement. For customers who call the Company, the live call conversation and the up-front IVR ensure that customers, hardship and non-hardship, are educated about financial hardship benefits and payment plans. See EOE-093, Attachment 32. For the IVR, 100% of customers who contact the Company’s Credit Contact Center hear about and are prompted to prequalify for financial hardship. Lastly, the Company uses a multi-channel communication strategy, including print, digital, web, traditional, and social media, to educate customers about year-round enrollment for financial hardship status and payment arrangements. Refer to the Company’s response in EOE-094i for how non-hardship customers are educated about payment arrangements. ii EOE-094 Question: (PAYMENT ARRANGEMENTS) Describe the process(es) the Company uses to educate customers regarding nonhardship payment arrangements. Please include copies of all materials currently provided to customers regarding all non-hardship payment arrangements. EOE-094 Response: The Company educates customers regarding non-hardship payment arrangements in a variety of channels that include USPS mail, on-bill messaging, digital notifications, bill inserts, web/social media, and through in-person or virtual outreach events. Bill Messaging and Bill Inserts (included with bills):Page 9 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-379 Page 4 of 5 • • • • Programs to Help (sent monthly to residential customers from September through April). See EOE-094, Attachment 1. Your Rights: Important Information About Your Service (sent annually to all customers). See EOE-094, Attachment 2. News for You (sent daily in March and August through direct on-bill messaging). See EOE-094, Attachment 3. Get Help with your Bill (sent daily to all customers when electronic bill is ready). See EOE-094, Attachment 4. Shut-off Inserts (included with shut-off letters): • A Shut Off Notice: What You Can Do (sent year-round to residential customers). See EOE-094, Attachment 5. • Programs to Help (sent year-round to residential customers). See EOE-094, Attachment 1. • Winter Protection (sent to residential customers from November through April). See EOE-094, Attachment 6. News, Web and Social Media: • Eversource.com/billhelp (web page available to all customers). See EOE-094, Attachment 7. • Social Media Graphic (graphic available on Eversource CT social media pages). See EOE-094, Attachment 8. • Get Help Customer Update (digital newsletter sent periodically to residential customers the company has an email for). See EOE-094, Attachment 9. In-Person or Virtual Event: • Bill Help (business cards available during direct customer contact). See EOE-094, Attachment 10. • Bill Assistance (annual virtual webinar targeted to residential non-hardship customers). Link to webinar example https://www.youtube.com/watch?v=HTNIN8dBLWo • News Release. See EOE-094, Attachment 11. Please refer to the Company’s response in EOE-093i, which indicates how CL&P educates customers, including nonhardship customers, on financial hardship and payment plans. • See OCC-110, Attachment 2, for a copy of the Call Review Template that is used as a guide by the Company’s Credit Call Vendors during live call conversations to ensure that customers, hardship and nonhardship, are educated about financial hardship benefits and payment plans. • In addition, on Eversource.com, customers who log in to their account who are eligible for the Matching Payment Program are automatically provided only that option – because it is the best option for them with the lowest monthly payment amounts and arrears forgiveness. There have been several regulatory proceedings across several PURA dockets that have directed modifications in this area. The Company follows these regulatory directives on payment plans offered to non-hardship customers: • Docket No. 20-03-151: • On July 6, 2022, PURA correspondence approved the Company’s proposed commercial payment plans.2 • Docket No. 21-07-013: • PURA’s April 20, 2022, Decision4 at page 20 provided the Company with payment plan parameters in Table 3ii for non-hardship customers.Page 10 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-379 Page 5 of 5 • Docket No. 24-05-015: • PURA’s November 6, 2024, Decision6 and Order No. 2 modifies the payment required by nonfinancial hardship customers from 5%, or $25 to avoid shutoff up to 10% of a customer’s arrearage. • Docket No. 26-05-017: • See EOE-094, Attachment 12, for payment plan offerings as filed on June 1, 2026, as Joint Attachment 04: How It Works_Payment Plans.Page 11 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-380 Page 1 of 3 Date Filed: October 27, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Education, Outreach, and Enforcement Question: (ELECTRIC SYSTEM IMPROVEMENTS-ESI) Refer to Responses EOE-064 and EOE-158. Provide a discussion of the ESI’s history, to include detail on the permitted capital funding levels by year, the requirements for annual submissions, the timing of changes to revenue requirements, how excess capital funding is handled, and other relevant information. Additionally, identify any changes to the ESI that resulted from subsequent dockets or settlement agreements. Response: The ESI was part of the Settlement Agreement approved in Docket No. 17-10-46. Specifically, the Settlement Agreement stated the following for 2017 Plant Additions in Section 3 (a) (i): (1) Core Capital and System Resiliency. Gross plant additions (“Plant Additions”) of $400 million for calendar year 2017 shall be recovered in base distribution rates. If actual Plant Additions, for both core capital and system resiliency, are greater or less than $400 million, then the actual result for calendar year 2017 shall be reflected (in the form of a credit to the Company or a credit to customers, as appropriate) in a new rate tracking mechanism for capital Plant Additions and the associated O&M expense (“New Capital Tracker”). Further, the Settlement Agreement stated the following for Plant Additions in 2018, 2019, 2020 and thereafter, in Section 3 (a)(ii): (1) Core Capital. The Company’s proposed capital expenditures for “core” capital projects for calendar years 2018, 2019 and 2020, as filed in the Application, are approved. (a) Plant Additions for core capital projects of $270 million for calendar years 20182020 shall be recovered in base distribution rates. If Plant Additions for core capital projects are greater than $270 million per year for calendar years 2018-2020, then the Company shall recover “reliability” Plant Additions (which are a subset of core capital projects) for that time period through the New Capital Tracker up to the amount in excess of $270 million. (b) Plant Additions up to $300 million annually for core capital projects for the period commencing after the expiration of calendar year 2020 shall be recovered in the New Capital Tracker until the Company’s distribution rates are adjusted in itsPage 12 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-380 Page 2 of 3 next distribution rate case. Plant Additions for core capital projects in excess of $300 million during this period shall be deferred for recovery to the Company’s next rate case. (2) New System Resiliency. The Company’s proposed new system resiliency projects for calendar years 2018, 2019 and 2020, as filed in the Application, are approved. System resiliency Plant Additions for calendar year 2018 and thereafter, as filed in the Application, shall be recovered through the New Capital Tracker that shall be adjusted on a semi-annual basis commencing July 1, 2018. (a) Annual plans of proposed system resiliency work and actual after-the fact results shall be filed with PURA each November 30th and May 31st, respectively, consistent with the current approach established in the most recent system resiliency decision in Docket No. 12-07- 06RE01. (b) If the Company seeks approval and funding for any new system resiliency projects which are not currently in the evidentiary record in Docket No. 17-10-46, it must obtain prior approval for such new system resiliency projects from PURA. (3) The Company’s actual costs and collections under the New Capital Tracker will be reconciled in the Company’s annual rate adjustment mechanism (“RAM”) tracker reconciliation proceeding, which reconciles all of the Company’s tracking rates at the same time for administrative convenience (see, e.g., Docket Nos. 18-03-01, 17-03-01, 16-03-01, PURA Annual Review of the Rate Adjustment Mechanisms of The Connecticut Light and Power Company). (4) Grid Modernization. Any grid modernization Plant Additions and associated O&M approved by PURA in a separate, future docket shall also be recovered in the New Capital Tracker. Lastly, the Settlement Agreement stated the following additional provisions related to the New Capital Tracker in Section 3 (a)(iii) Miscellaneous Provisions: (1) This Settlement Agreement will not limit the Company’s management’s prerogative on necessary capital expenditures to maintain a safe and reliable system and will not be used as a basis to reduce Test Year capital expenditures in a future rate case. (2) Although the Settlement Agreement does not address rate design – and each Settling Party will be able to litigate its respective position on rate design in this Docket No. 17-1046 – the allocation of revenue responsibility and form of distribution rate design amongPage 13 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-380 Page 3 of 3 rate classes approved by PURA in this rate case shall be applied to rate design of the abovedescribed New Capital Tracker. (3) All capital recovery under this Settlement Agreement – in both base distribution rates and in the New Capital Tracker – for core capital projects and system resiliency projects will include recovery of the effect of plant, accumulated deferred income taxes (“ADIT”), and accumulated depreciation for the cumulative additional Plant Additions. Revenue requirements will include pre-tax return on investment, return of investment (depreciation), property taxes, gross earnings tax and uncollectible expense. Since the approval of the Settlement Agreement in PURA’s April 18, 2018, Decision in Docket No. 17-10-46, the “New Capital Tracker” was named the Electric System Improvements (“ESI”) mechanism. Consistent with the Settlement Agreement language above, the ESI reconciles revenue requirement calculations for calendar year capital recovery in the Company’s annual RAM tracker reconciliation proceeding. Furthermore, the recovery of these revenue requirement calculations for calendar year capital recovery are shifted by four months to coincide with the timing of the new base rates for Rate Years 1, 2, 3 and thereafter that went into effect on May 1st of 2018, 2019 and 2020 as part of the approved Settlement Agreement in Docket No. 17-10-46. Since the ESI resulted from the approved Settlement Agreement agreed to and signed by Eversource Energy, Office of Consumer Counsel and Public Utilities Regulatory Authority Prosecutorial Staff, there have been no changes made to the Settlement Agreement, and by extension the operation of the ESI, other than Amendment One to the Settlement Agreement. Amendment One to the Settlement Agreement was approved in PURA’s April 18, 2018, Decision in Docket No. 17-10-46. This amendment did not make any changes to the operational aspects of the ESI. However, Amendment One did make some changes to certain System Resiliency/Vegetation Management costs recoverable through the ESI.Page 14 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-381 Page 1 of 2 Date Filed: October 27, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Education, Outreach, and Enforcement Question: (EARNINGS SHARING MECHANISM-ESM) Discuss the method or methods used by the Company to calculate the ESM results (e.g., cost of capital method) and explain how the Company accounts for estimated activity, including revenue that would be subject to annual true-up within the RAM dockets. Response: Under the terms of the Settlement Agreement approved in Docket No. 17-10-46, earnings at the end of each calendar year above the distribution company’s authorized ROE of 9.25% must be shared with customers and shareholders on a 50/50 basis. As such, the Company performs a calculation that divides the operating income of the distribution company by the rate base of the distribution company to calculate a rate of return (“ROR”) for the distribution company. The cost of debt is then subtracted from the ROR and the resulting percentage is divided by the equity ratio to arrive at the actual earned ROE for the distribution company. This method is referred to as the cost of capital method. Generally speaking, the activity that flows through the RAM does not have an impact on the above calculation. This is because the rate components that make up the RAM are fully-tracking reconciling rate mechanisms that collect revenues for the distribution company, with deferrals of over or under collections to the next rate period. Due to the deferrals, there is no impact to the operating income of the distribution company from most RAM activity. The exception to this is the revenue requirement calculations for capital items placed in service that are included for recovery in the ESI, NBFMCC and SBC. These revenue requirement calculations include the recovery of a return on investment that is not deferred. Since this return on investment is not deferred, it flows into the operating income of the distribution company, which is the numerator of the ROR calculation that the ESM is based on. Further, all plant additions, accumulated depreciation and accumulated deferred income taxes on those plant additions that are part of the revenue requirement calculations that are included for recovery in the ESI, NBFMCC and SBC are included in the rate base of the distribution company, which is the denominator of the ROR calculation that the ESM is based on. In this way, the ROR contribution of the plant investments that are recovered through the ESI, NBFMCC and SBC are included in the overall ROR of the distribution company that is calculated for ESM purposes.Page 15 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-381 Page 2 of 2 Lastly, the RAM rate mechanisms are fully reconciling mechanisms based on actual costs and any differences between estimates of expense items are deferred. To the extent a RAM rate mechanism’s rate was based on the prior period’s historical costs, that rate will produce revenues that either over or under collect that period’s actual costs. Such over or under collections are deferred in accordance with Generally Accepted Accounting Principles (“GAAP”) (meaning they do not produce excess operating income or an operating income deficiency) and refunded or recovered in the next rate period.Page 16 of 105
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-08 Date Issued October 13, 2026 EOE-382 Page 1 of 1 Date Filed: October 27, 2026 Witness: Brendan J. O’Brien and Garrett J. Murray Request from: Office of Education, Outreach, and Enforcement Question: (EARNINGS SHARING MECHANISM-ESM) Identify if there are any non-regulated costs included within the ESM calculation to include, but not be limited to, charitable contributions, lobbying costs, and amortization of goodwill. If non-regulated costs are included, identify each of the cost categories, the amounts for each year 2020-2025, and explain why the costs are included. Response: Assuming that the reference to “non-regulated costs” means costs that are recorded and maintained “below the line” because the costs have no relation to the provision of utility service to customers, the Company does not include “non-regulated” costs in the ESM calculation. This would include, but not be limited to, “charitable contributions, lobbying costs, and amortization of goodwill.” However, this would not include costs that are recorded above-the-line; pertain to the provision of service to customers and may not be recovered in the cost of service due to ratemaking decisions or agreements in the last rate case. If costs are recorded above the line and pertain to the cost of providing service to customers, those costs are included in the Earnings Sharing computation. Under the terms of the Settlement Agreement approved in Docket No. 17-10-46, earnings at the end of each calendar year above the distribution company’s authorized ROE of 9.25% shall be shared with customers and shareholders on a 50/50 basis. To comply with this obligation, the Company performs a calculation that divides the operating income of the distribution company by the rate base of the distribution company to calculate a rate of return (ROR) for the distribution company. The cost of debt is then subtracted from the ROR and the resulting percentage is divided by the equity ratio to arrive at the actual earned ROE for the distribution company. This method is referred to as the cost of capital method. Non-regulated costs such as charitable contributions, lobbying costs, and amortization of goodwill are not included in the operating income of the distribution company, because they are recorded below the line. Thus the numerator of the ROR calculation excludes expenses recorded below the line for purposes of computing the ESM. Costs recorded above the line will be reflected in the operating income of the Company, regardless of whether the costs are included in rates.