  1. Page 127 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RRU-138 Page 1 of 2 Date Filed: November 03, 2026 Witness: Matthew P. Fallon Request from: Public Utilities Regulatory Authority Question: (LONG TERM DEBT) Provide a narrative describing the Company's efforts to refinance its existing long-term debt. Response: CL&P’s outstanding long-term debt is redeemable prior to each series’ respective Par Call Date, via make-whole provisions. A make-whole provision permits the long-term debt to be redeemed at any time prior to the Par Call Date, in whole or in part, at the option of CL&P, provided CL&P pays to the investors at the time of redemption a price calculated using the applicable treasury rate plus a spread of 50 basis points. The premium paid at the time of the redemption would fully compensate the investors for the forgone interest income. On or after each series Par Call Date (1, 3 or 6 months prior to the maturity date based on the tenor of the bonds), CL&P may redeem the respective series of bonds in whole or in part, at the option of CL&P, at a redemption price of 100% of the principal amount of the bonds being redeemed. In advance of each series Par Call Date, the Company evaluates if it would be economic to redeem the bonds. For example, most recently, CL&P’s $400 million, 0.75% 2020 Series A, first mortgage bonds matured on December 1, 2025. The Par Call Date of the 2020 Series A Bonds was November 1, 2025, allowing the bonds to be redeemed at a redemption price of 100% of the principal on or after November 1, 2025. However, as prevailing long-term debt rates were higher than the 2020 Series A bonds 0.75% coupon rate, the bonds were not redeemed early, given that doing so would not have been economic. Please refer to Table 1, below, for the details of CL&P’s outstanding long-term debt, including each series Par Call Date.
  2. Page 128 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RRU-138 Page 2 of 2 Table 1 AMOUNT ISSUED The Connecticut Light And Power Company First Mortgage Bonds 2004 Series B $130,000,000 2005 Series B $100,000,000 2006 Series A $250,000,000 2007 Series B $150,000,000 2007 Series D $100,000,000 2014 Series A $475,000,000 2015 Series A $350,000,000 2017 Series A $500,000,000 2018 Series A $800,000,000 2021 Series A $425,000,000 2023 Series A $500,000,000 2023 Series B $300,000,000 2024 Series A $350,000,000 2024 Series B $300,000,000 2025 Series A $400,000,000 COUPON RATE(%) DATE ISSUED DATE DUE PAR CALL DATE 5.750 5.625 6.350 5.750 6.375 4.300 4.150 3.200 4.000 2.050 5.250 4.900 4.650 4.950 4.950 9/15/2004 4/7/2005 6/7/2006 3/27/2007 9/17/2007 4/24/2014 5/20/2015 3/10/2017 3/28/2018 6/30/2021 1/10/2023 7/6/2023 1/23/2024 8/13/2024 1/13/2025 9/15/2034 4/1/2035 6/1/2036 3/1/2037 9/1/2037 4/15/2044 6/1/2045 3/15/2027 4/1/2048 7/1/2031 1/15/2053 7/1/2033 1/1/2029 8/15/2034 1/15/2030 9/15/2034 4/1/2035 6/1/2036 3/1/2037 9/1/2037 10/15/2043 12/1/2044 12/15/2026 10/1/2047 4/1/2031 7/15/2052 4/1/2033 12/1/2028 5/15/2034 12/15/2029
  3. Page 129 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RRU-139 Page 1 of 2 Date Filed: November 03, 2026 Witness: Ann Bulkley Request from: Public Utilities Regulatory Authority Question: (FINANCIAL DATA) Summarize the changes to economic and financial indicators that have taken place, since January 1, 2019, using the table below as a guide. Please provide all source documents for the information provided. Financial/Economic Indicator Gross Domestic Product (GDP-PI) Consumer Price Index (CPI) Unemployment Rate (National) Unemployment Rate (Connecticut) US Treasury Bills (90 day) US Treasury Bills (180 day) US Treasury Bonds (10 year) US Treasury Bonds (20 year) US Treasury Bonds (30 year) Market-to-book ratios for the Company Market-to-book ratios for the Parent Company with public common equity Market -to-book ratios for the Electric utility Industry Dividend Yield-ES Source Percentage change 1/01/2019 to 01/01/2019 6/30/2026 6/30/026
  4. Page 130 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RRU-139 Page 2 of 2 Dividend Yield-Electric Industry Average 5-year projected EPS Growth Rate-Electric Industry Average 5-year retention EPS Growth Rate-Electric Industry Average Federal Corporate Tax Rate Beta- Electric Industry Average Capital StructureCL&P Capital Structure-Electric Industry Average Value Line Financial Strength-Electric Bond Rating-Electric Industry Average Cost of Debt-CL&P Cost of Debt-Electric Industry Average Response: Please refer to RRU-139, Attachment 1, for the requested information.
  5. Page 131 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-058 Page 1 of 1 Date Filed: October 30, 2026 Witness: Leanne M. Landry and Jeffrey D. Turano Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-4, Ex.CLP-ADDITIONS-4 Supplemental, Ex. CLP-Additions-1, p. 56. Identify and provide in an unlocked spreadsheet a list of all projects associated with plant additions related to distributed generation (DG) and energy efficiency (EE) investments. Provide the information for each project showing the following: a. b. c. d. All new additions, on a monthly basis; Whether the project is related to DG or EE; Which portion of the project is reimbursable; and Reference to the project’s location in Exhibit CLP-ADDITIONS-4. Response: Please refer to RSR-058, Attachment 1, which identifies each project associated with distributed generation (DG), including the corresponding line references in Exhibit CLP-ADDITIONS-4, and the Exhibit CLP-ADDITIONS-4 Supplemental filings. Energy efficiency projects are 100% expense and will not be included in Exhibit CLP-ADDITIONS-4. The attachment also identifies the reimbursable portion of each project, as reflected in the applicable Project Authorization Forms (PAFs). The Company notes that information regarding new plant additions on a monthly basis for 2026 is provided as part of the Company’s supplemental filings.
  6. Page 132 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-059 Page 1 of 4 Date Filed: November 06, 2026 Witness: David L. Gladey, John P. Dipaola-Tromba, Steven Lamontagne, Leanne M. Landry, Elli Ntakou and Jeffrey D. Turano Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-1, p. 63. Provide the following regarded the “Direct Buried Replacement” projects: a. Documentation supporting the statement: “on an industry-wide basis that much of the original XLP and HMP-insulated primary cable installed in the DB system had not achieved its engineered life expectancy.” b. An exhibit showing the engineered life expectancy by type (e.g., XLP, HMP-insulated) and vintage of direct-buried (DB) assets on the Company’s system; c. An exhibit showing the actual service life of all the Company’s DB plant at the time of replacement for the years 2017 through 2026 (to-date). d. An unlocked spreadsheet showing the number and duration of premature DB cable failures by year and their contribution to blue-sky SAIDI and SAIFI performance. Response: a. The statement that much of the original XLPE and HMP-insulated primary cable installed in the distribution system had not yet achieved its engineered life expectancy is supported by industry research, utility operating experience, and cable-aging studies conducted by EPRI, NEETRAC, cable manufacturers, and other industry researchers. Studies of distribution cable performance have generally identified expected service lives in the range of 30 to 40 years for early-generation XLPE and HMP cable designs under normal operating conditions, while recognizing that actual service life is highly dependent on installation type, operating environment, loading, exposure to moisture, and cable construction. Industry experience has demonstrated that cable age alone is not a reliable indicator of end of life. Premature failures in some early cable installations were often associated with factors such as water-treeing, contamination, manufacturing deficiencies, shield defects, or moisture ingress rather than the intrinsic exhaustion of the insulation system. Soil type and installation, i.e. direct buried versus cable in conduit, are significant to the overall life expectancy of a underground cable. As a result, many XLPE and HMP cable circuits have remained electrically serviceable beyond their original design expectations.
  7. Page 133 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-059 Page 2 of 4 EPRI asset demographic information indicates that significant populations of XLPE and HMP cable remain in service at ages exceeding 35 years and, in many cases, beyond 50 years. In addition, recent evaluations of approximately 40-year-old service-aged cable have found that many cable systems continue to exhibit acceptable electrical and material performance. Accordingly, while replacement of direct-buried cable may be warranted based on reliability performance, failure history, condition assessment results, operational risk, or broader asset management considerations. The type of failures and overall service age of direct buried cable is supportive of some of the following industry documentation such as the following: EPRI Research – EPRI’s work implicitly recognizes that cable age alone is not equivalent to end-of-life and that remaining-life assessment is both possible and necessary because many assets survive beyond their nominal design life. 1. EPRI Distribution Cable Research EPRI's Distribution Cable Research Digest has long cited approximately 40 years as the expected service life of modern underground medium-voltage cable systems. EPRI has also sponsored extensive work on remaining-life estimation for XLPE cables, including Estimation of Remaining Life of XLPE-Insulated Cables and related aging-model studies designed specifically to assess service life beyond original installation dates. 2. EPRI Asset Demographics Data EPRI's current distribution asset demographic database shows that 25% of HMWPE assets are older than 57 years and 25% of XLPE assets are older than 46 years, which demonstrates that large populates of these cable types remain in service well beyond what many utilities historically considered their normal 30-40 year design life. Please refer to RSR-059, Attachment 1. NEETRAC Research – NEETRAC projects support the argument that replacement programs often targeted cables because of specific condition concerns and failure risk rather than because the insulation had necessarily consumed its full engineering life. 1. NEETRAC Historical Assessment of XLPE Life NEETRAC's paper Long-Life XLPE Insulated Power Cable notes that when medium-voltage XLPE cable was first introduced, utilities expected: "20 or even 30 years" of reliable service. Please refer to RSR-059, Attachment 2.
  8. Page 134 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-059 Page 3 of 4 The paper further explains that many early failures were caused by water-treeing mechanisms, manufacturing deficiencies, contamination, and moisture-related degradation rather than fundamental exhaustion of the polyethylene insulation system. Please refer to RSR-059, Attachment 2. NEETRAC states that improvements in materials and manufacturing greatly improved longterm performance and reliability. Please refer to RSR-059, Attachment 2. 2. Recent NEETRAC / Alabama Power 40-Year Field Evaluation One of the most valuable recent studies examined TR-XLPE cable removed after approximately 40 years of continuous service from Alabama Power's Galleria Mall system: • Installed in 1985 • Evaluated after ~40 years in service • Included electrical and material performance testing • Specifically designed to assess cable condition near the historically expected servicelife threshold, please refer to RSR-059, Attachment 3. The study's purpose was to determine whether cable approaching or exceeding the traditional 40-year design-life expectation remained fit for service. b. The Company does not maintain the information necessary to produce the requested exhibit. Installation vintage information is unavailable for a significant portion of the Company's direct-buried cable assets, and insulation type information is incomplete for many assets. As a result, the Company is unable to reliably classify all direct-buried assets by both vintage and insulation type and therefore cannot produce the requested exhibit. c. As it relates to the Company's Direct Buried Replacement Program, the Company’s plant assets replaced and retired are accounted for under the mass-distribution property method. Under such a method, the Company’s plant accounting system utilizes the group method of depreciation and retirement, rather than a direct one-for-one matching principle of individual asset additions and retirements for each utility property. Please refer to OCC-793 i for further discussion on the Broad Group Procedure that the Company utilizes to depreciate and retire its utility property. Therefore, because the specific vintage year of each retired unit is not identifiable, the Company is unable to provide the actual service life of all the Company's Direct Buried utility property when these individual units are removed and retired during the years 2017 through 2026.
  9. Page 135 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-059 Page 4 of 4 d. Please refer to RSR-059, Attachment 4. The Company note that, given (b) above, the Company is not able to delineate “premature” DB events and therefore RSR-059, Attachment 4, lists all DB events from 2017-2025. Prior Referenced Response: i OCC-793 Question: Refer to Exhibit CLP-ADDITIONS-1, p. 45. Approximately $4.3 billion of capital additions has been placed in service since January 1, 2017. Identify all such additions retired, abandoned or written off before the end of their depreciable life, with the in-service and retirement dates, the original cost, the amount remaining in rate base, and the reason. OCC-793 Response: Please refer to OCC-793, Attachment 1, for all additions of specific property since January 1, 2017, that were retired before the end of their depreciable life including in-service and retirement dates, original cost, amounts remaining in rate base and the reason for retirement. Retirements of specific property are generally recorded at the full value of the individual asset, whereas mass property retirements are accounted for using the applicable mass property retirement methodology. In some cases, specific property asset retirements are partial, or trended. This occurs when the original asset record includes units of property not separately unitized at the time of installation. When the original cost of the retired asset cannot be specifically identified, the Company utilizes the Handy-Whitman index to trend the replacement cost back to the original installation year to estimate its historical cost. The estimated amount is then retired from the existing asset and charged to the accumulated depreciation account. This process ensures that the cost of the replacement is removed from utility plant while the remaining portion of the original asset continues to be reflected in plant in service. CL&P predominantly utilizes the Broad Group Procedure to depreciate utility property. Under the Broad Group Procedure, homogenous assets are grouped together and depreciated under a single average service life. When an asset within the group is retired, the asset is considered fully accrued, regardless of the asset’s actual service life, and accumulated depreciation is debited for the full book cost of the asset. If an asset is retired prior to the average service life, any impact to depreciation expense will be recovered over time by assets that exceed the average service life of the group. The asset retirement dispersion is analyzed in future depreciation studies when creating an updated, proposed average service life and accompanying accrual rate.
  10. Page 136 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-060 Page 1 of 1 Date Filed: October 28, 2026 Witness: David L. Gladey and Jeffrey D. Richard Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-1, p. 71. Provide the following information about third-party pole attachment make-ready work: a. A copy of the billable/nonbillable determination matrix; and b. A description and template of the “standardization documentation” requirements. Response: a. Please refer to the billable/nonbillable determination matrix previously provided as RRU002, Attachment 1. b. The Company does not maintain a separate template for "standardization documentation" related to billable/non-billable make-ready determinations. Rather, the basis for each determination is documented within the Power Survey in the Alden One application and associated work order records. Vendors are instructed to provide descriptive notes supporting the determination, including information regarding the work performed and the basis for the billable or non-billable classification. Supporting information may also be reflected in related sketches, engineering records, and associated work order documentation. The Company utilizes the information documented in these records to support subsequent reporting and categorization of billable and non-billable work.