  1. Page 133 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-059 Page 2 of 4 EPRI asset demographic information indicates that significant populations of XLPE and HMP cable remain in service at ages exceeding 35 years and, in many cases, beyond 50 years. In addition, recent evaluations of approximately 40-year-old service-aged cable have found that many cable systems continue to exhibit acceptable electrical and material performance. Accordingly, while replacement of direct-buried cable may be warranted based on reliability performance, failure history, condition assessment results, operational risk, or broader asset management considerations. The type of failures and overall service age of direct buried cable is supportive of some of the following industry documentation such as the following: EPRI Research – EPRI’s work implicitly recognizes that cable age alone is not equivalent to end-of-life and that remaining-life assessment is both possible and necessary because many assets survive beyond their nominal design life. 1. EPRI Distribution Cable Research EPRI's Distribution Cable Research Digest has long cited approximately 40 years as the expected service life of modern underground medium-voltage cable systems. EPRI has also sponsored extensive work on remaining-life estimation for XLPE cables, including Estimation of Remaining Life of XLPE-Insulated Cables and related aging-model studies designed specifically to assess service life beyond original installation dates. 2. EPRI Asset Demographics Data EPRI's current distribution asset demographic database shows that 25% of HMWPE assets are older than 57 years and 25% of XLPE assets are older than 46 years, which demonstrates that large populates of these cable types remain in service well beyond what many utilities historically considered their normal 30-40 year design life. Please refer to RSR-059, Attachment 1. NEETRAC Research – NEETRAC projects support the argument that replacement programs often targeted cables because of specific condition concerns and failure risk rather than because the insulation had necessarily consumed its full engineering life. 1. NEETRAC Historical Assessment of XLPE Life NEETRAC's paper Long-Life XLPE Insulated Power Cable notes that when medium-voltage XLPE cable was first introduced, utilities expected: "20 or even 30 years" of reliable service. Please refer to RSR-059, Attachment 2.
  2. Page 134 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-059 Page 3 of 4 The paper further explains that many early failures were caused by water-treeing mechanisms, manufacturing deficiencies, contamination, and moisture-related degradation rather than fundamental exhaustion of the polyethylene insulation system. Please refer to RSR-059, Attachment 2. NEETRAC states that improvements in materials and manufacturing greatly improved longterm performance and reliability. Please refer to RSR-059, Attachment 2. 2. Recent NEETRAC / Alabama Power 40-Year Field Evaluation One of the most valuable recent studies examined TR-XLPE cable removed after approximately 40 years of continuous service from Alabama Power's Galleria Mall system: • Installed in 1985 • Evaluated after ~40 years in service • Included electrical and material performance testing • Specifically designed to assess cable condition near the historically expected servicelife threshold, please refer to RSR-059, Attachment 3. The study's purpose was to determine whether cable approaching or exceeding the traditional 40-year design-life expectation remained fit for service. b. The Company does not maintain the information necessary to produce the requested exhibit. Installation vintage information is unavailable for a significant portion of the Company's direct-buried cable assets, and insulation type information is incomplete for many assets. As a result, the Company is unable to reliably classify all direct-buried assets by both vintage and insulation type and therefore cannot produce the requested exhibit. c. As it relates to the Company's Direct Buried Replacement Program, the Company’s plant assets replaced and retired are accounted for under the mass-distribution property method. Under such a method, the Company’s plant accounting system utilizes the group method of depreciation and retirement, rather than a direct one-for-one matching principle of individual asset additions and retirements for each utility property. Please refer to OCC-793 i for further discussion on the Broad Group Procedure that the Company utilizes to depreciate and retire its utility property. Therefore, because the specific vintage year of each retired unit is not identifiable, the Company is unable to provide the actual service life of all the Company's Direct Buried utility property when these individual units are removed and retired during the years 2017 through 2026.
  3. Page 135 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-059 Page 4 of 4 d. Please refer to RSR-059, Attachment 4. The Company note that, given (b) above, the Company is not able to delineate “premature” DB events and therefore RSR-059, Attachment 4, lists all DB events from 2017-2025. Prior Referenced Response: i OCC-793 Question: Refer to Exhibit CLP-ADDITIONS-1, p. 45. Approximately $4.3 billion of capital additions has been placed in service since January 1, 2017. Identify all such additions retired, abandoned or written off before the end of their depreciable life, with the in-service and retirement dates, the original cost, the amount remaining in rate base, and the reason. OCC-793 Response: Please refer to OCC-793, Attachment 1, for all additions of specific property since January 1, 2017, that were retired before the end of their depreciable life including in-service and retirement dates, original cost, amounts remaining in rate base and the reason for retirement. Retirements of specific property are generally recorded at the full value of the individual asset, whereas mass property retirements are accounted for using the applicable mass property retirement methodology. In some cases, specific property asset retirements are partial, or trended. This occurs when the original asset record includes units of property not separately unitized at the time of installation. When the original cost of the retired asset cannot be specifically identified, the Company utilizes the Handy-Whitman index to trend the replacement cost back to the original installation year to estimate its historical cost. The estimated amount is then retired from the existing asset and charged to the accumulated depreciation account. This process ensures that the cost of the replacement is removed from utility plant while the remaining portion of the original asset continues to be reflected in plant in service. CL&P predominantly utilizes the Broad Group Procedure to depreciate utility property. Under the Broad Group Procedure, homogenous assets are grouped together and depreciated under a single average service life. When an asset within the group is retired, the asset is considered fully accrued, regardless of the asset’s actual service life, and accumulated depreciation is debited for the full book cost of the asset. If an asset is retired prior to the average service life, any impact to depreciation expense will be recovered over time by assets that exceed the average service life of the group. The asset retirement dispersion is analyzed in future depreciation studies when creating an updated, proposed average service life and accompanying accrual rate.
  4. Page 136 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-060 Page 1 of 1 Date Filed: October 28, 2026 Witness: David L. Gladey and Jeffrey D. Richard Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-1, p. 71. Provide the following information about third-party pole attachment make-ready work: a. A copy of the billable/nonbillable determination matrix; and b. A description and template of the “standardization documentation” requirements. Response: a. Please refer to the billable/nonbillable determination matrix previously provided as RRU002, Attachment 1. b. The Company does not maintain a separate template for "standardization documentation" related to billable/non-billable make-ready determinations. Rather, the basis for each determination is documented within the Power Survey in the Alden One application and associated work order records. Vendors are instructed to provide descriptive notes supporting the determination, including information regarding the work performed and the basis for the billable or non-billable classification. Supporting information may also be reflected in related sketches, engineering records, and associated work order documentation. The Company utilizes the information documented in these records to support subsequent reporting and categorization of billable and non-billable work.
  5. Page 137 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-061 Page 1 of 1 Date Filed: November 06, 2026 Witness: David L. Gladey and Jeffrey D. Richard Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-1, pp. 73–74, Ex. CLP-ADDITIONS9. Provide the following for the selections identified in the attachment “RSR-61, Attachment – PURA Selections” for both worksheets “Selections – Prior to 5-11-2022” and “Selections – Others”: a. Work order documentation; b. Records of personnel sign-off on the work order; c. Documentation of the full make-ready design including construction sketch, Maximo design, and Pole Foreman Analysis; and d. All documented records of the “work order analysis.” Response: a. c. and d. Please refer to RSR-061, Attachment 1 CONFIDENTIAL, through RSR-061, Attachment 9 CONFIDENTIAL. Pole Foreman Analysis is not available for all work orders. Availability is dependent on the age of the work order, the procedures and business processes that were in effect at the time the work was performed, and applicable vendor record retention practices. As a result, supporting analysis may not exist or may no longer be available for certain historical work orders. b. Work Order approval authority for Electric Distribution activities is delegated as follows: • Designer: Approval authority up to $20,000 • Supervisor: Approval authority up to $100,000 • Manager: Approval authority up to $500,000 • Director: Approval authority up to $100,000,000 • Vice President: Approval authority up to $100,000,000 • Executive Vice President: Approval authority up to $100,000,000 Accordingly, the required sign-off authority is determined based on the total estimated work order value and routed to the appropriate approval level.
  6. Page 138 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-062 Page 1 of 2 Date Filed: October 30, 2026 Witness: John P. Dipaola-Tromba, Sean D. Redding, Jenna M. Turner, Leanne M. Landry and Jeffrey D. Turano Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-4, Ex. CLP-ADDITIONS-4 (Supplemental). Provide in an unlocked spreadsheet a complete listing by work order of all charges for the following vegetation management-related annual projects. a. CTROW17; b. ETR2017; c. ETR2018; d. ETR2019; e. ETR2020; f. ETR2021; g. ETT2016; h. ETT2017; i. CTREL23; j. CTREL24; k. CTREL25; l. DOT24; m. DOT25; n. ETR2022; o. ETR2023; p. ETR2024; q. ETR2025; r. ETTCF22; s. ETTCF23; t. ETTCF24; u. ETTCF25; v. VEGDOT22; and w. VEGDOT23. Response: Please refer to Table 1, identifying the line in Exhibit CLP-ADDITIONS-5 on which each project appears. Exhibit CLP-ADDITIONS-5 lists the Company’s in-service capital additions by year, funding project, work order and FERC account.
  7. Page 139 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-062 Page 2 of 2 Table 1 Project a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. p. q. r. s. t. u. v. w. CTROW17 ETR2017 ETR2018 ETR2019 ETR2020 ETR2021 ETT2016 ETT2017 CTREL23 CTREL24 CTREL25 DOT24 DOT25 ETR2022 ETR2023 ETR2024 ETR2025 ETTCF22 ETTCF23 ETTCF24 ETTCF25 VEGDOT22 VEGDOT23 Exhibit 5 Line Reference 121,964 257,820 257,971 258,116 258,269 258,420 259,173 259,301 121,610 121,751 121,871 221,396 221,402 258,573 258,726 258,872 259,019 259,922 259,958 260,012 260,062 311,655 311,670
  8. Page 140 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-063 Page 1 of 2 Date Filed: November 03, 2026 Witness: David L. Gladey, John P. Dipaola-Tromba, Leanne M. Landry and Jeffrey D. Turano Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-4. Explain the difference between the annual project categories listed below. Provide examples of types of work and categories of plant that would be included in each annual project. a. b. c. d. “CT D SS Emergent Annual”; “CLP DIST SS FAILED EQUIPMENT ANNUAL”; “Emergent Line”; and “Insurance Claims / Keep Cost.” Response: The annual project categories noted are budgeted and approved to support a high volume of workorders and support work across the Company’s electric distribution service area in Connecticut. Capital work orders initiated against these post 2022 annual projects must include total costs less than or equal to $500K. This threshold was $100K of direct costs for projects prior to 2022. Any work order that exceeds this amount will require a separate Project Authorization Form (PAF) and Delegation of Authority (DOA) approval. CT D SS Emergent Annual and CLP DISP SS FAILED EQUIPMENT ANNUAL are annual programs under which separate, unique, small-scale, qualifying capital projects can be performed, using a workorder to track each separate small-scale project. The parent project number, DSEQ, establishes the annual CT Distribution Substation (SS) Emergent Equipment program under which small-scale projects can be created at the workorder level. This annual project includes the labor, materials, and equipment necessary to address replacing failed distribution substation assets. These annual projects may include types of work and categories of plant such as failed batteries, damaged substation cables or conduits, defective relays or metering, and other distribution substation equipment requiring replacement. Emergent Line Annual covers the replacement and repair of failed, damaged, or obsolete equipment on the electric distribution system. The work is typically initiated in response to customer-reported outages, trouble tickets, or equipment failures requiring the repair or replacement of existing distribution system facilities. This annual project includes the labor,
  9. Page 141 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-063 Page 2 of 2 materials, and equipment necessary to restore customer service and address failed distribution assets. Examples of work may include replacing broken crossarms, failed arresters, damaged conductors, defective transformers, and other distribution equipment requiring replacement. Plant categories included in this annual project may include, but are not limited to, poles, overhead and underground conductors, line transformers, services, protective devices, and related distribution system equipment. Insurance Claims / Keep Cost Annual covers distribution system costs associated with the replacement or repair of overhead facilities, underground facilities, and distribution cable damaged by third parties and subject to insurance claims. Due to timing constraints and certain nonreimbursable charges, a portion of this expenditure may not be recovered and are therefore funded through this annual project. Examples of work completed under this annual project may include customer-performed tree work that results in outages, pole accident repairs, cable dig-up restorations, and repairs to distribution system equipment damaged by third parties. Plant categories included in this annual project may include, but are not limited to, poles, overhead and underground conductors, line transformers, services, and distribution cable.
  10. Page 142 of 144

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set PURA-13 Date Issued October 16, 2026 RSR-064 Page 1 of 1 Date Filed: October 30, 2026 Witness: David L. Gladey, John P. Dipaola-Tromba, Leanne M. Landry and Jeffrey D. Turano Request from: Public Utilities Regulatory Authority Question: (PLANT ADDITIONS) Application, Ex. CLP-ADDITIONS-4, Ex. CLP-ADDITIONS-4 (Supplemental). Provide in an unlocked spreadsheet a complete listing by work order of all charges for the emergent equipment failure-related annual projects labeled “EMRGNTLN (CDEMANNL).” The listing should include labels indicating the year of the plant additions and the specific annual project (e.g., “Emergent Line”). Response: Please refer to RSR-064, Attachment 1, which identifies all funding projects associated with emergent equipment failure-related annual project and the line within Exhibit CLP-ADDITIONS5 each project appears. Exhibit CLP-ADDITIONS-5 lists the Company’s in service capital additions by year, funding project, work order and FERC account.

As listed on the current system

Corres. 11/16/2026 [26-05-10] (Keegan Werlin LLP) - Discovery Compilation (PURA Set 13, EOE Set 8)

This filing on the current system (opens in a new tab)