  1. Page 18 of 47Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-995 Page 1 of 4 Date Filed: November 10, 2026 Witness: Jared A. Lawrence and Jason Tharp Request from: Office of Consumer Counsel Question: (BRIDGE METERS) Please provide the Authority decision and/or ruling approving the Company installing the 467,145 bridge meters it has installed. Response: The Company does not require PURA’s approval for installation of bridge meters. The installation of meters is a basic function of utility service, falling into the category of capital investment that PURA reviews on the basis of prudence at the time that recovery of the investment is requested in rate base. On the CL&P system, implementation of bridge meters proceeded on the basis of a business case contemplating the obsolescence of automated meter reading (“AMR”) technology and the opportunity to obtain enhanced functionality on the distribution system, as the evaluation of implementation of Advanced Metering Infrastructure (“AMI”) took place in Docket No. 17-1203RE02 over an extended time frame (2019-2024). The installation of bridge meters does not involve the need for a comprehensive implementation plan involving the integration of new backoffice information systems and accelerated installation across the entire customer base, which are the circumstances that drive the need for an associated cost-recovery mechanism and other approvals of PURA to support that type of implementation. Specifically, beginning in 2017, the Company began to evaluate the installation of “bridge” meters to replace a portion of its hard-to-reach AMR meters with a goal of increasing operational efficiencies for service disconnects and reconnects; decreasing the amount of customer write-offs and bad debts through more and faster remote disconnects; and addressing the “failure curve” for meters at or approaching end of life. Bridge meters are AMR meters with remote turn-on and turnoff capability through the Company’s existing meter reading system. Bridge meters can also be used for specialty applications, including net and demand readings. An AMR meter with specialty applications added to it – like the capability to measure demand – is more expensive than purchasing a bridge meter and programming it to perform specialty applications. This is due to the fact that AMR technology is antiquated and requires more expensive components than the more flexible bridge meter. Because the Company’s existing metering infrastructure was at its end-of-life and therefore prone to error or failure, replacement was necessary in order to avoid billing inaccuracies or estimates. With the success of the bridge-meter project in meeting operational and bad-debt reduction goals, the Company increased the level of meter-related capital expenditures in 2018, 2019 and 2020,
  2. Page 19 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-995 Page 2 of 4 and migrated to remote-disconnect capable meters as its meter of choice for all replacement installations. To this day, bridge meters continue to offer significant safety and operational benefits with their ability to remotely read and operate when access is an issue, which is common in metro areas. The Company expects to continue to utilize both bridge-meter technology and AMR meter technology pending full implementation of AMI. Specific benefits of bridge-metering technology include the following: Remote disconnect/reconnect switch: • Many of the residential meter types include a remote disconnect/reconnect switch. That switch can be operated by agents of Eversource without the need to physically access the meter. The agents must still visit the premises to get close to the meter for the signal to reach. • The disconnect feature is primarily used to decrease the amount of customer write-offs and bad debt. Allowing employees to disconnect the meter without physical access helps in situations where access is prevented or unsafe conditions. • The primary benefit of the remote reconnect feature is the ability to restore power to the customer without requiring the customer to be home to grant access when the meter is located inside. Automatic demand reset: • Legacy meter types require the Meter Reader to perform manual demand resets monthly so the meter can correctly record demand values for applicable customers/rates. The bridge meter can automatically reset the demand value when the meter is read each month. This cuts down the time and effort involved with reading these meter configurations. Polyphase phase angles: • Polyphase bridge meters have the added benefit of providing phase angle data when meter data is extracted. Phase angle data is used to troubleshoot metering or service issues. There have been examples of equipment errors being detected with phase angle data. Meter feature standardization: • Prior to bridge meters, the Company used different meter types for demand customers, net customers, net demand customers and production meters. Multiplying each of these needs across the various service configurations results in dozens of different meter types. The
  3. Page 20 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-995 Page 3 of 4 bridge meter is able to handle all these billing requirements with the same meter which greatly simplifies inventory and reduces meter inventory shortages. Annual installations are summarized as follows: Year 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Total Installed Bridge Meters 5,161 50,292 85,581 105,285 54,345 21,291 16,426 29,710 69,896 18,237 13,222 469,446 Installed AMR Meters 39,086 28,224 17,958 3,798 1 20,476 35,157 14,852 3,784 1,432 173 164,941 The table above provides a breakdown of all bridge and AMR meters that are currently physically installed in Connecticut. The different rows separate meters into the year they were purchased. The total quantities differ from the 467,145 figure referenced due to minor fluctuations in reporting of installed and removed meters which occur on a daily basis. Additionally, it is necessary to highlight that the methodology of categorizing physically installed meters broken out by purchase year, matches previously filed meter breakdowns. Since there are natural delays between purchasing and installing meters in the field, it may appear as if past stated vintages are increasing (i.e. there is an increase in 2025 meters than previously stated). This variance is due to reporting on meters that were purchased in 2025 were physically installed in the field in 2026. This is true for all years resulting in older vintage volumes decreasing, and newer vintage meter volumes increasing each time this analysis is performed. Going forward - with the implementation of AMI - advances in the industry throughout the previous decade have enabled additional capabilities in AMI meters at comparable cost, increasing the relative cost-effectiveness of an AMI system. Modern AMI meters now leverage advancements in mesh network technology and 4G LTE and 5G communication technologies, enabling near real-time data sharing through device-to-device communication. This facilitates greater situational awareness for the utility. Equipped with more powerful processors and expanded storage, these meters can download applications and run analytical algorithms to address various use cases, such as mapping meters to transformers and providing customers with detailed
  4. Page 21 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-995 Page 4 of 4 insights into their energy usage. Additionally, modern AMI meters are capable of grid-edge computation, processing vast amounts of data to produce actionable insights for both the customers and the grid. The meters can autonomously decide which data to send back to the utility, optimizing network utilization and reducing the amount of time needed to process, analyze, and make decisions based on that data. Advanced AMI use cases now include neutral monitoring, connectivity model verification, and advanced load disaggregation, alongside traditional capabilities such as remote connect/disconnect, internal metering, tamper detection, and power loss and restoration notifications. The Company’s meter replacement strategy aims to provide all customers in the territory with equal access to the benefits the AMI deployment.
  5. Page 22 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-996 Page 1 of 1 Date Filed: November 10, 2026 Witness: Jared A. Lawrence and Jason Tharp Request from: Office of Consumer Counsel Question: (METERS) Please provide for each year from 2018 through the present the average unit cost of each type: of AMR meter(s) the Company installed; each type of bridge meter(s) the Company installed; and each type of AMI meter(s) the Company installed. Response: Please refer to Table 1 below for the requested information: Table 1: Average Unit Cost of Installed Meter by Type Meter Type Legacy AMR Legacy AMR Bridge AMR Bridge AMR AMI AMI Service 2018 2019 2020 2021 2022 2023 2024 2025 Self-Contained Transformer Rated $138 $200 $180 $38 $37 $41 $35 $38 $97 $121 $0 $145 $72 $75 $77 $90 Self-Contained Transformer Rated Self-Contained Transformer Rated $127 $115 $118 $107 $115 $143 $139 $125 $176 $0 $161 $0 $188 $0 $187 $0 $187 $0 $186 $0 $197 $0 $199 $0 $0 $0 $0 $0 $0 $0 $0 $0
  6. Page 23 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-997 Page 1 of 2 Date Filed: November 10, 2026 Witness: Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry, John G. Griffin, Craig Dikeman and Matthew J. Correia Request from: Office of Consumer Counsel Question: (MS24E) Please refer to the Response to OCC-955. a. Please cite to the contractual provision contained in the contract with E-J Electric provided in response to OCC-44 that permits the vendor to begin billing at double time while traveling to a job work site. b. Where was this crew housed/staying on the night of March 11, 2024? Response: a. Please refer to OCC-044, Attachment, at 2 page 1153 which includes the list of exhibits referenced within the contract with E-J Electric. The Exhibit B Pricing Schedule was not included with the E-J Electric MSA provided in OCC-044 i. Please refer to EOE-206, Attachment 1, for a copy of the Exhibit B Pricing Schedule applicable to the E-J Electric contract cited above. Please refer to Exhibit B Pricing Schedule, Section 4.4 Emergency Response Work, section (a); “Owner shall compensate Contractor for Emergency Response Work assigned to Contractor based on Contractor’s applicable Emergency Response rates from the commencement of such Emergency Response Work at the Site through the termination of Emergency Response Work at the Site, excluding rest time during that period. Emergency Response rates for labor shall be rates equal to the Double Time Rates set forth in Appendix PS-6 PRICING SCHEDULE - T&M.” b. Per Exhibit ACC-2(CLPI-5A-2)(MS24E), at page 157, the crews self-lodged at the Holiday Inn Express in Rocky Hill. Prior Referenced Response i OCC-044 Question: (Contracts) For all external line crews and vegetation contractors whose costs are reflected in the storms in this docket and for all current external line crews, please provide all contracts and addendums thereto in effect from January 1, 2024, to the present.
  7. Page 24 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-997 Page 2 of 2 OCC-044 Response: Please refer to OCC-044, Attachment 1, for a listing of external line crew and vegetation contractors whose services were utilized in the storms under review in this docket and all current external line crews. Attachment 1 includes page number references to the associated contracts, which are provided as OCC-044, Attachment 2 CONFIDENTIAL.
  8. Page 25 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-998 Page 1 of 1 Date Filed: November 09, 2026 Witness: Jared A. Lawrence and Timothy W. McGrath Request from: Office of Consumer Counsel Question: (ACCOUNT NUMBERS) Referring to OCC-915, and OCC-916, Interrogatory Responses. Why does the Company state that it “may transfer the payment” instead of “will”? Response: If a customer has multiple billing account numbers and a payment is applied to another billing account associated with them, the customer may elect to leave the payment on that account rather than have it transferred. If a customer provides proof of payment and the payment is located on a billing account with which they have no association, the Company will transfer the payment balance to the correct billing account.
  9. Page 26 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-999 Page 1 of 1 Date Filed: November 09, 2026 Witness: Jared A. Lawrence and Timothy W. McGrath Request from: Office of Consumer Counsel Question: (ACCOUNT NUMBERS) Referring to OCC-915, and OCC-916, Interrogatory Responses. For years 2021 –2026 in an Excel spreadsheet provide a list of customer accounts that had a customer incorrectly pay into a wrong account. Include the total which was paid to the wrong account. Include the total number of instances and instances per account impacted. Response: Misapplied payment and payment transfer requests are sent by Customer Service Representatives to the Payments and Bill Print team through payment inquiry requests submitted in the Customer Information system or through email requests. There is no reporting available for email requests, and no way to isolate the misapplied payment or payment transfer requests from other payment inquiry requests submitted through the Customer Information System.
  10. Page 27 of 47

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-30 Date Issued October 27, 2026 OCC-1000 Page 1 of 1 Date Filed: November 09, 2026 Witness: Jared A. Lawrence and Timothy W. McGrath Request from: Office of Consumer Counsel Question: (ACCOUNT NUMBERS) Referring to OCC-915, and OCC-916, Interrogatory Responses and OCC-992, interrogatory. For each customer account which had this customer account error provide the amount of payments/funds/money which was transferred to the correct account and amount of payments/funds/money which was NOT transferred to the correct account. Response: The Company interprets this question to reference OCC-999, instead of OCC-992. Please refer to the Company’s response to OCC-999 i. Prior Referenced Response i OCC-999 Question: (ACCOUNT NUMBERS) Referring to OCC-915, and OCC-916, Interrogatory Responses. For years 2021 –2026 in an Excel spreadsheet provide a list of customer accounts that had a customer incorrectly pay into a wrong account. Include the total which was paid to the wrong account. Include the total number of instances and instances per account impacted. OCC-999 Response: Misapplied payment and payment transfer requests are sent by Customer Service Representatives to the Payments and Bill Print team through payment inquiry requests submitted in the Customer Information system or through email requests. There is no reporting available for email requests, and no way to isolate the misapplied payment or payment transfer requests from other payment inquiry requests submitted through the Customer Information System.