Interrogatories
To CL&P, questions 119 thru 138
Filed by Allco Finance Limited1 file
Part of docket 26-05-10Files1
Allco_Interrogatories_Set_Eleven_PURA_26-05-10_tm.pdf
PDF · 241 KB · 24 pagesText searchable
Download Allco_Interrogatories_Set_Eleven_PURA_26-05-10_tm.pdfRead the text of Allco_Interrogatories_Set_Eleven_PURA_26-05-10_tm.pdf
Page 1 of 24
STATE OF CONNECTICUT PUBLIC UTILITIES REGULATORY AUTHORITY APPLICATION OF THE CONNECTICUT LIGHT AND POWER COMPANY D/B/A EVERSOURCE ENERGY TO AMEND ITS RATE SCHEDULES : : : : DOCKET NO. 26-05-10 SEPTEMBER 24, 2026 INTERROGATORIES OF ALLCO FINANCE LIMITED TO THE CONNECTICUT LIGHT AND POWER COMPANY D/B/A EVERSOURCE ENERGY — SET ELEVEN Pursuant to the Authority’s August 19, 2026 ruling granting Allco Finance Limited (“Allco”) intervenor status, and in accordance with the Authority’s Rules of Practice, Regs. Conn. State Agencies § 16-1-1 et seq., Allco propounds the following interrogatories — numbered consecutively with Allco’s prior sets (Q-ALLCO-001 through Q-ALLCO-118) — to The Connecticut Light and Power Company d/b/a Eversource Energy (“Eversource” or the “Company”). These interrogatories follow up on the Company’s responses filed September 16, 22, and 23, 2026 to ALLCO-020, ALLCO-021, ALLCO-029, ALLCO-033, ALLCO-034, ALLCO-054, ALLCO-055, ALLCO-057, ALLCO-059, ALLCO-062, ALLCO-063, and ALLCO-064 and to ICC-005, ICC-008, ICC-010, ICC-011, and ICC-017; address the Company’s interconnection cost estimating, final accounting, CIAC tax treatment, and ISO-NE referral practices; and (Q-ALLCO-137 through Q-ALLCO-146) seek the market, financialstatement, model-input, and credit data needed to determine the Company’s market cost of common equity, without repeating Q-ALLCO-046 through Q-ALLCO-054 (where a response to those interrogatories already supplies an item, the Company may so state and identify the response). The definitions and instructions set forth in Allco’s Set One apply. In addition, “Allco Applications” means interconnection applications LEG-22708, LEG-22709, LEG-22710, LEG22711, LEG-22712, LEG-22713, LEG-22714, LEG-22750, LEG-22751, LEG-22752, LEG22995, INT-29207, INT-29208, INT-29209, INT-29241, INT-29243, INT-39859, INT-39863, INT-90809, and INT-90811, and any other interconnection application submitted by or on behalf of Allco or its affiliates; “Level 1,” “Level 2,” and “Level 3” have the meanings given in the Authority’s Guidelines for Generator Interconnection; and “PowerClerk” means the interconnection application portal and database identified in the Company’s responses to ALLCO-017, ALLCO-057, and ICC-011, and any predecessor or successor system; “Windham Solar Facilities” means the five inverter-based photovoltaic generating units of Windham Solar 1Page 2 of 24
LLC at Williams Crossing Road, Lebanon, interconnected under Standard Fast Track and Study Process Generator Interconnection Agreements dated May 11, 2016, as amended; “Abington Solar Projects” means the two approximately 1 MW solar projects of Allco affiliates in Abington (Pomfret) for which the Company completed a system impact study in or before 2017; “ISO-NE” means ISO New England Inc.; “Determination” means any evaluation, review, screening, or decision — including under ISO-NE’s Section I.3.9 or “Proposed Plan Application” procedures or so-called “PP5” practices — as to whether a state-jurisdictional distributed generation interconnection requires ISO-NE review, approval, or study; and “Spencer Hill Projects” means the solar projects at or near 132 Spencer Hill Road, Winchester, including applications INT90809 and INT-90811. “Eversource Energy” means Eversource Energy, the Company’s publicly traded parent (NYSE: ES); “ROE Witness” means each witness sponsoring the Company’s return-on-equity or cost-of-capital testimony in this proceeding; “Proxy Group” means each group of companies used by the ROE Witness in any cost-of-equity model; “market-to-book ratio” means the market price of common stock divided by the book value of common equity per share; “CFO pre-WC/debt” means cash flow from operations before changes in working capital divided by total debt, as defined by Moody’s Investors Service; “FFO/debt” means funds from operations divided by debt as defined by S&P Global Ratings; “CIAC Tax Adder” has the meaning given in the Company’s response to ALLCO-064; and “Notice 2016-36” means IRS Notice 2016-36, 2016-25 I.R.B. 1029. Please answer separately and fully in writing, identify the witness responsible, and provide responsive schedules in native (Excel) format with formulas intact. INTERROGATORIES Q-ALLCO-119: (Follow-up to ALLCO-057 — Level 2 and Level 3 applications.) The Company’s response to ALLCO-057 confined its figures to Level 1 applications and defined “completed or otherwise closed” as applications that received Permission to Operate. ALLCO057 asked for all Connecticut DG interconnection applications. For each calendar year 2020 through 2025, separately for Level 2 applications, Level 3 applications, and any other category of application that is not Level 1, state: (a) the number and aggregate MW AC of applications received; (b) the number that received Permission to Operate; (c) the number withdrawn; (d) the number denied, rejected, or cancelled by the Company; (e) the number pending at December 31 of that year; (f) the number and aggregate MW AC that required electric power system 2Page 3 of 24
modifications or upgrades; and (g) item (f) as a percentage of items (a), (b), and (e). Provide the schedule in native Excel format derived from PowerClerk, and state why the Company’s response to ALLCO-057 omitted Level 2 and Level 3 applications. Q-ALLCO-120: (Follow-up to ALLCO-057 and ALLCO-007 — pendency.) For all applications pending at December 31, 2025, separately for Level 1, Level 2, and Level 3: (a) state the number pending less than one year, one to three years, three to five years, and more than five years after the application-received date recorded in PowerClerk; and (b) for each Level 2 or Level 3 application pending more than three years, identify the application number, the MW AC, the circuit and substation, the current PowerClerk status, the date of the most recent Company action, and the reason the application remains pending. Applicant identities other than Allco and its affiliates may be anonymized. Q-ALLCO-121: (Follow-up to ICC-011, ICC-017, and ALLCO-017 — PowerClerk milestone data.) The Company’s responses to ICC-011 and ICC-017 state that PowerClerk records “application status changes which are then used to track milestones,” and its response to ALLCO-057 states that the figures provided were “derived from PowerClerk.” Its response to ALLCO-017 states that the Company “does not track” the time between its receipt of a generator-executed interconnection agreement and its countersignature. (a) Identify each status, milestone, and date field that PowerClerk records for an application, and state for each whether a timestamp is captured automatically or entered manually. (b) For each Allco Application, produce the complete PowerClerk status-change history with the date and time of each status change, including the dates the application was received, deemed complete, screened, studied, approved (contingent or otherwise), the date an interconnection agreement was issued, the date a generator-executed agreement was received, the date of the Company’s countersignature, and the date of Permission to Operate. (c) For all Level 2 and Level 3 applications received from January 1, 2019 through the present, produce in native Excel format the same fields listed in (b). (d) State whether, in light of (a) through (c), the Company withdraws the statement in its response to ALLCO-017 that it “does not track” countersignature timing, and if not, reconcile that statement with the data PowerClerk records. Q-ALLCO-122: (Follow-up to ICC-008 — missed timeframes and ISO-NE review.) The Company’s response to ICC-008 states that a missed Guideline timeframe “does not, by itself, advance the project to the next stage, waive screens or studies, or require issuance of an 3Page 4 of 24
Interconnection Agreement,” and that “ISO-NE review required for projects greater than 1 MW is outside the state Guideline clocks and can extend the overall.” (a) For each Allco Application, identify each Guideline timeframe the Company did not meet, the applicable Guideline section, the date the timeframe expired, the reason it was missed, whether Allco requested a status update, and whether the Company provided the three-business-day response described in ICC008. (b) Identify the statute, regulation, Guideline provision, ISO-NE tariff or procedure, or Company practice on which the Company relies for the statement that ISO-NE review is “required for projects greater than 1 MW,” and state when the Company began applying that requirement. (c) For each Allco Application greater than 1 MW, state the date the Company referred the application to ISO-NE, the date of ISO-NE’s determination, the outcome, any study or fee required, and the elapsed time between application and issuance of an interconnection agreement. (d) State whether any provision of the Guidelines authorizes the Company to withhold issuance or countersignature of an interconnection agreement pending ISO-NE review, and identify it. Q-ALLCO-123: (ALLCO-034(d) — the legal advice on § 16-243p(b).) The Company’s response to ALLCO-034(d) states that it “has been advised by legal counsel that the confidentiality-designation and redaction work does not fall within any of the enumerated classes or categories of costs that are ineligible for recovery through rates under Conn. Gen. Stat. § 16243p(b)” because the work is “incurred to comply with legal obligations governing disclosure of public records and confidential information.” (a) Identify the counsel (firm and individual) who gave that advice, the date(s) on which it was given, and whether it was given orally or in writing. (b) Produce each opinion, memorandum, letter, e-mail, or other document containing or reflecting the advice. (c) If the Company withholds any such document on a claim of privilege, identify for each its date, author, recipients, subject matter, and the privilege claimed, and state whether the Company intends to rely on the advice of counsel, in whole or in part, to support recovery of any cost in this proceeding. (d) State, in the Company’s own words and with reference to the text of § 16-243p(b), each reason the Company contends that confidentialitydesignation and redaction work performed for filings and discovery responses in this proceeding is not a “direct or indirect cost[] associated with its … participation in” this rate proceeding; whether fees paid or payable to Keegan Werlin LLP for that work are “attorneys’ fees” within the statute; and whether the time of the Company’s internal legal counsel and project4Page 5 of 24
management staff devoted to that work is “the portion of employee salaries associated with such … participation.” (e) Identify every other category of cost of this proceeding that the Company contends is recoverable on the rationale that it is “incurred to comply with legal obligations,” stating for each the amount and the revenue-requirement schedule and line in which it appears. Q-ALLCO-124: (ALLCO-034(b) — supplementation.) The Company’s response to ALLCO-034(b) states that Keegan Werlin LLP “has not yet invoiced the Company” for redaction and confidentiality-designation services, that the Company “does not separately track” the time of internal resources on that work, and that the response “will be supplemented.” (a) State the date of Keegan Werlin LLP’s engagement for that work, the hourly rates or other basis of compensation, any budget or estimate, the hours recorded through September 30, 2026, and the amount invoiced or accrued through that date; and produce the engagement letter or other document defining the scope of the engagement. (b) State TCDI’s total billings through September 30, 2026 and the Company’s current estimate of total TCDI cost for this proceeding. (c) For each month since the Application was filed, state, by title, the hours and loaded cost of the Company’s and ESC’s internal legal counsel, project-management, regulatory, and other personnel devoted to confidentiality-designation and redaction work, using time records where they exist and, where they do not, a documented estimate stating its basis. (d) Identify the account(s) to which each amount in (a) through (c) has been charged and whether any amount has been deferred as a regulatory asset. (e) State the date by which the Company will serve the supplementation it has promised. Q-ALLCO-125: (ALLCO-034(c) — cost tracking for this proceeding.) The Company’s response to ALLCO-034(c) states that it “is tracking the costs associated with the redaction and confidentiality-designation work and plans to seek recovery for these costs in this proceeding.” (a) Identify the system, account, project number, work order, or other code the Company uses to track those costs. (b) State whether the Company tracks, by the same or any other means, every other cost of its attendance in, participation in, preparation for, or appeal of this proceeding — including outside counsel and consultant fees, expert fees, and the time of Company and ESC employees — and, if not, identify each category that is not tracked and explain how the Company proposes to demonstrate that such costs have been excluded from rates as § 16-243p(b) requires. (c) Produce, in native Excel format, the current balance of each tracked category of 5Page 6 of 24
proceeding-related cost, by vendor or employee group and by month, from May 20, 2026 through September 30, 2026. Q-ALLCO-126: (Windham Solar Facilities — estimate, collection, actual cost, and reconciliation.) With respect to the interconnection of the Windham Solar Facilities: (a) state the Company’s estimate of Upgrade costs as set out in Appendix G of the Interconnection Agreements as executed in May 2016 and as revised by each subsequent amendment, and the date of each; (b) state each amount the Company collected from Windham Solar LLC for interconnection costs, the date collected, and the account in which it was recorded; (c) state the actual cost recorded in the Company’s books for the Upgrades and interconnection facilities constructed for the Windham Solar Facilities, by work order and cost element, including any overhead or CIAC loaders applied, and produce the work-order cost detail in native format; (d) state each amount refunded or credited to Windham Solar LLC, the date, and the basis; (e) state whether the Company performed a final accounting or reconciliation of actual to estimated costs for that interconnection, and if so its date and result, and if not, why not; and (f) state the amount, if any, by which amounts collected exceeded the actual cost recorded in (c), and the current disposition of any such excess. Q-ALLCO-127: (Windham Solar Facilities — transfer-trip and substation components; post-2017 charges.) (a) State the estimated and the actual cost of the transfer-trip scheme and of the substation work included in the Upgrade estimate for the Windham Solar Facilities, identify the technology installed (power-line carrier, fiber optic, or other), and state who bore the cost of each. (b) Identify every charge billed to or withheld from Windham Solar LLC in connection with the Lebanon interconnection since September 1, 2017, including any operations and maintenance, ongoing, study, metering, or upgrade charge, stating the amount, date, and basis of each, or state that there have been none. Q-ALLCO-128: (Abington Solar Projects — line-extension estimate and CIAC.) With respect to the system impact study and cost estimate the Company provided for the Abington Solar Projects in or about 2017: (a) state the estimated cost of converting approximately 2.1 miles of single-phase 4.8 kV line to three-phase, the unit cost per mile on which it was based, and the source of that unit cost; (b) state the amount of the estimate designated as CIAC, the percentage applied, and the tax or other rationale for it, and identify the Company policy or tariff provision under which CIAC was assessed; (c) state whether the Company obtained or 6Page 7 of 24
considered any third-party contractor pricing for the work, and if so identify it; (d) state the Company’s actual average cost per mile for single-phase-to-three-phase line conversions completed in each year 2017 through 2025, and produce the supporting work-order data in native format; and (e) state whether the Company’s current interconnection cost estimates for line conversions are derived from actual historical unit costs, and if so identify the unit-cost tables used. Q-ALLCO-129: (ISO-NE Determinations — practice and timing.) The Company’s response to ICC-008 states that “ISO-NE review required for projects greater than 1 MW is outside the state Guideline clocks and can extend the overall.” For each calendar year 2023 through 2025 and 2026 to date: (a) state the number of Connecticut DG interconnection applications the Company referred to ISO-NE for a Determination, by Level and by size band; (b) state the criterion or criteria the Company applied in deciding to refer each application (including any practice that a generator greater than 1 MW connected to a substation with 20 MW of DER online and in queue requires a Level III transmission study), identify who formulated each criterion and when, and identify every communication with ISO-NE concerning it; (c) state the average, median, and maximum elapsed time from referral to Determination; (d) state whether the time an application spends awaiting a Determination is excluded from the interconnection-timeline metrics proposed in Exhibit CLP-CUSTOMER-1, and if so under what authority; and (e) produce, in native format, a schedule listing each referred application, the date of referral, the date of Determination, the outcome, and any study or fee required. Q-ALLCO-130: (ISO-NE Determinations — fees and study costs charged to customers.) For January 1, 2023 to the present: (a) identify every fee, study deposit, or cost (including system impact study fees and PSCAD or other modeling costs, and including the approximately $85,000 system impact study fee demanded in connection with the Spencer Hill Projects) that the Company has demanded, collected, or passed through to any Connecticut DG interconnection customer in connection with an ISO-NE Determination, review, or study, stating the application, amount, date, and current status; (b) identify the account(s) in which each such amount is recorded and state whether any such amount, or any Company cost of performing or supporting such studies, is included in rate base, the Test Year or Rate Year revenue requirement, or any tracker or deferral in this proceeding; and (c) state whether any such amount has been refunded or credited to the customer, and if so when. 7Page 8 of 24
Q-ALLCO-131: (Substation DER thresholds and SHARE.) (a) Identify each Company substation at which DER online plus DER in queue equals or exceeds 20 MW, including the Campville 14R substation, stating for each the DER online, the DER in queue, and the number and aggregate MW of pending applications; (b) for each such substation, identify any investment proposed in the Application (including under the SHARE proposal in Exhibit CLP-TSP-3) to expand hosting capacity or to relieve the constraint, its estimated cost, and its proposed rate treatment; and (c) state whether study fees, deposits, or upgrade payments collected from interconnection customers at those substations are, or will be, credited against the cost of any such investment before it is added to rate base, and if not, why not. Q-ALLCO-132: (Follow-up to ICC-005 and ICC-010 — monthly PowerClerk Reports and the executable-IA policy.) The Company’s response to ICC-010 states that “[m]anagement receives a monthly PowerClerk Report where Process timelines are reviewed to ensure that the timelines are adhered to,” and its response to ICC-005 states that “[t]he EDC cannot issue an executable Interconnection Agreement until applicable ISO-NE requirements are met.” (a) Produce each monthly PowerClerk Report, in native format, from January 1, 2020 to the present, and identify each metric, timeline, and milestone it reports and the recipients of the report. (b) State the date on which the Company adopted the policy that it will not issue an executable Interconnection Agreement until ISO-NE requirements are met, identify the Guideline provision, PURA order, ISO-NE tariff provision, or other authority on which it rests, and identify the document in which the policy is recorded. (c) For each Allco Application, state whether that policy was applied, the date the Company determined ISO-NE requirements had or had not been met, and the date, if any, on which the Company communicated that determination to the applicant. (d) State whether the policy in (b) is applied to applications of 1 MW or less, and if not, identify the Company’s basis for treating LEG-22708 and LEG-22709 (or any other Allco Application of 1 MW or less) as subject to ISO-NE review. Q-ALLCO-133: (Follow-up to ALLCO-055 — Burns & McDonnell charges billed to interconnection customers.) The Company’s response to ALLCO-055 states that $752,873 was paid to Burns & McDonnell for services relating to Connecticut distributed generation interconnection, that those amounts “are not in the cost of service or rate base,” and that they “are recorded to FERC Account 186010, and are then billed to customers / counterparties for reimbursable work.” (a) For each year 2018 through 2025 and the Test Year, state the total Burns 8Page 9 of 24
& McDonnell charges recorded to Account 186010 for Connecticut DG interconnection work and the total billed to interconnection customers, and identify each Allco Application to which any such charge was billed, the amount, the date, and the invoice or work-order reference. (b) State whether any percentage overhead, CIAC, or other loader was applied to Burns & McDonnell charges when billed to interconnection customers, and if so identify the loader and percentage. (c) State whether the project-management and administration functions performed by Burns & McDonnell are the same functions for which the Company applies a projectmanagement, administration, or overhead percentage to interconnection customers, and if not, describe the difference. (d) State the total Test Year and Rate Year cost of administering the Connecticut DG interconnection program that is recovered from ratepayers through the revenue requirement (ALLCO-010: $1,257,007 / $1,342,362) and, separately, the total amount of administration, project-management, or overhead charges collected from interconnection customers in each year 2018 through 2025, and explain how the Company ensures the same administrative cost is not recovered from both ratepayers and interconnection customers. Q-ALLCO-134: (Follow-up to ALLCO-059 and ALLCO-002 — CIAC offset timing and rate base.) The Company’s response to ALLCO-059 states that CIAC “would not be considered a component of rate base until the underlying capital project is placed in service,” that “the underlying capital project costs in rate base would be wholly offset by CIAC at the time of final project billing and reconciliation,” and that the Account 252500 balance was ($28,277,769) at June 2026. (a) Identify, in native format, each interconnection project placed in service from January 1, 2018 through June 30, 2026 for which CIAC or other interconnection-customer payments were collected but final project billing and reconciliation had not been completed as of June 30, 2026, stating for each the in-service date, the amount collected, the plant cost recorded, and the elapsed time since in-service. (b) State the aggregate plant in service at June 30, 2026 attributable to such projects that is included in rate base in this proceeding without a corresponding CIAC offset, and the revenue-requirement effect of that inclusion. (c) State the Company’s policy on the time within which final project billing and reconciliation is to be completed after in-service, and the average and maximum elapsed time actually experienced for projects placed in service in each year 2018 through 2025. (d) State whether the Company earns a return on plant funded by interconnection-customer payments during the period between inservice and reconciliation, and if so quantify it for the Test Year. (e) State the date by which the 9Page 10 of 24
Company will serve the supplementation promised in its response to ALLCO-059, and identify each element of that interrogatory it contends cannot be answered and why. Q-ALLCO-135: (Follow-up to ICC-005 — applications held pending ISO-NE requirements.) The Company’s response to ICC-005 states that any generating facility over 1 MW “must comply with ISO-NE rules, including Tariff Section I.3.9 and Planning Procedure 5,” and that “[t]he EDC cannot issue an executable Interconnection Agreement until applicable ISONE requirements are met.” (a) State the date on which the Company first withheld, delayed, or declined to issue an executable Interconnection Agreement on the ground that ISO-NE requirements had not been met, identify the application to which that first occurred, and, if that date differs from the policy adoption date given in response to Q-ALLCO-132(b), explain the difference. (b) Identify, in native (Excel) format, every distribution interconnection application in Connecticut, from January 1, 2018 to the present, to which the practice described in ICC-005 has been applied — that is, every application for which the Company has declined to issue, or has withheld, an executable Interconnection Agreement pending an ISO-NE review, screening, study, determination, or other requirement — stating for each: (i) the application number and PowerClerk identifier; (ii) the nameplate capacity in kW; (iii) the date the application was filed; (iv) the date the Company completed its own Guidelines-process review (or the current Guidelines milestone); (v) the date the Company referred the application to ISO-NE, the ISO-NE process invoked (Section I.3.9 proposed plan application, Planning Procedure 5 screening, Level I/II/III study, or other), and the ISO-NE queue or reference number, if any; (vi) the date of each ISO-NE determination or study result received, and its substance; (vii) the current status of the application with the Company (including whether an executable Interconnection Agreement has been issued and on what date) and with ISO-NE; (viii) the elapsed time from application filing to the issuance of an executable Interconnection Agreement, or to the present if none has been issued; and (ix) whether the applicant was notified in writing that the executable Interconnection Agreement was being withheld pending ISO-NE requirements, and on what date. (c) For each application listed in (b) that was subsequently withdrawn, cancelled, or deemed withdrawn, state the date and the stated reason. (d) State the number of applications in (b) that are 1 MW or less, and for each explain why the ISO-NE requirements described in ICC-005 for facilities “over 1 MW” were applied. 10
As listed on the current system
Interrogs from Allco Finance Limited to CL&P 119 thru 138-Issued 09/24/2026 [26-05-10]