Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 140

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy3 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files3

Search terms highlighted
Eversource rate increase is on 7 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
7 pages match
  1. Page 1 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 1 of 54 February 22, 2012 Update, Reply and PBR Plan Review for AUC Proceeding 566 – Rate Regulation Initiative 1
  2. Page 2 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 2 of 54 Project Team Jeff D. Makholm, Ph.D. Agustin J. Ros, Ph.D. NERA Consulting Economists 200 Clarendon Street, 11th Floor Boston, Massachusetts 02116 617+1 617 927 4500 617 +1 617 927 4501 2
  3. Page 3 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 3 of 54 Contents I. Introduction ..................................................................................................................................4 II. Executive Summary ....................................................................................................................4 III. NERA‘s TFP Study....................................................................................................................9 A. Suggestions for Improvements in the NERA Data Set ......................................................10 B. Truncation of the Time Period for Analysis ......................................................................13 C. Applicability of the TFP Growth Study for an Alberta PBR Plan .....................................17 1. ―Similarity to Alberta‖ .................................................................................................18 2. ―Data Problems‖ ..........................................................................................................21 3. ―Methodological Flaws/Inconsistencies‖.....................................................................22 4. ―Lack of Experience‖ ...................................................................................................24 IV. The Proposed PBR Plans .........................................................................................................25 A. Relevant Jurisdictions ........................................................................................................25 B. PBR Regulatory Precedent in Canada and the United States ............................................29 C. Common Features of PBR Plans for Canadian and US Energy Distributors ....................34 1. Inflation ........................................................................................................................34 2. X-factor ........................................................................................................................34 3. Z-factor ........................................................................................................................35 4. Earnings Sharing/Re-openers.......................................................................................35 5. Service Quality.............................................................................................................35 D. Uncommon Features of the Utilities‘ and Interveners‘ PBR Plans ...................................36 1. K-factor ........................................................................................................................36 2. Y-factor ........................................................................................................................39 3. Efficiency Carryover ....................................................................................................41 4. The Growth of ―Trackers‖ ...........................................................................................41 E. Pros and Cons of the Proposed PBR Plan Elements ..........................................................44 1. Inflation ........................................................................................................................44 2. X-Factor .......................................................................................................................44 3. Z-Factor........................................................................................................................47 4. Earnings sharing/Re-openers .......................................................................................47 5. Service Quality.............................................................................................................50 6. K-Factor .......................................................................................................................50 7. Y-Factor .......................................................................................................................51 8. Efficiency Carryover ....................................................................................................52 V. Appendix ...................................................................................................................................53 3
  4. Page 4 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 4 of 54 I. Introduction 1. The Alberta Utilities Commission (AUC) has asked NERA to participate as an independent expert in two ways in its performance-based regulation (PBR) initiative: (1) to undertake, explain and defend a total factor productivity (TFP) study that NERA considers useful for this PBR initiative in Alberta; and (2) to assess the PBR plans proposed by the Utilities, and the alternatives and modifications proposed by the interveners, against NERA‘s experience with relevant PBR regulatory practices in other relevant jurisdictions. NERA delivered a TFP study (along with the complete data set and computational spreadsheets), designed to be useful for electric and gas utilities in Alberta, in December 2010. In July 2011, NERA received the PBR submissions of the Utilities; in October 2011, NERA answered information requests from both the Utilities and interveners (and received the Utilities‘ responses to their own information requests); and in December 2011, NERA received the PBR submission of the interveners. NERA‘s TFP study and those filings constitute the basis for this report. II. Executive Summary 2. In the December 2010 TFP report, we emphasized the purpose of PBR in Canada and the United States: to permit regulated prices to change to reflect general price and industry productivity movements without the need for a base rate case, thus lengthening ―regulatory lag‖ and better exposing regulated utilities to the type of incentives facing competitive firms. NERA‘s TFP study employed now-familiar methods and empirical sources that are grounded in scholarly work pre-dating the advent of PBR. As an element of a regulatory plan that should provide incentives for utilities to seek profitable innovations, we stressed the importance of transparency, stability and objectivity in the formula that governs price movements between future base rate cases. We stated that objective uniformity in a readily-available source of data 4
  5. Page 5 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 5 of 54 for the industry TFP component of a PBR plan in Alberta is of paramount importance, and that only the Federal Energy Regulatory Commission (FERC) ―Form 1‖ data met such a standard. 3. The Utilities generally accepted our method and source of data as pertinent to PBR for Alberta gas and electric utilities. The differences in their TFP recommendations flow partly from using only the last 10-15 years of our study and partly from performing additional TFP computations using other sources. One intervener, the Consumers‘ Coalition of Alberta (CCA), recommended incremental improvements to our study, one of which we adopt as helpful that changes our result of average TFP growth from 0.87 percent to 0.96 percent. 1 Another intervener, the Office of the Utilities Consumer Advocate (UCA), recommended that our study should be disregarded as not relevant to Alberta utilities. 4. With respect to the Utilities‘ use of only a portion of NERA‘s time series, we respond by noting that there is no evidence of which we are aware, from disinterested or scholarly sources outside this proceeding, of an event or a circumstance that so changed the nature of the utility businesses tracked by the FERC Form 1 as to invalidate the relevance of the longest period represented by those data. PBR-based incentives for regulated firms are based on the value of long-term regulatory commitments, which in turn depend on the reasonableness and objectivity of the data and analysis used in their formation. The equilibrium prices in a competitive market (from which the incentives inherent in PBR plans are drawn) are themselves based on long-term trends. We know of no ex ante basis to be selective regarding the time period used to compute average TFP growth for the industry. In the absence of such external or scholarly reasons for truncating the time period, we continue to support the use of the largest time period available for empirical study as the most objective basis for the TFP component of a well-structured PBR plan. 11 The tables and backup that accompanied our original report are attached to this update. 5
  6. Page 6 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 6 of 54 5. With respect to the claim by the UCA that the TFP growth study is not applicable to Alberta utilities, we disagree. It is evident from the UCA‘s evidence, and its information requests (IRs) to NERA, that what troubles the UCA most is the lack of detailed data on a range of characteristics for the population of firms in the study (e.g., geography and climate) that would allow those companies to serve as ―proxies,‖ in the UCA‘s words, for Alberta utilities. But a TFP growth study for a well-structured PBR plan is not about finding proxy firms for the regulated utilities in question. Rather, it is about measuring underlying industry productivity growth trends representing the kind of diverse individual company circumstances that one would expect to see in a competitive industry. That is to say, we did not in the TFP growth study seek a ―model company‖ but an industry productivity growth trend. As such, we conclude that the UCA‘s general criticism of NERA‘s methods in performing a TFP study is not germane to our study. 6. With respect to the PBR plans proposed by the Utilities in general, and the alternatives and modifications proposed by the interveners, we draw a number of conclusions as requested by the AUC. The first concerned what can usefully be deemed ―relevant jurisdictions.‖ PBR started in the United Kingdom as an element of new regulatory institutions created for privatized utilities there. It appeared first in Canada and the United States in the regulation of telecommunications companies. We conclude, however, that neither utility regulatory jurisdiction outside North America nor the experience with telecommunications regulation is aptly relevant as a practical guide for the AUC in this proceeding. The regulation of utilities outside North America rests generally on a set of institutions that are newer and materially different than the longstanding regulatory institutions shaping rate regulation in Canada and the United States, and the X-factor plays a different role in those places. For telecommunication in 6
  7. Page 7 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 7 of 54 Canada and the United States, PBR was a bridge to genuine competition in the provision of such services and the demise of base rate cases generally, a circumstance not shared by energy distribution. 7. With respect to the elements of the Utilities‘ and interveners‘ PBR plans, most are familiar in PBR plans in Canada and the United States. For example, the inflation element, the X-factor for industry productivity (with or without a ―stretch‖ factor), the Z-factor (for exogenous cost-raising events) and the earnings sharing/reopener aspects of the proposed plans are broadly similar to what the AUC encountered in its 2009 case regarding ENMAX (Proceeding ID. 12). The service quality proposals come in two familiar forms: set standards (like AUC Rule 002) or reward/penalty mechanisms focussed on a group of measurable service standards. 8. Some of the elements of the Utilities‘ plans, however, are uncommon. EPCOR proposes to limit the PBR plan formula to labour and overhead costs only. Two of the utilities (three if one counts ATCO‘s electric and gas submissions separately) include a K-factor, which serves to embrace the forecast capital expenditure needs over the multi-year period of the plan. All of the utility plans propose what is called a Y-factor for various lists of pass-through and deferral items to be added to rates outside the PBR formula. To a greater or lesser degree, these aspects of the proposed PBR plans are derogations from theory underlying PBR and do not appear in PBR formulas from other North American jurisdictions. 9. We conclude that the uncommon features of the Utilities‘ PBR proposals are so owing to both conceptual and practical problems that other jurisdictions seem in general to have desired to avoid. EPCOR‘s proposal to limit the PBR to non-capital costs effectively cuts its proposal off from the economic theory upon which most North American PBR plans rest. To be sure, the 7
  8. Page 8 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 8 of 54 theoretical underpinning of PBR, which seeks to mimic competitive pressures in lengthening regulatory lag, imposes pressures on utilities that are in fact not competitive for the distribution utility services they provide. 10. Nevertheless, even for utilities, capital and labour/overheads have some degree of substitutability for which a ―total‖ factor productivity growth study is designed to allow. It is questionable in this respect whether a PBR regime based on ―partial‖ factor productivity (PFP), which presumes that capital and other costs are not substitutable, is worth the considerable effort that it takes to implement an ―inflation minus productivity‖ formula. 11. The K-factor proposals present more practical difficulties. Utility rate regulation in Canada and the United States generally rests on what is ―known and measurable,‖ which reflects the longstanding institutions of legislated accounting regulations and judicial precedent regarding the value of regulated property. Other regulators, like those in the United Kingdom and Australia, employ long-term forecasts (up to 8 years) of utility costs in rate making. But rate regulation in those countries is comparatively new and does not exhibit the accounting and constitutional foundations adopted decades ago in Canada and the United States. Given the general scepticism that North American regulators display with forecast costs for ratemaking, we do not think that the K-factor proposals are a practical part of a PBR plan, as such. 12. The Y-factor reflects pass through and deferral items that the Utilities would like to treat outside the ―inflation minus productivity‖ part of the PBR formula. To be sure, the process of having rates change for various cost items without a base rate case is becoming more common to regulation generally through the use of ―trackers,‖ quite apart from PBR regulation. Trackers make good sense in those jurisdictions that have them, as we review those plans in this study. Such trackers allow for the efficient and timely recovery of particular costs requiring specialized 8
  9. Page 9 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 9 of 54 treatment without necessitating a base rate case. We would recommend that each recommended tracker receive the same kind of specialized treatment, and ex post accounting, evinced by other regulators generally. We do not recommend that the PBR formula, as such, be expanded beyond what is customary in North America to become a catch-all for a broad base of deferral and passthrough items. We agree with the caution of the City of Calgary that a PBR plan should not come to resemble ―a 5-year test period under cost of service ratemaking.‖2 Such would more resemble the practices of jurisdictions in the United Kingdom and Australia, which we think is inconsistent with the deeper and more meticulous institutional foundation for rate regulation generally in Canada and the United States. 13. ―Efficiency carryover‖ mechanisms, which would make rates for subsequent periods somehow a function of performance in the prior period, are uncommon also. The sources of those suggestions is a desire to have the profit incentives of a PBR plan transcend to some degree the next base rate case, when rates would otherwise be squared with costs and profitable innovations capitalized for ratepayers. The discussions over whether to make PBR regulation more of a moving average with such efficiency carryover mechanisms are conceptual only. We have seen no evidence demonstrating that that particular innovation to PBR—a partial lengthening of regulatory lag—is worth the additional complications it would pose for the periodic future base rate cases. III. NERA’s TFP Study 14. NERA‘s TFP growth study prompted three types of reaction from the Utilities and interveners: (1) suggestions on improvements to NERA‘s data set; (2) truncations of the time period of the analysis of average TFP growth for the construction of an X-factor; and (3) 2 City of Calgary, page 6 of 57. 9
  10. Page 10 of 54

    The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 10 of 54 suggestions that the population of companies used to perform the TFP growth study is not applicable or useful in the current circumstances in Alberta. We will deal with these three reactions in turn. A. 15. Suggestions for Improvements in the NERA Data Set Pacific Economics Group Research LLC (PEG), on behalf of the CCA, recommends (at page 36) that we ―recalculate the labor quantity by taking the difference between the growth in salaries and wages and the inflation in a appropriate salary and wage price index using relation [4].‖ Relation [4] is: Growth Inputs = growth Cost – growth Input Prices. 16. This issue arises because, as we stated in our original report at page 9, ―[b]eginning in 2002, the FERC Form 1 no longer contains employee data‖ and ―we estimated the number of employees by using the previous years‘ electric distribution payroll growth rate for the years 2002 to 2009.‖ 17. We accept PEG‘s recommendation and use the growth in the U.S. Bureau of Labor Statistics (BLS) Series of Wages and Salaries in the utilities sector to determine an inflationadjusted electric distribution payroll growth for the years 2002 to 2009. We then use this inflation-adjusted electric distribution payroll growth for the years 2002 to 2009 to estimate the number of employees for those years. The U.S. BLS wage and salaries growth for utilities sector averaged approximately 3.1 percent during the period 2002 to 2009 (see table below). 10
Words on different pages

As listed on the current system

Question(s) Answered 140 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/09/2026