The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 45 of 54 require the meticulous gathering and processing of large data sets and are reasonably costly to perform. But they have a solid scholarly foundation that pre-dates their use for PBR plans, and they are capable of being readily updated in the future rate cases that such PBR plans call for. Most of all, such productivity growth studies are objective—a preeminent requirement given the money at stake over the multi-year runs of PBR plans and the role of the regulator as a quasijudicial arbiter of the traditional clash of interests between utility investor-owners and the public served by those utilities. Objectivity is the most important criterion—ability to replicate in the future is second. 96. The utility X-factor proposals offered by the Utilities cannot be labeled objective, in one of two ways. The first is the truncation of our study without an objective basis for doing so, which we discuss at length above. The second is in the ad hoc selection of productivity index numbers not representative of the industry in question or also for time periods that are not drawn from objective or scholarly sources outside this case—much the same issue as the truncation of our study. We do not mean to be excessively critical of the various discussions offered by Dr. Carpenter for ATCO, Dr. Cicchetti for Epcor, Dr. Schoech and Mr. Canfield for AltaGas, or Ms. Freyer for Fortis Alberta. However, the X-factors that they offer are based on time periods or sources that cannot be freed from these analysts‘ subjective judgment. For a parameter that will affect ratepayer bills for multiple years, we conclude that any deviation from objectivity is a drawback. 97. The X-factors recommended by the Utilities are uniformly negative. The theory upon which PBR is based, which draws from the pressures facing competitive firms, makes no distinction or restriction for the sign of the X-factor. But there are two practical considerations concerning what the Utilities have recommended in this regard. First, as an empirical matter, 45Page 46 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 46 of 54 negative X-factors are outside the realm of experience for PBR plans in North America. Second, we do not think that it would be misplaced for the AUC to question the imposition of a PBR plan that would dictate a period of automatic real price (or revenue) increase in light of the utility industry‘s very longstanding experience with the opposite trend. 98. Dr. Lowry and his PEG colleagues, for the CCA, perform an index number study of the same type as ours, using a 14 year period for measuring gas distributions costs. We do not know whether that is the longest possible time period available for the data used for that study, as the case with the NERA study. While we support Dr. Lowry‘s method, and we appreciate his suggestions for improvements for our own, we also note that he uses input data that he considers proprietary. Without those proprietary data, his study is not replicable by others—either now or at the time of the next base rate case when the parameters of the PBR regime would be subject to re-set. In any event, the X-factor that Dr. Lowry recommends is in the range that one would consider acceptable given experience for other energy utilities in North America. 99. Dr. Lowry also includes an econometric analysis to predict TFP growth that he describes as ―more customized to business conditions in Alberta.‖ Because any econometric analysis of the factors that contribute to the size of the TFP growth numbers in a index study is unavoidably the result of many judgments that are difficult for non-specialists to understand, we would not recommend such econometric analyses for the purpose of setting the level of consumer prices in a PBR plan—as opposed to econometric studies for peer-reviewed scholarly research. 100. We have no opinion on the stretch factor recommended by Dr. Cicchetti. Ultimately, stretch factors are subjective judgments on the extent to which, given the history of the utilities in a jurisdiction, the change to PBR may spur innovation and cost reduction not shown 46Page 47 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 47 of 54 previously. We have not studied the Alberta utilities for such purposes, and hence we cannot offer an opinion. 3. 101. Z-Factor Regulators commonly use Z-factors to protect utilities against material events outside of their control—just as competitors in an industry would all adjust prices for exogenous cost changes that affect them all. All of the Utilities and interveners propose a Z-factor, and we support the practice. 4. 102. Earnings sharing/Re-openers An ESM reduces the risk of a PBR plan unintentionally tipping the regulatory balance in favor of customers or shareholders. As the AUC stated in Decision 2009-035, p. 57: [m]ost parties [in the ENMAX PBR application] suggested that earnings sharing should be adopted if the Commission considers that there is a significant risk of setting the productivity target either too high or too low. UCA in particular noted that PBR design errors, such as mistaken estimates of potential productivity, can result in sizeable increases in regulated monopolies‘ profits. … The earnings sharing mechanism was viewed by parties as an important safety measure to limit such increases. 103. We agree. While an ESM can reduce efficiency incentives, it may be prudent to include them to reduce regulatory risk. 50-50 sharing of earnings of excess earnings and earnings shortfalls is the most common sharing agreement and does not favor either customers or shareholders. Including a ―deadband‖ within which utilities do not share deviations in earnings improves efficiency incentives, but increases financial risks for customers and shareholders alike. 47Page 48 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 48 of 54 104. Under certain circumstances, the PBR plan may warrant amendments or termination before the end of the term of the plan. All of the applicants propose re-openers and off-ramps to amend or adjust the PBR plan if circumstances warrant such a change. Re-openers and off-ramps are common aspects of incentive plans, and we recommend such a mechanism in the current plan. 105. Earnings sharing reduces the incentives to the company, as when earnings are shared the company keeps less than the full profit it earns. Regulatory ―recontracting,‖ and the threat of it, also reduces the company‘s incentives. A balance between these two needs could include no sharing whatsoever. The early U.S. telecommunications plans featured earnings sharing mechanisms (along with relatively broad Z-factors and duration of less than 5 years). Since 1994, the duration until the first review for new plans has been five years or longer. Similarly, although earnings sharing was fairly common in early plans, no plan adopted after 1993 has included sharing.32 106. Earnings sharing can lend stability to a PBR regime, particularly one that is in its first generation. At the outset, no one can say with certainty that the parameters set will prove to be the right ones—parameters that result in the company having a reasonable opportunity to earn a fair return on its investments while still not rewarding the company unduly. The stabilizing effect of earnings sharing can be depicted as in Figure 2. 32 Tardiff, T. and Taylor, W.E., ―Revising Price Caps: The Next Generation of Incentive Regulation Plans,‖ Topics in Regulatory Economics and Policy, Crew, Michael A. (Ed.), Vol. 24, Springer, 1997. 48Page 49 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 49 of 54 Figure 2. Ex Post Profit Sharing Ex Post Profit Sharing ROR Range A 6.4-10.0 0.00 B 10.0-13.0 0.50 C > 13.0 0.75 kept Price Cap Recontracting Prevention (rebate) = 0.75 8.2% = 0 A 107. Sharing Line = 0.5 B C reported In Figure 2, 8.2 percent is shown as the target cost of capital for illustrative purposes.33 The dead band is 1.8 percent. If the company earns between 6.4 and 10 percent, there is no profit-sharing. If the company earns between 10 and 13 percent, it shares one half of the profits earned in that interval. If the company earns in excess of 13 percent, it shares one half of the profits from 10 to 13 percent plus 75 percent of the profits above 13 percent. In the Figure, losses are treated symmetrically. 108. The shaded area is the size of the rebate. The rebate dampens both the company‘s profits and losses. This dampening effect grows as the reported profits deviate by a greater degree from the allowed return. The rebate lessens the incentive to recontract. This protection from recontracting grows. It does so as achieved profits for the year deviate from what was expected when the profit sharing regime was set up. 33 This is purely as an illustration. Actual capital costs for utilities in Canada are higher. 49Page 50 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 50 of 54 109. The cost of earnings sharing is that, to the extent sharing is in effect (i.e., outside the dead band), it dampens the incentives of a company to innovate to cut costs and expand sales. That is, some efficiency incentives are given up in return for a more stable regime. In Figure 2, the sharing line slopes upward, but at a decreasing rate as we move away from the origin (denoting that the sharing percentage increases). At expected profit levels, little or no sharing takes place and companies have full incentive to maximize profits. As profits increase, the level of sharing increases as well. The shape of this sharing line can help to provide a natural stability for PBR plans. 5. 110. Service Quality We agree with the perspectives of Dr. Cicchetti for Epcor and Dr. Lowry for the CCA on the question of service quality—that a plan to include a balance of rewards and penalties is a useful part of a PBR regime. To be sure, AUC Rule 002 is a reasonable benchmark for maintaining safe, adequate, and reliable service in the public interest. Nevertheless, PBR is driven by a belief in the power of profit incentives, and we are not in possession of any information that would lead us to conclude that balanced rewards and penalties—which dominate among North American PBR plans—are unwise to implement in Alberta. 6. 111. K-Factor Among the Utilities, the stated goal of K-factors is to ensure that the companies recover prudent capital expenditures. Of course, the regulatory compact generally specifies that utilities recover prudently-incurred costs in a in a reliable and timely manner. But PBR plans generally do not include K-factor provisions. The OEB, for its part, described the rationale for excluding such elements for the second generation PBR plan for Ontario electricity distributors: 50Page 51 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 51 of 54 Typically, an incentive regulation mechanism is intended to encompass both capital and operating costs. This increases incentives for operating performance. In a capital intensive business such as electricity distribution, containing capital expenditures is a key to good cost management. The addition of a capital investment factor would mean that incentive under the price cap mechanism would be significantly reduced because the factor would address incremental capital spending separately and outside of the price cap. Further, it would unduly complicate the application, reporting, and monitoring requirements for 2nd Generation IRM because it would require special consideration to be implemented effectively.34 112. We would agree, as a general matter. Utilities must make capital expenditures to continue to operate in a safe and reliable manner; however these expenditures may be treated in a manner better targeted than an encompassing K-factor. Numerous regulatory bodies have adopted infrastructure trackers (see Section D.) for specific capital expenditures, and that is the approach we recommend here. The capital expenditures that are candidates for such trackers must be comparatively unusual and narrowly defined (such as cast iron pipe replacement for gas distributors or specific aged infrastructure replacement for electric distributors). The AUC did not approve a capital factor in its 2009 decision regarding Enmax.35 7. 113. Y-Factor Y-factors operate under the premise that management and/or ratepayers should not be held responsible for costs beyond their control. We agree. However, this classification of costs should be very limited. An overly broad Y-factor would reduce efficiency incentives under PBR. 114. The Utilities propose a variety of Y-factor items. Some have more precedence than others. We recommend that the Commission carefully examine each of the proposed Y-factor items to determine whether they satisfy the criteria for flow through that it set out in Decision 34 OEB, December 20, 2006 Report of the Board on Cost of Capital and 2 nd Generation Incentive Regulation for Ontario‘s Electricity Distributors, p. 37. 35 AUC Decision 2009-035. 51Page 52 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 52 of 54 2009-035: ―[F]low through rate adjustments arise from cost elements that are not unforeseen one time events. Flow-through items arise in the normal course of business, but are such that the company has no control over them.‖36 115. While the Commission did allow flow-through treatment for three specific items in the ENMAX Order, the Commission went on to state, ―EPC proposed that the above items be included in the Commission approved FBR formulas as an ―F‖ adjustment. The Commission does not consider it necessary to include these elements in the rate adjustment formulas because they are not rates adjusted by the formulas. They will continue to be treated as they are currently.‖37 8. 116. Efficiency Carryover As we have stated above, efficiency carryover mechanisms are uncommon in North America. We conclude that it is best to view the issue as a desire to lengthen regulatory lag by other means and could well be dealt with in that context. To be sure, the Utilities that support the measure offer only conceptual arguments for it. As such, we do not think that there is a reason for the AUC to depart from generally accepted practice and avoid the incremental complexity of an efficiency carryover mechanism. 36 AUC Decision 2009-035, p. 55. 37 AUC Decision 2009-035, p. 55. 52Page 53 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 53 of 54 V. Appendix Table 7. Examples of Electric Recovery Mechanisms for Qualified Investments State Arkansas Company SWEPCO Tracker Name Generation Recovery Rider Eligible Investments Rider allows recovery of costs associated with the Stall generating facility that has received a certificate of environmental compatibility and public need issued by the Arkansas Public Service Commission California Southern California Edison Advanced Metering Infrastructure Balancing Account Colorado Public Service Company of Colorado Transmission Cost Adjustment Expenditures up to the total authorized funding level of $1,633.5 million are deemed reasonable and the revenue requirement associated with those expenditures shall be recovered through the SmartConnect (Advanced Metering Infrastructure) without any after-the-fact reasonableness review. Rider to recover ongoing costs, other than operating and maintenance costs, associated with incremental transmission investments. Iowa MidAmerican Energy Cooper Tracking Mechanism Louisiana Cleco Power Infrastructure and Incremental Costs Recovery Missouri Atmos Energy Infrastructure System Replacement Surcharge The infrastructure system replacement surcharge (ISRS) covers only a part of the expenses that the Company must incur to maintain and upgrade its system and to relocate facilities in connection with local, state and federal public improvement projects. New Jersey Public Service Electric and Gas Solar Loan II Program Allows the Company to recover costs to install 51 MW of solar on homes, businesses and municipal buildings. Ohio Duke Energy Ohio Infrastructure Modernization Rider Infrastructure Modernization to recover increased costs for maintaining and modernizing the distribution system, including SmartGrid investments and a $9 million investment in an electronic bulletin board to enable Duke and alternative power suppliers to post market prices for consideration by consumers. Oklahoma Oklahoma Gas and Electric Smart Grid Rider Tariff Rider to recover up to $20 million of capital O&M costs related to company-proposed SmartPower deployment of 42,000 smart meters in Norman, OK. Pennsylvania PPL Electric Utilities Renewable Energy Development Rider Recover costs associated with installing a device or devices not exceeding 10 KW which are, in the Company’s sole judgment, a bonafide technology for use in generating electricity from qualifying renewable energy installations. Additions Tracker provided a mechanism for recovery of the amount of Cooper Nuclear Station capital expenditures filed with the Iowa Utilities Board for recovery through the application of the tracker. The Infrastructure and Incremental Costs Recovery Mechanism applies only to Acadiana Load Pocket Transmission Project. Source: Company Tariffs 53Page 54 of 54
The Connecticut Light and Power d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 24, 2026 ALLCO-140 Attachment 1 Page 54 of 54 Table 8. Examples of Gas Recovery Mechanisms for Qualified Investments State Georgia Company Atlanta Gas Light Tracker Name Pipeline Replacement Program Illinois Peoples Gas Light and Co Rider Incremental Cost Recovery Indiana Vectren North Distribution Reliability Adjustment Mass. Bay State Gas Targeted Infrastructure Factor Mass. National Grid Targeted Infrastructure Factor The Massachusetts DPU issued a decision in a rate case for National Grid Massachusetts companies Boston Gas, Essex Gas and Colonial Gas. The DPU adopted targeted infrastructure recovery factors for the companies. The TIRFs provide for the recovery of costs associated with the accelerated replacement of gas mains and the companies are allowed to surcharge customers up to 1% of total revenue. Michigan SEMCO Cap. Infrastructure Investment Auto. Adj. Mechanism This mechanism will enable SEMCO Energy to recover the incremental capital-related costs associated with the accelerated removal and replacement of cast iron and unprotected steel service lines and mains. Nebraska All NG Utilities NA New Hamp. National Grid Texas Atmos Energy Corp. Cast Iron Bare Steel Replacement Bare Steel Pipe Replacement Utah Questar Gas The ISRS allows the rates of a gas utility to be adjusted twice per year to provide for the recovery of costs of eligible infrastructure system replacements. New Hampshire – National Grid New Hampshire - Energy North Natural Gas Energy North Natural Gas has had a Cast Iron Bare Steel (CIBS) Replacement Program for several years. This rate is designed to recover costs related to the Company‘s steel service line replacement program. A risk-based approach will be adopted to allow replacement of the highest priority steel service lines within this time period. The Utah PSC authorized Questar Gas to implement a three-year pilot Infrastructure Replacement Adjustment (IRA) mechanism to track and recover between rate cases the costs associated with the replacement of high-pressure natural gas feeder lines. (1) Age and performance of existing pipeline (2) Reconditioned pipe (3) Operating and maintenance history. (4) Pipeline safety compliance. Infrastructure Replacement Adjustment Eligible Investments The Atlanta Gas Light Pipeline Replacement Program is a 15-year project to replace more than 2,300 miles of bare steel and cast iron natural gas pipeline in Georgia. Each year in the fall, the Georgia PSC reviews the company‘s infrastructure replacement expenses from the previous year and then approves the new surcharge amount. Peoples Gas Light & Coke‘s tracking mechanism for investments related to gas main replacement programs was authorized in 2010 and implemented in 2011. The program covers replacement mains and related appurtenances such as services, meters, regulators, measuring and regulating stations, city-gate check stations, and other ancillary infrastructure. North received approval to implement a tracking mechanism that allows the utility to defer expenses associated with investments in infrastructure replacement projects. Vectren defers the recovery of depreciation expense and property taxes and continues to utilize the allowance for funds used during construction (AFUDC) for 4 years from the date that each replacement was put in service. Columbia Gas of Massachusetts received approval of its Targeted Infrastructure Reinvestment Factor (TIRF) as part of its last base rate case in October 2009. The TIRF allows for the recovery of the revenue requirement associated with bare steel capital additions for the previous calendar year, including: mains, services, service tie-ins, meters, meter installations, regulators, and industrial measuring and regulating equipment. Source: Company Tariffs 54
As listed on the current system
Question(s) Answered 140 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/09/2026