Extracted from the file · 1 page · 576 characters

Text of ALLCO-027 Attachment 3.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ALLCO-027 Attachment 6 REDACTED (CL&P RFP).pdf

Extracted from the file · 5 pages · 7,247 characters

Text of ALLCO-027 Attachment 8 REDACTED.pdf

Extracted from the file · 2 pages · 514 characters

Text of ALLCO-027 Attachment 9.pdf

Extracted from the file · 1 page · 741 characters

Text of ALLCO-027 Attachment 9.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ALLCO-027 Attachment 4 REDACTED.pdf

Extracted from the file · 409 pages · 1,259,015 characters

  1. Page 159 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 159 of 238 3.0. NSTAR GAS PRICING STRUCTURE: PHASE I WORK 3.1. PBR Pre-Filed Written Evidence Item Description (Role, Material, etc.) Julia Frayer Ma. Cherrylin Trinidad Marie Fagan Barbara Porto Hannah Braun Lorenzo Perez Brian Redmond Sub-Total Self-Performed Work: 3.2. Unit varies by task varies by task varies by task varies by task varies by task Varies by task Varies by task USD per hour USD per hour USD per hour USD per hour USD per hour USD per hour USD per hour Unit Price Cost $ 66,465.00 PBR Research and Support Work Item Description (Role, Material, etc.) Ma. Cherrylin Trinidad Hannah Braun Sub-Total Self-Performed Work: 3.3. Quantity Quantity Unit varies by task varies by task USD per hour USD per hour Unit Price Cost $ 28,935.00 TFP and Report Item Description (Role, Material, etc.) Julia Frayer Barbara Porto Brian Redmond Sub-Total Self-Performed Work: Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Quantity Unit varies by task varies by task Varies by task USD per hour USD per hour USD per hour Unit Price Cost $ 18,225.00 Page 37 Eversource Confidential
  2. Page 160 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 160 of 238 3.4. Benchmarking and Report Item Description (Role, Material, etc.) Julia Frayer Marie Fagan Lorenzo Perez Sub-Total Self-Performed Work: Quantity Unit varies by task varies by task Varies by task USD per hour USD per hour USD per hour Unit Price Cost $ 39,667.50 3.5. Meetings Unit Price Cost $ 4.0. NSTAR GAS PRICING STRUCTURE: PHASE II WORK 4.1. Responding to Data Requests Item Description (Role, Material, etc.) Julia Frayer Ma. Cherrylin Trinidad Hannah Braun Lorenzo Perez Brian Redmond Sub-Total Self-Performed Work: Quantity Unit varies by task varies by task varies by task varies by task varies by task USD per hour USD per hour USD per hour USD per hour USD per hour Unit Price Cost $ 39,020.00 4.2. Additional Analysis / Research Work Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 38 Eversource Confidential
  3. Page 161 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 161 of 238 Item Description (Role, Material, etc.) Ma. Cherrylin Trinidad Hannah Braun Lorenzo Perez Brian Redmond Sub-Total Self-Performed Work: Quantity Unit varies by task varies by task varies by task varies by task USD per hour USD per hour USD per hour USD per hour Unit Price Cost $ 27,950.00 4.3. Meetings Item Description (Role, Material, etc.) Julia Frayer Ma. Cherrylin Trinidad Hannah Braun Sub-Total Self-Performed Work: Quantity Unit varies by task varies by task varies by task USD per hour USD per hour USD per hour Unit Price Cost $ 17,950.00 4.4. Rebuttal Testimony Item Description (Role, Material, etc.) Julia Frayer Ma. Cherrylin Trinidad Hannah Braun Lorenzo Perez Brian Redmond Sub-Total Self-Performed Work: Quantity Unit varies by task varies by task varies by task varies by task varies by task USD per hour USD per hour USD per hour USD per hour USD per hour Unit Price Cost $ 15,650.00 4.5. Testifying as Expert Witness / Preparation Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 39 Eversource Confidential
  4. Page 162 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 162 of 238 Item Description (Role, Material, etc.) Julia Frayer Ma. Cherrylin Trinidad Sub-Total Self-Performed Work: Quantity Unit varies by task varies by task USD per hour USD per hour Unit Price Cost $ 14,380.00 4.6. Assist with Legal Briefs Item Description (Role, Material, etc.) Julia Frayer Ma. Cherrylin Trinidad Hannah Braun Lorenzo Perez Brian Redmond Sub-Total Self-Performed Work: Total estimated project expenses Quantity Unit varies by task varies by task varies by task varies by task varies by task USD per hour USD per hour USD per hour USD per hour USD per hour Unit Price Cost $ 6,480.00 $3,000.00 TOTAL FOR NSTAR GAS PHASE I AND PHASE II WORK : $290,722.50 TOTAL PHASE I & II: $710,418.50 TOTAL PHASE I & II WITH 10% DISCOUNT: $ TOTAL WITH ADDITIONAL TIERED VOLUME DISCOUNT: Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 40 Eversource Confidential
  5. Page 163 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 163 of 238 EXHIBIT D: STATEMENT OF WORK December 16, 2025 Subject: Adjusted proposal for the Development and Support for Performance-Based Ratemaking Plans for NSTAR Gas/ CL&P To the Eversource Energy Procurement Team: Pursuant to an email received from Eversource on December 9, 2025, London Economics International LLC (“LEI”) submits this cover letter in connection with the Development and Support for Performance-Based Ratemaking (“PBR”) Plans request for proposal (“RFP”) issued on November 7, 2025. LEI submitted three proposal variations to this RFP: the original proposal dated November 14, 2025,1 a proposal with additional discounts on November 18, 2025,2 and then an alternative proposal with reduced scope of work that resulted in a reduced budget on December 1, 2025.3 In the December 9, 2025 email, Eversource confirmed that it would like to move forward with total factor productivity (“TFP”) and benchmarking studies for both the NSTAR Gas and CL&P rate case applications and requested that LEI “send over a new cover letter including this in the cost.” This cover letter responds to the request from Eversource on December 9, 2025. LEI has used the alternative proposal from December 1, 2025 and added back the additional hours for the TFP and benchmarking studies identified in the original proposal. The TFP and benchmarking studies were included in Phase I scope of work and therefore the Phase I budget has increased. At this time, LEI has conservatively assumed that Phase II estimated effort does not change, nor have we adjusted the staffing to include the possibility of other testifying witnesses for the TFP and benchmarking studies. 1 LEI’s original technical and cost proposal was submitted via Ariba on November 14, 2025. In that proposal, LEI included TFP and benchmarking as optional studies for both the NSTAR Gas and CL&P rate case applications. The cost proposal (prepared in Excel format) presented the professional budgets applicable to the TFP and benchmarking work for both the NSTAR Gas and CL&P cases, were Eversource to choose to move forward with this work. The total budget inclusive of both studies for both rate cases (Phases I and II) totaled just under $839,000 (approximately $365,000 for the NSTAR Gas rate case and $474,000 for the CL&P rate case, inclusive of $6,000 for expenses across the two projects). LEI applied a 10% courtesy discount to this total amount—resulting in a total professional budget of about $755,000. 2 LEI was given the opportunity to provide a price discount on November 18, 2025. That same day, LEI provided an updated price proposal that consisted of additional, tiered discounts: an additional 5% discount after $500,000 in billings; an additional 5% discount after $600,000 in billings; and an additional 5% discount after $700,000 in billings. LEI proposed that this tiered volume discount apply on top of the 10% courtesy discount from the original proposal—bringing the total professional budget down to about $740,000. The scope of work remained unchanged from that described in the original technical proposal from November 14, 2025. 3 On November 26, 2025, the RFP was reopened to allow bidders the opportunity to reduce their price proposals further. In response, on December 1, 2025, LEI submitted an alternative proposal that (1) removed TFP and benchmarking studies from the Phase I scope of work for both the NSTAR Gas and CL&P rate cases and (2) reduced the number of staff hours for the Phase II budget. The TFP and benchmarking studies were removed because they were not explicitly requested in the original RFP. The reduced hours for Phase II reflected the possibility that regulatory staff and intervenors would be asking fewer questions, based on the industry precedent around PBR regulatory topics in both Massachusetts and Connecticut. In any case, Phase II effort would continue to be invoiced on time and materials (“T&M”) basis and therefore invoices would be issued only for actual hours expended. Given the change in scope, the total budget estimate under this alternative proposal totaled $499,000 (approximately $219,000 for the NSTAR Gas rate case and $280,000 for the CL&P rate case, and was inclusive of $6,000 for expenses across the two projects). Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 41 Eversource Confidential
  6. Page 164 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 164 of 238 This results in a total effort of over 1,570 hours across Phase I and Phase II for both rate applications and undiscounted professional fee budget of about $710,000, inclusive of an expense budget of $3,000 per rate application. Applying the 10% courtesy discount from the original proposal from November 14, 2025 and the additional tiered volume discounts from November 18, 2025 results in a total professional fee and expense budget of about $629,000. A summary of the new overall budget, and how it has evolved over the course of this RFP process, is provided in Figure 1. Figure 1. Progression of the budget Original proposal (11/14/2025) with additional tiered discounts (11/18/2025) New proposal Alternative with TFP and proposal benchmarking (12/1/2025) (12/16/2025) NSTAR Gas Phase I $ Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 42 Eversource Confidential
  7. Page 165 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 165 of 238 Phase II $ Total expenses $ Total $ 364,942.50 $ 218,722.50 $ 290,722.50 $ 280,421.00 $ 419,696.00 CL&P Phase I $ Phase II $ Total expenses $ Total $ 473,926.00 Total (Phase I & II) $ $ Total with 10% courtesy discount -- $ Total with additional, tiered volume discount $ -- 629,376.65 Ma. Cherrylin Trinidad Director Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 43 Eversource Confidential
  8. Page 166 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 166 of 238 2 Workplan LEI to group the various tasks into three workstreams, as shown in Figure 1. Workstreams #1 and #2 will be worked on concurrently, with the work performed culminating in the direct pre-filed testimony in Workstream #3. These workstreams apply to both the NSTAR Gas and CL&P cases; the difference lies in the timing given the different filing dates envisioned by Eversource for its two affiliates. Figure1. Proposed tasks under each orkstream W Phase #1 Workstream #1: Prepare PBR ratemaking mechanism plan 1.1 Develop PBR ratemaking mechanism Workstream #2: Research alternative PBR plans 2.1 Review alternative proposals in regional jurisdictions 2.2Review updates in Massachusetts/Connecticut PBR proceeding 2.3Evaluate Company’s cost performance under current plan 2.4Confirm compatibility of plan with existing mechanisms and requirements Phase #2 Workstream #3: Prepare and defend -filed pretestimony 3.1 Present direct pre -filed testimony to support PBR proposal s 3.2Defend methods used to determine elements and adjustment factors 3.3Support proposals based on responses to information requests 3.4Assist in interrogation of testimony as may be submitted by other parties 3.5Attend technical sessions and evidentiary hearings for direct and cross examination 3.6Assist in drafting of legal briefs submitted to regulators 2.1 Workstream #1: Prepare a PBR ratemaking plan Workstream #1 consists of one task, which is developing the PBR ratemaking plans that will be filed to the Massachusetts and Connecticut regulators. 2.1.1 Designing the PBR ratemaking plan LEI has provided reliable testimony backed by strong empirical evidence. LEI is also at the forefront of understanding the most pertinent issues as well as evolutions that are both regulatory and market in nature that concern distribution utilities, as well as potential opportunities that these issues may present in the future. LEI will be able to prepare PBR policy testimony supporting each Company’s PBR proposal and how these proposals work better to align the interests of customers, regulators, and shareholders. This will not only include underlying principles and general benefits to customers of PBR but also specific benefits of the Companies’ proposed PBR plans. Combined with LEI’s knowledge of global developments in PBR regimes in the US, Canada, and Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 44 Eversource Confidential
  9. Page 167 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 167 of 238 across jurisdictions globally, LEI will be able to utilize and incorporate utility industry trends in its PBR policy testimony for NSTAR Gas/CL&P. Generally, a well-designed PBR plan is consistent and has a clearly delineated, challenging, yet also achievable value proposition that focuses on cost efficiency and reliability. The PBR plan also needs to show that the formula and selected components create a “win-win” solution, where both the interests of customers and the utilities are considered and balanced against each other. Moreover, the PBR plan should be able to demonstrate that it is consistent with recent industry trends and is appropriate given current business conditions. This can be done by backing up the submission with discussions of economic theory and real-world experiences, such as reference to recent productivity trends in the market and regulatory developments in other jurisdictions. Lastly, the plan should highlight the Company’s success stories—to show what the Company has done and what it will continue to do. This can be done through case study examples or “business cases.” An econometric benchmarking study will be especially useful in this regard. There are various components of PBR; determining the individual components right for the Company requires careful consideration and must also be viewed holistically. This is because the choice of one parameter may influence the selection of other components. For example, the X factor is not independent of the inflation factor because an inflation index using macroeconomic output-based measures must take some level of productivity gains into account. LEI understands the language of PBR and can clearly articulate these important considerations and provide supporting evidence. LEI also has years of experience working with Eversource and its outside counsel—we also have a firm grasp of the language that Eversource prefers to use in its filings and the concerns it has when filing cases to the Massachusetts and Connecticut regulators. It is critical to consider not just appropriate component parameters but also their interaction in combination. For example, an earnings sharing mechanism (“ESM”) may dampen the incentive for efficiency improvements by sharing savings achieved by the utility with customers. The term of the PBR regime should also be considered in light of the X factor. Utilities generally prefer PBR terms that align with their perceived ability to perform vis-àvis the X factor. For example, a well performing utility may prefer a longer term that provides a longer potential period over which to reap the “rewards” of efficiency. In contrast, utilities that are not confident about achieving their productivity targets may view a shorter period as a lower risk proposition. In this regard, the Massachusetts and Connecticut PBR plans are likely to differ. LEI will provide guidance with regards to the potential implications (including financial) of different PBR rate case elements on the Company and how to put together a compelling rate case filing. LEI has assisted several utilities in identifying potential PBR components to include in their regulatory and ratemaking regimes. Generally, PBR components include choice of an inflation factor, X factor, treatment of certain capital expenditures (discussed separately below), performance standards, ESMs, the treatment of unforeseen and exogenous events (using exogenous factors or triggers), length of the regulatory period, and the triggers for an “exit” or “off ramp.” We will also provide our input on the PBR components that NSTAR Gas/CL&P may already be considering—as we did when we worked with Yankee Gas. LEI has extensive accumulated experience with PBR applications across North America, as well as with the treatment of distributed networks. LEI also specifically has experience working on PBR development together with Eversource in both Massachusetts and Connecticut. LEI has assisted utilities in determining the appropriate components of PBR, including rebasing applications for the end of the PBR term. As such, LEI would be qualified to guide and support Eversource in developing the PBR components as well as other PBR elements such as capital trackers and risk-mitigation mechanisms. 2.2 Workstream #2: Research alternative PBR plans LEI to perform four tasks under Workstream #2. These tasks include reviewing alternative proposals in regional jurisdictions for requirements and precedents of PBR plans, reviewing PBR developments in Massachusetts and Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 45 Eversource Confidential
  10. Page 168 of 238

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Date Issued September 2, 2026 ALLCO-027 Attachment 5 REDACTED Page 168 of 238 Connecticut, evaluating the cost performance of NSTAR Gas/CL&P under their current respective rate plans, and confirming the compatibility of LEI’s PBR proposals with existing mechanisms and requirements of Eversource’s existing recovery mechanisms. LEI will review the PBR proceedings in Massachusetts and Connecticut to understand PBR precedent given to date by the MA DPU/ PURA for the states’ utilities.4 LEI will also research other jurisdictions in ISO-NE (Maine, New Hampshire, and Vermont, and/or Massachusetts and Connecticut, if LEI is only chosen to support Eversource on one of the two rate cases) to determine alternative PBR plans and precedent that have arisen from recent rate case proceedings and decisions. These rate case proceedings will encompass both electric and gas utilities. If requested, LEI may reach further out than the New England states for this jurisdictional overview. LEI will also evaluate the cost performance of NSTAR Gas/CL&P under their current plans and confirm the compatibility of LEI’s PBR proposals with existing mechanisms and requirements of Eversource’s existing recovery mechanism. 2.3 Workstream #3: Prepare and defend pre-filed testimony LEI offers six tasks under Workstream #3. These tasks include presenting direct pre-filed testimony to support LEI’s PBR proposal, defending the methods used to determine elements and adjustment factors in the testimonies, defending the PBR proposals as information requests get filed by the regulator and other parties, assisting Eversource in the interrogation of testimony as may be submitted by other parties, attending technical sessions and evidentiary hearings for direct and cross examination of the proposals, and assisting in drafting of legal briefs. This Workstream would follow Workstreams #1 and #2, as those Workstreams will culminate in LEI’s PBR ratemaking mechanism proposals in preparation of the pre-filed testimonies. 2.3.1 First two tasks: Present direct pre-filed testimony to support LEI’s PBR proposals that defend the methods used to determine elements and adjustment factors in such testimonies LEI will draft the pre-filed testimonies that will support the overall alternative ratemaking proposals and defend the approaches used to determine any proposed elements or adjustment factors to the existing PBR regimes. In addition to the scope of work described in the previous sections, LEI will prepare testimony in support of the merits of NSTAR Gas’s/CL&P’s PBR proposals, highlighting factors including (but not necessarily limited to): • core economic rationales for and general benefits to customers from PBR; • financial incentive properties of the Company’s PBR proposals and its anticipated benefits for customers; 4 Given LEI’s intimate understanding of the revenue adjustment reopener in Docket No. 21-05-15RE01, LEI would spend the majority of its time familiarizing itself with the decisions made in the performance mechanisms (Docket No. 21-0515RE02) and distribution system planning (Docket No. 21-05-15RE03) reopeners. LEI is also monitoring the docket for the final decision in Docket No. 21-05-15RE01 on the revenue adjustment mechanism. PURA has neither updated its calendar nor provided any indication of when the final decision will be issued. However, since the Yankee Gas decision was issued recently (November 5, 2025), LEI assumes that the revenue adjustment mechanism decision should be issued relatively soon. Cover Agreement – 2026 PBR NSTAR and CL&P London Economics International Page 46 Eversource Confidential

Text of ALLCO-027 Attachment 7 REDACTED (1).pdf

Extracted from the file · 41 pages, 19 without text · 46,195 characters

As listed on the current system

Question(s) Answered 27 (CL&P dba Eversource Energy) Date Filed: 09/24/2026

This filing on the current system (opens in a new tab)