Text of CIEC-043_Final.pdf

Extracted from the file · 1 page · 1,715 characters

Words on different pagesRead the text of CIEC-043_Final.pdf

Text of CIEC-044_Final.pdf

Extracted from the file · 1 page · 979 characters

Words on different pagesRead the text of CIEC-044_Final.pdf

Text of CIEC-045_Final.pdf

Extracted from the file · 1 page · 2,237 characters

Words on different pagesRead the text of CIEC-045_Final.pdf

Text of CIEC-046_Final.pdf

Extracted from the file · 1 page · 2,520 characters

Words on different pagesRead the text of CIEC-046_Final.pdf
Words on different pages
  1. Page 1

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CIEC-09 Date Issued October 29, 2026 CIEC-047 Page 1 of 2 Date Filed: November 12, 2026 Witness: Edward A. Davis and Kimberly R. Parsons Request from: Connecticut Industrial Energy Consumers Question: Please refer to the Rates Panel Testimony at page 24, lines 18-22, and page 25, lines 1-8. a. Please state whether the Company has a definition of “data center” or “large-scale computational load” that it would use to determine whether a customer’s load is data center load. If so, provide it. b. Please identify the number of inquiries the Company has received since January 1, 2024 regarding new or expanded load from (i) data centers and (ii) manufacturing or other industrial customers, by size range. Response: a. Please see the Company’s response to CIEC-036 i. b. Such information is not readily available. Prior Referenced Response: i CIEC-036 Question: With reference to the Panel’s response to OCC-464, explain whether: a. b. The term “large-scale computational loads” includes only data centers, or if it also may be applied to other non-residential loads. There are specific criteria that Eversource uses to define what constitutes a “data center”? If the answer is in the affirmative, provide and explain the criteria. CIEC-036 Response: a. The Company’s response relied on “data center” as the context for what is meant by the term “large scale computational load” referred to. b. There may be many different types of customers and loads whose characteristics fall within the classification of a data center. The State of Connecticut’s Office of Legislative research report, “Data Center Energy Impacts and State Responses” refers to a description of a data center as, generally, “a physical facility that houses and runs large computer systems.” The report further provides: “A data center typically contains
  2. Page 2

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CIEC-09 Date Issued October 29, 2026 CIEC-047 Page 2 of 2 multiple computer servers, data storage devices, and network equipment to store, manage, process, and transmit large amounts of data”. 1 The term “large-scale” provides additional specificity regarding what might be attributable to a specific data center. As stated in response to OCC-464, the Company believes the appropriate treatment of such loads, including whether a specific rate or customer-specific terms are warranted should be determined through deliberations with state agencies when that load materializes. “Data Center Energy Impacts and State Responses”, Connecticut General Assembly, Office of Legislative Research, 2025-R-0164, Mary Fitzpatrick, October 14, 2025 1

Text of CIEC-048_Final.pdf

Extracted from the file · 3 pages · 4,409 characters

Text of CIEC-049_Final.pdf

Extracted from the file · 2 pages · 5,446 characters

Words on different pagesRead the text of CIEC-049_Final.pdf

Text of CIEC-050_Final.pdf

Extracted from the file · 2 pages · 2,003 characters

Text of CIEC-052_Final.pdf

Extracted from the file · 3 pages · 6,788 characters

Words on different pagesRead the text of CIEC-052_Final.pdf

As listed on the current system

Question(s) Answered 38, 42, 43, 44, 45, 46, 47, 48, 49, 50, 52 (Connecticut Light and Power Company dba Eversource) Date Filed: 11/12/2026

This filing on the current system (opens in a new tab)