Interrogatory responses
Answers to questions 11
Files3
CLF-011 Attachment 20.pdf
PDF · 4.8 MB · 106 pagesText searchable
Download CLF-011 Attachment 20.pdfRead the text of CLF-011 Attachment 20.pdf
CLF-011 Attachment 21.pdf
PDF · 9.5 MB · 268 pagesText searchable
Download CLF-011 Attachment 21.pdfRead the text of CLF-011 Attachment 21.pdf
CLF-011 Attachment 22.pdf
PDF · 2.5 MB · 29 pagesText searchable
Download CLF-011 Attachment 22.pdfRead the text of CLF-011 Attachment 22.pdf
Page 11 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 11 of 106 1 CBA analyses, the assumption was that those were 2 zero. 3 incentives at the time and the input from the 4 potential study being that our customers would likely 5 need to see 100 percent incentive from the utility in 6 order to move forward with a change in type of 7 technology. And that was just based on the volatility of So, yes and no. 8 9 They are in there, but they are currently assumed as zero. COMMISSIONER GILMAN: 10 And does that even 11 include other utility incentives? 12 the Company's beneficial electrification and clean 13 heat incentives that would be applicable to people in 14 the NPA areas already? WITNESS JONES: 15 For example, like Good question. So there 16 is a line item in the CBA for utility incentive. It 17 doesn't disaggregate whether or not that funding is 18 from the DSM/BE Plan, the Clean Heat Plan, or 19 otherwise. And I think that was intentional given 20 21 that the cost recovery mechanism is at issue in this 22 case. 23 you know, in addition to what was already funded or 24 where the mechanism would come from. 25 lumped into the utility incentive category. It wasn't clear whether or not that would be, So it was just 11Page 12 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 12 of 106 COMMISSIONER GILMAN: 1 Okay. So, in 2 essence, what the Company counts in the NPA CBA -- 3 this is torture for someone who doesn't know these 4 acronyms -- but what the Company assumes they are for 5 the incentive given for the purpose of NPA, is the 6 bulk incentive from the utility even if a portion of 7 that would have been given, anyway, under the Clean 8 Heat Plan regardless of the NPA or not? 9 WITNESS JONES: That is correct. 10 COMMISSIONER GILMAN: Okay. Let me see. 11 Like I said, I wished to be more organized, but here 12 we are. The GIP M docket also directed the Company 13 14 to apply appropriate discounting to the equipment 15 costs based on the average age of existing equipment 16 to properly acknowledge that customers inevitably 17 have a cost to change out their equipment even if 18 they don't electrify even just to get new gas 19 equipment. 20 So I wanted to confirm if you are 21 understanding the Company had done that in the CBA 22 that they run. 23 WITNESS JONES: Yeah. So I recall the 24 miscellaneous docket decision recommending that we 25 consider adding that kind of benefit for gas 12Page 13 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 13 of 106 1 appliance replacements, I think is what you are 2 mentioning. And at this point, the Company still 3 4 stands by including those, but not quantifying those. 5 And the main reason for that is that we do not have 6 proper information on what customer appliances are. 7 Therefore, that type of discount would really be a 8 guess, at best. The one thing that I will say, though, is 9 10 within the CBA tool, if you note, there is a 11 different line item for different measures. 12 one line item for early replacement and another line 13 item for replace on burnout. 14 lesser incentive for if it's a replace on burnout 15 appliance. And we are offering the So not exactly the same intention, but did 16 17 We have kind of attempt to reconcile that discrepancy. COMMISSIONER GILMAN: 18 Okay. But as you 19 characterize participant costs -- like cost to 20 participants to, say, electrify, do you assume any 21 discount for the inevitability that their equipment 22 will have to be replaced at some point in time, 23 anyway? 24 25 WITNESS JONES: Yeah. So to clarify, I think you mean participant cost as in like equipment 13Page 14 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 14 of 106 1 cost paid out of the pocket from the participant? 2 COMMISSIONER GILMAN: 3 WITNESS JONES: 4 Correct. That was not discounted, that is correct. COMMISSIONER GILMAN: 5 And did you 6 understand that to be a directive from the GIP M 7 docket? 8 WITNESS JONES: I understood it to be a 9 recommendation from the M docket, but one that the 10 Company still believes is pretty skeptical at this 11 point given that our lack of understanding on each 12 individual appliance. 13 COMMISSIONER GILMAN: Okay. And then just 14 quickly as to the electric impact that the Company 15 assumes in the projections for basically electric 16 capacity, whether distribution, generation, 17 transmission. 18 As I understand it, the Company is 19 essentially taking the estimated gas load at peak, 20 converting it into kilowatt hours from Btus, and then 21 applying a COP of one assuming, essentially, electric 22 resistance level efficiency. 23 how that is happening? Is that accurate as to 24 WITNESS JONES: That is correct. 25 COMMISSIONER GILMAN: And is that 14Page 15 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 15 of 106 1 happening at essentially the extrapolated level of 2 use at negative 39 degrees Farenheit for that 3 equipment? 4 WITNESS JONES: Yes. 5 COMMISSIONER GILMAN: Okay. For the 6 marginal electric distribution capacity costs, the 7 GIP M docket directed the Company to estimate the 8 winter peak hour demand, convert it to electricity by 9 accounting for some diversity of equipment operating 10 at the peak hour, electric resistance backup, heat 11 pumps, as well as some load control ability. And further indicated that the costs 12 13 should also consider the location of the NPA, 14 equipment, capacity, temperature impacts depending on 15 whether the peak hour is in the summer or winter, and 16 the timing of the load related to that as well as the 17 timing of the expense. 18 So I didn't see any acknowledgement of 19 these considerations in the CBA methodology, but I 20 just wanted to check if any of those considerations 21 were inputted into the CBA methodology. WITNESS JONES: 22 Yeah, so this topic is 23 discussed briefly in my supplemental direct 24 testimony, but maybe just to reiterate what was said 25 in there. 15Page 16 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 16 of 106 So for the Eastern Mountain Gas System, we 1 2 currently have a winter peaking system, at least on 3 the distribution side of the house. 4 peak occurs in the evening as opposed to the gas peak 5 in the morning. And that winter But it's pretty close. So for the purposes of the CBA, we assumed 6 7 that the heating peak would be 100 percent 8 coincidental with the existing peak for the purposes 9 of analysis. COMMISSIONER GILMAN: 10 But for the 11 electrical equipment capacity, do you assume that 12 that happens in the summer even though the peak is in 13 the winter given that electrical equipment tends to 14 have a higher capacity at lower temperature range? WITNESS JONES: 15 I'm not sure that I 16 understand the question. Could you maybe rephrase it 17 or restate it for me one more time? COMMISSIONER GILMAN: 18 Sure. To the 19 extent -- and I think this was covered in the GIP M 20 docket. 21 temperature could impact a transformer or other 22 distribution system equipment, and that lower 23 temperatures may advantage having higher capacity 24 available on those, has the Company assumed some of 25 that in their assumptions for the impact on, say, But to the extent that the ambient 16Page 17 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 17 of 106 1 distribution system peaks, especially considering 2 that those distribution system peaks are projected to 3 happen at cold temperatures, not hot temperatures? 4 WITNESS JONES: For the purpose of CBA 5 analysis, no. 6 Company witness Thompson if that was considered at 7 all as he evaluated what electric distribution system 8 infrastructure upgrades may be required to support 9 the Mountain Energy Project. 10 WITNESS THOMPSON: 11 12 You might want to follow up with So I can follow up with that, Grace. The capacity of the feeders that we use 13 would essentially be the summer peaking system. 14 thing I will say is there is several different 15 variables with it, right? You have elevation that 16 you have to account for. You have to account for 17 wind speed, ambient temperature. 18 One So there is a lot of inputs that account 19 for that capacity. 20 looking into in terms of capacity -- the available 21 capacity of the feeders in the winter months. 22 And it is one thing that we are COMMISSIONER GILMAN: As it is currently 23 done, you are using the kind of weather expectations 24 of the summer even on the portion of the system that 25 is winter peaking and for the addition of these loads 17Page 18 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 18 of 106 1 that are adding to a winter peak rather than a summer 2 peak? WITNESS THOMPSON: 3 4 From my understanding, yes, that's correct. COMMISSIONER GILMAN: 5 Okay. In the CBA, 6 curious on the avoided gas commodity cost if the 7 Company grossed that up at all to account for lost 8 and unaccounted for gas as was directed in the GIP M 9 docket. 10 WITNESS JONES: So for this application, 11 that wouldn't necessarily be appropriate because the 12 avoided gas commodity was from the baseline gas 13 infrastructure project, which was also a supplemental 14 supply facility. 15 the area, there is really no line loss associated 16 with transportation of that gas. 17 COMMISSIONER GILMAN: And so since it's all localized in Okay. Then the GIP 18 M docket also directed the Company to utilize the 19 actual revenue requirement associated with the 20 infrastructure project -- understandably, this is a 21 slightly different animal given that the 22 infrastructure project is also a supplemental 23 supply -- in order to appropriately capture the 24 actual expected cost of the project is expected to be 25 borne by ratepayers. So I'm curious if the Company 18Page 19 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 19 of 106 1 has made any adjustments to their CBAs in that 2 regard. WITNESS JONES: 3 So I think this was 4 discussed in the miscellaneous docket, but it is the 5 Company's position that we could either look at 6 revenue or net salvage. 7 direction of including the net salvage value in order 8 to appropriately quantify what the actual capital 9 investment would be of any electric infrastructure or 10 gas infrastructure. And the Company took the COMMISSIONER GILMAN: 11 Okay. Related to 12 indoor air pollutants, the M docket also directed the 13 Company to try to quantify indoor air pollutant 14 impacts where possible. 15 an update if the Company has attempted to do so or 16 included in any information in the CBA in that 17 regard. 18 And I was just curious for WITNESS JONES: The Company still does not 19 believe that there is really a justifiable or 20 quantifiable measure or method in order to determine 21 those indoor air pollutants. 22 but not quantified. So they were included 23 I will also say that it's my opinion that 24 those would pretty much be de minimis in the overall 25 look of net present value at this scale. 19Page 20 of 106
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 20 Page 20 of 106 COMMISSIONER GILMAN: 1 Okay. So just to 2 clarify in my mind, is it the Company's position that 3 there are no indoor impacts or -- indoor air quality 4 impacts, or that you don't have a quantifiable number 5 to use to represent the indoor air quality impacts? WITNESS JONES: 6 Thank you for clarifying. 7 It is the latter, the quantification method. 8 COMMISSIONER GILMAN: Okay. So as part of 9 the settlement, you know, it seems to me that the 10 Company appears to be expecting that the CBA will, at 11 least to some degree, be relitigated in the 2025 Gas 12 Infrastructure Plan that was filed in May; and that 13 the Company is essentially planning to use that CBA 14 framework, whatever comes out of the 2025 GIP, in the 15 December 2028 Mountain Energy filing. 16 if you followed all that, but if you can confirm that 17 is the plan. WITNESS JONES: 18 Yes. I don't know But I would also 19 clarify that that language was really added as a 20 method to like clarify that whatever the most recent 21 planning tools are, those should be the tools used in 22 2028. 23 are going to use our most updated methodology. 24 25 So it goes a little bit without saying that we But we wanted to make sure that there was a specific point within the settlement order to 20
As listed on the current system
Question(s) Answered 11 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 08/27/2026