Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 26, 28, 29, 33, 34, 37, 38, 40

Files10

Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of BETP-033_Final.pdf

Extracted from the file · 1 page · 1,388 characters

Words on different pagesRead the text of BETP-033_Final.pdf

Text of BETP-033 Attachment 1.pdf

Extracted from the file · 7 pages · 14,274 characters

Text of BETP-034_Final.pdf

Extracted from the file · 1 page · 1,700 characters

Words on different pagesRead the text of BETP-034_Final.pdf

Text of BETP-037_Final.pdf

Extracted from the file · 1 page · 999 characters

Words on different pagesRead the text of BETP-037_Final.pdf

Text of BETP-038_Final.pdf

Extracted from the file · 1 page · 1,030 characters

Words on different pagesRead the text of BETP-038_Final.pdf
Words on different pages
  1. Page 10 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 10 of 31 Step 1: Define Risk Scenarios The first step in Risk Assessment is to review existing plans, studies, after action reports, and other resources to define specific Risk Scenarios to include as part of the Risk Assessment. A Risk Scenario (as described in the Framework) is a hypothetical situation comprising of a threat (e.g., flooding, cyber attack, or extreme heat) and an energy infrastructure asset (e.g., electric power substation) or system (e.g., electric transmission and distribution network) impacted by that threat. For example, a review of existing resources may reveal that hurricanes are a major and increasing threat to coastal areas of the state and that past hurricane events have caused significant power outages. Based on this information, a Risk Scenario may be developed that involves the threat of a Category 3 hurricane to the electric grid in the state’s coastal region. Other scenarios may be similarly constructed in the Risk Assessment and may vary based on the nature of threats and energy infrastructure in the state. Specific information related to threat, vulnerability, and consequence for each Risk Scenario would be collected during the stakeholder engagement process in Step 3, and additional Risk Scenarios may be identified during this process. The initial definition of Risk Scenarios may be informed through a review of existing threat resources, including the State’s Hazard Mitigation Plan (HMP), Threat and Hazard Identification and Risk Assessment (THIRA), or existing studies from local universities or others. Additional resources for assessing state threats and hazards are listed in Appendix C. U.S. Threat Data Resources. Energy infrastructure assets and systems include electric sector assets such as power plants, transmission lines, and substations; petroleum sector assets such as refineries, pipelines, and storage terminals; and natural gas sector assets such as gas processing plants, transmission pipelines, and storage facilities. A full list of energy infrastructure asset and system types, along with resources for geospatial information, is provided in Appendix D. Energy Infrastructure Geospatial Data Resources. Not all infrastructure in this Appendix needs to be considered in the Risk Assessment. The scope of the Risk Assessment may be limited to those infrastructure assets or systems whose loss may have a significant consequence to the state. Resources for understanding and assessing the consequence or criticality of energy infrastructure can be identified in the SESP Energy Profile (see outline published at State Energy Security Plan (SESP) Resources hub) or by reviewing other existing studies of state or regional critical energy infrastructure. Forward Looking Threat Assessment If conducting an independent threat or hazard assessment, state officials may need to consider the impact of changing climatic conditions on historical probabilities. Approaches to adapt forwardlooking climate information to assess threat probabilities may include (but not limited to) the following: 1. Weighting recent years (~10-15 years) more heavily when calculating threat probability over long historical periods. 2. Applying long-term trends to recent threat probability assessments to increase or decrease threat probabilities over time. 3. Using adapted or downscaled results from global climate models as the basis for forecasts.
  2. Page 11 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 11 of 31 Conducting an Energy Infrastructure Threat Assessment If no existing threat assessment resources exist, an independent assessment may be conducted by analyzing climate data from various government sources (NOAA, USGS, etc.) and mapping those threats against energy infrastructure. GIS data sources for energy systems and assets can be found in Appendix D. Energy Infrastructure Geospatial Data Resources, and threat data sources can be found in Appendix C. U.S. Threat Data Resources. If conducting an independent threat assessment, it may be important to consider the impact of changing climates on historical threat probabilities. The White House Office of Science and Technology Policy’s (OSTP) March 2023 guide on Selecting Climate Information to Use in Climate Risk and Impact Assessments provides high-level guidance on selecting resources (e.g., data, tools, reports, case studies) for understanding climate threats, with a particular focus on understanding exposure to current and future climate-related threats and their potential impacts. Step 2: Identify Key Stakeholders After defining Risk Scenarios, key energy sector stakeholders should be engaged to build on the existing knowledge and understanding of risk. Key energy sector stakeholders may include state agencies and regulators, energy infrastructure operators, and others with equities in strengthening energy infrastructure security, reliability, and resilience. The exact number and selection of stakeholders will vary from state to state based on the structure of the state government and specific Risk Scenarios being assessed. Before engaging private sector entities, it is encouraged to review and discuss Risk Scenarios with state agencies, especially the state energy office, emergency management agency, the state fusion center, and the public utilities commission. In many states, it may be important to also engage the governor’s office and tribal and local governments to include necessary perspectives. When identifying relevant energy infrastructure owners and operators to engage, a starting point is to review the state’s SESP Energy Profile. Relationships between the private sector and government are crucial to effective communication and information sharing; it is important to understand which agencies in your state have existing relationships with energy infrastructure owners and operators before approaching them for information. In states with only a few energy providers or infrastructure operators, it may be feasible to conduct stakeholder interviews with every major operator. In other states, it may be practical to engage directly with only the largest operators while collaborating with local or regional industry groups that represent collections of smaller operators. For example, working with a state petroleum marketers association, which represents sellers and distributors of petroleum products; a state municipal electric association, which represents public power providers; or a critical infrastructure working group convened by a state’s emergency management agency may provide sufficient insights to inform the risk assessment.
  3. Page 12 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 12 of 31 Exhibit 4. Examples of Potential Risk Assessment Stakeholders Government • State energy office • State public utilities commission • State emergency management agency • State governor’s office • State fusion center • U.S. Department of Energy (DOE) • U.S. Army Corps of Engineers • U.S. Coast Guard • State National Guard • Local governments • Tribal governments • State public health agency • U.S. Department of Homeland Security, Cybersecurity, Infrastructure Security Agency (DHS CISA) security advisors • U.S. Department of Defense (DOD) Energy Infrastructure Owners/Operators • Investor-owned utilities • ISO/RTOs • Rural and municipal electric association • Rural electric cooperatives • Municipal utilities • Independent power producers • Petroleum marketers association • Petroleum pipeline operators • Petroleum terminal Operators • Petroleum refiners • Natural gas association • Natural gas pipeline operators • Natural gas local distribution companies (LDCs) • LNG terminal operators • Propane marketers association • Heating oil distributors • Retail fuel sellers • Port operators • Rail operators Other • National Association of State Energy Officials (NASEO) • National Association of Regulatory Utility Commissioners (NARUC) • Local universities/colleges • Critical energy consumers (e.g., hospitals, water treatment facilities) • Airport fuel farm operators • Trade organizations • Military bases
  4. Page 13 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 13 of 31 Step 3: Engage Key Stakeholders After key stakeholders have been identified, the next step is to engage these stakeholders to discuss the Risk Scenarios defined in Step 1 and to gather relevant information about energy infrastructure risk, including information on threats, energy infrastructure vulnerabilities, and the consequences of energy infrastructure outages. APPROACHES TO STAKEHOLDER ENGAGEMENT There are various approaches to engage stakeholders including: • • • Group meetings allow for engagement with multiple stakeholders (either virtual or inperson) at the same time. Group meetings are particularly effective for communicating information out to multiple parties but may be less effective at gathering information from industry due to general reluctance by industry to discuss challenges in an open forum. Individual stakeholder interviews offer the opportunity to gather company-specific information, ask follow-up questions as needed, and generally allow for more indepth discussions in a closed setting. Conducting individual interviews can be time consuming, depending on the number of interviews, and can take longer to identify contacts and schedule. Questionnaires facilitate the collection of a consistent set of information from multiple entities with a relatively low level of time and effort. Significant time and care may be needed to design survey questions to capture clear and consistent responses. While this approach works well for specific, well-framed questions, it may limit the depth of information collected. Surveys may include a mix of question types (e.g., multiple choice, rating scale) to capture responses in a variety of formats but may require open-ended fields to allow stakeholders to clarify or expand on their responses. The approaches above are not mutually exclusive, and stakeholder engagement often works best when multiple approaches are utilized. For example, a successful engagement may start with several stakeholder group meetings (e.g., for electric utilities, petroleum marketers) to explain the goals of the Risk Assessment. To emphasize the importance of the effort to energy infrastructure owners and operators, high-ranking government officials may be invited to make remarks, such as representatives from the governor’s office, public utility commissioners, or members of the emergency management agency. The group meetings may be followed up with surveys to quickly gather specific and consistent information related to the Risk Assessment from multiple parties. Finally, individual interviews may be scheduled with larger infrastructure operators to gather more details or supplement the information collected through the surveys. STAKEHOLDER ENGAGEMENT BEST PRACTICES The following best practices are recommended to ensure that efforts to engage and gather information from stakeholders are successful: • Leverage existing contacts across the state government to set up engagements with energy infrastructure operators. Many state agencies already work with energy infrastructure operators, typically in a regulatory fashion. For example, the state public utility commission typically oversees the state’s investor-owned electric and
  5. Page 14 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 14 of 31 • • • • natural gas utilities; state environmental agencies may regulate emissions and/or emergency response plans for power plants, refineries, pipelines, and terminal operators; and the state department of transportation may register HAZMAT vehicles, such as tanker trucks, that distribute petroleum products. Working through state or regional industry groups, such as state petroleum marketers associations, may help facilitate engagements with infrastructure operators in the state. Review publicly available information before engaging stakeholders. Private sector entities participating in Risk Assessment will typically be doing so on a voluntary basis. State engagements should be focused on gathering information that is not already in the public domain. Reviewing the SESP Risk Profile, company annual reports, or information published by the Energy Information Administration will provide a baseline of understanding and will allow the discussion to focus on nonpublic information. Explain the purpose of the SESP. Prior to requesting information from stakeholders, it is important to help stakeholders understand the purpose and necessity of the SESP and the Risk Assessment. This includes describing the goals of SESP, why the stakeholder’s participation is important, and how the results of the Risk Assessment may be used to inform energy sector Risk Mitigation strategies that may affect the stakeholder. Furthermore, it may be important to emphasize during initial outreach that the development of the SESP is not a regulatory activity and that participation in the SESP process will not be used to punish or penalize industry. Define key risk terms and rating scales to ensure clarity. Throughout stakeholder interactions, it is helpful to provide precise definitions of key terms such as 'threat,' 'vulnerability,' and 'consequence'. To the extent that stakeholders provide numeric or non-numeric ratings of risk components, rating scales should be clearly defined to ensure consistency. Use non-disclosure agreements (NDAs) and other protections to assure confidentiality. Private companies are generally reluctant to share business-sensitive information or information that may provide insight into weakness or vulnerabilities in their systems that could be exploited. It is important to provide assurances to participating companies that information shared with the state will remain confidential and will not be released publicly either intentionally or unintentionally. This may involve the use of non-disclosure agreements (NDAs) and/or the use of legal protections that prevent gathered data or information from disclosure. The National Governors Association published a paper on State Protection of Critical Energy Infrastructure (CEII) that contains some examples of state laws designed to protect this information. STAKEHOLDER QUESTIONS Stakeholder interviews should be designed to collect specific information on the threat, vulnerability, and consequence of the Risk Scenarios being considered by the Risk Assessment. Questions for stakeholders may involve a mix of specific questions designed to gather specific information and open-ended questions that allow the stakeholders to discuss broader risk and risk mitigation topics. Discussions with stakeholders may identify additional Risk Scenarios that may be included in the Risk Assessment. Optionally, questions may be asked about potential Risk Mitigation Measures related to the Risk Scenarios under consideration to help inform the SESP Risk Mitigation Approach.
  6. Page 15 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 15 of 31 Step 4: Develop Risk Problem Statements In Step 3, specific information was collected on the threat, vulnerability, and consequence of select Risk Scenarios—hypothetical situations involving specific threats to specific energy infrastructure assets or systems. For each Risk Scenario, this information may be summarized using the Risk Assessment Template (see Exhibit 3) to develop a Risk Problem Statement that clearly describes and details the threat, vulnerability, and consequence of the Risk Scenario. An example of a Risk Problem Statement is presented in Exhibit 5 below. Risk Problem Statements should be developed for each of the Risk Scenarios evaluated as part of the Risk Assessment.
  7. Page 16 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 16 of 31 Exhibit 5. Example Risk Problem Statement Risk Scenario A: 2-foot Flooding /Big State City Substations THREAT VULNERABILITY CONSEQUENCE RISK The Big State River in the southern district of Big State City has flooded three times over the past 20 years, including twice in the past 5 years with river levels reaching as high as 1.5 feet above flood stage during the 2021 flood event. Flooding has occurred more frequently in recent years due to new developments impacting stormwater drainage in Big State City and due to more frequent high-precipitation rainfall events. According to current climate projections, heavy rainfall events are expected to occur more frequently in the future, increasing the threat to assets located in the floodplain. Current flood prevention measures at Big State Utility’s electric power substations in the southern district of Big State City are sufficient to prevent flooding when river levels are up to 2 feet above flood stage. Beyond 2 feet, existing flood prevention measures would be insufficient to protect the facility, which would be severely damaged if fully inundated. Repairs to inundated substation infrastructure would likely take several weeks to fully repair. Big State Utility estimates that 5 of its high-voltage substations (69-kV+) are potentially exposed to the flood threat and that these substations serve a total of approximately 100,000 customers in the southern district of Big State City. Simultaneous loss of all 5 substations would leave about 25% of Big State City without power, including the downtown commercial district and Big State City Hospital, which is the largest of three hospitals in Big State City. Big State City Hospital has an emergency backup generator capable of serving critical facility loads, but this generator can only operate for approximately 48 hours before refueling. If flooding along the Big State River exceeds 2 feet, existing flood protections could be exceeded at approximately five Big State Utility high-voltage substations that serve the southern district of Big State City, potentially disrupting power supply to the downtown commercial district, including Big State City Hospital.
  8. Page 17 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 17 of 31 Step 5: Calculate Risk Scores The final step in Risk Assessment is to develop ranks, scores, or tiered ratings for each Risk Scenario using information detailed in the Risk Problem Statements. Calculating Risk Scores allows Risk Scenarios to be compared with one another on a consistent basis, which may help inform the Risk Mitigation Approach and other planning activities. While there are many ways to calculate Risk Scores or ratings, it is important that whatever method used be consistently applied across Risk Scenarios. This guidebook provides a simple approach that: • • • Assesses a relative score/rating to each of the three risk components that make up the Risk Assessment formula (threat, vulnerability, and consequence) for each Risk Scenario. Calculates a total Risk Score for each Risk Scenario by multiplying the component scores in the Risk Assessment formula (see Exhibit 1 in the chapter on Risk Assessment Framework). Compares the total Risk Scores for each Risk Scenario in a table or Risk Matrix. This approach may be expanded to include additional risk components, utilize different rating scales or component weightings, or other adjustments that take state-specific situations and priorities into account. For example, some states may choose to expand the consequence component into separate direct and indirect consequence components. Whatever the choice of methodology, any factors, scales, or weightings used should be clearly explained when Documenting the Risk Assessment. ASSESSING COMPONENT SCORES Assigning scores for each of the key risk components requires the use of clearly defined scales that relate to underlying quantitative metrics (e.g., annual event probability) or qualitative descriptors. Risk scales can correspond to the underlying metrics in various ways, including uniform scales, adjusted uniform scales, and “rough order of magnitude” scales. Examples of three different 5-point threat scales based on underlying annual threat probabilities are shown in Exhibit 6, and the various methods for scaling are discussed below the exhibit. The scales presented in this chapter correspond to underlying metrics, many of which may be difficult to assess with precision. Given the inherent uncertainty in this activity, this guidebook suggests using scales that group Risk Scenarios into tiers that correspond to wide ranges in the underlying metrics. Exhibit 6. Threat Probability Assessment Using Different Quantitative Scaling Options Category Annual Threat Probability (% per year) Score Tier Uniform Scale Adjusted Uniform Scale Rough Order of Magnitude Scale 1 Low 0%-20% 0%-10% <1% 2 Med-Low 20%-40% 10%-20% 1%-5% 3 Medium 40%-60% 20%-30% 5%-15% 4 Med-High 60%-80% 30%-40% 15%-35% 5 High 80%-100% >40% >35%
  9. Page 18 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 18 of 31 In Exhibit 6 the uniform scale is perfectly scaled to the maximum value of 100% with each 20% increase in the annual threat probability associated with a one-point or one-level increase on the threat scale. The adjusted uniform scale shown in the exhibit is similar to the uniform scale except the levels are set to allow for more differentiation at lower probabilities (in this case, below 40%), reflecting where the majority of the underlying data lies. How to adjust a uniform scale to fit the underlying data is a matter of judgement. The third approach shown in the exhibit is the rough order of magnitude approach, which uses uneven changes in the threat probability between threat levels. For example, in Exhibit 6, the interval is 1% for Low-Low (<1%), 4% for Medium-Low (1%-5%), 10% for Medium (5%15%), 20% for Med-High (15%-35%), and 65% for High (>35%). The rough order of magnitude approach is often helpful when the underlying data are hard to estimate precisely (large statistical error bars) or in situations where subject matter experts feel more comfortable providing general “ballparks” given inherent uncertainty of the values being estimated. Note that relative risk scales have the effect of reducing the difference between the high and low ends of the scale. For example, a threat with a 50% annual probability would by definition occur 100 times more often than a threat with a 0.5% annual probability but would have a threat score only 3 times as high using the uniform scale in Exhibit 6 and 5 times as high using the adjusted uniform or rough order of magnitude scales. Example assessment scales for vulnerability and consequence are presented in Exhibit 7 and Exhibit 8. Vulnerability scores are expressed in terms of the duration of the infrastructure outage. Consequence scores in Exhibit 8 are expressed in terms of the percentage of state supply or customers experiencing service disruptions. Exhibit 7. Vulnerability Assessment Using Different Quantitative Scaling Options Category Vulnerability (Duration) Score Tier Uniform Scale (Days) Adjusted Uniform Scale (Days) Rough Order of Magnitude Scale 1 Low 0-1 <1 Minutes 2 Med-Low 1-2 1-3 A few hours 3 Medium 2-3 3-7 ~1 day 4 Med-High 3-4 7-14 Several days 5 High 5+ 14+ 1 week+
  10. Page 19 of 31

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 06, 2026 BETP-038 Attachment 1 Page 19 of 31 Exhibit 8. Consequence Assessment Using Different Quantitative Scaling Options Category Consequence (Share of State Supply or Customers) Score Tier Uniform Scale Adjusted Uniform Scale Rough Order of Magnitude Scale 1 Low 0%-20% 0%-10% <1% 2 Med-Low 20%-40% 10%-20% 1%-5% 3 Medium 40%-60% 20%-30% 5%-15% 4 Med-High 60%-80% 30%-40% 15%-35% 5 High 80%-100% >40% >35% If using a quantitative consequence scale as in Exhibit 8, it may be necessary to adjust the scale or add weightings for different energy types, recognizing that different forms of energy will have different indirect impacts on society. For example, the loss of customer electric power service is likely to have a larger immediate impact on society than the loss of petroleum fuels. Alternatively, states may choose to employ a qualitative scale that takes both direct and indirect consequences into account. Exhibit 9 provides an example qualitative scale for consequence scoring that provides descriptions of consequences that account for the extent of the disruption (widespread versus localized) and secondary consequences, such as impacts of the loss of energy supply on lifeline 2 sectors, vulnerable populations, and the economy. Exhibit 9 provides consequence descriptions for each of the main energy types—electricity, liquid fuels, and natural gas. Electricity is further divided between consequences that involve service outages, typically caused by damage to the transmission and distribution lines, and electricity shortages that may involve generation outages or demand spikes that put grid reliability at risk and that may result in rolling blackouts or even grid collapse. The consequence tiers in Exhibit 9 build on one another in that descriptions of consequences in lower tiers carry up to the higher tiers, unless superseded by text in the higher tier descriptions. For example, if “below-average inventories” are mentioned in the tier 3 box, then below-average inventories are also included for tier 4 events even if not explicitly listed in the tier 4 box. States using any of the example assessment scales presented in this guidebook (particularly Exhibit 9) should adapt these scales to reflect state-specific situations and priorities. It may be difficult for stakeholders to precisely predict the consequences of a specific Risk Scenario. What matters more than precision is consistently grouping Risk Scenarios into 2 A lifeline enables the continuous operation of critical government and business functions and is essential to human health and safety or economic security Community Lifelines | FEMA.gov. Lifeline sectors include safety and security; food, hydration, and shelter; health and medical; energy; communications; transportation; hazardous materials; and water systems. See Appendix B for further information on key dependencies and interdependencies between the energy subsectors (electricity, petroleum, and natural gas) and other lifeline sectors.

Text of BETP-040_Final.pdf

Extracted from the file · 1 page · 1,141 characters

Words on different pagesRead the text of BETP-040_Final.pdf

As listed on the current system

Question(s) Answered 26, 28, 29, 33, 34, 37, 38, 40 (The Connecticut Light and Power Company) Date Filed: 10/26/2026

This filing on the current system (opens in a new tab)