Interrogatory responses

Answers to questions 1, 3, 4, 7, 12, 14, 18, 19

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Text of NECTA-004 Attachment 1.pdf

Extracted from the file · 1 page · 3,037 characters

Text of NECTA-007_Final.pdf

Extracted from the file · 1 page · 992 characters

Text of NECTA-012_Final.pdf

Extracted from the file · 1 page · 862 characters

Text of NECTA-014_Final.pdf

Extracted from the file · 1 page · 2,075 characters

  1. Page 1

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-018 Page 1 of 1 Date Filed: September 23, 2026 Witness: David L. Gladey and Jeffrey Richard Request from: New England Connectivity and Telecommunications Association Question: (Pole Management & SPA) Refer to Exhibit CLP-ADDITIONS-1, at pp. 66-67. Provide all methods and procedures documents and process flow diagrams related to the Single Pole Administration’s oversight and management of third party attachments. Response: The Company is providing the following documents in response to this request: • NECTA-018, Attachment 1 CONFIDENTIAL: TD-038, Revision 3, “Administration of Third-Party Attachments to Eversource CT Poles, effective 03/21/2024 • NECTA-018, Attachment 2: Alden One Third-Party Attachment Workflow Process Diagram Please refer to NECTA-018, Attachment 1 CONFIDENTIAL, and NECTA-018, Attachment 2. These documents describe the Single Pole Administration’s responsibilities and workflow for processing third-party pole attachment applications, administering applicable attachment agreements, coordinating and tracking make-ready activities, issuing and tracking applicable invoices and payments, maintaining attachment records, monitoring application status, and monitoring compliance with applicable regulatory requirements and timelines. The Single Pole Administration’s role with respect to field surveys, engineering determinations, and construction activities is limited to administrative coordination, and workflow and status management. The underlying technical review, engineering determinations, and field work are performed by the responsible engineering, operations, contractor or joint pole owner organizations, as applicable.

Text of NECTA-018 Attachment 1 REDACTED.pdf

Extracted from the file · 12 pages, 1 without text · 17,643 characters

Text of NECTA-018 Attachment 2.pdf

Extracted from the file · 1 page · 148 characters

Text of NECTA-019_Final.pdf

Extracted from the file · 1 page · 1,761 characters

As listed on the current system

Question(s) Answered 1, 3, 4, 7, 12, 14, 18, 19 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 09/23/2026