Interrogatory responses

Answers to questions 507, 508, 509, 510, 511, 512, 517, 518

ResponseFiled by The Connecticut Light and Power Company dba Eversource Energy53 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files53

Text of OCC-510_Final.pdf

Extracted from the file · 3 pages · 6,553 characters

Text of OCC-511_Final.pdf

Extracted from the file · 8 pages · 17,894 characters

Text of OCC-512_Final.pdf

Extracted from the file · 1 page · 992 characters

Text of OCC-517_Final.pdf

Extracted from the file · 1 page · 826 characters

Text of OCC-518_Final.pdf

Extracted from the file · 1 page · 601 characters

Text of OCC-512 Attachment 3 REDACTED.pdf

Extracted from the file · 33 pages · 5,436 characters

Text of OCC-512 Attachment 2 REDACTED.pdf

Extracted from the file · 33 pages · 5,436 characters

Text of OCC-512 Attachment 1.pdf

Extracted from the file · 626 pages · 635,148 characters

Text of OCC-507 Attachment 42.pdf

Extracted from the file · 3 pages · 10,259 characters

Text of OCC-507 Attachment 41.pdf

Extracted from the file · 9 pages · 3,276 characters

Text of OCC-507 Attachment 40.pdf

Extracted from the file · 5 pages · 8,775 characters

Text of OCC-507 Attachment 38.pdf

Extracted from the file · 19 pages · 96,311 characters

Text of OCC-507 Attachment 37.pdf

Extracted from the file · 49 pages · 120,692 characters

Text of OCC-507 Attachment 36.pdf

Extracted from the file · 59 pages · 136,630 characters

Text of OCC-507 Attachment 35.pdf

Extracted from the file · 38 pages · 102,807 characters

Text of OCC-507 Attachment 34.pdf

Extracted from the file · 5 pages · 1,210 characters

Text of OCC-507 Attachment 33.pdf

Extracted from the file · 13 pages · 52,489 characters

Text of OCC-507 Attachment 32.pdf

Extracted from the file · 5 pages · 14,030 characters

Text of OCC-507 Attachment 29.pdf

Extracted from the file · 8 pages · 37,747 characters

Text of OCC-507 Attachment 28.pdf

Extracted from the file · 18 pages · 75,925 characters

Text of OCC-507 Attachment 27.pdf

Extracted from the file · 35 pages · 66,295 characters

Text of OCC-507 Attachment 26.pdf

Extracted from the file · 19 pages · 68,589 characters

Text of OCC-507 Attachment 25.pdf

Extracted from the file · 12 pages · 53,851 characters

Text of OCC-507 Attachment 24.pdf

Extracted from the file · 2 pages · 482 characters

Text of OCC-507 Attachment 23.pdf

Extracted from the file · 268 pages · 869,686 characters

Text of OCC-507 Attachment 22.pdf

Extracted from the file · 178 pages · 528,336 characters

  1. Page 221 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 Docket No. 22-08-08 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 221 of 296 OCC-507 CL&P Attachment 21 Page 221 of 296 Page 215 Notably, if the WICC radio transmission towers were to lose power, the lighting for flight path safety as required by the U.S. Department of Transportation Federal Aviation Administration would be affected. Ex. UI-CETP-5, p. 2. The current plan to keep power available to the radio towers during an electrical outage is to use a back-up generator, which UI notes is “non-sustainable for a long period of time.” Id. The generator, installed in 2017, is fueled by propane. Late Filed Ex. 125, p. 1. The current system configuration of keeping six to eight 100-pound bottles of propane on PBI would be able to fuel the generator for approximately four days, with replacement propane transported via ferry as a fire in 1996 destroyed part of the bridge between PBI and the mainland of Bridgeport, limiting access to the island. Id., Ex. UI-CETP-5, p. 2. Further, UI notes that sources estimate the useful life of a standby generator to be between 1,500 and 3,000 run hours and that a generator should be run a maximum of 500 hours continuously to maintain useful life. Late Filed Ex. 125, p. 1. Additionally, the operation manual for the generator on PBI recommends regular service every 250 hours. Id. Also, the generator only serves the WICC radio towers and not the other customer on PBI, the pavilion owned by the City of Bridgeport, which has no back-up power. Ex. UI-CETP-5, p. 2. Alternatively, if the cable were to be replaced to mitigate future electric service interruptions to PBI, the cost estimate ranges from $10 to $12 million dollars, in part because there is no available route for an overhead solution. Ex. UI-CETP-1, p. 25. The proposed solar and storage project, which UI asserts is “the most costeffective option,” is estimated to cost $1.052 million, with $19.5 thousand in O&M costs in 2025. Ex. UI-CETP-5, pp. 1-3. The proposed project is a 210 kilowatt (kW) photovoltaic (PV) solar system paired with 315 kilowatt-hours (kWh) of battery storage. Id. The system is designed to replace the existing cable and provide reliable power at all hours to the two customers on PBI, which combined average approximately 11,000 kWh annually. Id., p. 1. The system is also designed to withstand a Category 3 hurricane. Id. Notably, UI states that the system size is approximate, but expects the final design to be similar to the proposed system, as the proposed system was preliminarily sized through discussions with a few third-party developers who provided similar system size estimates. UI-CETP-5, p. 1; Hr’g Tr. Mar. 7, 2023, 2699:2-2700:11. Additionally, the O&M costs for the system were calculated as 1.8% of the capital expenditure costs, which is a typical practice of the Company. Hr’g Tr., 2707:15-2708:7. UI states that in the case of a storm where the system was not operating properly, personnel would be sent to maintain the system while the batteries provided interim power. Hr’g Tr., 2706:17-2707:14. Specifically, UI notes that the Company will not own the solar system but would have an agreement with the company who does own the solar system to ensure that the solar panels are maintained. Hr’g Tr., 2707:4-14. The Company also states that the PBI solar and storage project was not submitted as a project in Connecticut’s Energy Storage Solutions Program, or as a project pursuant to Public Act 22-55, An Act Concerning Energy Storage Systems and Electric Distribution System Reliability, as this system is “designed as an innovative project intended to replace existing, aged infrastructure past the end of its useful life to ensure reliable and safe 24 x 7 x 365 service to the customers on the island, not to provide back-up to customers nor reduce system peaks”, and consequently does not meet either program’s objectives. Interrog. Resp. CAE-17, p. 1. However, UI notes several benefits of the PBI project including: (1) that energy storage will be necessary to integrate renewable energy
  2. Page 222 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 222 of 296 OCC-507 CL&P Attachment 21 Docket No. 22-08-08 Page 222 of 296 Page 216 sources to meet Connecticut’s clean energy goals and this project will allow UI to gain knowledge about how such systems can be operated; (2) that this project provides operational resilience to customers in a hard to serve area of the company’s territory; (3) that this project will help UI to assess opportunities to meet customer needs in unique ways and other potential locations and applications for battery storage; (4) that this project will provide greenhouse gas savings; and (5) that this project will assist Connecticut in reaching its goal of 650 MW of energy storage by 2027. Ex. UI-CETP-5, p. 2; Hr’g Tr. Mar. 7, 2023, 2708:8-2709:4. Lastly, the Company notes that the PBI project, and lessons learned from it, will benefit all UI customers due to the potential use of solar and storage projects in other locations, and consequently seeks to recover costs incurred for the PBI project through base distribution rates. Ex. UI-CETP-1, p. 24. The Authority acknowledges the logistical and environmental difficulties in replacing the cable currently servicing PBI, as well as the substantially larger cost estimate to replace the cable relative to implementing a solar plus storage solution. Further, the Authority notes that using the generator back-up as a long-term solution is not feasible due to the required frequency of refueling and machine maintenance. The Authority finds the proposed project to likely be the most cost-effective available solution and one that provides broader benefits to the Company and ratepayers of Connecticut. Accordingly, the Authority approves the proposed PBI solar plus storage project, subject to the below conditions. First, the Authority clarifies that UI is not currently statutorily authorized to be the owner of the solar system and directs UI to select a third-party with which to execute a PPA via a competitive RFP. Accordingly, the Company will be directed to file with the Authority the results of the RFP including the details of all bids, including the winning bid, with the Authority as compliance. Second, the Authority notes that it has not identified where in base distribution rates that the PBI solar and storage project has been accounted for in the Company’s Application. To the extent that the PBI project costs have been included in the Application, the Authority disallows cost recovery through the base distribution rates at this time as (1) insufficient evidence was provided to demonstrate that the final costs are prudent and (2) the project is not used and useful at this time, the former of which is required to allow for the recovery of expenses and both of which are required for rate base treatment as discussed in Section IV., Rate Base. Accordingly, any such costs should be removed from the approved revenue requirement.152 The Authority does, however, authorize deferred accounting to allow the Company to track the costs of the PBI solar plus storage project. The tracked costs will be reviewed for the prudence and reasonableness of any incurred costs during the Company’s next rate case proceeding. The Company may also request inclusion of any annual expenses related to O&M in the same rate case proceeding. The Authority will review such O&M costs for prudence and reasonableness at that time. Lastly, as directed in the July 12, 2021 Ruling to Motion No. 14 in Docket No. 1010-12, Petition Filed by Cumulus Media, Inc. for an Investigation Pursuant to § 16-20 of 152 The Authority did not identify any costs related to the PBI solar plus storage solution in the requested Rate Year 2023/2024 revenue requirement.
  3. Page 223 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 223 of 296 OCC-507 CL&P Attachment 21 Docket No. 22-08-08 Page 223 of 296 Page 217 the General Statutes of Connecticut, the Company must file for the Authority’s review and approval in the instant proceeding option(s) for a rate structure for the customers on the island pursuant to Conn. Gen. Stat. § 16-19e(a)(4) in order to allocate the cost of such service (Proposals) prior to the PBI solar plus storage project taking service. Such Proposals should be consistent with the Company’s current terms and conditions, including the guarantee of a minimum annual payment for a term of years. The Proposals shall include a timeline of requested approvals, all partnerships and other contractual agreements that the Company has and plans to enter into for the project, and any other documents and legal parameters necessary to execute the Proposal. Any rate structure options considered and presented may take into account the non-energy benefits that this project may provide to the Company and its ratepayers as a whole, including environmental and societal benefits. G. ELECTRIC POWER RESEARCH INSTITUTE EXPANDED MEMBERSHIP The Company proposes to expand its membership to the Electric Power Research Institute (EPRI) to “facilitate research and industry collaboration around clean energy,” including “program sets” related to energy storage, distributed generation, DER integration, electric transportation, and electrification. Ex. UI-CETP-1, p. 31. The Authority declines UI’s request because there is insufficient evidence in the record explaining how the expanded membership will specifically benefit ratepayers. Additionally, there is conflicting and confusing testimony in the record regarding the actual costs for the expanded EPRI membership. According to an interrogatory response, the Company requests that it recover a total of $565,900 over four years. Interrog. Resp. OCC-246. However, in a subsequent interrogatory response, the Company stated that its annual EPRI dues from 2017 through 2022 averaged $310,269. Interrog. Resp. OCC-387. Further, the Company testified at the hearing that it sought to increase its membership expense by “a little over $36,000” on an annual basis. Hr’g Tr. Mar. 8, 2023, 2805: 12-14. Finally, a schedule submitted by the Company indicated only a $17,00 increase in its membership expense. Sch. WP C3.03. Therefore, the actual cost of the extended membership is unclear to the Authority. Additionally, when asked about the program sets, the Company testified that it already belonged to two program sets it represented it wanted to join in the Application. Hr’g Tr. Mar. 8, 2023, 2806:1-4. Moreover, the Company only provided general and speculative remarks about potential benefits to its expanded membership and did not describe any quantifiable benefits to ratepayers. See Hr’g Tr. Mar. 8, 2023, 2806:1-25, 2807: 1-8. Therefore, the record is unclear as to how much the expanded membership would cost, what program sets the Company belongs to, what the benefits of expanded membership in those program sets are, and how specifically the expanded membership would benefit ratepayers. Finally, P.A. 23-102 § 3 (a), effective from passage on June 6, 2023, and before Rate Year 2023/2024 commences on September 1, 2023, expressly prohibits a public service company such as UI from recovering through rates any direct or indirect costs associated with “membership, dues, sponsorships or contributions to a business or industry trade association or group or related entity incorporated under Section 501 of the Internal Revenue Code of 1986, or any subsequent corresponding internal revenue code of the United States, as amended from time to time.” As such, the
  4. Page 224 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 224 of 296 OCC-507 CL&P Attachment 21 Docket No. 22-08-08 Page 224 of 296 Page 218 Authority denies UI’s request to recover its proposed expanded EPRI membership costs from ratepayers. VIII. APPROVED REVENUE REQUIREMENT The table below summarizes the various components of the Company’s approved revenue requirement, as adjusted by the Authority, and provides the total approved revenue requirement for the rate year. Table 80: Approved Revenue Requirement Section IV.A. V.A. VI.A. VI.B. VI.C. VI.D. VI.D. VI.D. VI.D. VI.D. VI.D. VI.D. Revenue Component Rate Base Weighted Cost of Capital Allowed Cost of Capital Allowed Expenses: Operations & Maintenance Depreciation Amortization Payroll Taxes Gross Earnings Tax Municipal Property Taxes State Income Tax Federal Income Tax Provision for Deferred Taxes CT ITC Total Allowed Revenue Requirement Amounts ($000) 1,105,196 6.475% 71,561 150,860 72,536 6,605 5,419 26,156 35,053 1,325 10,885 2,703 1,762 384,865 IX. REVENUE ADJUSTMENT MECHANISMS A. EARNINGS SHARING MECHANISM (ESM) 1. Summary The Company proposed that its earnings sharing mechanism (ESM) continue as it is currently structured, with earnings above the allowed ROE measured on a calendar year basis shared 50/50 with customers. The Company is proposing to modify the structure so that the customers’ 50% share, if any, would be first utilized to amortize and accelerate the recovery of UI’s storm regulatory asset, if applicable, before being utilized as a cash credit. Application, Ex. UI-RRP-1, p. 9; Interrog. Resp. RRU 24. The Company indicated the mechanism returned approximately $15.66 million to customers, inclusive of carrying charges, due to earnings above the allowed ROE in 2017, 2018, and 2019. UI Interrog. Resp. RRU-26. In 2020, the customers’ 50% share of earnings sharing was utilized to offset deferred major storm expenses. Id.
  5. Page 225 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 225 of 296 OCC-507 CL&P Attachment 21 Docket No. 22-08-08 Page 225 of 296 Page 219 As shown in RRU-16, Attachment 1, the Company’s calculation of its earned ROE for purposes of the ESM reflects its actual capital structure. Interrog. Resp. EOE-181. UI has utilized its actual capital structure when calculating earnings sharing for the last two decades. Id. 2. Positions of the Parties EOE recommends that the Authority provide guidance to the Company requiring all future ESM reporting to calculate the ROE using the lesser of the (1) authorized or (2) carried equity position, and to apply ESM carrying costs as of January 1 of the subsequent year. Additionally, EOE asserts that the Company should be required to separately identify and exclude all disallowed costs from the ESM reporting going forward and provide an affirmation of the accuracy of their disallowed expenses. This guidance would still allow for the Company to achieve its authorized ROE based on its authorized capital structure and would then share excess earnings in accordance with the rate case decision. This approach would also ensure that customers are not negatively impacted in situations where the Company deviates from directives and orders outlined in a rate case decision. EOE Brief, p. 51. EOE further argues that while deviations from a regulated entity’s authorized capital structure would not result in changes to rates charged to customers (ratepayers), such deviations would, however, impact an entity’s actual calculated ROE and WACC. When the actual equity percentage increases within the capital structure, the WACC would increase as there would be less debt charged at the lower cost. The inverse also holds true. Specific to ROE, a larger percentage of equity results in a lower calculated ROE as the utility income would be diluted within the calculation. This ultimately means that a regulated utility that exceeds its authorized equity percentage would derive a lower actual ROE, while still receiving the same amount of income (pre-ESM). Specific to the ESM, this means that a regulated utility could increase its carried equity percentages to derive a lower calculated ROE, which would negatively impact the customer’s portion of the earnings sharing resulting in less money being returned to ratepayers or used to offset the Storm Regulatory Asset. EOE Brief, p. 51. EOE highlighted how this would have benefited the ratepayers in past situations where the ESM was triggered. EOE indicated that the common equity level in the Company’s capital structure has grown from 54.44% in 2017, to 59.15% in 2021, despite being set at 50% for ratemaking purposes. EOE Brief, p. 50. In 2017-2019, UI exceeded its allowed ROE and shared $16.46 million of overearnings, based upon the equity ratio shown in UI’s actual capital structure. Interrog. Resp. EOE-181. However, had earnings been calculated using the 50% equity ratio allowed for ratemaking purposes, rather than the Company’s actual capital structure, ratepayers would have seen an additional earnings sharing bill credit in 2020 of $2.07 million, as well as $5.83 million greater ESM payments over the 2017–2019 rate plan period. EOE Brief, p. 51. Similarly, the OCC indicated that allowing UI to calculate earnings for ESM purposes using its actual capital structure defeats the rationale of the original rate case decision that set the authorized ROE, allowed ratemaking capital structure, and resulting weighted cost of capital. If a 50/50 capital structure was utilized for setting revenue requirements, an identical capital structure should be utilized to determine the level of earnings sharing in a given rate year. OCC Reply Brief, p. 22.
  6. Page 226 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 Docket No. 22-08-08 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 226 of 296 OCC-507 CL&P Attachment 21 Page 226 of 296 Page 220 In addition to supporting EOE’s recommended calculation of the ESM, OCC also proposed a modification to the ESM. Specifically, while the OCC does not necessarily oppose using ESM proceeds to pay off deferred storm costs, the OCC contends that the application of ESM funds to storm costs should be limited to storm costs that have been the subject of a review in a rate case or storm review case by PURA. As a result, only storm costs found to be prudent would be eligible to be funded by ESM proceeds. New storm costs should not automatically be charged against ESM until they are approved for recovery by PURA following a comprehensive and collaborative review in which the Company must meet its burden to demonstrate that incurred costs were necessary and prudent. OCC Brief, p. 249. The OCC noted that if PURA does accept this modification, that the Authority should consider a sharing of one-quarter to storm deferred costs, one-quarter to shareholders, and one-half to ratepayers as a bill credit. The pay-down of deferred storm costs improves the financial matrix of the Company by reducing the level of deferred assets on the Company’s balance sheet. Under the Company’s proposal, OCC argues that shareholders would enjoy the full 50% benefit of the ESM mechanism, in addition to the benefit of this reduction in risk, while ratepayers would contribute their entire share of overearnings. Dividing overearnings between shareholders, ratepayers, and deferred costs would better reflect the balance intended in the ESM mechanism’s design. Id., p. 250. The OCC also petitioned the Authority to consider the reporting of the actual earned ROE. The OCC argues that UI accounted for costs that were not included in the revenue requirement as operating expenses, affecting the measurement of the Company’s actual earned ROE. OCC Brief, p. 250. Specifically, the OCC states that UI has a long history of paying incentive compensation levels that exceed the amount allowed in rates and charging the excess amount above the line, thus reducing their earned ROE. Id. These actions cause the Company to earn below its allowed rate of return and experience a reduction in overearnings in years in which they in fact over earn. Id. The OCC requests that the Authority order UI to report its earned return based on a level of allowed expenses that does not include costs that were excluded for ratemaking purposes. Id. 3. Authority Analysis The Authority orders UI to continue the ESM with a 50/50 split from the first dollar of over-earning above the allowed ROE calculated on a calendar year basis. In addition, the Authority agrees with the arguments presented by EOE and the OCC that the measurement of the ROE should use the lesser of the authorized or actual equity position when tabulating the ROE, as utilizing the Company’s actual capital structure subverts the function of imbuing a capital structure for ratemaking purposes. The Authority also agrees with the OCC that the ESM revenue should only be applied to the storm regulatory asset after a prudence review by the Authority for two reasons: (1) consistent with the treatment of regulatory assets in this Decision and past PURA precedent, see Section IV.E.1., General, carrying charges do not accrue on regulatory assets prior to a prudence review; thus, there are no carrying cost benefits associated with applying ratepayers’ share of the ESM to a storm regulatory asset prior to the prudence review; and (2) applying ratepayers’ share of the ESM to a storm regulatory asset before a full review by the Authority introduces the risk that such costs are used to offset imprudent costs. The Authority will
  7. Page 227 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 227 of 296 OCC-507 CL&P Attachment 21 Docket No. 22-08-08 Page 227 of 296 Page 221 determine the amount of ESM revenue to be applied to the current storm regulatory asset or any future storm regulatory assets for which the Authority has completed a prudency review on a case-by-case basis at the time the Company identifies ESM revenues. Lastly, the Authority also agrees with the OCC that incentive compensation (or indeed, any costs excluded for ratemaking purposes) above the levels authorized in the rate case should not be used to reduce the calculated ROE, as such incremental incentive payments are definitionally earnings; the Company is entitled to distribute such earnings how it sees fit, but only after the ratepayers’ share of any overearnings is appropriately allocated. Accordingly, the Authority directs UI to incorporate the above changes into its ESM moving forward. The Authority further directs the Company to file a motion in the instant proceeding when ESM revenues are identified for a given calendar year outlining the amount of ESM revenues due to customers and a proposed plan for returning such revenues to customers. B. PROPOSED ROE ADJUSTMENT MECHANISM The Company proposed an ROE adjustment mechanism to adjust the ROE to reflect current conditions in each year of the multi-rate plan starting at the beginning of rate year two. Bulkley PFT, p. 70. The proposed mechanism would provide for symmetrical adjustment to the ROE upwards or downwards by 45% of the upcoming year’s projected average spread between the one-year Treasury Bill and the two-year U.S. Treasury Note as estimated by the Blue Chip Financial Forecast. Id., p. 72. The OCC is opposed to the proposed ROE adjustment mechanism for several reasons: (1) the Company recommendation would be formulaic and require an annual reopening proceeding before the Authority; (2) the methodology proposed is incorrect; and (3) the OCC does not support a multi-year rate plan; thus, an annual ROE reopening would be unnecessary. OCC Brief, p. 248; Interrog. Resp. RRU-247. Walmart also opposed the Company’s proposed ROE adjustment mechanism indicating it deprives PURA of its authority to set an allowed ROE. Kronauer PFT, p. 11; Walmart Brief, p. 5. The Authority disallows the Company’s proposed annual ROE adjustment mechanism as such a proposal deprives PURA of the ability to fully examine the entire economic and financial conditions of the economy and Company. Instead, the proposed ROE adjustment mechanism reduces the ROE process to a one dimensional formulaic if-then analysis based on movements in short-term US Treasury rates. There are many errors centered on the use of short-term U.S. Treasury rates as the benchmark. First, as noted in Section V.E.3., Capital Asset Pricing Model, utility assets are long-lived assets and typically the 30-year U.S. Treasury rates are used in utility cost of capital analyses. Second, the Company’s proposal is based solely on UI’s expert witness’ own analysis and reporting of a Virginia Commerce Commission’s white paper. Interrog. Resp. RRU-245 and RRU-245, Att. 2. Third, the Company’s request is based upon estimated movements to interest rates over the coming year, which would essentially require the Authority to link its ratemaking authority to Wall Street analysts’ projections as the Blue Chip Financial Forecasts essentially compiles financial forecaster’s projections related to various economic indicators. Fourth, the Company will not be operating under a multi-rate year plan, as outlined in Section III.B., Multi-Year Rate Plan, making the proposed ROE adjustment mechanism moot.
  8. Page 228 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 Docket No. 22-08-08 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 228 of 296 OCC-507 CL&P Attachment 21 Page 228 of 296 Page 222 Finally, and most importantly, the Authority finds that an annual reopener to the ROE to address anticipated movements to U.S. short-term Treasury rates would result in increased customer rate uncertainty and is not in the public interest. C. PROPOSED PBR METRICS The Company proposed a demonstration program to test various performancebased metrics to develop useful information and data for future implementation of a PBR framework for the Company. Ex. UI-1, p. 25. The Company’s proposed demonstration program anticipates the completion of the Authority’s PBR proceedings in Docket Nos. 21-05-15, 21-05-15RE01, 21-05-15RE02, and 21-05-15RE03 (collectively, the PBR proceedings). The proposal includes five performance-based metrics that “would not have a financial incentive associated with them but would be tracked and analyzed for future rate cases. The five metrics are: (1) DER interconnection; (2) EV managed charging; (3) electric storage adoption; (4) Net Promoter Score (“NPS”); and (5) customer e-bill adoption.” Ex. UI-1, p.27. UI proposed to use insights from tracking the metrics to make determinations about the continuation of metric tracking and the reasonableness of the proposed thresholds. Ex. UI-1, p. 32. The Authority declines to formally approve UI’s PBR demonstration program. The Authority appreciates the spirit of the demonstration program, which appears to be in preparation for the implementation of PBR; however, the identification, tracking, and reporting of a discreet set of metrics is not currently necessary. Tracking and reporting metrics is not a new business practice for UI. In complying with various existing Authority orders, compliance filings, and reporting requirements, UI is already wellpracticed with the tracking, measurement, and reporting of metrics. Additionally, UI is currently responsible for tracking and reporting many other metrics and scorecards through the annual review of the Affordability Programs and Offerings, the state’s clean energy programs, and the Reliability and Resilience Frameworks through Docket Nos. XX-05-01, XX-08-01 through XX-08-06, and XX-08-09,153 respectively, among others. The Company’s efforts to track and report a new set of PBR demonstration metrics would be better spent ensuring faithful and quality fulfillment of existing metric reporting requirements. Diligent data tracking and reporting within existing Authority requirements can serve the same intended purpose of the demonstration program, to further build the Company’s experience with and capacity for rigorous data reporting. Many (if not all) of these existing metrics and reporting requirements are likely to be considered for inclusion or potential consolidation in Docket No. 21-05-15RE02, which focuses on reported metrics, scorecards, and Performance Incentive Mechanisms in the service of the regulatory goals and priority public outcomes adopted in the PBR Decision. Accordingly, the Authority encourages the Company to pursue the spirit of the proposed PBR demonstration program through existing reporting requirements and active participation in Docket No. 21-05-15RE02 but declines to formally approve the program at this time. 153 “XX” represents the last two digits of the calendar year in which the proceeding is conducted.
  9. Page 229 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 Docket No. 22-08-08 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 229 of 296 OCC-507 CL&P Attachment 21 Page 229 of 296 Page 223 X. RATE DESIGN A. LEGAL FRAMEWORK UI is a public service company within the meaning of Conn. Gen. Stat. § 16-1. The Authority is statutorily charged with regulating the rates of Connecticut’s public service companies. Conn. Gen. Stat. § 16-19. Consequently, UI must “file any proposed amendment of its existing rates with the [A]uthority.” Conn. Gen. Stat. § 16-19(a). Once a proposed amendment has been filed, the Authority “shall make such investigation of such proposed amendment of rates as is necessary to determine whether such rates conform to the principles and guidelines set forth in section 16-19e, or are unreasonably discriminatory or more or less than just, reasonable and adequate, or that the service furnished by such company is inadequate to or in excess of public necessity and convenience, . . .” Id.154 In striking this balance and making pragmatic adjustments, the Authority is guided by Conn. Gen. Stat. § 16-19e(a), which states, in relevant part, that the Authority shall examine proposed rates in accordance with the following principles: (4) that the level and structure of rates be sufficient, but no more than sufficient, to allow public service companies to cover their operating costs including, but not limited to, appropriate staffing levels, and capital costs, to attract needed capital and to maintain their financial integrity, and yet provide appropriate protection to the relevant public interests, both existing and foreseeable . . . ; (5) that the level and structure of rates charged customers shall reflect prudent and efficient management of the franchise operation. In furtherance of this statutory framework, the Authority typically employs the rule of cost causation, which allocates costs to customers and cost categories based on the costs they cause a utility to incur. The Authority also generally attempts to equalize class rates of return, as such practice ensures that rates are not “unreasonably discriminatory,” while balancing the regulatory philosophy of gradualism to, among other reasons, avoid customer rate shock. See Electricity Regulation in the US: A Guide, Regulatory Assistance Project, p. 67.155 Consistent with the philosophy of gradualism, the Authority typically requires rate class revenue reductions or increases to be within one and quarter times the overall distribution revenue increase. See 2016 Rate Case Decision, p. 108; see, also, 2013 Rate Case Decision, p. 153. Finally, the Authority considers whether “existing or future rate structures place an undue burden upon those persons of [lowincome] status” as contemplated by Conn. Gen. Stat. § 16-19e(b). The Authority weighs the above principles and considerations in determining appropriate cost and revenue allocation approaches and rate designs. 154 Conn. Gen. Stat. § 16-19(a) also permits the Authority to “evaluate the reasonableness and adequacy of the performance or service of the public service company using any applicable metrics or standards adopted by the authority pursuant to section 16-244aa.” 155 Available at: https://www.raponline.org/wp-content/uploads/2016/07/rap-lazar-electricity-regulation-USjune-2016.pdf.
  10. Page 230 of 296

    Connecticut Light and Power Company Docket No. 26-05-10 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 31, 2026 OCC-507 Attachment 21 Page 230 of 296 OCC-507 CL&P Attachment 21 Docket No. 22-08-08 Page 230 of 296 Page 224 B. SALES FORECASTS AND REVENUE The Authority approves UI’s sales and revenues forecast for the Rate Year as the Authority finds the proposed sales and revenues forecast and the Company’s out-ofmodel adjustments reasonable. The Company forecasted the monthly billed sales and the number of customers for calendar years 2022, 2023, and the 12-month period beginning September 1, 2023. The Company used calendar year 2021 (i.e., the 12months ending December 31, 2021) as the historical test year. Ex. UI-MP-1, Executive Summary. The Company forecasts overall electric deliveries to decrease, on average, by 1.19% annualized156 between the Test Year and Rate Year 2023/2024. Id., p. 17. The forecasted reduction in billed deliveries is driven by a forecasted reduction in deliveries to industrial and residential customers. However, commercial customer deliveries are forecasted to increase slightly between 2023 and 2026. Id. The reduction in billed deliveries to the industrial class is reflective of the trends in the economic variables the Company used to develop the sales and customer growth models. Specifically, industrial customer sales are highly correlated with manufacturing employment data in Connecticut. Interrog. Resp. CAE-27. The Company sourced economic data from an information services provider, IHS Markit. UI-MP-1 p. 7. IHS Markit projects manufacturing employment for Connecticut to decline, on average, by 2.28% per year from 2022 to 2026. Interrog. Resp. CAE-27. The table below summarizes the average annualized growth rates for the residential, commercial, industrial, and street lighting customer billed deliveries, as well as the annualized growth rates for the total billed deliveries. Table 81: Billed Deliveries Annualized Growth Rates Class Residential Commercial Industrial Street Lighting Total 2023/2024 (%) -2.13 -0.07 -2.34 -4.27 -1.19 2024/2025 (%) 2025/2026 (%) -1.18 -0.63 +0.08 +0.17 -1.48 -1.16 -4.914 -5.28 -0.63 -0.32 Ex. UI-MP-1, pp. 9-12. The Company forecasts that the overall number of customers will increase, on average, by 0.21% annually between the Test Year and Rate Year 2023/2024. Ex. UIMP-1, p. 17. The forecasted increase in customers is driven by a forecasted increase in the number of commercial and residential customers, while the number of industrial and streetlight customers is forecast to decrease. Ex. UI-MP-2, Sch. B, p. 8. UI reports that residential customer growth is highly correlated with the number of households in Connecticut. Interrog. Resp. CAE-26. UI relied on IHS Markit projections that show an increase in the number of households in Connecticut beginning in 2023. Id. The Company’s forecasting methodology differs from methodologies used in previous rate cases. Historically, the Company used an Excel-based formulaic approach 156 An annualized growth rate is a growth rate over a given time period adjusted to give the equivalent growth rate over one year. Specifically, the growth rate over the 32-month period between the end of the Test Year (i.e., December 31, 2021) and the end of Rate Year 2023/2024 (i.e., August 31, 2024) was annualized by dividing the rate by 32 and then multiplying by 12. Ex. UI-MP-2.

Text of OCC-507 Attachment 20.pdf

Extracted from the file · 167 pages · 508,170 characters

Text of OCC-507 Attachment 19.pdf

Extracted from the file · 137 pages · 450,996 characters

Text of OCC-507 Attachment 18.pdf

Extracted from the file · 247 pages · 763,200 characters

Text of OCC-507 Attachment 17.pdf

Extracted from the file · 2 pages · 6,387 characters

Text of OCC-507 Attachment 16.pdf

Extracted from the file · 2 pages · 484 characters

Text of OCC-507 Attachment 15.pdf

Extracted from the file · 202 pages · 895,816 characters

Text of OCC-507 Attachment 14.pdf

Extracted from the file · 6 pages · 8,947 characters

Text of OCC-507 Attachment 13.pdf

Extracted from the file · 19 pages · 93,122 characters

Text of OCC-507 Attachment 12.pdf

Extracted from the file · 19 pages · 95,631 characters

Text of OCC-507 Attachment 11.pdf

Extracted from the file · 7 pages · 10,667 characters

Text of OCC-507 Attachment 8.pdf

Extracted from the file · 2 pages · 3,673 characters

Text of OCC-507 Attachment 4.pdf

Extracted from the file · 6 pages · 8,272 characters

Text of OCC-507 Attachment 2.pdf

Extracted from the file · 8 pages · 30,345 characters

Text of OCC-507 Attachment 1.pdf

Extracted from the file · 32 pages · 164,962 characters

Text of OCC-507 Attachment 39.pdf

Extracted from the file · 22 pages · 32,510 characters

Text of OCC-507 Attachment 31.pdf

Extracted from the file · 8 pages · 37,747 characters

Text of OCC-507 Attachment 30.pdf

Extracted from the file · 5 pages · 22,063 characters

Text of OCC-507 Attachment 10.pdf

Extracted from the file · 3 pages · 4,485 characters

Text of OCC-507 Attachment 9.pdf

Extracted from the file · 10 pages · 15,175 characters

Text of OCC-507 Attachment 7.pdf

Extracted from the file · 3 pages · 5,747 characters

Text of OCC-507 Attachment 6.pdf

Extracted from the file · 4 pages · 6,545 characters

Text of OCC-507 Attachment 5.pdf

Extracted from the file · 4 pages · 5,724 characters

Text of OCC-507 Attachment 3.pdf

Extracted from the file · 65 pages · 195,008 characters

As listed on the current system

Question(s) Answered 507, 508, 509, 510, 511, 512, 517, 518 (The Connecticut Light and Power Company dba Eversource Energy) Date Filed: 09/14/2026

This filing on the current system (opens in a new tab)