Interrogatory responses

Answers to questions 566, 569, 570, 575, 578

Files6

Text of OCC-575_Final.pdf

Extracted from the file · 2 pages · 3,973 characters

Text of OCC-578_Final.pdf

Extracted from the file · 1 page · 1,564 characters

  1. Page 1 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 1 of 46 2021 Non-Wires Alternative Framework VERSION 1.0 Primary Contact: Gerhard Walker [email removed] 1
  2. Page 2 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 2 of 46 CONTENTS 1. Tables and Figures .................................................................................................................................................................. 5 2. Abbreviations ......................................................................................................................................................................... 6 3. Introduction ........................................................................................................................................................................... 1 4. Stakeholders ........................................................................................................................................................................... 2 5. Initial NWA Screening............................................................................................................................................................. 3 A. Critical Suitability Criteria .................................................................................................................................................. 3 B. Additional Considerations ................................................................................................................................................. 3 6. General Framework ................................................................................................................................................................ 4 A. Considered Resources ....................................................................................................................................................... 4 B. Forecasting and Planning Horizons ................................................................................................................................... 5 System forecast Horizon ........................................................................................................................................................ 5 Financial Planning Horizon ..................................................................................................................................................... 5 Terminal Cost ......................................................................................................................................................................... 5 Deferring Capacity Need ........................................................................................................................................................ 6 C. 7. NWA Dispatch Options...................................................................................................................................................... 6 Reliability Model .................................................................................................................................................................... 8 A. EXEMPTIONS FROM the N-1 Reliability DESIGN STANDARD............................................................................................. 8 B. Reliability Assumptions for Customer Programs............................................................................................................... 8 C. Reliability Assumptions for Grid Scale Batteries ............................................................................................................... 9 D. Reliability Assumptions for DG .......................................................................................................................................... 9 8. Dispatch Model .................................................................................................................................................................... 10 A. Prioritization of DER Dispatch ......................................................................................................................................... 10 B. Solar Generation ............................................................................................................................................................. 10 C. Energy Efficiency ............................................................................................................................................................. 12 D. Demand Response .......................................................................................................................................................... 14 Snap Back and Pre-Conditioning .......................................................................................................................................... 14 Availability of DR Resources ................................................................................................................................................. 15 E. Conservation Voltage Reduction ..................................................................................................................................... 17 F. Battery Storage ............................................................................................................................................................... 17 G. Fuel Cell ........................................................................................................................................................................... 18 H. Combined Heat and Power ............................................................................................................................................. 18 I. Emergancy Generation ................................................................................................................................................... 18 2
  3. Page 3 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 3 of 46 9. Cost Model ........................................................................................................................................................................... 19 A. Traditional Solution ......................................................................................................................................................... 19 B. NWA Cost Types .............................................................................................................................................................. 19 C. Annual Rates of Change .................................................................................................................................................. 21 D. Earning Factors Utility Programs ..................................................................................................................................... 22 E. Life Cycle Assumptions .................................................................................................................................................... 22 F. Solar Generation ............................................................................................................................................................. 23 Utility Scale Solar Generation............................................................................................................................................... 23 Behind the Meter Solar Generation: .................................................................................................................................... 23 G. Energy Efficiency ............................................................................................................................................................. 24 H. Demand Resonse ............................................................................................................................................................ 25 Commerical .......................................................................................................................................................................... 25 Residential ............................................................................................................................................................................ 26 Storage ................................................................................................................................................................................. 26 I. Conservation Voltage Reduction ..................................................................................................................................... 27 J. Battery Storage ............................................................................................................................................................... 27 K. Fuel Cell ........................................................................................................................................................................... 28 L. Combined Heat and Power ............................................................................................................................................. 28 M. Emergency Generation ................................................................................................................................................... 29 10. Revenue Requirements ................................................................................................................................................... 30 A. General Assumptions ...................................................................................................................................................... 30 Accounts ............................................................................................................................................................................... 30 Depreciation Accrual Rate .................................................................................................................................................... 30 PRE-TAX WACC ..................................................................................................................................................................... 30 Property Purchases .............................................................................................................................................................. 31 Program Cost ........................................................................................................................................................................ 31 O&M Cost ............................................................................................................................................................................. 31 AsseT Revenue ..................................................................................................................................................................... 31 B. MACRS ............................................................................................................................................................................. 31 MACRS 7 Years (363 - Storage Battery Equipment) ............................................................................................................. 31 MACRS 5 Years (344/345 - Solar Panels, Inverters, Generators) ......................................................................................... 32 MACRS 20 Years (344/345 - Solar Panels, Inverters, Generators) ....................................................................................... 32 C. State Specific Rates ......................................................................................................................................................... 32 11. Revenue Estimation Model ............................................................................................................................................. 33 3
  4. Page 4 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 4 of 46 A. Regional Network Service (RNS) and Local Network Service (LNS): ............................................................................... 33 B. ISO Registration Model ................................................................................................................................................... 33 C. ISO Market Participation ................................................................................................................................................. 35 D. ISO Market Assumptions ................................................................................................................................................. 36 Real-Time and DAy Ahead Market (Wholesale Energy) ....................................................................................................... 36 Forward Capacity Market (FCM) .......................................................................................................................................... 36 E. DER Revenue TImelines................................................................................................................................................... 36 F. DER Revenue ................................................................................................................................................................... 38 Solar PV ................................................................................................................................................................................ 38 Energy Efficiency .................................................................................................................................................................. 38 Demand Response................................................................................................................................................................ 39 Conservation Voltage reduction .......................................................................................................................................... 39 Battery Storage .................................................................................................................................................................... 39 Fuel Cell & CHP ..................................................................................................................................................................... 40 Emergancy Generation ......................................................................................................................................................... 40 4
  5. Page 5 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 5 of 46 1. TABLES AND FIGURES Table 1: DER Technologies Considered as NWAs ........................................................................................................................... 4 Table 2: Saturated Reliability Factor for Utility Programs .............................................................................................................. 9 Table 3: Application of Annual Change Rates Based on Cost Component ................................................................................... 21 Table 4: Program Earning Rates ................................................................................................................................................... 22 Table 5: Life Cycle Assumptions by Asset Type ............................................................................................................................ 22 Table 6: 7 Year MARCS ................................................................................................................................................................. 31 Table 7: 5 Year MARCS ................................................................................................................................................................. 32 Table 8: 20 Year MARCS ............................................................................................................................................................... 32 Table 9: State Specific Rates......................................................................................................................................................... 32 Table 10: Applicable Energy Market Revenue Models by Type of DER ....................................................................................... 35 Figure 1: Financial Timelines in NWA Framework .......................................................................................................................... 6 Figure 2: Application of Minimal Weather Adjusted Solar Generation Capacity to a Capacity Deficit ........................................ 12 Figure 3: Daily Lighting EE Profile ................................................................................................................................................. 13 Figure 4: Annual Commercial HVAC EE Profile ............................................................................................................................. 13 Figure 5: Daily Profile for Commercial HVAC EE ........................................................................................................................... 14 Figure 6: HVAC Residential HVAC EE Profile................................................................................................................................. 14 Figure 7: Example DR Event with Pre-Conditioning and Snap Back ............................................................................................. 15 Figure 8: Annual DR Capacity Availability Profile ......................................................................................................................... 16 Figure 9: Available DR Capacity Profile ........................................................................................................................................ 16 Figure 10: Revenue Timelines of NWA DERs ................................................................................................................................ 37 5
  6. Page 6 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 6 of 46 2. ABBREVIATIONS BESS: Battery Energy Storage System BTM: Behind the Meter CHP: Combined Heat and Power CPR: Clean Power Research CVR: Conservation Voltage Reduction DER: Distributed Energy Resource DG: Distributed Generation DR: Demand Response EE: Energy Efficiency EG: Emergency Generation ENST: Eversource NWA Screening Tool EV: Electric Vehicle FC: Fuel Cell LR: Load Reducer MARCS: Modified Accelerated Cost Recovery System MG: Modelled Generation NWA: Non-Wires Alternative PV: Photovoltaics SOG: Settlement Only Generation 6
  7. Page 7 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 7 of 46 3. INTRODUCTION 1 2 3 4 As part of Docket No. 17-12-03RE071, PURA Investigation into Distribution System Planning of the Electric Distribution Companies – Non-Wires Alternative, Eversource submitted a Written Comments outlining a Non-Wires Alternatives (NWA) Screening Process. Within this process, Eversource identified three (3) main Phases; 5 6 7 a. b. c. 8 9 10 11 In Phase II, Eversource calls for a system wide screening of NWA opportunities based on an NWA Screening Tool. This NWA Screening Tool is an Eversource internal development which allows Eversource System Planning to screen capacity project needs at specific locations for potential application of NWA solutions. The intention being, that only sites that are suitable and viable for NWA solutions will move to a more detailed, engineering analysis stage. 12 13 14 15 16 17 18 19 20 21 The Eversource NWA Screening Tool is designed to enable rapid initial screening of NWA options against traditional system upgrade projects. The NWA Screening Tool will also provide appropriate sizing of such solutions. The objective of the tool is not to provide detailed and accurate costing or technical solution design, but rather to provide a quick, repeatable, scalable process for initial screening of NWA options using levelized cost estimates and basic technical assumptions. To enable this rapid screening, the NWA Screening Tool uses levelized values and standard assumptions for costing of solutions. Furthermore, the NWA Screening Tool only focuses on deferring station capital upgrades and does not incorporate a power flow engine, but rather uses substation load forecasts. Once an NWA solution passes the NWA Screening Tool as a viable solution, Eversource System Planning will still need to perform detailed steady-state and transient analysis studies as well as develop engineering designs and cost estimates for the identified solution at a specific location. And this stage, it is still possible that an NWA solution fails to proceed due to technical issues or cost constraints. 22 23 24 To guide a successfully development of the NWA Screening Tool and screening analysis, Eversource developed this NWA Framework. The NWA Framework describes all the assumptions applicable to the NWA Screening Process. This document represents the Eversource NWA Framework. Within the NWA Framework the following key topics are discussed: 25 26 27 28 29 30 a. b. c. d. e. f. Technology Screening and Approval NWA Screening Process Per Identified Need Vendor Qualification and Solution Deployment General Assumptions: Reliability Model: Dispatch Model: Cost Model: Revenue Requirements Model: Revenue Estimation Model: Provides an overview of the general assumptions made in the screening process Details how the reliability of NWAs is modeled within the NWA Screening Tool. Describes dispatch and technical modeling of DERs within an NWA Solution Highlights the cost parameters that are used to determine cost of solutions Provides information on revenue requirements calculations conducted identifies revenue streams that could be captured by DERs in NWA Solutions 31 1 1
  8. Page 8 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 8 of 46 4. STAKEHOLDERS 32 33 34 ▪ Lead Developer and Coordinator ▪ Subject Matter Experts o Regulatory Finance Gerhard Walker 35 36 37 38 39 40 41 42 43 44 45 o Energy Efficiency o o o o Grid Mod Market Participation Reliability and Asset Health Index: Distribution Planning Brian Rice Conner Eller Mike Goldman Roshan Bhakta Brian Greenfield Steven Casey David Errichetti Jaydeep Deshpande Juan Martinez 46 47 48 49 50 51 52 53 54 55 56 57 58 ▪ Reviewers o Distribution Planning MA o Distribution Planning CT o Distribution Planning NH o DER Planning MA o DER Planning CT o DER Planning NH o Transmission Planning o o Juan Martinez Dalia Nunes Matthew Cosgro Shakir Iqbal Dave Ferrante Richard Labrecque Janny Dong Joe Adadjo Ben Byboth David Burnham Andrew Tan Grid Modernization ISO Policy & Economic Analysis 59 60 61 62 63 64 65 ▪ Director/Executive Review o Distribution Planning o Transmission Planning o System Planning o Grid Modernization o Engineering Lavelle Freeman Jacob Lucas Digaunto Chatterjee Jennifer Schilling Aftab Khan 66 2
  9. Page 9 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 9 of 46 5. INITIAL NWA SCREENING 67 68 69 The NWA Framework calls for an initial screening to ensure that from a practical and company policy standpoint the project does not pose any insurmountable obstacles for an NWA Solution before further analysis has been conducted. 70 A. CRITICAL SUITABILITY CRITERIA 71 The Critical Suitability Criteria pose a go-no-go decision point in the NWA Screening Process. 72 73 74 75 76 77 a. 78 79 Any project site that does not pass all three criteria will be disqualified from further NWA considerations and Eversource will move forward with developing a traditional solution. b. 80 Asset Health Index < 0.5: Any station with a transformer’s asset health index above 0.5 will not be considered as an NWA candidate. A health index greater than 0.5 equals a turn insulation drop below 400. (new transformers are at ~1000). Industry/literature2 accepted practice is that <400 is a replacement candidate. Year of First Violation ≥ 2: Any constraint that appears with 2 or less years from the base year will not be considered for an NWA option, as the timeframes for solution design and procurement would not suffice. A standard, out of the box traditional solution provides a faster, and safer alternative to address the issues. B. ADDITIONAL CONSIDERATIONS 81 82 83 The additional screening considerations are intended to help guide a discussion in case the final cost benefit is close to 1. If any of the additional considerations is answered with a “No”, a decision against the NWA solution might be made, but needs to be evaluated on a case by case basis. 84 85 86 87 a. b. c. d. Is it reasonable to assume at this time that a Non-Wires Alternative can be physically sited in the area? Is it reasonable to assume at this time that there are no environmental concerns with Non-Wires Alternatives in the area? Is it reasonable to assume at this time that local residents would accept a Non-Wires Alternative Solution in the area? Is there no other capital project already approved in the same station? 88 2 EPRI 3002019254 Analysis Assessment and Comparison 3
  10. Page 10 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 10 of 46 89 90 91 92 6. GENERAL FRAMEWORK The following Chapter outlines the general NWA Framework, including which distributed energy resources (DER) are considered, how reliability is considered, and how forecasts and financial planning horizons are applied. A. CONSIDERED RESOURCES 93 94 95 The NWA Framework is designed to consider both in front of and behind the meter (FTM / BTM) DER technologies in the NWA Evaluation Process. BTM DERs are assumed to be 3rd party owned and operated through a utility program. Table 1 outlines the DER technologies which are considered in the NWA Framework as options for deferring capital investments. 96 Table 1: DER Technologies Considered as NWAs NWA Definition Capabilities Reduction of load through energy efficiency initiatives in addition to naturally occurring and already planned for energy efficiency. Reduces load profile overall but limited by availability that is defined by customer makeup Temporary reduction of consumption through demand response programs ▪ Commercial DR ▪ Residential DR Reduces load for a fixed time with pre-conditioning and snap back effects Solar PV installations ▪ Utility Scale Solar PV ▪ BTM Solar PV Non-dispatchable output that is dictated by solar irradiance profiles Lithium Ion Battery Systems ▪ Utility Scale BESS (Infront of meter) ▪ BTM BESS System needs to provide enough capacity to recharge during cycles, can provide both active and reactive power Combined Heat and Power (CHP) Customer Program CHP solutions incentivized by the Utility Energy Efficiency Program Modeled to run continuously and generates revenue from electricity and heat. Dispatch capability assumed through Enbala DR Platform Conservation Voltage Reduction (CVR) Voltage modification scheme that reduces system voltage to lower system load Very limited impact which is highly dependent of the feeder makeup and types of loads, typically below 3% Fuel Cell (FC) Customer Program FC solutions incentivized by the Utility Energy Efficiency Program Modeled to run continuously and generates revenue from electricity and heat. Dispatch capability assumed through Enbala DR Platform Emergency Generation (EG) Contracted generators (Diesel, Gas, etc.) that can be called upon by the utility On-call resources with high reliability and flexibility; not renewable, could be noisy and have high emissions; typically, expensive to maintain. Energy Efficiency (EE) Demand Response (DR) Photovoltaic (PV) Battery Energy Storage System (BESS) 97 4

As listed on the current system

Question(s) Answered 566, 569, 570, 575, 578 (The Connecticut Light and Power Company) Date Filed: 09/22/2026

This filing on the current system (opens in a new tab)