  1. Page 7 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 7 of 46 3. INTRODUCTION 1 2 3 4 As part of Docket No. 17-12-03RE071, PURA Investigation into Distribution System Planning of the Electric Distribution Companies – Non-Wires Alternative, Eversource submitted a Written Comments outlining a Non-Wires Alternatives (NWA) Screening Process. Within this process, Eversource identified three (3) main Phases; 5 6 7 a. b. c. 8 9 10 11 In Phase II, Eversource calls for a system wide screening of NWA opportunities based on an NWA Screening Tool. This NWA Screening Tool is an Eversource internal development which allows Eversource System Planning to screen capacity project needs at specific locations for potential application of NWA solutions. The intention being, that only sites that are suitable and viable for NWA solutions will move to a more detailed, engineering analysis stage. 12 13 14 15 16 17 18 19 20 21 The Eversource NWA Screening Tool is designed to enable rapid initial screening of NWA options against traditional system upgrade projects. The NWA Screening Tool will also provide appropriate sizing of such solutions. The objective of the tool is not to provide detailed and accurate costing or technical solution design, but rather to provide a quick, repeatable, scalable process for initial screening of NWA options using levelized cost estimates and basic technical assumptions. To enable this rapid screening, the NWA Screening Tool uses levelized values and standard assumptions for costing of solutions. Furthermore, the NWA Screening Tool only focuses on deferring station capital upgrades and does not incorporate a power flow engine, but rather uses substation load forecasts. Once an NWA solution passes the NWA Screening Tool as a viable solution, Eversource System Planning will still need to perform detailed steady-state and transient analysis studies as well as develop engineering designs and cost estimates for the identified solution at a specific location. And this stage, it is still possible that an NWA solution fails to proceed due to technical issues or cost constraints. 22 23 24 To guide a successfully development of the NWA Screening Tool and screening analysis, Eversource developed this NWA Framework. The NWA Framework describes all the assumptions applicable to the NWA Screening Process. This document represents the Eversource NWA Framework. Within the NWA Framework the following key topics are discussed: 25 26 27 28 29 30 a. b. c. d. e. f. Technology Screening and Approval NWA Screening Process Per Identified Need Vendor Qualification and Solution Deployment General Assumptions: Reliability Model: Dispatch Model: Cost Model: Revenue Requirements Model: Revenue Estimation Model: Provides an overview of the general assumptions made in the screening process Details how the reliability of NWAs is modeled within the NWA Screening Tool. Describes dispatch and technical modeling of DERs within an NWA Solution Highlights the cost parameters that are used to determine cost of solutions Provides information on revenue requirements calculations conducted identifies revenue streams that could be captured by DERs in NWA Solutions 31 1 1
  2. Page 8 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 8 of 46 4. STAKEHOLDERS 32 33 34 ▪ Lead Developer and Coordinator ▪ Subject Matter Experts o Regulatory Finance Gerhard Walker 35 36 37 38 39 40 41 42 43 44 45 o Energy Efficiency o o o o Grid Mod Market Participation Reliability and Asset Health Index: Distribution Planning Brian Rice Conner Eller Mike Goldman Roshan Bhakta Brian Greenfield Steven Casey David Errichetti Jaydeep Deshpande Juan Martinez 46 47 48 49 50 51 52 53 54 55 56 57 58 ▪ Reviewers o Distribution Planning MA o Distribution Planning CT o Distribution Planning NH o DER Planning MA o DER Planning CT o DER Planning NH o Transmission Planning o o Juan Martinez Dalia Nunes Matthew Cosgro Shakir Iqbal Dave Ferrante Richard Labrecque Janny Dong Joe Adadjo Ben Byboth David Burnham Andrew Tan Grid Modernization ISO Policy & Economic Analysis 59 60 61 62 63 64 65 ▪ Director/Executive Review o Distribution Planning o Transmission Planning o System Planning o Grid Modernization o Engineering Lavelle Freeman Jacob Lucas Digaunto Chatterjee Jennifer Schilling Aftab Khan 66 2
  3. Page 9 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 9 of 46 5. INITIAL NWA SCREENING 67 68 69 The NWA Framework calls for an initial screening to ensure that from a practical and company policy standpoint the project does not pose any insurmountable obstacles for an NWA Solution before further analysis has been conducted. 70 A. CRITICAL SUITABILITY CRITERIA 71 The Critical Suitability Criteria pose a go-no-go decision point in the NWA Screening Process. 72 73 74 75 76 77 a. 78 79 Any project site that does not pass all three criteria will be disqualified from further NWA considerations and Eversource will move forward with developing a traditional solution. b. 80 Asset Health Index < 0.5: Any station with a transformer’s asset health index above 0.5 will not be considered as an NWA candidate. A health index greater than 0.5 equals a turn insulation drop below 400. (new transformers are at ~1000). Industry/literature2 accepted practice is that <400 is a replacement candidate. Year of First Violation ≥ 2: Any constraint that appears with 2 or less years from the base year will not be considered for an NWA option, as the timeframes for solution design and procurement would not suffice. A standard, out of the box traditional solution provides a faster, and safer alternative to address the issues. B. ADDITIONAL CONSIDERATIONS 81 82 83 The additional screening considerations are intended to help guide a discussion in case the final cost benefit is close to 1. If any of the additional considerations is answered with a “No”, a decision against the NWA solution might be made, but needs to be evaluated on a case by case basis. 84 85 86 87 a. b. c. d. Is it reasonable to assume at this time that a Non-Wires Alternative can be physically sited in the area? Is it reasonable to assume at this time that there are no environmental concerns with Non-Wires Alternatives in the area? Is it reasonable to assume at this time that local residents would accept a Non-Wires Alternative Solution in the area? Is there no other capital project already approved in the same station? 88 2 EPRI 3002019254 Analysis Assessment and Comparison 3
  4. Page 10 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 10 of 46 89 90 91 92 6. GENERAL FRAMEWORK The following Chapter outlines the general NWA Framework, including which distributed energy resources (DER) are considered, how reliability is considered, and how forecasts and financial planning horizons are applied. A. CONSIDERED RESOURCES 93 94 95 The NWA Framework is designed to consider both in front of and behind the meter (FTM / BTM) DER technologies in the NWA Evaluation Process. BTM DERs are assumed to be 3rd party owned and operated through a utility program. Table 1 outlines the DER technologies which are considered in the NWA Framework as options for deferring capital investments. 96 Table 1: DER Technologies Considered as NWAs NWA Definition Capabilities Reduction of load through energy efficiency initiatives in addition to naturally occurring and already planned for energy efficiency. Reduces load profile overall but limited by availability that is defined by customer makeup Temporary reduction of consumption through demand response programs ▪ Commercial DR ▪ Residential DR Reduces load for a fixed time with pre-conditioning and snap back effects Solar PV installations ▪ Utility Scale Solar PV ▪ BTM Solar PV Non-dispatchable output that is dictated by solar irradiance profiles Lithium Ion Battery Systems ▪ Utility Scale BESS (Infront of meter) ▪ BTM BESS System needs to provide enough capacity to recharge during cycles, can provide both active and reactive power Combined Heat and Power (CHP) Customer Program CHP solutions incentivized by the Utility Energy Efficiency Program Modeled to run continuously and generates revenue from electricity and heat. Dispatch capability assumed through Enbala DR Platform Conservation Voltage Reduction (CVR) Voltage modification scheme that reduces system voltage to lower system load Very limited impact which is highly dependent of the feeder makeup and types of loads, typically below 3% Fuel Cell (FC) Customer Program FC solutions incentivized by the Utility Energy Efficiency Program Modeled to run continuously and generates revenue from electricity and heat. Dispatch capability assumed through Enbala DR Platform Emergency Generation (EG) Contracted generators (Diesel, Gas, etc.) that can be called upon by the utility On-call resources with high reliability and flexibility; not renewable, could be noisy and have high emissions; typically, expensive to maintain. Energy Efficiency (EE) Demand Response (DR) Photovoltaic (PV) Battery Energy Storage System (BESS) 97 4
  5. Page 11 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 11 of 46 98 B. FORECASTING AND PLANNING HORIZONS 99 100 To allow a technical and economic comparison on a level playing field, solutions are compared not simply with their initial capital need, but over longer time horizons to ensure that they 101 102 a. b. 103 As a result, the NWA Framework considers two-time frames, the System Forecast and the Financial Planning Horizon. 104 SYSTEM FORECAST HORIZON 105 106 107 108 109 110 The System Forecast Horizon describes the timeline over which the EDC can forecast load and generation growth on their system. The NWA Framework assumes a 10-year System Forecast Horizon. Within that 10-year horizon the utility can provide a load growth and DER adoption forecast which allows determination of the expected system peaks. Capacity deficits can only be determined within that 10-year forecasting horizon. As a result, traditional and DER investments can only be made within those ten years. The NWA Framework does not concern itself with the forecasting methodologies but takes a completed forecast as an input for each of the ten (10) years. 111 112 The System Forecast Horizon is set at the Base Year + 10 years. The Base Year describes the last year with a complete annual timeseries data set using 15-min interval data. 113 FINANCIAL PLANNING HORIZON 114 115 116 The Financial Planning Horizon defines the time horizon over which the NWA solution is assumed to be active. Within the Financial Planning Horizon, the tool will automatically track replacement of components, such as battery cells, as needed and O&M costs. The Financial Planning Horizon hereby needs to be larger than 117 FirstConstraintYear + DeferalYears − BaseYear 118 119 This is to ensure that the cost of the NWA is considered for the entire time span over which it needs to defer the traditional solution. 120 121 122 123 124 125 The NWA Framework suggests following approach to setting up the Financial Planning Horizon: Shortest Expected Lifespan. Using the shortest asset lifespan in addition to the year of construction yields the total financial planning horizon. E.g. with the inclusion of a battery storage system, the shortest expected lifespan is 12 years for the battery cells. The financial planning horizon can now be 12 to 22 years from the base year, depending on when the battery asset is constructed. E.g., the Battery Solution is to be constructed in year 8 of the System Forecast, as a result the Financial Planning Horizon is 8 + 12 = 20 years from the Base Year. 126 127 Note: The financial planning horizon needs to reach further at all times than the date to which the traditional solution is deferred. 128 TERMINAL COST 129 130 131 132 With a varying Financial Planning Horizon all assets are considered with their entire lifetime revenue requirements impact. For this purpose, the Framework requires revenue requirements up to the financial planning horizon, which includes 1) new investments such as asset replacements as well as O&M, and 2) the terminal cost after the planning horizon which no longer includes O&M or new investments and simply sums the remaining cumulative net present value revenue requirements. Can meet future capacity needs in a reliable manner Can maintain economic feasibility over longer time spans 06.B.01 5
  6. Page 12 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 12 of 46 133 DEFERRING CAPACITY NEED 134 135 136 137 138 a. Deferral within the System Forecast Horizon: If an NWA solution defers the capacity only so much that the need arises again within the 10-year System Forecast Horizon, a simple value of deferral is calculated using the applicable inflation rate, technology cost reduction, and discount rate to create a change in NPV revenue requirements. Therefore, the NPV of the cost of the NWA solution plus the NPV of the cost of the deferred traditional solution must be less than the NPV of the cost of the traditional solution alone. This is shown in the equation below: 139 NWA(t)NPV + Traditional(t + n)NPV ≤ Traditional(t)NPV 140 141 142 143 144 145 146 147 148 where the traditional solution is depreciated over 40 years. 149 150 b. 06.B.02 Deferral past the System Forecast Horizon: With a ten (10) year forecasting horizon, it may happen that an NWA solution is capable of deferring the capacity need past the horizon. In this case, the capacity need is deferred to the first year after the forecast. With a 10-year forecast, the maximum possible deferral is ten (10) years. This limits the value an NWA can produce by deferring capital investments by no more than 10 years, as the assumption is that in year eleven (11) the capital project would be needed. • Situational: Based on the forecast trends and the chosen NWA solution, a decision can be made to declare the deferral to be ≥ 10 years. E.g. if forecasts show a decline Figure 1 illustrates an example of the application of different timelines in the financial planning model. Hereby, a capacity need at year five (5) is deferred by five (5) years. Flexible Financial Planning Horizon Terminal Value 10yrs – Forecasting Horizon Need Identified year 5 NWA Solution Depreciation NWA Solution O&M Applicable Replacements 40yrs – Traditional Solution Depreciation Deferred 40yrs – Traditional Solution Depreciation Flexible Deferral 5 years 50yrs Base Year 151 NWA Deployed 2025 Traditional Solution 2030 152 Figure 1: Financial Timelines in NWA Framework 153 C. NWA DISPATCH OPTIONS 154 155 156 157 158 NWA Decommission For EDCs to consider DERs as NWAs they need to provide the same level of availability as traditional solutions. While, in most cases, the EDC will be able to forecast high load conditions and the associated dispatch need, unforeseen conditions need to be taken into consideration as well. Such conditions can include storm impacts or other events of natural or human cause that interrupt or disable capacity carrying parts of the system. In such an event, much like the traditional solution counterpart, load might need to be transferred to the NWA on very short notice. 6
  7. Page 13 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 13 of 46 159 In conclusion, there are two dispatch options 160 161 162 163 164 165 a. 166 167 168 169 Note: Dispatch option b. is the more limiting for NWA technologies but cannot be excluded from the evaluation criteria, as without it, the EDC needs to provide a contingency for the unplanned dispatch, which would likely be the traditional solution upgrade that the NWA was aiming at deferring in the first place. As a result, several market participation options will not be considered by the Framework specifically because they do not meet this asset readiness standard. b. Planned Dispatch: up to 48-hours ahead, the EDC can determine peak load events and provide dispatch schedules for the NWA to mitigate such situations. This time frame allows the NWA to get “ready” for the dispatch if it is in non-ideal conditions. Unplanned Dispatch: the EDC calls upon an NWA within seconds of the actual dispatch due to an unforeseen event of natural or human origin. The NWA does not have time to get “ready” for its dispatch but still needs to provide the full service. 170 7
  8. Page 14 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 14 of 46 7. RELIABILITY MODEL 171 172 173 174 In order to assume availability of DERs that are used as an NWA, the company needs to ensure sufficient reserve margin, especially for assets that are controlled through utility owned programs. With NWA assets being part of the electric distribution grid’s supply capability, the same N-1 approaches apply as they would to transformers and other hardware. 175 This section describes the NWA Framework for reliability rules around DERs used for NWA purposes. 176 177 178 179 180 181 182 A. EXEMPTIONS FROM THE N-1 RELIABILITY DESIGN STANDARD a. b. 183 Energy Efficiency programs replace existing hardware with newer, more efficient hardware. Once replaced, the new hardware permanently consumes less energy than its predecessor. As a result, Energy Efficiency measures can be exempted from an N-1 design criterion. Conservation Voltage Reduction includes the installation of new voltage regulating equipment at the station and along feeder lines. This equipment is not typically designed to N-1 standards, and for the purpose of the NWA Framework, CVR will therefore not be part of any N-1 design criterion. B. RELIABILITY ASSUMPTIONS FOR CUSTOMER PROGRAMS 184 185 186 For residential customer sited DR, Battery Storage, and Solar assets which are controlled through customer programs an assumption on participation is made. The following equations are utilized to calculate the minimal customer behavior adjusted reliable capacity where the number of assets under contract is (n) 187 a. 188 PPVReliable_BTM = (∑ PPVInstalled_BTM ) ∗ εcapPV (1 − ) 189 b. 190 PDRReliable = (∑ PDRInstalled_BTM ) ∗ εcapDR (1 − ) 191 c. 192 PBESReliable = (∑ PBESInstalled_BTM ) ∗ εcapBES (1 − ) 193 194 d. 195 PDRComFirm = (∑ PDRComReliable ) − max(PDRComReliable ) 196 197 198 εcap represents the saturation limit of distributed DR and PV. For example, if εcap = 0.8 then no more than 80% of installed assets will ever be accounted for. The following values are used based on historic observations by the Eversource Energy Efficiency Group. 199 Table 2 shows the respective saturation factor for reliability calculations with Residential Solar 1 7.B.01 n Residential Demand Response 1 7.B.02 n BTM Battery Storage 1 7.B.03 n Commercial Demand Response is treated slightly differently and functions similar to a normal N-1 approach where the largest asset is removed from the overall observation. 7.B.04 8
  9. Page 15 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 15 of 46 PAvailable 200 ε = lim 201 Table 2: Saturated Reliability Factor for Utility Programs 7.B.05 n→∞ PInstalled 202 𝛆𝐜𝐚𝐩𝐏𝐕 𝛆𝐜𝐚𝐩𝐃𝐑 𝛆𝐜𝐚𝐩𝐁𝐄𝐒 0.95 0.80 0.80 C. RELIABILITY ASSUMPTIONS FOR GRID SCALE BATTERIES 203 204 Utility owned and operated grid-scale batteries are considered to be in the same N-1 reliability group as the station’s transformers. The resulting capacity which will be considered for grid scale-batteries is therefore calculated as follows 205 PBatFirm = 206 207 Note: It is therefore advisable that no single BESS exceeds the size of the largest station transformer as it would be entirely removed for the firm capacity calculation. 208 (∑ PBat ); (∑ PBat ) − max(PBat ) ; max(PBat ) ≤ max (PTransformer ) max(PBat ) > max (PTransformer ) 7.C.01 D. RELIABILITY ASSUMPTIONS FOR DG 209 210 All DG NWA solutions (Solar, Fuel Cell, CHP, Emergency Generators) are considered to be in a separate reliability group. The largest DG is excluded in the NWA Framework to calculate the Reliable DG Capacity PDGReliable analogous to the transformer + 211 large scale BESS group. 212 PDGReliable = (∑ PDG ) − max(PDG ) 213 DER assets included in PDG are 214 a. Solar DG: For solar DG, PDGSolar represents the installed capacity adjusted for minimal certain 215 216 b. Fuel Cells: weather adjusted output. See Solar Generation for details. PDGFC represents the nameplate installed capacity 217 218 c. d. CHP: Emergency Generators: PDGCHP represents the nameplate installed capacity PDGEG represents the nameplate installed capacity 7.D.01 219 9
  10. Page 16 of 46

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 OCC-578 Attachment 1 Page 16 of 46 8. 220 221 222 223 DISPATCH MODEL In order to determine their ability to solve technical issues, the dispatch, especially of flexible resources such as BESS, needs to be accurately modeled. The NWA Framework makes assumptions on DER dispatch modes and capabilities as outlined in the following Chapter 224 A. PRIORITIZATION OF DER DISPATCH 225 The NWA Framework assumes that in a multi-solution NWA portfolio, the dispatch priorities are as follows: 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 a. b. c. 250 Permanently Altering Assets: These technologies permanently alter the load of the system and are therefore always available and do not require an active dispatch to produce their benefit. The tool will use their contribution first to determine if any remaining dispatch is required. • Energy Efficiency Continuously Running Assets: Assets that are assumed to be continuously running are considered next. Given the nature of the resources, curtailment of their output would not make fiscal sense. Their contribution is set to nominal throughout the day which is observed. Any remaining capacity need is handled by dispatchable assets. • Solar: Has no variable cost and generates revenue when running • CHP: Installed through program funding with an assumed dispatch capability through DR system • Fuel Cell: Installed through program funding with an assumed dispatch capability through DR system Dispatchable Assets: Dispatchable assets can change their dispatch characteristics to the extent that their technical limitations allow them to. • CVR: Dispatch of tap changers at transformers, capacitors, and in-line voltage regulators with no marginal cost of dispatch • Utility Program Dispatch: Any utility program, such as DR management, fall under this category i. DR (Commercial and Residential DR), limited to one dispatch a day • Utility Owned Asset Optimization and Battery Programs: Remaining capacity need can be managed by storage. Storage is prioritized before emergency generation assets from an ecological standpoint. This includes the use of Battery Storage DR Programs. i. Utility Scale Battery Storage ii. BTM Storage Control Programs • Contracted Emergency Assets: As a last resort emergency generation asset can be dispatched to fill any remaining capacity gap. Their environmental impacts and associated costs make them the least desirable solution. i. Emergency Generator B. SOLAR GENERATION 251 252 253 254 For consideration of solar distributed generation as an NWA the technology’s technical capabilities are defined as follows by the NWA Framework (these apply to both utility scale and BTM installations, their different considerations by the NWA Framework on reliability can be reviewed in 7.D. Reliability Assumptions for DG; any values considered in this section are the result of those reliability assumptions). 255 256 a. Time Variant Output: Solar PV installations can only generate power during the hours when the sun is shining (typically daytime hours in the U.S.), therefore, any capacity deficits which occur outside those hours cannot be addressed through 10